PROPOSED MASTER CONSTRUCTION SCHEDULE

Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT


Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
1 LMV_MASTER SCHEDULE_TLC_24 JUNE 2022 774 days 17 Aug '22 29 Oct '24
2 I. CLIENT MILESTONE 562 days 16 Aug '22 31 Mar '24
3 Letter of Award 0 days 16 Aug '22 16 Aug '22 Letter of Award
4 Outbuild 0 days 18 Dec '23 18 Dec '23 18-12
5 Data Centre_MS#2 0 days 01 Oct '23 01 Oct '23 01-10
6 LMV Data Centre work 0 days 18 Dec '23 18 Dec '23 18-12
7 Energy Centre 0 days 26 Jan '24 26 Jan '24 26-01
8 LMV Data Centre work 0 days 18 Dec '23 18 Dec '23 18-12
9 BMS to be "online" 0 days 26 Jan '24 26 Jan '24 26-01
10 Moulding Building 0 days 15 Jan '24 15 Jan '24 15-01
11 MS#1 0 days 15 Dec '23 15 Dec '23 15-12
12 External Silo area, 1.103 material Drying Room & 1.106 Equip 0 days 01 Nov '23 01 Nov '23 01-11
cleaning Room
13 All other rooms except Mol 1.102 areas 0 days 24 Nov '23 24 Nov '23 24-11
14 Mol 1.102 0 days 15 Dec '23 15 Dec '23 15-12
15 MS#2 All Areas 0 days 15 Jan '24 15 Jan '24 15-01
16 Service Building 1 day 15 Feb '24 15 Feb '24
17 MS#1&2 Data Centre 0 days 01 Dec '23 01 Dec '23 01-12
18 MS#1 LMV data Centre work 0 days 26 Jan '24 26 Jan '24 26-01
19 MS#1 Mould Bunka 1.417 0 days 15 Oct '23 15 Oct '23 15-10
20 MS#2 All other rooms 0 days 16 Jan '24 16 Jan '24 MS#2 All other rooms
21 All areas (MEPF running on manual control) 0 days 05 Feb '24 05 Feb '24 05-02
22 Running on full "online" BMS control 0 days 15 Feb '24 15 Feb '24 15-02
23 First production Goal 0 days 31 Mar '24 31 Mar '24 First production Goal
24 Access Road & Connection (by VSIP 3) 0 days 01 Nov '22 01 Nov '22 01-11
25 Construction Permit Obtain 0 days 30 Dec '22 30 Dec '22 30-12
26 II. CONSTRUCTION WORKS 774 days 17 Aug '22 29 Oct '24
27 EARLY WORKS: 479 days 17 Aug '22 28 Dec '23
28 Early Contractor Involment on Design Works 93 days 17 Aug '22 18 Nov '22 Early Contractor Involment on Design Works
29 DOCUMENTATION WORKS 194 days 18 Aug '22 16 Mar '23
30 Master Schedule Submit / Approval 21 days 18 Aug '22 08 Sep '22 Master Schedule Submit / Approval
31 HSSE Plan Submission / Approval 21 days 25 Aug '22 15 Sep '22 HSSE Plan Submission / Approval
32 Quality Control Plan Submission / Approval 21 days 01 Sep '22 22 Sep '22 Quality Control Plan Submission / Approval
33 Material Submission / Approval_Refer to Procurement schedule 150 days 18 Aug '22 31 Jan '23 Material Submission / Approval_Refer to Procurement schedule submission detail plan
submission detail plan
34 Method statements Submission / Approval_Refer to Method 150 days 29 Sep '22 13 Mar '23 Method statements Submission / Approval_Refer to Method submission detail plan
submission detail plan
35 Shop Drawing Submission / Approval_Refer to Shop Drawing 150 days 02 Oct '22 16 Mar '23 Shop Drawing Submission / Approval_Refer to Shop Drawing submission detail plan
submission detail plan
36 PROCUREMENT WORKS 478 days 18 Aug '22 28 Dec '23
37 Longlead Material Importing 478 days 18 Aug '22 28 Dec '23
38 CSA Works 209 days 01 Sep '22 14 Apr '23
39 Reinforcement rebar with EPD Certificate 75 days 01 Sep '22 15 Nov '22 Reinforcement rebar with EPD Certificate
40 Steel Structure 105 days 01 Sep '22 15 Dec '22 Steel Structure
41 Hardener floor 56 days 09 Sep '22 03 Nov '22 Hardener floor
42 Façade Panel 156 days 11 Sep '22 01 Mar '23 Façade Panel
43 Ceiling 156 days 11 Sep '22 01 Mar '23 Ceiling
