Finalization of vendor for procurement of Substation Equipment and subsequently submission of Drawing 5B

Type test Type Test


Order GTP/Drawing Submission
Sl Item Description Name of Vendor GTP/Drg Status done / submission TT Status Remarks
Status Date
extended date
33 KV Sub Station Work
1 2.5 MVA 33/11 kV Transformer Vijai Electricals Done 12/15/2021 Approved in CAT-I UNDER STAGE INSPECTION
2 100 KVA, 33 kV/0.415kv station Trf Vijai Electricals Done 12/15/2021 Approved in CAT-I UNDER STAGE INSPECTION
3 11 Mtr, Galvanised, STP Not Applicable
4 33kV, 1250A VCB CG Power 3/15/2022 DRG APPROVED,GTP SFR to be extended
33KV DBCR Isolator (Without Earth
5 Ultima Done 12/30/2021 APPROVED extended APPROVED
Switch)
6 33KV DBCR Isolator (With Earth Switch) Ultima Done 12/30/2021 APPROVED extended APPROVED
7 33kV, 1 phase CT Vishal Transformer Done 1/25/2022 APPROVED extended APPROVED
8 33kV, 1 phase PT Vishal Transformer Done 1/25/2022 APPROVED extended APPROVED
9 33kV, Bus Post Insulator Bikaner Ceramics Done 1/30/2022 APPROVED extended APPROVED
10 45kV, Bus Post Insulator extended
11 30 KV, 1 phase, 10 KA LA Lamco Done 1/30/2022 APPROVED extended APPROVED
12 9 KV, 1 phase, 10 KA LA Lamco Done 1/30/2022 APPROVED extended APPROVED
13 STP (E410C) 12 mts SKIPPER Done 11/30/2021 UPLOADED extended
STP (E410C) 12 mts Utkarsh Done UPLOADED extended
Galvanised fabricated structure for 33 kV
14 KSE Done 4/15/2022
bus & Line Gantry
Galvanised fabricated structure for 33 kV
15 KSE Done 4/15/2022
bus & Line Gantry-Grade 'C'
Galvanised fabricated structure for DP,
16 KSE Done 4/15/2022 ISOLATOR AND BPI SUBMITTED
LA, BPI, etc.
Galvanised fabricated structure for DP,
17 KSE Done 4/15/2022
LA, BPI, etc. -Grade 'C'
18 Nut & bolts, foundation bolts and washer under Finalization 4/15/2022

70 KN B&S disc insulator (4 nos disc STAGE 1 UNDER


19 Bikaner Ceramics Done 1/30/2022 APPROVED 4/1/2022
insulator) PROCESS

Hardware & Accessories for 70 KN B&S


20 Jainco Done 1/25/2022 APPROVED extended APPROVED
disc insulator (4 nos disc insulator)
21 75 x 8 mm MS flat for earth mat KSE Done 1/15/2022 APPROVED
22 60 x 8 mm galvanised flat for raiser KSE Done 1/15/2022 APPROVED
40 mm dia 3000 mm long GI pipe for
23 KSE Done 1/15/2022 sent for revision
treated earthing
40 mm dia long MS rod (To be used for
24 KSE Done 1/15/2022 APPROVED extended APPROVED
deep earthing in drilled holes)
25 33KV C&R Panel for 2.5MVA Transformer Popular Switchgears Done 3/15/2022 SUBMITTED
26 33KV C&R Panel for 33KV Line Popular Switchgears Done 3/15/2022 SUBMITTED
11 kV, 630 Amp C&R Cum VCB Panel for
27 Pascal 3/18/2022 SUBMITTED
incoming 11 kV feeder
11 kV, 630 Amp C&R Cum VCB Panel for
28 Pascal 3/18/2022 SUBMITTED
Outgoing 11 kV feeder

