Professional Documents
Culture Documents
56 Dry Cooler 212 days 09 Sep '22 24 Apr '23 Dry Cooler
57 Fire Fighting Pump 280 days 09 Sep '22 03 Jul '23 Fire Fighting Pump
58 Water Tank ( Fire-fighting & Domestic ) 156 days 09 Sep '22 27 Feb '23 Water Tank ( Fire-fighting & Domestic )
59 Gas suppression system 240 days 09 Sep '22 24 May '23 Gas suppression system
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
180 Rebar, form work, concrete for 1st column 15 days 27 Feb '23 13 Mar '23 Rebar, form work, concrete for 1st column
181 Rebar, form work, concrete for 2nd slab 10 days 09 Mar '23 18 Mar '23 Rebar, form work, concrete for 2nd slab
182 Rebar, form work, concrete for 2nd colmn 14 days 12 Mar '23 25 Mar '23 Rebar, form work, concrete for 2nd colmn
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
193 Rebar, form work, concrete for 1st column 15 days 07 Mar '23 21 Mar '23 Rebar, form work, concrete for 1st column
194 Rebar, form work, concrete for 2nd slab 10 days 17 Mar '23 26 Mar '23 Rebar, form work, concrete for 2nd slab
195 Rebar, form work, concrete for 2nd colmn 14 days 20 Mar '23 02 Apr '23 Rebar, form work, concrete for 2nd colmn
196 Rebar, form work, concrete for 3rd slab 10 days 29 Mar '23 07 Apr '23 Rebar, form work, concrete for 3rd slab
197 Rebar, form work, concrete for 3rd column 7 days 01 Apr '23 07 Apr '23 Rebar, form work, concrete for 3rd column
198 Rebar, form work, concrete for roof 6 days 07 Apr '23 12 Apr '23 Rebar, form work, concrete for roof
199 Steel Structure 118 days 31 Dec '22 15 May '23
200 Steel structure fabrication 60 days 31 Dec '22 16 Mar '23 Steel structure fabrication
201 Steel Structure installation 21 days 13 Apr '23 05 May '23 Steel Structure installation
202 Decking structure 10 days 06 May '23 15 May '23 Decking structure
203 Finishing Works 150 days 31 Mar '23 29 Aug '23
204 Mansonry Work 65 days 31 Mar '23 05 Jun '23 Mansonry Work
205 Door and Window 45 days 13 May '23 26 Jun '23 Door and Window
206 Roof Finishing 21 days 27 Apr '23 19 May '23 Roof Finishing
207 Waterproofing Works 14 days 26 May '23 08 Jun '23 Waterproofing Works
208 Tiling Works 35 days 09 Jun '23 13 Jul '23 Tiling Works
209 Ceiling Works 30 days 23 Jun '23 22 Jul '23 Ceiling Works
210 Wall Finishing 30 days 21 Jun '23 20 Jul '23 Wall Finishing
211 Painting Works 35 days 19 Jun '23 23 Jul '23 Painting Works
212 Metal Works 21 days 10 Jul '23 30 Jul '23 Metal Works
213 Façade Finishing 40 days 06 Jun '23 15 Jul '23 Façade Finishing
214 Sanitary Installation 21 days 23 Jun '23 13 Jul '23 Sanitary Installation
215 Fix Furniture 30 days 08 Jul '23 06 Aug '23 Fix Furniture
216 Skylights Installation 14 days 31 Jul '23 13 Aug '23 Skylights Installation
217 Others Works 14 days 16 Aug '23 29 Aug '23 Others Works
218 MEPF Works 220 days 19 Feb '23 30 Sep '23
219 Earthing system 35 days 20 Feb '23 26 Mar '23 Earthing system
220 Underground Piping/Conduit 35 days 19 Feb '23 25 Mar '23 Underground Piping/Conduit
221 Embeded Conduit 90 days 06 Mar '23 05 Jun '23 Embeded Conduit
222 Tray/Trunking, Piping, Duct works 70 days 31 Mar '23 10 Jun '23 Tray/Trunking, Piping, Duct works