44 TPO Roof 200 days 11 Sep '22 14 Apr '23 TPO Roof
45 Steel & Roller Shutter Door 120 days 18 Sep '22 31 Jan '23 Steel & Roller Shutter Door
46 Door and window alu. Frame 140 days 18 Sep '22 20 Feb '23 Door and window alu. Frame
47 Dock Leveller 140 days 25 Sep '22 27 Feb '23 Dock Leveller
48 MEPF Works 478 days 18 Aug '22 28 Dec '23
49 Lastest date for delivery Equipment to Site 0 days 14 Jun '23 14 Jun '23 14-06
50 Material/Equipment Submision for approval 90 days 18 Aug '22 16 Nov '22 Material/Equipment Submision for approval
51 Purchasing Process 290 days 18 Sep '22 22 Jul '23 Purchasing Process
52 Chiller x 2 sets 293 days 09 Sep '22 16 Jul '23 Chiller x 2 sets
53 Chiller x 4 sets 457 days 09 Sep '22 28 Dec '23 Chiller x 4 sets
54 AHU 156 days 26 Nov '22 18 May '23 AHU
55 Air Compressor unit with Oil separator/dryer/Air receiver 254 days 09 Sep '22 07 Jun '23 Air Compressor unit with Oil separator/dryer/Air receiver

56 Dry Cooler 212 days 09 Sep '22 24 Apr '23 Dry Cooler
57 Fire Fighting Pump 280 days 09 Sep '22 03 Jul '23 Fire Fighting Pump
58 Water Tank ( Fire-fighting & Domestic ) 156 days 09 Sep '22 27 Feb '23 Water Tank ( Fire-fighting & Domestic )
59 Gas suppression system 240 days 09 Sep '22 24 May '23 Gas suppression system

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 1 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
60 Fire Alarm System 226 days 09 Sep '22 10 May '23 Fire Alarm System
61 BMS System (Include DDC Panel Assembly) 300 days 08 Oct '22 21 Aug '23 BMS System (Include DDC Panel Assembly)
62 SCADA System 160 days 27 Oct '22 20 Apr '23 SCADA System
63 MV Switchgear 170 days 08 Sep '22 12 Mar '23 MV Switchgear
64 Transformer 182 days 08 Sep '22 24 Mar '23 Transformer
65 MSB,UPS 160 days 26 Nov '22 22 May '23 MSB,UPS
66 LV Local Panel 164 days 26 Nov '22 26 May '23 LV Local Panel
67 Power busbar 150 days 26 Nov '22 12 May '23 Power busbar
68 Generator 212 days 08 Sep '22 23 Apr '23 Generator
69 PV equipment 100 days 08 Oct '22 31 Jan '23 PV equipment
70 Lighting Fittings and Control 184 days 26 Nov '22 15 Jun '23 Lighting Fittings and Control
71 Cable 100 days 26 Nov '22 21 Mar '23 Cable
72 CABLE LADDER /CABLE TRAY 70 days 26 Nov '22 19 Feb '23 CABLE LADDER /CABLE TRAY
73 PIPES 100 days 26 Nov '22 21 Mar '23 PIPES
74 II.1. FACILITY SET UP 41 days 18 Aug '22 28 Sep '22
75 Documents Submission/ Approval for Facility 19 days 18 Aug '22 06 Sep '22
76 Design/Shop drawing/ Method statement submission for Site 14 days 18 Aug '22 31 Aug '22 Design/Shop drawing/ Method statement submission for Site Office
Office
77 Design/Shop drawing/ Method statement Approval for Site 14 days 23 Aug '22 06 Sep '22 Design/Shop drawing/ Method statement Approval for Site Office by Client
Office by Client
78 1. Site Office (Owner, Consultant, Contractor…) 31 days 28 Aug '22 28 Sep '22
79 Soil & Stone 0x4 application and compaction 5 days 28 Aug '22 01 Sep '22 Soil & Stone 0x4 application and compaction
80 Concreting for floor 3 days 03 Sep '22 05 Sep '22 Concreting for floor
81 Truss & metal sheet installation 7 days 06 Sep '22 12 Sep '22 Truss & metal sheet installation
82 Panel Installation 5 days 13 Sep '22 17 Sep '22 Panel Installation
83 Gypsum board ceiling 5 days 15 Sep '22 19 Sep '22 Gypsum board ceiling
84 Floor finishings 12 days 17 Sep '22 28 Sep '22 Floor finishings
