ENGINEERING, PROCUREMENT AND CONSTRUCTION(EPC) WORKS AND SERVICES FO

SPC-JIMT Project

Weekly Plan for Test and precommissioning Activities


UPDATED: 06-Mar-2018

No Description of works Discipline Area

1 hydraulic test for fire water main ring Mechanic

2 hydraulic test for Foam main ring Mechanic

3 hydraulic test for Fire water Tank inlet piping Mechanic

hydraulic test for Fire water pump inlet


4 Mechanic
piping
hydraulic test for Fire water Pump Outlet
5 Mechanic
piping

6 Water Flushing for fire water main ring Mechanic

7 Water Flushing for Foam main ring Mechanic

Water Flushing for Fire water pump inlet


8 Mechanic Fire water Tank
piping
Water Flushing for Fire water Pump Outlet
9 Mechanic Fire water Tank
piping

10 Fire water tank box up Mechanic Fire water Tank

11 Water Inject to Fire water Tank Mechanic Fire water Tank

Diesel inject to Daily Tank of Fire water


12 Mechanic Fire water pump
pump

Vendor CMA site Pre-inspection(including


13 FW pump, MAP, SAP, Fire alarm panel, call Electrical Whole site
point, smoke and heat detector, sirens.

Insulation check and wiring check for all the


14 Electrical Whole site
electrical power cable and signal cable

15 Substation LV power on Electrical Substation


Turn on power the fire water pump
16 Electrical Fire water pump
witnessed by CMA

1 of 3
CTION(EPC) WORKS AND SERVICES FOR JURONG ISLAND MARKETING TERMINAL PROJECT, SINGAPO

Plan Start Plan End Act End

2018/2/26 2018/2/26

2018/3/1 2018/3/1

2018/2/27 2018/2/27

2018/2/27 2018/2/27

2018/3/2 2018/3/2

2018/2/26 2018/2/28

2018/3/1 2018/3/2

2018/3/2 2018/3/3

2018/3/2 2018/3/3

2018/2/28 2018/2/28

2018/3/2 2018/3/2

2018/3/4 2018/3/4

2018/3/1 2018/3/1

2018/3/1 2018/3/13

2018/3/5 2018/3/5 2018/3/5

2018/3/5 2018/3/5 2018/3/5

2 of 3
NG ISLAND MARKETING TERMINAL PROJECT, SINGAPORE

Remark

Completion

Completion

Completion

Completion

Completion

Inter flushing was completed, RFI for


inspection on 7th March 2018
Inter flushing was completed, RFI for
inspection on 7th March 2018
Inter flushing was completed, RFI for
inspection on 7th March 2018
Inter flushing was completed, RFI for
inspection on 7th March 2018

Completion

1/2 water was input into T61 and T62

Completion

in progress

in progress

Completion

Completion