223 Lightning protection and grounding system 40 days 24 May '23 02 Jul '23 Lightning protection and grounding system
224 Cabling and wiring works 30 days 27 May '23 25 Jun '23 Cabling and wiring works
225 Installation of Air Con., Lighting, Camera, etc… 48 days 23 Jun '23 09 Aug '23 Installation of Air Con., Lighting, Camera, etc…
226 Installation of Electrical Panel,UPS 30 days 31 Jul '23 29 Aug '23 Installation of Electrical Panel,UPS
227 Data Center MEP works 30 days 11 Jul '23 09 Aug '23 Data Center MEP works
228 Lift Installation 50 days 21 Jun '23 09 Aug '23 Lift Installation
229 Temporary Substation 500KVA 60 days 31 Jul '23 30 Sep '23 Temporary Substation 500KVA
230 Testing and Commissioning 23 days 30 Aug '23 22 Sep '23 Testing and Commissioning
231 Handover to owner 31 days 30 Aug '23 30 Sep '23
232 Defect rectification 30 days 30 Aug '23 29 Sep '23 Defect rectification
233 Handover to owner 1 day 30 Sep '23 30 Sep '23 Handover to owner
234 LMV Data Centre work (by Others) 96 days 13 Sep '23 18 Dec '23 LMV Data Centre work (by Others)
235 Coordinate with other works 96 days 13 Sep '23 18 Dec '23 Coordinate with other works
236 Parking 164 days 13 Apr '23 26 Sep '23
237 RC Structure 52 days 13 Apr '23 05 Jun '23
238 Excavation including compaction 21 days 13 Apr '23 05 May '23 Excavation including compaction
239 Lean concrete 21 days 16 Apr '23 08 May '23 Lean concrete
240 Rebar, form work, concrete for Foundation 35 days 23 Apr '23 29 May '23 Rebar, form work, concrete for Foundation
241 Rebar, form work, concrete for groundbeam and Stump 35 days 02 May '23 05 Jun '23 Rebar, form work, concrete for groundbeam and Stump column
column
242 Grass concrete Road 56 days 02 Jun '23 27 Jul '23
243 Excavation and remove soil 14 days 02 Jun '23 15 Jun '23 Excavation and remove soil
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
264 Rebar, form work, concrete for column 5 days 01 Jul '23 05 Jul '23 Rebar, form work, concrete for column
265 Rebar, form work, concrete for roof 8 days 06 Jul '23 13 Jul '23 Rebar, form work, concrete for roof
266 Finishing works 27 days 14 Jul '23 09 Aug '23
267 Brickwall and plastering 14 days 14 Jul '23 27 Jul '23 Brickwall and plastering
268 Door & window installation 10 days 21 Jul '23 30 Jul '23 Door & window installation
269 Roof Finishing 10 days 24 Jul '23 02 Aug '23 Roof Finishing
270 Tiling work 7 days 21 Jul '23 27 Jul '23 Tiling work
271 Water proofing 7 days 14 Jul '23 20 Jul '23 Water proofing
272 Painting 10 days 28 Jul '23 06 Aug '23 Painting
273 Other finishings 7 days 03 Aug '23 09 Aug '23 Other finishings
274 MEP works 57 days 06 Jun '23 01 Aug '23
275 Underground Piping/Conduit 2 days 06 Jun '23 07 Jun '23 Underground Piping/Conduit
276 Embeded Conduit 16 days 12 Jun '23 27 Jun '23 Embeded Conduit
277 Cable ladder,Piping, Electric Panel 14 days 09 Jul '23 22 Jul '23 Cable ladder,Piping, Electric Panel
278 Cabling and wiring works 10 days 18 Jul '23 27 Jul '23 Cabling and wiring works
279 Installation of Lighting, Socket 5 days 28 Jul '23 01 Aug '23 Installation of Lighting, Socket