33 KV Substation_Supply Page 1
Finalization of vendor for procurement of Substation Equipment and subsequently submission of Drawing 5B
Type test Type Test
Order GTP/Drawing Submission
Sl Item Description Name of Vendor GTP/Drg Status done / submission TT Status Remarks
Status Date
extended date
33 KV Sub Station Work
11 kV, 630 Amp C&R Cum VCB Panel for
29 Pascal 3/18/2022 SUBMITTED
11KV Bus-Coupler
30 24 V, 80AH, Ni-Cd sealed Battery under Finalization 4/15/2022
31 Battery Charger alongwith DCDB under Finalization 4/15/2022
32 415V AC Distribution board under Finalization 4/15/2022
33 Bay marshelling Kiosk under Finalization 4/15/2022
34 11 kV, XLPE, 3Cx400 sq mm under Finalization 4/15/2022
35 11 kV, XLPE, 3Cx120 sq mm under Finalization 4/15/2022
11kV, Indoor End termination kit for
36 under Finalization 4/15/2022
3Cx400 mm2
11kV, Indoor End termination kit for
37 under Finalization 4/15/2022
3Cx120 mm2
11kV, Outdoor End termination kit for
38 under Finalization 4/15/2022
3Cx120 mm2
1.1kV, 3.5Cx50 Sq.mm PVC Insulated
39 under Finalization 4/15/2022
Armored cable
1.1KV, 4Cx10 Sq.mm PVC Insulated
40 under Finalization 4/15/2022
Armored Cable
1.1KV, 2Cx10 Sq.mm PVC Insulated
41 under Finalization 4/15/2022
Armored Cable
1.1KV, 2Cx2.5 Sq.mm PVC Insulated
42 under Finalization 4/15/2022
Armored Cable
1.1KV, 5Cx2.5 Sq.mm PVC Insulated
43 under Finalization 4/15/2022
Armored Cable
1.1KV, 10Cx2.5 Sq.mm PVC Insulated
44 under Finalization 4/15/2022
Armored Cable
1.1KV, 12Cx2.5 Sq.mm PVC Insulated
45 under Finalization 4/15/2022
Armored Cable
46 Lighting System-Switchyard under Finalization 4/15/2022
47 Lighting System-Control Room under Finalization 4/15/2022
Clamp & Connector for 02 Trf 01 33 kV
48 under Finalization 4/15/2022
line Bay
Clamp & Connector for 02 Trf 03 33 kV
49 under Finalization 4/15/2022
line Bay
Clamp & Connector for 01 line bay in
50 under Finalization 4/15/2022
existing S/s
51 33KV, AB Switch for Station Transformer Ultima 4/15/2022 APPROVED APPROVED
52 33KV, HG Fuse for Station Transformer Ultima Done 1/25/2022 APPROVED APPROVED
53 11KV, AB Switch for Outgoing DP Hightension Done 1/25/2022 APPROVED APPROVED
54 ACSR Wolf Conductor Laser Done 1/25/2022 APPROVED APPROVED
55 Digital IR Tester (2kV-5kV) under Finalization 4/15/2022
56 Digital multimeter under Finalization 4/15/2022
57 Earth resistance tester under Finalization 4/15/2022

33 KV Substation_Supply Page 2
Finalization of vendor for procurement of Substation Equipment and subsequently submission of Drawing 5B
Type test Type Test
Order GTP/Drawing Submission
Sl Item Description Name of Vendor GTP/Drg Status done / submission TT Status Remarks
Status Date
extended date
33 KV Sub Station Work
Stainless Steel Oil sampling bottle (One
58 under Finalization 4/15/2022
Litre Capacity)
59 11 kV Discharge Rod(1 set of 3 rods) under Finalization 4/15/2022
60 Battery Voltage Tester under Finalization 4/15/2022
61 33 kV Discharge Rod (1 set of 3 rods) under Finalization 4/15/2022
Supply of Oil Filtration machine with
62 under Finalization 4/15/2022
filtration capacity of 4K litre per hour
Dry Chemical Powder type extinguisher (6
63 under Finalization 4/15/2022
Kg)
64 CO2 Type of 4.5Kg extinguisher under Finalization 4/15/2022
65 CO2 Trolly Mounted of 22.5 Kg under Finalization 4/15/2022

33 KV Substation_Supply Page 3
Finalization of vendor for procurement of 33KV Line Material and subsequently submission of Drawing 5B
Type test done / Type Test
Sl Item Description Name of Vendor Order Status GTP/Drawing Submission Date Status TT Status Remarks
extended submission date

33 kV Line

1 ACSR Racoon conductor Laser Done 1/15/2022 Approved in CAT-I APPROVED

2 STP (E410C) 12 mts (Single Part) SKIPPER Done 11/30/2021 Approved in CAT-I extended

STP (E410C) 12 mts (Double Part) SKIPPER Done Drawing Approved in CAT-1; GTP submitted extended

3 STP (E410C) 12 mts (Single Part) Utkarsh Done 11/30/2021 Approved in CAT-I extended

STP (E410C) 12 mts (Double Part) Utkarsh Done Approved in CAT-I extended

4 STP (E410C) 14.5 mts. SKIPPER Done 11/30/2021 GTP Approved in CAT-I, Drawing under revision extended

5 STP (E410C) 14.5 mts. Utkarsh Done 11/30/2021 Approved in CAT-I extended

6 33 kV pin Insulator Bikaner Ceramics Done 1/30/2022 Approved in CAT-I 4/4/2022

7 33 kV, 10 KN Pin, nut and washers KSE Done 12/30/2021 Approved in CAT-I extended APPROVED

