SIKA-102
Fast Setting Cemenitious Mortar Waterplug
Waterproofing - Industrial Flooring - Structure Repair / strengthening - Joint Sealant - Grouting - Bridge Joint
Langkah-langkah kerja :
1. Kerja-kerja membersih, membuang dan menyedut air yang bertakung, lumut, sampah
dan kotoran dengan menggunakan mesin penyedut bertekanan tinggi.
2. Kerja-kerja memecah dan membesarkan honey comm pada dinding konkrit dan
menampal semula dengan menggunakan dengan menggunakan water plug dari jenis
“sika-102 fast setting cemenitious mortar waterplug”
3. Kerja-kerja melepa tiga (3) lapisan bahan kalis air dari jenis “Sika Seal 107
Sementious” pada permukaan lantai concrete dengan skriting setinggi 5 kaki dari lantai
concrete.
Waterproofing - Industrial Flooring - Structure Repair / strengthening - Joint Sealant - Grouting - Bridge Joint
4. Kerja-kerja membuat fillet angle pada setiap bucu antara lantai dan dinding dengan
menggunakan “non-srink path repair mortar” dari jenis sika monotop R
Waterproofing - Industrial Flooring - Structure Repair / strengthening - Joint Sealant - Grouting - Bridge Joint
Product
Concrete surface must be clean, sound substrate free of movement cracks or blowholes, no loose
or friable materials, no oily contaminations, no water repellents / protective coating / curing
compound, well dampened but free of surface water and leaks, free of fungus growth. Minimum
ambient and surface temperature : 8°c.
Brush application.
1st Coat –Prewet slab and well substrate (up to 300mm high ) to saturated surface dry (SSD)
condition .Brush on a coat of Sikatop Seal 107 on the sides of the walls to a height of ~200mm.
Whilst the slap substrate is still damp ,pour the 1st Coat of the well mixed Sikatop Seal 107 to the
surface .Use a plastic brush or broom and sweep the slurry material in the single direction, rubbing
the slurry well into the slab .Allow the 1st Coat is to be hardened sufficiently (normally after 4-10
hours at 20º c).
2nd Coat – Follow the similar procedure of application as the 1st Coat .However sweep the slurry
in a transverse/crisscross direction .Allow to harden for 3 days. If the 2nd Coat is to be applied the
next day, prewet the 1st Coat using fine spray of water.
3th Coat – Follow the similar procedure of application as the 1st Coat .However sweep the slurry
in a transverse/crisscross direction .Allow to harden for 3 days.If the 3th Coat is to be applied the
next day ,prewet the 1st Coat using fine spray of water.
Protect the freshly applied Sikatop seal 107 against direct sunligh ,strong winds and rain.Under
severe temperature ,curing may be required by using dam Hessian or polythene sheet
.
Cleaning.
Clean tools and equipment immediately with water .Hardened material can only be removed
mechanically.
Safety
Applicators are recommended to wear gloves while working.