UTILIZATION OF THE 20% COMPONENT OF IRA FOR DEVELOPMENT PROJECTS 2nd QUARTER, CY 2020
SANTA RITA PAMPANGA
Project Status
Project Status
No. of
Target Extensions,
Completion % of Total Cost if any
Program or Project Location Total Cost Date Started Date Completion Incurred to Date Remarks
Improvement of FMR @ Zone 1
h. going to Dayat, Sta. Monica SANTA RITA PAMPANGA Realigned
Repair/Backfilling/Concreting of
Various Local Streets, Alleys,
Pathways, Canals and Box Culvert in
the Municipality SANTA RITA PAMPANGA Realigned
Community Developments Programs
to Different Barangays SANTA RITA PAMPANGA 800,000.00 January 2020 December 2020 100% 800,000.00
Other Infrastructure Projects SANTA RITA PAMPANGA Realigned
Environmental Management Programs
Solid Waste Mangement
Beautification, Clean & Green
a. Program and ECO Park Maintenance SANTA RITA PAMPANGA 3,000,000.00 January 2020 December 2020 15.14% 454,179.53
PURCHASE OF RICE/PALAY,
SUPPLIES, COMMODITIES AND
OTHER NECSESSARY COVID-19
RELATED PPAS AND EXPENSES
SANTA RITA PAMPANGA 17,312,315.80 April 2020 December 2020 44.24% 7,659,794.08 New Program
TOTAL 23,612,315.80 9,086,170.11