Professional Documents
Culture Documents
Page 1
1 Earned Value (EV) - Definition 3 Earned Value Management (EVM) - Definition
Measure of the value of work performed so far, also called the
budgeted cost of work performed (BCWP). The “value” of the work A project progress control system that integrates work scope,
earned at the date of analysis (data date).1 schedule, and resources to enable objective comparison of the earned
1- AACE International
value to the actual cost and the planned schedule of the project.1
2 Example 01 1- AACE International
Scope: To build 6 houses 4 EVM Terms
Deadline: 6 months.
System Description Meaning
Budget per house : $ 10,000 Terms
1000
CV = 750 – 1228 = - 478
SV CV
500
CPI = 750 / 1228 = 0,61