85 Door and window installation 5 days 19 Sep '22 23 Sep '22 Door and window installation
86 MEP installation 8 days 17 Sep '22 24 Sep '22 MEP installation
87 Office equipment installation 7 days 20 Sep '22 26 Sep '22 Office equipment installation
88 2. Toilet 13 days 03 Sep '22 15 Sep '22
89 Septic tank for toilet 2 days 03 Sep '22 04 Sep '22 Septic tank for toilet
90 Brickwall, plastering, plumbing & tiling for toilet 5 days 05 Sep '22 09 Sep '22 Brickwall, plastering, plumbing & tiling for toilet
91 Roof & partition for toilet 2 days 10 Sep '22 11 Sep '22 Roof & partition for toilet
92 Sanitary ware installation 2 days 12 Sep '22 13 Sep '22 Sanitary ware installation
93 Other finishing works 2 days 14 Sep '22 15 Sep '22 Other finishing works
94 3. Site Guard House 7 days 28 Aug '22 04 Sep '22
95 Farbication of temporary metal shed 3 days 28 Aug '22 30 Aug '22 Farbication of temporary metal shed
96 Concrete for floor 2 days 31 Aug '22 01 Sep '22 Concrete for floor
97 Installation of guard post 2 days 03 Sep '22 04 Sep '22 Installation of guard post
98 4. Temporary road (include Mobile material area, Packing 21 days 30 Aug '22 20 Sep '22
area)
99 Soil compaction 21 days 30 Aug '22 20 Sep '22 Soil compaction
100 Stone 0x4 application and compaction 18 days 03 Sep '22 20 Sep '22 Stone 0x4 application and compaction
101 5. Walk way 17 days 05 Sep '22 21 Sep '22
102 Soil compaction 7 days 05 Sep '22 11 Sep '22 Soil compaction
103 Stone 0x4 application and compaction 6 days 16 Sep '22 21 Sep '22 Stone 0x4 application and compaction
104 6. Truck washing area 6 days 30 Aug '22 05 Sep '22
105 Soil compaction 1 day 30 Aug '22 30 Aug '22 Soil compaction
106 Stone 0x4 application and compaction 2 days 31 Aug '22 01 Sep '22 Stone 0x4 application and compaction
107 Concrete 3 days 03 Sep '22 05 Sep '22 Concrete
108 Brickwall & manhole 3 days 03 Sep '22 05 Sep '22 Brickwall & manhole
109 7. Fabrication yard 6 days 31 Aug '22 06 Sep '22
110 Soil compaction 2 days 31 Aug '22 01 Sep '22 Soil compaction
111 Stone 0x4 application and compaction 2 days 03 Sep '22 04 Sep '22 Stone 0x4 application and compaction
112 Concrete 2 days 05 Sep '22 06 Sep '22 Concrete
113 8. Collection rubbish area 5 days 05 Sep '22 09 Sep '22
114 Soil compaction 1 day 05 Sep '22 05 Sep '22 Soil compaction
115 Stone 0x4 application and compaction 2 days 06 Sep '22 07 Sep '22 Stone 0x4 application and compaction
116 Concrete 2 days 08 Sep '22 09 Sep '22 Concrete
117 9. Temporary fence & barricade 15 days 30 Aug '22 14 Sep '22
118 Installation frame 10 days 30 Aug '22 09 Sep '22 Installation frame
119 Installation mesh 10 days 05 Sep '22 14 Sep '22 Installation mesh
120 10. Smoking area 2 days 10 Sep '22 11 Sep '22
Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 2 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
121 Fabrication of smoking hut 1 day 10 Sep '22 10 Sep '22 Fabrication of smoking hut
122 Installation 1 day 11 Sep '22 11 Sep '22 Installation
123 11. Temporary gate 7 days 12 Sep '22 18 Sep '22
124 Farbication 4 days 12 Sep '22 15 Sep '22 Farbication
125 Installation 3 days 16 Sep '22 18 Sep '22 Installation
126 12. Temporary drainage & water supply 15 days 30 Aug '22 14 Sep '22
127 Excavation 4 days 30 Aug '22 03 Sep '22 Excavation
128 Installation of pile & manhole 4 days 04 Sep '22 07 Sep '22 Installation of pile & manhole
129 Connection 3 days 08 Sep '22 10 Sep '22 Connection
