Bangladesh, Matarbari

2 x 600MW Coal Fired Power Plant Project

SECTION – 8

ERECTION SCHEDULE
Coal Power Generation Company Bangladesh Limited (CPGCBL)

Erection Schedule for Site Fabrication Tanks


ID Task Name Duration Start Finish 22 23
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan
M44 M45 M46 M47 M48 M49 M50 M51 M52 M53 M54 M55 M56 M57 M58 M59 M60 M61 M62 M63 M64 M65 M66
1 Project Key Milestone 2524days 2017/08/22 2024/07/20
2 Power Plant Unit 1 & Common 2341days 2017/08/22 2024/01/19
3 Notice to Proceed (NTP) 0days 2017/08/22 2017/08/22
4 Power Plant Construction Work Start 0days 2020/05/22 2020/05/22
5 Ready for Erection Work 0days 2021/05/21 2021/05/21 05/21 Ready for Erection Work

6 Boiler Hydro Test (Unit 1) 0days 2022/09/22 2022/09/22 09/22 Boiler Hydro Test (Unit 1)

7 Back Energization (Unit 1) 0days 2022/10/22 2022/10/22 10/22 Back Energization (Unit 1)

8 Initial Oil Firing (Unit 1) 0days 2023/04/22 2023/04/22


9 Initial Steam Admission (Unit 1) 0days 2023/05/22 2023/05/22
10 Initial Synchronization (Unit 1) 0days 2023/06/06 2023/06/06
11 Initial Coal Firing (Unit 1) 0days 2023/06/22 2023/06/22
12 TOC (PAC) Unit 1 0days 2024/01/19 2024/01/19
13 Power Plant Unit 2 486days 2023/03/22 2024/07/20
14 Boiler Hydro Test (Unit 2) 0days 2023/03/22 2023/03/22
15 Back Energization (Unit 2) 0days 2023/04/22 2023/04/22
16 Initial Oil Firing (Unit 2) 0days 2023/10/22 2023/10/22
17 Initial Steam Admission (Unit 2) 0days 2023/11/22 2023/11/22
18 Initial Synchronization (Unit 2) 0days 2023/12/07 2023/12/07
19 Initial Coal Firing (Unit 2) 0days 2023/12/24 2023/12/24
20 TOC (PAC) Unit 2 0days 2024/07/20 2024/07/20
30 Consortium Interface Milestone 365days 2022/06/22 2023/06/22
31 Unit 1 365days 2022/06/22 2023/06/22
32 Fire Fighting Wate Available for WTP Commissioning 0days 2022/06/22 2022/06/22 06/22 Fire Fighting Wate Available for WTP Commissioning

33 Availability of Waste Water Treatment Plant for Hydro Test 0days 2022/09/05 2022/09/05 09/05 Availability of Waste Water Treatment Plant for Hydro Test

35 Main Cooling Water Available for CCCW System 0days 2022/09/28 2022/09/28 09/28 Main Cooling Water Available for CCCW System

37 Commissioning Power Available 0days 2022/10/28 2022/10/28 10/28 Commissioning Power Available

38 Cooling Water System In Service (Unit #1) 0days 2022/11/04 2022/11/04 11/04 Cooling Water System In Service (Unit #1)

39 Available of CCCW Supply for Boiler Area (Unit #1) 0days 2022/11/04 2022/11/04 11/04 Available of CCCW Supply for Boiler Area (Unit

52 Unit 1 & Common 2234days? 2017/08/22 2023/10/03


53 Balance of Plant inc 400kV GIS (Sumitomo TPSC Scope of Works) 2234days? 2017/08/22 2023/10/03
139 Fuel and Ash Handling System 2124days? 2017/08/22 2023/06/15
148 High Speed Diesel (HSD) Oil System 1995days? 2017/08/22 2023/02/06
159 HSD Storage Tank & Forwarding Pump 589days 2021/06/21 2023/01/31
160 Construction 489days 2021/06/21 2022/10/22
161 HSD Storage Tank & Forwarding Pump : Civil Partial Handover (C Tank Foundation) 0days 2021/06/21 2021/06/21 06/21 HSD Storage Tank & Forwarding Pump : Civil Partial Handover (C Tank Foundation)

162 HSD Storage Tank & Forwarding Pump : M&E Work (C Tank) 210days 2021/06/21 2022/01/16 HSD Storage Tank & Forwarding Pump : M&E Work (C Tank)

163 HSD Storage Tank & Forwarding Pump : Civil Partial Handover (A Tank Foundation) 0days 2021/07/21 2021/07/21 07/21 HSD Storage Tank & Forwarding Pump : Civil Partial Handover (A Tank Foundation)

