Professional Documents
Culture Documents
Report
2
Table of Contents
Task 1...............................................................................................................................................3
Part b............................................................................................................................................4
Gantt Chart...............................................................................................................................6
Network Diagram....................................................................................................................7
Task 2...............................................................................................................................................9
30,000 = CV(1+0.05)^1.................................................................................................................14
References......................................................................................................................................15
3
Task 1
Part a: Agile Project Management Methodology
The agile project management and system development methodology commits the work to be
done incrementally. This includes various stages in successive form. Following this approach, a
part of the system is released before the whole system is developed. This is done to ensure that
system is following the functional requirements and get the feedback of the client. These brief
period of work and releases are called sprints. This project management methodology is different
from waterfall software development in a way that it provides flexibility and involves regular
feedback from the project client, and it does not follow the approach of collecting requirements
altogether and developing the system all at once (Ciric et al., 2018). Agile methodology differs
from the traditional approaches in the manner that it does not release the entire system at the end
of project lifecycle, rather system modules are released in sprints. It is a documentation driven
approach suitable for large projects where different departments are to be connected as in the
given Supply Chain Management System. With these traditional methodologies, the completed
project is released at the very end of the project cycle.
Part b
Work breakdown Structure
Work breakdown structure (WBS) provides a systematic approach to distribute work into
different activities. It uses divide and conquer method for large complex projects (Han, 2021). It
gives a pictorial view of work packages thus providing visibility and ease of tracking the
progress. It's a way to divide and conquer large projects to get things done faster and more
efficiently. The goal of WBS is to make project manageable. It breaks down the work along with
the material resources and the human resource assigned to each work package.
5
Project design
2 6 days Tue 6/28/22 Tue 7/5/22 3
development
2.1 design modifications 6 days Tue 6/28/22 Tue 7/5/22 3
Review back-end
3.3 4 days Wed 7/6/22 Mon 7/11/22 9
development
adjust functional
3.4 9 days Tue 7/12/22 Fri 7/22/22 13
changes
3.5 Changes updated 4 days Mon 7/25/22 Thu 7/28/22 14
Gantt Chart
The Gantt Chart is an assisting tool in project management which helps in planning and
scheduling the project. It simplifies the projects of all sizes and provides the readability to track
the progress of work (Chakrabarti, 2022). The work-packages are represented into bars and flow
among project phases is shown through arrows, describing dependencies, schedule and
deadlines.
Apr '22 May '22 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5
6/22
7/5
12/13
7
Apr '22 May '22 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23
24 1 8 15 22 29 5 12 19 26 3 10 17 24 31 7 14 21 28 4 11 18 25 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 5 12 19 26 5
7/5
12/13
12/28
1/4
Network Diagram
The workflow in a project is visually presented through the network diagram. It consists of the
boxes describing the start and finish of an activity, providing sequencing and scheduling of all
project activities (Ahmadi et al., 2018).
Project business feasibility Study key stakeholder meeting Functional requirements approved Project design development design modifications
Start: Mon 6/6/22 ID: 1 Start: Mon 6/20/22 ID: 2 Start: Thu 6/23/22 ID: 3 Start: Tue 6/28/22 ID: 7 Start: Tue 6/28/22 ID: 8
Finish: Fri 6/17/22 Dur: 10 days Finish: Wed 6/22/22 Dur: 3 days Finish: Mon 6/27/22 Dur: 3 days Finish: Tue 7/5/22 Dur: 6 days Finish: Tue 7/5/22 Dur: 6 days
Res: Res: Res: Comp: 0% Res:
changes made
Requirements signed off
Start: Wed 6/22/22 ID: 5
Finish: Wed 6/22/22 Dur: 1 day? Milestone Date: 6/22/22
Res: ID: 6
Changes updated
Start: Wed 12/14/22ID: 15
Finish: Mon 12/19/22Dur: 4 days
Res:
Task 2
Part a: Risk Management
Following are the anticipated risks in the project that have been analyzed through brainstorming
and lessons learned from the similar management systems.
non-functional requirements
Project feasibility study missed out external
market analysis.
Initiation and Design phase
Project manager did not set out clear working
strategy for each sprint leading to disharmony
of interests.
