Cement Mill 1 Planned Stoppage

ID Asset Code Description Departemnt Duration % Start Finish


Complete Jan 21, '23 Jan 28, '23
S M T W T F S
1 Production Activities 144 hrs 0% Sun 1/22/23 Sat 1/28/23
2 4611BM1 Cut Feed Production 0 hrs 100% Sun 1/22/23 Sun 1/22/23 1/22
3 4611BM1 Start Feed Production 0 hrs 0% Sun 1/29/23 Sun 1/29/23 1
4 Safety Activities 144 hrs 50% Sun 1/22/23 Sat 1/28/23
5 Energy Isolation Electrical 1 hr 100% Sun 1/22/23 Sun 1/22/23
6 Energy De-isolation Electrical 1 hr 0% Sat 1/28/23 Sat 1/28/23
7 Mechanical Activities 144 hrs 93% Sun 1/22/23 Sat 1/28/23
8 4221BE1 Repair cracked buckets by welding Mechanical 2 days 50% Thu 1/26/23 Sat 1/28/23
9 4415BC1 Seal feeding chutes Mechanical 4 hrs 100% Thu 1/26/23 Thu 1/26/23
10 4415BC1 Repair stepped chute Mechanical 1 hr 0% Thu 1/26/23 Thu 1/26/23
11 4415BC1 open feeding chutes inspection doors Mechanical 3 hrs 100% Thu 1/26/23 Thu 1/26/23
12 4415BC1 Change side skirts Mechanical 1 hr 100% Thu 1/26/23 Thu 1/26/23
13 4415BC1 Install return skirt at drive drum Mechanical 1 hr 100% Thu 1/26/23 Thu 1/26/23
14 4415SX1 Install scrapper chain Mechanical 4 hrs 65% Thu 1/26/23 Thu 1/26/23
15 4611MD1 Open Main drive bearings for inspection Mechanical 8 hrs 50% Wed 1/25/23 Wed 1/25/23
16 4611MD1 Change oil seals for inboard bearing Mechanical 2 hrs 0% Thu 1/26/23 Thu 1/26/23
17 4611BM1 Open mill for inspection Mechanical 2 hrs 100% Sun 1/22/23 Sun 1/22/23
18 461BM1 open mill discharge chute Mechanical 1 hr 100% Tue 1/24/23 Tue 1/24/23
19 4611BM1 Change air hose for outlet water injection system
Mechanical 3 hrs 0% Sat 1/28/23 Sat 1/28/23
20 461BM1 open shoe bearings inspection doors Mechanical 4 hrs 100% Thu 1/26/23 Thu 1/26/23
21 4612SR1 Adjusting seal air gap for the separator Mechanical 3 days 100% Sun 1/22/23 Wed 1/25/23
22 4612SR1 Change LSS seal for separator gearbox Mechanical 3 days 100% Sun 1/22/23 Wed 1/25/23
23 4612SR1 open separator inspection door Mechanical 1 hr 100% Sun 1/22/23 Sun 1/22/23
24 4615BE1 Repair cracked buckets by welding Mechanical 4 days 100% Sun 1/22/23 Thu 1/26/23
25 4617FN1 Change fan main drive Mechanical 3 days 100% Sun 1/22/23 Wed 1/25/23
26 4617BF1 Open bag filter inspection doors and hopper inspection
Mechanicaldoors
1 hr 100% Fri 1/27/23 Fri 1/27/23
27 4617BF2 Open bag filter inspection doors and hopper inspection
Mechanicaldoors
1 hr 100% Fri 1/27/23 Fri 1/27/23
28 4617FN6 Install cooling fan cover for motor Mechanical 1 hr 100% Sun 1/22/23 Sun 1/22/23
29 4615AS2 open inspection doors Mechanical 2 hrs 100% Fri 1/27/23 Fri 1/27/23
30 4615AS3 open inspection doors Mechanical 2 hrs 100% Fri 1/27/23 Fri 1/27/23
31 4617FN4 open fan bearings for inspection Mechanical 12 hrs 100% Thu 1/26/23 Thu 1/26/23
32 4617FN3 Repair shaft Mechanical 3 days 100% Sun 1/22/23 Sat 1/28/23
33 4915BE1 change driven shaft bearings Mechanical 5 hrs 100% Wed 1/25/23 Wed 1/25/23
34 Inspection Activities 143 hrs 88% Sun 1/22/23 Sat 1/28/23
35 4415BC1 check feeding chute deflectors Inspection 2 hrs 100% Thu 1/26/23 Thu 1/26/23
36 4611MD1 Check Main drive bearings Inspection 2 hrs 50% Wed 1/25/23 Wed 1/25/23
37 461BM1 Check Mill internals Inspection 2 hrs 100% Sun 1/22/23 Sun 1/22/23
38 461BM1 check shoe bearings and tyre condition Inspection 4 hrs 50% Tue 1/24/23 Thu 1/26/23
39 461BM1 check discharge chute Inspection 2 hrs 100% Tue 1/24/23 Tue 1/24/23

