2 Apron work complete Remain 24.5 days Mon 9/18/23 Sun 10/15/23 119.88 days
pqc only
3 Remain Area of Apron develop 21 days? Wed 9/20/23 Fri 10/13/23 PQC workers will be available at site " priority 121.63 days?
basis".
4 Delta taxi Area-30*120 sqr mtr 79.63 days Mon 10/2/23 Sun 12/31/23 52.5 days
5 Remain Area of Delta taxi Area 109.38 days? Sat 10/28/23 Thu 2/29/24
6 Earth work 12.25 days Mon 10/2/23 Sun 10/15/23 7 5.25 days
7 GSB laying 6.13 days Sun 10/22/23 Sat 10/28/23 8 0.88 days
8 WMM laying 11.38 days Mon 10/30/23 Sat 11/11/23 96.25 days
10 PQC with all finishing work 42 days Mon 12/4/23 Sat 1/20/24 35 days
11 Drain work 29.75 days Sat 10/28/23 Thu 11/30/23 79.63 days