8 70 KN B&S disc insulator (3 nos disc insulator) Bikaner Ceramics Done 1/30/2022 Approved in CAT-I APPROVED

Hardware & Accessories for 70 KN B&S disc insulator (3


9 KSE Done 12/30/2021 Approved in CAT-I extended APPROVED
nos disc insulator)

10 70 KN B&S disc insulator (4 nos disc insulator) Bikaner Ceramics Done 1/30/2022 Approved in CAT-I APPROVED

Hardware & Accessories for 70 KN B&S disc insulator (4


11 KSE Done Approved in CAT-I APPROVED
nos disc insulator)
Preformed insulator bindings (suitable for ACSR
12 KSE Done 12/30/2021 Approved in CAT-I extended APPROVED
conductor) for 33 kV pin insulator

13 Guy Strain Insulators designation 'C' Bikaner Ceramics Done 1/30/2022 Approved in CAT-I extended APPROVED

14 Stay wire (7/8 SWG) UIC Done 1/30/2022 sent for revision

15 8 SWG GI for guarding, lacing & earthing UIC Done 1/30/2022 sent for revision

16 40 mm dia 3000 mm long GI pipe KSE Done 12/30/2021 SUBMITTED extended

17 Hardware fittings for 33KV stay Set KSE Done 12/30/2021 Approved in CAT-I extended

18 Stay wire (7/10 SWG)

33 kV Line_Supply Page 1
Finalization of vendor for procurement of 66KV Line Material and subsequently submission of Drawing 5B
Type test done / Type Test submission
Sl Item Description Name of Vendor GTP/Drawing Submission date TTR Status Remarks
extended date

66 kV Line

1 Galvanised Items for Tower Parts (HT & MS) 4/15/2022

2 Galvenised Items for Stub (HT & MS) 4/15/2022

3 Galvenised N&B for Stub 4/15/2022

4 Galvenised N&B for Tower Parts 4/15/2022

5 Earthing of Tower (Counter Poise type) 4/15/2022

6 Danger Plate APPROVED EXTENDED

7 Number Plate APPROVED EXTENDED


KSE

8 Phase Plate (Set of 03) APPROVED EXTENDED

9 ACSR DOG Conductor APPROVED EXTENDED

10 45kN Composite Long Rod Insulator YET TO SUBMIT

11 Single Tension Insulator String submitted

12 Midspan Compression Joint APPROVED EXTENDED

13 Repair Sleeves APPROVED EXTENDED

14 Vibration Damper APPROVED EXTENDED

66 kV Line _Supply Page 1


Finalization of vendor for procurement of OPGW Equipment and subsequently submission of Drawing 5B
Type test done / Type Test submission
Sl Item Description Name of Vendor GTP/Drawing Submission Date TT Status Remarks
extended date
OPGW Works

1 OPGW-24 Fibre (DWSM) 4/15/2022

2 Hardware & Accessories - 24 Fibre (Suspension Assembly) 4/15/2022


Hardware & Accessories - 24 Fibre (Tension Assembly:
3 4/15/2022
Dead End, Pass Through, Joint Box)
Hardware & Accessories - 24 Fibre (Tension Assembly at
4 4/15/2022
suspension Tower for joint Box)
5 Hardware & Accessories - 24 Fibre (Vibration Damper) 4/15/2022

6 Hardware & Accessories - 24 Fibre (Down Lead Clamp) 4/15/2022

7 Aerial FO Cable 24F (DWSM) 4/15/2022


Hardware Fittings & Accesories- Aerial FO Cable 24F

Vendor Finalization under various stages.


8 4/15/2022
(DWSM)
9 UG FO Cable - 24 DWSM 4/15/2022

10 PLB HDPE Pipe - OD 40mm 4/15/2022

11 FODP-48F 4/15/2022

12 FODP-96F 4/15/2022

13 Approach Cable-24F (DWSM) 4/15/2022

14 Approach Cable Installation Document 4/15/2022

15 BOM

Bill of Material of SDH 4/15/2022

Optical Link Budget calculation 4/15/2022

Bill of Material of PDH 4/15/2022

Bill of Material of DCPS and Battery Bank 4/15/2022

Bill of Material of NMS 4/15/2022

Bill of Material of Spares 4/15/2022

Bill of Material of test Equipment 4/15/2022

Bill of Material of GPS clock and equipment cabinet 4/15/2022

Bill of Material of SDH 4/15/2022