280 Testing 2 days 02 Aug '23 03 Aug '23 Testing
281 Pump House 131 days 14 Jul '23 22 Nov '23
282 Tank Foundation 26 days 14 Jul '23 08 Aug '23
283 Excavation Works 10 days 14 Jul '23 23 Jul '23 Excavation Works
284 Rebar, form work, concrete for Foundation R6250 14 days 17 Jul '23 30 Jul '23 Rebar, form work, concrete for Foundation R6250
285 Rebar, form work, concrete for Foundation R7750 10 days 27 Jul '23 05 Aug '23 Rebar, form work, concrete for Foundation R7750
286 Rebar, form work, concrete for Foundation R4000 7 days 02 Aug '23 08 Aug '23 Rebar, form work, concrete for Foundation R4000
287 Pump House Building 121 days 24 Jul '23 22 Nov '23
288 RC Structure 43 days 24 Jul '23 05 Sep '23
289 Excavation including compaction 2 days 24 Jul '23 25 Jul '23 Excavation including compaction
290 Lean concrete 1 day 26 Jul '23 26 Jul '23 Lean concrete
291 Pile cut off 1 day 27 Jul '23 27 Jul '23 Pile cut off
292 Rebar, form work, concrete for Foundation 10 days 28 Jul '23 06 Aug '23 Rebar, form work, concrete for Foundation
293 Rebar, form work, concrete for Stump column 6 days 07 Aug '23 12 Aug '23 Rebar, form work, concrete for Stump column
294 Rebar, form work, concrete for groundbeam and slab 8 days 13 Aug '23 20 Aug '23 Rebar, form work, concrete for groundbeam and slab
295 Rebar, form work, concrete for column 7 days 21 Aug '23 27 Aug '23 Rebar, form work, concrete for column
296 Rebar, form work, concrete for roof 8 days 28 Aug '23 05 Sep '23 Rebar, form work, concrete for roof
297 Finishing works 41 days 06 Sep '23 16 Oct '23
298 Brickwall and plastering 14 days 06 Sep '23 19 Sep '23 Brickwall and plastering
299 Door & window installation 10 days 20 Sep '23 29 Sep '23 Door & window installation
300 Roof Finishing 14 days 16 Sep '23 29 Sep '23 Roof Finishing
301 Floor Finishing 7 days 20 Sep '23 26 Sep '23 Floor Finishing
302 Wall Finishing 14 days 30 Sep '23 13 Oct '23 Wall Finishing
303 Painting 10 days 27 Sep '23 06 Oct '23 Painting
304 Other finishings 7 days 10 Oct '23 16 Oct '23 Other finishings
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
325 Rebar, form work, concrete for column 5 days 03 Oct '23 07 Oct '23 Rebar, form work, concrete for column
326 Rebar, form work, concrete for roof 6 days 08 Oct '23 13 Oct '23 Rebar, form work, concrete for roof
327 Finishing works 41 days 14 Oct '23 23 Nov '23
328 Brickwall and plastering 14 days 14 Oct '23 27 Oct '23 Brickwall and plastering
329 Door & window installation 10 days 28 Oct '23 06 Nov '23 Door & window installation
330 Roof Finishing 14 days 24 Oct '23 06 Nov '23 Roof Finishing
331 Floor Finishing 7 days 28 Oct '23 03 Nov '23 Floor Finishing
332 Wall Finishing 14 days 28 Oct '23 10 Nov '23 Wall Finishing
333 Painting 10 days 11 Nov '23 20 Nov '23 Painting
334 Other finishings 7 days 17 Nov '23 23 Nov '23 Other finishings
335 MEP Works 77 days 08 Sep '23 23 Nov '23
336 MEP Underground works 2 days 08 Sep '23 09 Sep '23 MEP Underground works
337 Earthing & Bonding system 10 days 08 Sep '23 17 Sep '23 Earthing & Bonding system
338 Tray/Trunking, Piping, Electric Panel works 30 days 04 Oct '23 02 Nov '23 Tray/Trunking, Piping, Electric Panel works
