SAFETY FENCE AT PHOSPHATE LINE Classic Schedule Layout 29-Sep-17 16:42

Activity Name Start Finish Original 2017


Duration Oct 22 Oct 29 Nov 05 Nov 12
S M T W T Fri S S M T W T Fri S S M T W T Fri S S M T W T Fri
JN 341 SAFETY FENCE PHOSPHATE LINE 23-Oct-17 09-Nov-17 18

JN 341.1 PREPERATION 23-Oct-17 25-Oct-17 3


Document Preperation 23-Oct-17 23-Oct-17 1 Document Preperation
Material Preperation 23-Oct-17 25-Oct-17 3 Material Preperation
Tools and Equipment Preperation 23-Oct-17 23-Oct-17 1 Tools and Equipment Preperation
Mobilization of Tools,Equipment, and Worker 23-Oct-17 23-Oct-17 1 Mobilization of Tools,Equipment, and Worker
JN 341.2 FABRICATION AND INSTALLATION 26-Oct-17 09-Nov-17 15

JN 341.2.1 Fabrication 26-Oct-17 06-Nov-17 12


JN 341.2.1.1 New Fabrication (Fence and Platform) 26-Oct-17 06-Nov-17 8
Marking/Cutting 26-Oct-17 26-Oct-17 1 Marking/Cutting
Fit-up and Inspection 27-Oct-17 27-Oct-17 1 Fit-up and Inspection
Welding and Inspection 30-Oct-17 30-Oct-17 1 Welding and Inspection
Galvanizing and Painting 31-Oct-17 06-Nov-17 5 Galvanizing and Painting
JN 341.2.1.2 Modification (fence) 27-Oct-17 06-Nov-17 11
Dismantling Existing fence 27-Oct-17 27-Oct-17 1 Dismantling Existing fence
Repair (Cutting, Fit-up and Welding) 30-Oct-17 03-Nov-17 5 Repair (Cutting, Fit-up and Welding)
Painting 06-Nov-17 06-Nov-17 1 Painting
JN 341.2.2 Installation (Fence and Platform) 07-Nov-17 09-Nov-17 3
Installation New Fence 07-Nov-17 09-Nov-17 3 Installation New Fence
Installation Platform 07-Nov-17 09-Nov-17 3 Installation Platform
Reinstall Fance modification 07-Nov-17 09-Nov-17 3 Reinstall Fance modification

Remaining Labor Units


10

0
S M T W T Fri S S M T W T Fri S S M T W T Fri S S M T W T Fri
Oct 22 Oct 29 Nov 05 Nov 12
2017

Actual Level of Effort Remaining Work Page 1 of 1 TASK filter: All Activities
Actual Work Critical Remain... © Oracle Corporation