130 Backfilling 4 days 11 Sep '22 14 Sep '22 Backfilling
131 13. Temporary electric system 19 days 01 Sep '22 20 Sep '22
132 Excavation 5 days 01 Sep '22 06 Sep '22 Excavation
133 Installation of lighting pole & foundation 7 days 04 Sep '22 10 Sep '22 Installation of lighting pole & foundation
134 Cable installation 7 days 06 Sep '22 12 Sep '22 Cable installation
135 Installation of transformer & MDB 10 days 08 Sep '22 17 Sep '22 Installation of transformer & MDB
136 Installation of house for transformer 7 days 13 Sep '22 19 Sep '22 Installation of house for transformer
137 Testing & commisioning 1 day 20 Sep '22 20 Sep '22 Testing & commisioning
138 Other finishing works 7 days 21 Sep '22 27 Sep '22 Other finishing works
139 Completion of temporary works 1 day 27 Sep '22 27 Sep '22 Completion of temporary works
140 Steel Structure Fabrication 259 days 17 Oct '22 20 Jul '23
141 Shop Drawings 45 days 17 Oct '22 30 Nov '22 Shop Drawings
142 Approval Shop Drawings 45 days 15 Nov '22 29 Dec '22 Approval Shop Drawings
143 Fabrication Works 150 days 15 Dec '22 31 May '23 Fabrication Works
144 Delivery to site 90 days 20 Apr '23 20 Jul '23 Delivery to site
145 Façade Panel 261 days 01 Nov '22 06 Aug '23
146 Shop Drawings 45 days 01 Nov '22 15 Dec '22 Shop Drawings
147 Approval Shop Drawings 45 days 22 Nov '22 06 Jan '23 Approval Shop Drawings
148 Fabrication Works 150 days 22 Dec '22 07 Jun '23 Fabrication Works
149 Delivery to site 120 days 07 Apr '23 06 Aug '23 Delivery to site
150 II.3. Site leveling & Backfill 135 days 17 Aug '22 30 Dec '22
151 Access Road & Connection (by VSIP 3) 1 day 01 Nov '22 01 Nov '22 Access Road & Connection (by VSIP 3)
152 Site Handover 1 day 17 Aug '22 17 Aug '22 Site Handover
153 Site Clearning 30 days 18 Aug '22 17 Sep '22 Site Clearning
154 Soil backfill and compacted 100 days 22 Sep '22 30 Dec '22 Soil backfill and compacted
155 II.4. Pile Works 79 days 28 Dec '22 01 Apr '23
156 Construction Permit (by Others) 1 day 30 Dec '22 30 Dec '22 Construction Permit (by Others)
157 Mobilize Equipment 3 days 28 Dec '22 31 Dec '22 Mobilize Equipment
158 Pile Test 21 days 31 Dec '22 05 Feb '23
159 Pile Driving 7 days 31 Dec '22 07 Jan '23 Pile Driving
160 Pile Test 14 days 08 Jan '23 05 Feb '23 Pile Test
161 Mass Pile Works 55 days 06 Feb '23 01 Apr '23
162 Outbuild 28 days 06 Feb '23 05 Mar '23
163 Zone 01 14 days 06 Feb '23 19 Feb '23 Zone 01
164 Zone 02 14 days 20 Feb '23 05 Mar '23 Zone 02
165 Energy 25 days 19 Feb '23 15 Mar '23 Energy
166 Moulding 27 days 06 Feb '23 04 Mar '23 Moulding
167 Service 28 days 05 Mar '23 01 Apr '23 Service
168 Others 14 days 16 Mar '23 29 Mar '23 Others
169 STREAM 1, 2, 3_CONSTRUCTION WORK 443 days 31 Dec '22 16 Apr '24
170 STREAM 01_Outbuilt, Misc building, External works 443 days 31 Dec '22 16 Apr '24
171 Outbuilt 255 days 31 Dec '22 30 Sep '23
172 RC Structure 59 days 13 Feb '23 12 Apr '23
173 Zone 1 51 days 13 Feb '23 04 Apr '23
174 Excavation including compaction 7 days 13 Feb '23 19 Feb '23 Excavation including compaction
175 Lean concrete 5 days 15 Feb '23 19 Feb '23 Lean concrete
176 Pile cut off 5 days 17 Feb '23 21 Feb '23 Pile cut off
177 Rebar, form work, concrete for Foundation 12 days 19 Feb '23 02 Mar '23 Rebar, form work, concrete for Foundation
178 Rebar, form work, concrete for Stump column 10 days 22 Feb '23 03 Mar '23 Rebar, form work, concrete for Stump column