339 Cable/wiring works 10 days 03 Nov '23 12 Nov '23 Cable/wiring works
340 Installation of Equipment 20 days 28 Oct '23 16 Nov '23 Installation of Equipment
341 Lightning protection system 7 days 07 Nov '23 13 Nov '23 Lightning protection system
342 Testing and Commissioning 7 days 17 Nov '23 23 Nov '23 Testing and Commissioning
343 Gate House 2 69 days 06 Sep '23 13 Nov '23
344 RC Structure 38 days 06 Sep '23 13 Oct '23
345 Excavation including compaction 2 days 06 Sep '23 07 Sep '23 Excavation including compaction
346 Lean concrete 1 day 08 Sep '23 08 Sep '23 Lean concrete
347 Pile cut off 1 day 09 Sep '23 09 Sep '23 Pile cut off
348 Rebar, form work, concrete for Foundation 8 days 10 Sep '23 17 Sep '23 Rebar, form work, concrete for Foundation
349 Rebar, form work, concrete for Stump column 5 days 18 Sep '23 22 Sep '23 Rebar, form work, concrete for Stump column
350 Rebar, form work, concrete for Groundbeam and slab 8 days 23 Sep '23 30 Sep '23 Rebar, form work, concrete for Groundbeam and slab
351 Rebar, form work, concrete for column 5 days 01 Oct '23 05 Oct '23 Rebar, form work, concrete for column
352 Rebar, form work, concrete for roof 8 days 06 Oct '23 13 Oct '23 Rebar, form work, concrete for roof
353 Finishing works 27 days 14 Oct '23 09 Nov '23
354 Brickwall and plastering 14 days 14 Oct '23 27 Oct '23 Brickwall and plastering
355 Door & window installation 10 days 21 Oct '23 30 Oct '23 Door & window installation
356 Roof Finishing 10 days 24 Oct '23 02 Nov '23 Roof Finishing
357 Tiling work 7 days 21 Oct '23 27 Oct '23 Tiling work
358 Water proofing 7 days 14 Oct '23 20 Oct '23 Water proofing
359 Painting 10 days 28 Oct '23 06 Nov '23 Painting
360 Other finishings 7 days 03 Nov '23 09 Nov '23 Other finishings
361 MEP works 67 days 08 Sep '23 13 Nov '23
362 Underground Piping/Conduit 2 days 08 Sep '23 09 Sep '23 Underground Piping/Conduit
363 Embeded Conduit 16 days 12 Sep '23 27 Sep '23 Embeded Conduit
364 Cable ladder,Piping, Electric Panel 14 days 03 Oct '23 16 Oct '23 Cable ladder,Piping, Electric Panel
365 Cabling and wiring works 10 days 20 Oct '23 29 Oct '23 Cabling and wiring works
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
601 Rebar, form work, concrete for 1st column 14 days 01 Jul '23 14 Jul '23 Rebar, form work, concrete for 1st column
602 Rebar, form work, concrete for 1st floor 10 days 15 Jul '23 24 Jul '23 Rebar, form work, concrete for 1st floor
603 Rebar, form work, concrete for 2nd column 7 days 25 Jul '23 31 Jul '23 Rebar, form work, concrete for 2nd column
604 Rebar, form work, concrete for 2nd floor 7 days 01 Aug '23 07 Aug '23 Rebar, form work, concrete for 2nd floor
605 RC Structure PP2 83 days 07 Jul '23 28 Sep '23
606 Excavation including compaction 18 days 07 Jul '23 24 Jul '23 Excavation including compaction
607 Lean concrete 18 days 09 Jul '23 26 Jul '23 Lean concrete
608 Pile cut off 18 days 11 Jul '23 28 Jul '23 Pile cut off
609 Rebar, form work, concrete for Foundation 28 days 16 Jul '23 12 Aug '23 Rebar, form work, concrete for Foundation
