You are on page 1of 3

Cement mix for finishing and gradient

1. Put the P.E sheet of ply wood prior to mix the cement on the ground
2. Mix the cement with water and sand and stir with shovel and hoe until acceptance level
3. Use a bucket or wheel barrow to carry the mix cement to designated area
4. Pour the cement and use shovel to distribute and use trowel to level it.
5. Keep the cement dry and cover with canvas if require

Job hazard analysis


Miscommunication S Undeliverable task - Conduct TBT & Pre-task briefing prior to Project Engineer - Stop work
Sika/Cement mix work. Site Supervisor - Re-arrange the
and leveling - Site supervisor need to proper brief and SSS work according
explain to workers Workers to Terminal
Transfer sand and - Obtain PTW prior to start work Authority
sika bag - PTW Applicant, SSS and Site Supervisor shall requirement.
visit the work site to familiarize themselves
with the area and any potential issues.

- Remove all materials from access way Site Supervisor - Stop work
Slippery surface S Body injury - Do proper housekeeping/collect all un-used SSS - Apply first aid
materials to temporary storage area All Workers - Report incident
- Wear good condition safety shoes to terminal
personnel/TOS
- Seek medical if
necessary
Manual handling S Muscle strains - Correct body posture and do not over Site Supervisor - Stop work
stretch. SSS - Apply first aid
- do not exceed safe working load 20kg/person All Workers - Report incident
- apply buddy system if load more than 20kg to terminal
or difficult to handle alone personnel/TOS
- Wear semi-rubber glove. - Seek medical if
necessary
Excessive heat H - Dehydration - Drink plenty of water Project Engineer - Stop work
- Heat stroke - Apply first aid
- Tiredness Site Supervisor - Report incident
- Get a rest enough to terminal
SSS
personnel/TOS
Workers Seek medical if
necessary

Concrete dust H Toxic fumes/dust - Wear proper gloves (semi coated) Site Supervisor - Stop work
inhalation and breathing - Safety glass protection - Cleaning the
- Wear proper dust mask (N95) sss chemical
system defect
- Work in ventilated areas to avoid dust affected area
All Workers
- Dilute the expose cement with water
Lorry movement S Collision - Using pedestrian walkway Site Supervisor - Stop work
a) Beware and alert with truck movement SSS - Apply first aid
- Ensure barricade working area and safety All Workers - Seek medical if
sign in place necessary
- Report incident
to terminal
personnel/TOS
via talkie channel
2
- - MCP zone 18 BG
21
-

You might also like