164 HSD Storage Tank & Forwarding Pump : M&E Work (A Tank) 210days 2021/07/21 2022/02/15 HSD Storage Tank & Forwarding Pump : M&E Work (A Tank)

165 HSD Storage Tank & Forwarding Pump : Civil Partial Handover (D Tank Foundation) 0days 2021/08/21 2021/08/21 08/21 HSD Storage Tank & Forwarding Pump : Civil Partial Handover (D Tank Foundation)

166 HSD Storage Tank & Forwarding Pump : M&E Work (D Tank) 210days 2021/08/21 2022/03/18 HSD Storage Tank & Forwarding Pump : M&E Work (D Tank)

167 HSD Storage Tank & Forwarding Pump : Civil Partial Handover (B Tank Foundation) 0days 2021/09/21 2021/09/21 09/21 HSD Storage Tank & Forwarding Pump : Civil Partial Handover (B Tank Foundation)

168 HSD Storage Tank & Forwarding Pump : M&E Work (B Tank) 210days 2021/09/21 2022/04/18 HSD Storage Tank & Forwarding Pump : M&E Work (B Tank)

352 Water Treatment Plant and Waste Water Treatment System 1910days 2017/08/22 2022/11/13
371 Water Treatment Plant 548days 2021/04/06 2022/10/06
372 Construction 441days 2021/04/06 2022/06/21
393 Water Tanks 295days 2021/08/31 2022/06/21
394 Service Cum Fire Water Storage Tank 181days 2021/08/31 2022/02/27
395 Service Cum Fire Water Storage Tank : Civil Full Handover 0days 2021/08/31 2021/08/31 08/31 Service Cum Fire Water Storage Tank : Civil Full Handover

396 Service Cum Fire Water Storage Tank : M&E Work 180days 2021/09/01 2022/02/27 Service Cum Fire Water Storage Tank : M&E Work

397 Service Cum Fire Water Storaget Tank : MC 0days 2022/02/27 2022/02/27 02/27 Service Cum Fire Water Storaget Tank : MC

398 Deminralized Water Storage Tank 150days 2021/10/31 2022/03/29


399 Demineralized Water Storage Tank : Civil Full Handover 0days 2021/10/31 2021/10/31 10/31 Demineralized Water Storage Tank : Civil Full Handover

400 Demineralized Water Storage Tank A & B : M&E Work ( 2 tanks) 150days 2021/10/31 2022/03/29 Demineralized Water Storage Tank A & B : M&E Work ( 2 tanks)

401 Demineralized Water Storaget Tank : MC 0days 2022/03/29 2022/03/29 03/29 Demineralized Water Storaget Tank : MC

402 Potable Water Storage Tank 151days 2021/08/31 2022/01/28


403 Potable Water Storage Tank : Civil Full Handover 0days 2021/08/31 2021/08/31 08/31 Potable Water Storage Tank : Civil Full Handover

404 Potable Water Storage Tank A & B : M&E Work (2 tanks) 150days 2021/09/01 2022/01/28 Potable Water Storage Tank A & B : M&E Work (2 tanks)

405 Potable Water Storaget Tank : MC 0days 2022/01/28 2022/01/28 01/28 Potable Water Storaget Tank : MC

406 Cold Condensate Storage Tank 121days 2022/02/21 2022/06/21


407 Cold Condensate Storage Tank : Civil Full Handover 0days 2022/02/21 2022/02/21 02/21 Cold Condensate Storage Tank : Civil Full Handover

408 Cold Condensate Storage Tank : M&E Work (Unit 1) 120days 2022/02/22 2022/06/21 Cold Condensate Storage Tank : M&E Work (Unit 1)

409 Cold Condensate Storaget Tank : MC 0days 2022/06/21 2022/06/21 06/21 Cold Condensate Storaget Tank : MC

1189 Unit 2 2264days? 2017/08/22 2023/11/02


1190 Balance of Plant inc 400kV GIS (Sumitomo TPSC Scope of Works) 2264days? 2017/08/22 2023/11/02
1291 Water Treatment Plant and Waste Water Treatment System 279days 2022/08/21 2023/05/26
1301 Condensate Water Storage Tank Unit 2 211days 2022/08/21 2023/03/19
1302 Construction 121days 2022/08/21 2022/12/19
1303 Cold Condensate Storage Tank : Civil Full Handover 0days 2022/08/21 2022/08/21 08/21 Cold Condensate Storage Tank : Civil Full Handover

1304 Cold Condensate Storage Tank : M&E Work (Unit 2) 120days 2022/08/22 2022/12/19 Cold Condensate Stora

1305 Cold Condensate Storaget Tank : MC 0days 2022/12/19 2022/12/19 12/19 Cold Condensate Stor