610 Rebar, form work, concrete for Ground beam & Stump column 28 days 30 Jul '23 26 Aug '23 Rebar, form work, concrete for Ground beam & Stump column
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
621 Steel Structure Erection 147 days 27 Aug '23 21 Jan '24
622 Steel Structure Frame 65 days 27 Aug '23 31 Oct '23 Steel Structure Frame
623 Steel Purlin 45 days 20 Sep '23 03 Nov '23 Steel Purlin
624 Safety Mesh 28 days 12 Oct '23 08 Nov '23 Safety Mesh
625 Metalsheet Roof 28 days 04 Nov '23 01 Dec '23 Metalsheet Roof
626 Fireproof Paint 30 days 23 Dec '23 21 Jan '24 Fireproof Paint
627 RC Work for upper floor 30 days 01 Nov '23 30 Nov '23 RC Work for upper floor
628 Ground Slab 77 days 07 Oct '23 22 Dec '23
629 Soil Leveling and compacted for ground floor 21 days 07 Oct '23 28 Oct '23 Soil Leveling and compacted for ground floor
630 Termite treatment & Lean Concrete 21 days 28 Oct '23 18 Nov '23 Termite treatment & Lean Concrete
631 Rebar, form work, concrete for Groundslab 35 days 18 Nov '23 22 Dec '23 Rebar, form work, concrete for Groundslab
632 Finishing Works 209 days 18 Sep '23 24 Apr '24
633 Mansonry Work 120 days 18 Sep '23 15 Jan '24 Mansonry Work
634 Door and Windown 60 days 17 Dec '23 25 Feb '24 Door and Windown
635 Waterproofing Works 21 days 06 Jan '24 26 Jan '24 Waterproofing Works
636 Roof Finshing 30 days 23 Dec '23 21 Jan '24 Roof Finshing
637 Tiling Works 21 days 16 Jan '24 06 Feb '24 Tiling Works
638 Ceiling Works 35 days 30 Jan '24 15 Mar '24 Ceiling Works
639 Panel Works 35 days 16 Jan '24 01 Mar '24 Panel Works
640 Floor Finishing 40 days 05 Feb '24 25 Mar '24 Floor Finishing
641 Painting Works 30 days 06 Mar '24 04 Apr '24 Painting Works
642 Metal Works 21 days 22 Mar '24 11 Apr '24 Metal Works
643 Others Works 14 days 11 Apr '24 24 Apr '24 Others Works
644 MEP Works 297 days 17 May '23 20 Mar '24
645 Earthing system 120 days 17 May '23 14 Sep '23 Earthing system
646 Underground Piping/Conduit 120 days 17 May '23 14 Sep '23 Underground Piping/Conduit
647 Tray/Trunking, Piping, Duct works 50 days 04 Nov '23 23 Dec '23 Tray/Trunking, Piping, Duct works
648 Lightning protection system 20 days 02 Dec '23 21 Dec '23 Lightning protection system
649 Cable Laying and Busway 50 days 29 Nov '23 17 Jan '24 Cable Laying and Busway
650 Installation of Air Con., Lighting, Camera, etc… 60 days 24 Dec '23 03 Mar '24 Installation of Air Con., Lighting, Camera, etc…
651 MV Switchgears, Transformers, LV Panels 45 days 26 Dec '23 19 Feb '24 MV Switchgears, Transformers, LV Panels
652 Data Center MEP Works 32 days 24 Dec '23 24 Jan '24 Data Center MEP Works
653 Testing and Commissioning 30 days 20 Feb '24 20 Mar '24 Testing and Commissioning
654 LEGO Handling Equipment 134 days 17 Apr '24 28 Aug '24 LEGO Handling Equipment
655 Manual Warehouse 281 days 07 Jul '23 24 Apr '24
656 RC Structure 80 days 07 Jul '23 25 Sep '23
657 Excavation including compaction 45 days 07 Jul '23 20 Aug '23 Excavation including compaction
658 Lean concrete 45 days 09 Jul '23 22 Aug '23 Lean concrete
659 Pile cut off 45 days 11 Jul '23 24 Aug '23 Pile cut off
660 Rebar, form work, concrete for Foundation 65 days 16 Jul '23 19 Sep '23 Rebar, form work, concrete for Foundation
