ID Task Name Duration Start Finish Successors Resource Remark November 21 September 1 June 11

Mode Names 2/6 6/26 11/13 4/1


1 Extension of Time 81.38 days Fri 6/30/23 Sat 9/30/23 It's laps due to rain. 133 days

2 Apron work complete Remain 24.5 days Mon 9/18/23 Sun 10/15/23 119.88 days
pqc only
3 Remain Area of Apron develop 21 days? Wed 9/20/23 Fri 10/13/23 PQC workers will be available at site " priority 121.63 days?
basis".
4 Delta taxi Area-30*120 sqr mtr 79.63 days Mon 10/2/23 Sun 12/31/23 52.5 days

5 Remain Area of Delta taxi Area 109.38 days? Sat 10/28/23 Thu 2/29/24

6 Earth work 12.25 days Mon 10/2/23 Sun 10/15/23 7 5.25 days

7 GSB laying 6.13 days Sun 10/22/23 Sat 10/28/23 8 0.88 days

8 WMM laying 11.38 days Mon 10/30/23 Sat 11/11/23 96.25 days

9 DRLC 9.63 days Mon 11/20/23 Thu 11/30/23 79.63 days

10 PQC with all finishing work 42 days Mon 12/4/23 Sat 1/20/24 35 days

11 Drain work 29.75 days Sat 10/28/23 Thu 11/30/23 79.63 days

12 Electrical work 39.38 days Tue 1/16/24 Thu 2/29/24

Task Summary External Milestone Duration-only Deadline


Split Project Summary Inactive Task Manual Summary Rollup Critical
Milestone Rolled Up Critical Inactive Milestone Manual Summary Critical Split
Slack Rolled Up Critical Split Inactive Summary Start-only Progress
Slippage External Tasks Manual Task Finish-only

You might also like