'20 Feb '20 Mar '20 Apr '20 May '20 Jun '20 Jul '20 Aug '20 Sep '20 Oct '20 Nov '20 Dec '21 Jan '
M2J2%20Project_draft%201 204 day Wed 20‐03‐1Mon 20‐12‐2
1. Phase ‐ Preparation Stage 55 days Wed 20‐03‐18Tue 20‐06‐02 06-02
1.1. Baseline research 6 days Mon 20‐03‐23Mon 20‐03‐30
1.1.1. Assessment of existing online education 0 days Tue Tue
resourses 20‐03‐24 20‐03‐24
1.1.2. Define additional features 2 days Wed 20‐03‐25Thu 20‐03‐26
1.1.3. Finalise speicifcations for online platform 3 days Thu 20‐03‐26 Mon 20‐03‐30
1.2. Project Concept 5 days Mon 20‐03‐30Fri 20‐04‐03
1.2.1. Define project team 2 days Mon 20‐03‐30Tue 20‐03‐31
1.2.2. Analyse data and develop project charter 3 days Tue 20‐03‐31 Thu 20‐04‐02
1.2.3. Budget 2 days Wed 20‐04‐0 Thu 20‐04‐02
1.3. Fundraising 24 days Tue 20‐03‐31 Fri 20‐05‐01
1.3.1. Prepare presentation 6 days Tue 20‐03‐31 Tue 20‐04‐07
1.3.2. Meeting with sponsors 15 days Mon 20‐04‐13Fri 20‐05‐01
1.4. Technical Side Prep ‐ Online Platform Building7 days Fri 20‐05‐01 Mon 20‐05‐1
1.4.1. Development and Publication of RFP/ SOW2 days Mon 20‐05‐11Tue 20‐05‐12
1.4.2. Bids/proposal evaluation 3 days Mon 20‐06‐01Wed 20‐06‐03
1.4.3. Approval and PO creation 2 days Thu 20‐06‐04 Fri 20‐06‐05
1.4.3. Meeting with the vendor 3 days Thu 20‐06‐04 Mon 20‐06‐08
1.4.4. Contract signing 1 day Fri 20‐06‐05 Fri 20‐06‐05
2. Phase ‐ Online Education Platform Development 21 days Mon 20‐06‐08Mon 20‐07‐06 07-06
2.1. Regular meetings with vendor MJ 21 days Mon 20‐06‐08Mon 20‐07‐06
2.1.1. Software expectations detail 14 days Mon 20‐06‐08Thu 20‐06‐25
2.1.2. Follow up Meetings to track progress 20 days Mon 20‐06‐08Fri 20‐07‐03
2.2. Delliverables report 21 days Mon 20‐06‐08Mon 20‐07‐06
2.2.1. Vendor MJ reporting deliverables 1 day Mon 20‐06‐08Mon 20‐06‐08
2.2.2. Project Team Acceptance 1 day Mon 20‐06‐08Mon 20‐06‐08
3. Phase ‐ Testing 26 days Mon 20‐07‐06Mon 20‐08‐10
3.1. Collecting Feedback 22 days Mon Tue
20‐07‐06 20‐08‐04
3.1.1. Development and approval of questions 1 day Thu 20‐07‐16 Thu 20‐07‐16
3.1.2. Recruitment of FGD participants 1 day Mon 20‐07‐13Mon 20‐07‐13
3.1.3. FGD with professors and students on trial 5 days Mon 20‐07‐13Fri 20‐07‐17
3.1.4. FGD data gathering 1 day Tue Tue
20‐07‐14 20‐07‐14
3.1.5. FGD Data analysis 3 days Wed Fri 20‐07‐17
20‐07‐15
3.2. Finalisation of the product (technical side) 3 days Wed Fri 20‐08‐07
20‐08‐05
3.3. Development of capacity‐building programs 35 days Tue Mon
20‐06‐09 20‐07‐27