661 Rebar, form work, concrete for Ground beam & Stump column 50 days 06 Aug '23 25 Sep '23 Rebar, form work, concrete for Ground beam & Stump column
662 Steel Structure Erection 176 days 05 Sep '23 09 Mar '24
663 Steel Structure Frame 55 days 05 Sep '23 29 Oct '23 Steel Structure Frame
664 Steel Purlin 42 days 21 Sep '23 01 Nov '23 Steel Purlin
665 Safety Mesh 28 days 10 Oct '23 06 Nov '23 Safety Mesh
666 Metalsheet Roof 28 days 02 Nov '23 29 Nov '23 Metalsheet Roof
667 Fireproof Paint 45 days 14 Jan '24 09 Mar '24 Fireproof Paint
668 Steel Structure for crane and racking 30 days 30 Oct '23 28 Nov '23 Steel Structure for crane and racking
669 Ground Slab 105 days 01 Oct '23 13 Jan '24
670 Soil Leveling and compacted for ground floor 30 days 01 Oct '23 31 Oct '23 Soil Leveling and compacted for ground floor
671 Termite treatment & Lean Concrete 30 days 31 Oct '23 30 Nov '23 Termite treatment & Lean Concrete
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
707 Steel Structure Erection 152 days 24 Aug '23 23 Jan '24
708 Steel Structure Frame 65 days 24 Aug '23 28 Oct '23 Steel Structure Frame
709 Steel Purlin 21 days 15 Oct '23 04 Nov '23 Steel Purlin
710 Safety Mesh 14 days 27 Oct '23 09 Nov '23 Safety Mesh
711 Metalsheet Roof 14 days 05 Nov '23 18 Nov '23 Metalsheet Roof
712 Fireproof Paint 45 days 10 Dec '23 23 Jan '24 Fireproof Paint
713 Steel Structure for crane and racking 30 days 29 Oct '23 27 Nov '23 Steel Structure for crane and racking
714 Ground Slab 49 days 22 Oct '23 09 Dec '23
715 Soil Leveling and compacted for ground floor 14 days 22 Oct '23 05 Nov '23 Soil Leveling and compacted for ground floor
716 Termite treatment & Lean Concrete 14 days 05 Nov '23 19 Nov '23 Termite treatment & Lean Concrete
717 Rebar, form work, concrete for Groundslab 21 days 19 Nov '23 09 Dec '23 Rebar, form work, concrete for Groundslab
718 Upper Structure floor 67 days 29 Oct '23 03 Jan '24
719 Install Metal Deck 45 days 29 Oct '23 12 Dec '23 Install Metal Deck
720 Rebar, form work, concrete for upper slab 60 days 05 Nov '23 03 Jan '24 Rebar, form work, concrete for upper slab
721 Finishing Works 133 days 19 Nov '23 10 Apr '24
722 Mansonry Work 60 days 19 Nov '23 17 Jan '24 Mansonry Work
723 Door and Windown 45 days 03 Jan '24 27 Feb '24 Door and Windown
724 Waterproofing Works 21 days 06 Jan '24 26 Jan '24 Waterproofing Works
725 Roof Finshing 30 days 23 Dec '23 21 Jan '24 Roof Finshing
726 Ceiling Works 21 days 01 Feb '24 03 Mar '24 Ceiling Works
727 Panel Works 21 days 01 Feb '24 03 Mar '24 Panel Works
728 Floor Finishing 21 days 22 Feb '24 13 Mar '24 Floor Finishing
729 Painting Works 28 days 25 Feb '24 23 Mar '24 Painting Works
730 Metal Works 21 days 10 Mar '24 30 Mar '24 Metal Works
731 Others Works 14 days 28 Mar '24 10 Apr '24 Others Works
732 MEP Works 181 days 05 Aug '23 02 Feb '24
733 Underground Piping/Conduit 35 days 05 Aug '23 09 Sep '23 Underground Piping/Conduit
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task
Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress
Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task