You are on page 1of 4

Project Start: Tue 10/4/05

Project Finish: Fri 2/2/07

ID Level Task Name Duration Start


1 1 Project Start 0 days Tue 10/4/05
2 1 Project Planning 10 days Tue 10/4/05
3 2 Project Charter 3 days Tue 10/4/05
4 2 Scope Definition 3 days Thu 10/6/05

5 2 Project Plan 5 days Mon 10/10/05


6 2 Planning Sign-off 0 days Mon 10/17/05
7 1 Business Requirements 20 days Thu 10/13/05
8 2 Requirements Definition 5 days Thu 10/13/05

9 2 Use Cases 10 days Tue 10/18/05


10 2 Test Cases 7 days Wed 10/26/05
11 2 Review and Acceptance 4 days Fri 11/4/05
12 2 Sign-off 0 days Wed 11/9/05
13 1 Design 24 days Mon 11/7/05

14 2 Framework Design 10 days Mon 11/7/05

15 2 Services Design 10 days Wed 11/16/05

16 2 Interface Design 10 days Fri 11/25/05


17 2 Data Modeling 10 days Fri 11/25/05

18 2 Design Sign-off 0 days Thu 12/8/05


19 1 Coding and Unit Test 201 days Fri 12/9/05
20 2 Database Design and Build 10 days Fri 12/9/05
21 2 Framework Components Coding 35 days Fri 12/16/05
22 2 Framework Unit Test 3 days Thu 6/22/06
23 2 Common Services coding 20 days Tue 6/20/06
24 2 Common Services Unit Test 5 days Tue 7/18/06
25 2 Specialized Services Coding 25 days Tue 7/18/06
26 2 Specialized Services Unit Test 5 days Tue 8/22/06

27 2 Interface Build 15 days Tue 8/22/06


28 2 Interface Unit Test 4 days Tue 9/12/06

29 2 Reports Build 15 days Tue 8/22/06


30 2 Reports Unit Test 3 days Tue 9/12/06
31 2 Coding Complete 0 days Fri 9/15/06
32 1 Integration and Assembly Test 30 days Mon 9/18/06

33 2 Integrate Services 10 days Mon 9/18/06

34 2 Integrate Interface 10 days Mon 10/2/06

35 2 Assembly Test 10 days Mon 10/16/06


36 2 Integration Complete 0 days Fri 10/27/06
37 1 User Acceptance 30 days Mon 10/30/06
38 2 Business Alignment 20 days Mon 10/30/06
39 2 Performance Test 15 days Mon 11/13/06

40 2 Test Results Review and Acceptance 5 days Mon 12/4/06


41 2 User Acceptance Sign-off 0 days Fri 12/8/06
42 1 Deployment 32 days Mon 11/20/06
43 2 User Training 20 days Mon 11/20/06
44 2 Infrastructure Readiness 10 days Mon 12/11/06

45 2 System Deployment 5 days Mon 12/25/06

46 2 Implementation Shake-down 2 days Mon 1/1/07


47 2 Implementation Sign-off 0 days Tue 1/2/07
48 1 Project Closure 23 days Wed 1/3/07
49 2 Post-Implementation Support 20 days Wed 1/3/07
50 2 Lessons Learned 3 days Wed 1/24/07
51 2 Project Complete 0 days Fri 2/2/07

Note: For the complete plan content and functionality please download this project plan in MS
Finish Predecessors Resource Names % Complete Hyperlink
Tue 10/4/05 Project Manager 0%
Mon 10/17/05 0%
Thu 10/6/05 1 Project Manager 0%
Mon 10/10/05 3FS-1 day Project Manager,Business Analyst 0%

Project Manager,Application Architect,Data


Fri 10/14/05 4FS-1 day Architect,Business Analyst 0%
Mon 10/17/05 5FS+1 day Project Manager 0%
Wed 11/9/05 0%
Wed 10/19/05 6FS-3 days Business Analyst 0%
Business Analyst,Application Architect,Data
Mon 10/31/05 8FS-2 days Architect 0%
Thu 11/3/05 9FS-4 days Business Analyst,Tester 1 0%
Wed 11/9/05 10 Project Manager,Business Analyst 0%
Wed 11/9/05 11 Business Analyst,Project Manager 0%
Thu 12/8/05 0%

Fri 11/18/05 12FS-3 days Application Architect,Senior Developer 1 0%

Tue 11/29/05 14FS-3 days Application Architect,Senior Developer 2 0%


Application Architect,Business
Thu 12/8/05 15FS-3 days Analyst,Senior Developer 3 0%
Thu 12/8/05 15FS-3 days Data Architect,Business Analyst 0%
Project Manager,Application Architect,Data
Thu 12/8/05 17,16 Architect 0%
Fri 9/15/06 0%
Thu 12/22/05 18 Data Architect,DBA 0%
Wed 6/21/06 20FS-5 days Senior Developer 1 0%
Mon 6/26/06 21 Senior Developer 1 0%
Mon 7/17/06 22FS-5 days Senior Developer 2 0%
Mon 7/24/06 23 Senior Developer 2 0%
Mon 8/21/06 24FS-5 days Senior Developer 3 0%
Mon 8/28/06 25 Senior Developer 3 0%

Mon 9/11/06 26FS-5 days Senior Developer 1,Business Analyst[50%] 0%


Fri 9/15/06 27 Senior Developer 1,Business Analyst 0%

Mon 9/11/06 26FS-5 days Senior Developer 2,Business Analyst[50%] 0%


Thu 9/14/06 29 Senior Developer 2,Business Analyst 0%
Fri 9/15/06 30,28 Project Manager 0%
Fri 10/27/06 0%
Application Architect,Data Architect,Senior
Fri 9/29/06 31 Developer 1 0%

Application Architect,Data
Architect,Business Analyst,Senior Developer
Fri 10/13/06 33 2 0%
Application Architect,Senior Developer
Fri 10/27/06 34 1,Senior Developer 2 0%
Fri 10/27/06 35 Project Manager 0%
Fri 12/8/06 0%
Fri 11/24/06 36 Business Analyst,Tester 1 0%
Fri 12/1/06 38FS-10 days Application Architect,Tester 2 0%
Business Analyst,Project
Fri 12/8/06 39 Manager,Application Architect 0%
Fri 12/8/06 40 Project Manager 0%
Tue 1/2/07 0%
Fri 12/15/06 41FS-15 days Business Analyst 0%
Fri 12/22/06 43FS-5 days Senior Developer 3 0%

Application Architect,Data Architect,Senior


Developer 1,Senior Developer 2,Senior
Fri 12/29/06 44 Developer 3,DBA 0%
Business Analyst,Application
Tue 1/2/07 45 Architect,Tester 1,Tester 2 0%
Tue 1/2/07 46 Project Manager 0%
Fri 2/2/07 0%
Tue 1/30/07 47 Senior Developer 1,Senior Developer 2 0%
Fri 1/26/07 49FS-5 days Project Manager 0%
Fri 2/2/07 50FS+5 days Project Manager 0%