Page 1
Cement Mill 1 Planned Stoppage

ID Asset Code Description Departemnt Duration % Start Finish


Complete Jan 21, '23 Jan 28, '23
S M T W T F S
40 4612SR1 check separator Inspection 2 hrs 100% Sun 1/22/23 Sun 1/22/23
41 4617BF1 check bag filter condition Inspection 2 hrs 100% Fri 1/27/23 Fri 1/27/23
42 4617BF2 check bag filter condition Inspection 2 hrs 100% Fri 1/27/23 Fri 1/27/23
43 4615AS2 Check Fabric condition Inspection 2 hrs 100% Sat 1/28/23 Sat 1/28/23
44 4615AS3 Check Fabric condition Inspection 2 hrs 100% Sat 1/28/23 Sat 1/28/23
45 4617FN4 check fan bearings Inspection 2 hrs 100% Thu 1/26/23 Thu 1/26/23
46 Electrical Activities 144 hrs?97% Sun 1/22/23 Sat 1/28/23
47 CM1 MCC Scheduled Maintenance for MCC Electrical 2 hrs 100% Sun 1/22/23 Sun 1/22/23
48 4117FN3.M01 Replace motor bearings Electrical 4 hrs 0% Sun 1/22/23 Sun 1/22/23
49 4417FN1.M01 Replace motor bearings Electrical 4 hrs 100% Sun 1/22/23 Mon 1/23/23
50 4417FN2.M01 Replace motor bearings Electrical 4 hrs 100% Mon 1/23/23 Mon 1/23/23
51 4611.MD1.M01 Scheduled Maintenance for CM1 Main Drive Electrical 2 hrs 100% Mon 1/23/23 Mon 1/23/23
52 4611MD1.M01 Scheduled Maintenance for LRS Systems andElectrical
HT Motors 24 hrs? 100% Tue 1/24/23 Wed 1/25/23
53 4611.MD1 Scheduled maintenance for Main Drive Reactor
Electrical 2 hrs 100% Tue 1/24/23 Tue 1/24/23
54 4611.MD1 Scheduled maintenance for Main Drive (HT) Electrical 2 hrs 100% Wed 1/25/23 Wed 1/25/23
55 4612SR1.M01 Scheduled Maintenance for separator main drive
Electrical 24 hrs? 100% Wed 1/25/23 Thu 1/26/23
56 4617FN1.M01 Replace motor by spare motor Electrical 72 hrs 100% Sun 1/22/23 Fri 1/27/23
57 4617FN3.M01 Replace motor bearings Electrical 4 hrs 100% Thu 1/26/23 Sun 1/29/23
58 4617FN1.M01 Scheduled Maintenance for Separator fan Main
Electrical
Drive reactor
2 hrs 100% Fri 1/27/23 Fri 1/27/23
59 Instrumentation Activities 144 hrs 100% Sun 1/22/23 Sat 1/28/23
60 General maintenance for Intensive filter Instrument 3 hrs 100% Sun 1/22/23 Sun 1/22/23
61 General maintenance for Thermax filter Instrument 3 hrs 100% Mon 1/23/23 Mon 1/23/23
62 General maintenance for Lime stone weigh feeder
Instrument 3 hrs 100% Tue 1/24/23 Tue 1/24/23
63 General maintenance for instrument RTD of level
Instrument
switch in3cement
hrs 100%
mill area
Wed 1/25/23 Wed 1/25/23

Page 2