Project acceptance criteria not properly stated.
Development phase
The modules and subsequent sprints timely is
miscalculated.
Weak coding and technical skills of
development team.
The project methodology did not complement
the project work.
Testing Phase The inability and lack of knowledge of testing
team to carry out tests to find out complex
bugs.
Delays are encountered in the project testing
phase.
Close project Under-trained staff at the client’s end to use
the system properly.
The client’s refusal to sign off the project due
to potential bugs.
Risks Mitigation
1. Project scope not properly defined and the project scope has to be thoroughly
documented discussed and signed off in a contract.
2. No clear distinction between functional There should be a project charter clearing
and non-functional requirements stating functional requirements.
3. Project feasibility study missed out The business analyst has to closely work with
external market analysis. project manager to carry out external market
analysis while deciding project budget.
4. Project manager did not set out clear The project manager has to develop a clear
working strategy for each sprint project plan to support the project
leading to disharmony of interests. development into clearly distinct sprints.
5. Project acceptance criteria not properly The project acceptance criteria need to be
stated. defined along the scope and signed off to
avoid future conflict.
6. The modules and subsequent sprints The work in each sprint has to be calculated
timely are miscalculated. along the resources for approximate
calculations.
7. Weak coding and technical skills of The development team has to be shortlisted
development team. after testing their skills.
8. The project methodology did not The overall functional requirements should be
complement the project work. discussed with development team and then
methodology has to be chosen.
9. The inability and lack of knowledge of The testing team ability to conduct different
testing team to carry out tests to find tests has to be analyzed first and then they
out complex bugs. should be taken on-board.
10. Delays are encountered in the project Testing team has to test each sprint release
13
Assuming that project owner invests OMR 300,000 for the development of SCM. He is looking
forward to earn OMR 30,000 profit annually once system is deployed to eliminate the delays in
supply chain and streamline the work.
Assuming that annual inflation of 5%, then current value has to be found
FV = CV(1+r/100)^n
CV = Current Value
r = Inflation
n = time
Putting values
FV = OMR 30,000
r=5
n =1
14
30,000 = CV(1+0.05)^1
CV = 30,000/1.05
CV = OMR 28,571.42
Hence, the current value owner’s profit is 708.80 OM OMR 28,571.42. so, the project is
financially feasible to be conducted since it is providing annual future value near to projected
one.
It is worthwhile to point here that there is no set criterion or rule of thumb for cost benefit
analysis, the simple equation can also be used to determine the future value that project could
yield (Nayar & Kumar, 2018).
15
References
1) Ahmadi, A., Suparno, S., Suharyo, O. S., & Susanto, A. D. (2018). Time Scheduling And
Cost Of The Indonesian Navy Ship Development Project Using Network Diagram And
Earned Value Method (Evm)(Case Study Of Fast Missile Boat Development). JOURNAL
ASRO, 9(2), 87-106.
2) Bergmann, T., & Karwowski, W. (2018, July). Agile project management and project
success: A literature review. In International Conference on Applied Human Factors and
Ergonomics (pp. 405-414). Springer, Cham.
3) Ciric, D., Lalic, B., Gracanin, D., Palcic, I., & Zivlak, N. (2018, March). Agile project
management in new product development and innovation processes: challenges and
benefits beyond software domain. In 2018 IEEE International Symposium on Innovation
and Entrepreneurship (TEMS-ISIE) (pp. 1-9). IEEE.
4) Chakrabarti, S. (2022). Management Aspects of Project Engineering. In Project
Engineering Primer for Chemical Engineers (pp. 179-204). Springer, Singapore.
5) Han, X. (2021). WBS-free scheduling method based on database relational
model. International Journal of System Assurance Engineering and Management, 12(3),
509-519.
6) Nunes, M., & Abreu, A. (2020). Managing open innovation project risks based on a
social network analysis perspective. Sustainability, 12(8), 3132.
7) Nayar, K. B., & Kumar, V. (2018). Cost benefit analysis of cloud computing in
education. International Journal of Business Information Systems, 27(2), 205-221.
8) Rasnacis, A., & Berzisa, S. (2017). Method for adaptation and implementation of agile
project management methodology. Procedia Computer Science, 104, 43-50.