TANJUNG AWAR AWAR COAL SHED PROJECT EXECUTION PLAN

2014 2015
No
OCT NOV DEC JAN FEB MARAPR MAY JUN JUL AUG
1 ENGINEERING DRAWINGS
2 MOBILIZATION AND PREPARING REQUIRED PERMIT
3 FABRICATION AREA SITE CLEARING & PREPARATION

SITE TEMPORARY FACILITIES PREPARATION (OFFICE,


4
WAREHOUSE,CANTEEN, FABRICATION WORK SHOP,ETC)

5 APPOINT SOIL INVESTIGATION THIRD PARTHY


6 SOIL INVESTIGATION WORK
7 ISSUED PO FOR PILING
ISSUED CONTRACT FOR SOIL BORING AND PILING
8
CONTRACTOR
9 BORING AND PILING WORK
10 FOUNDATION WORK
10 PROCUREMENT OF PIPING MATERIAL
11 GALVANIZING
12 DELIVERY PIPING MATERIAL TO SITE
13 RAFTER AND GORDING FABRICATION
13 RAFTER AND GORDING ERECTION
14 ERECTION OF ROOF
15 INSTALATION OF SKY LIGHT AND LIGHTENING PROTECTION
Remarks

FINISHED
Oct 17, '14
Oct 20 -Oct 27, '14

Oct 27 - Nov 10, '14


Oct 20,'14
Oct 20 - Nov 20, 14
Oct 20,'14

Nov 3,'14
Nov 10 - Dec 10, 2014
Nov 17 - Dec 17, 2014
Oct 20 - Nov 20, 14
Oct 27 - Nov 27, '14
Nov 3 - Dec 3, '14
Nov 10, '14 - March 10, '15
Tgl 15 jan' Erection 3 Row mulai Portal H JAN 13 - MAY 13,'15
May 1 - June 30 '15

May 15 - June 30 '15