179 Rebar, form work, concrete for ground beam and slab 15 days 22 Feb '23 08 Mar '23 Rebar, form work, concrete for ground beam and slab

180 Rebar, form work, concrete for 1st column 15 days 27 Feb '23 13 Mar '23 Rebar, form work, concrete for 1st column
181 Rebar, form work, concrete for 2nd slab 10 days 09 Mar '23 18 Mar '23 Rebar, form work, concrete for 2nd slab
182 Rebar, form work, concrete for 2nd colmn 14 days 12 Mar '23 25 Mar '23 Rebar, form work, concrete for 2nd colmn

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 3 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
183 Rebar, form work, concrete for 3rd slab 10 days 21 Mar '23 30 Mar '23 Rebar, form work, concrete for 3rd slab
184 Rebar, form work, concrete for 3rd column 7 days 24 Mar '23 30 Mar '23 Rebar, form work, concrete for 3rd column
185 Rebar, form work, concrete for roof 6 days 30 Mar '23 04 Apr '23 Rebar, form work, concrete for roof
186 Zone 2 54 days 18 Feb '23 12 Apr '23
187 Excavation including compaction 7 days 18 Feb '23 24 Feb '23 Excavation including compaction
188 Lean concrete 5 days 20 Feb '23 24 Feb '23 Lean concrete
189 Pile cut off 5 days 22 Feb '23 26 Feb '23 Pile cut off
190 Rebar, form work, concrete for Foundation 12 days 24 Feb '23 07 Mar '23 Rebar, form work, concrete for Foundation
191 Rebar, form work, concrete for Stump column 10 days 27 Feb '23 08 Mar '23 Rebar, form work, concrete for Stump column
192 Rebar, form work, concrete for ground beam and slab 15 days 02 Mar '23 16 Mar '23 Rebar, form work, concrete for ground beam and slab

193 Rebar, form work, concrete for 1st column 15 days 07 Mar '23 21 Mar '23 Rebar, form work, concrete for 1st column
194 Rebar, form work, concrete for 2nd slab 10 days 17 Mar '23 26 Mar '23 Rebar, form work, concrete for 2nd slab
195 Rebar, form work, concrete for 2nd colmn 14 days 20 Mar '23 02 Apr '23 Rebar, form work, concrete for 2nd colmn
196 Rebar, form work, concrete for 3rd slab 10 days 29 Mar '23 07 Apr '23 Rebar, form work, concrete for 3rd slab
197 Rebar, form work, concrete for 3rd column 7 days 01 Apr '23 07 Apr '23 Rebar, form work, concrete for 3rd column
198 Rebar, form work, concrete for roof 6 days 07 Apr '23 12 Apr '23 Rebar, form work, concrete for roof
199 Steel Structure 118 days 31 Dec '22 15 May '23
200 Steel structure fabrication 60 days 31 Dec '22 16 Mar '23 Steel structure fabrication
201 Steel Structure installation 21 days 13 Apr '23 05 May '23 Steel Structure installation
202 Decking structure 10 days 06 May '23 15 May '23 Decking structure
203 Finishing Works 150 days 31 Mar '23 29 Aug '23
204 Mansonry Work 65 days 31 Mar '23 05 Jun '23 Mansonry Work
205 Door and Window 45 days 13 May '23 26 Jun '23 Door and Window
206 Roof Finishing 21 days 27 Apr '23 19 May '23 Roof Finishing
207 Waterproofing Works 14 days 26 May '23 08 Jun '23 Waterproofing Works
208 Tiling Works 35 days 09 Jun '23 13 Jul '23 Tiling Works
209 Ceiling Works 30 days 23 Jun '23 22 Jul '23 Ceiling Works
210 Wall Finishing 30 days 21 Jun '23 20 Jul '23 Wall Finishing
211 Painting Works 35 days 19 Jun '23 23 Jul '23 Painting Works
212 Metal Works 21 days 10 Jul '23 30 Jul '23 Metal Works
213 Façade Finishing 40 days 06 Jun '23 15 Jul '23 Façade Finishing
214 Sanitary Installation 21 days 23 Jun '23 13 Jul '23 Sanitary Installation
215 Fix Furniture 30 days 08 Jul '23 06 Aug '23 Fix Furniture
216 Skylights Installation 14 days 31 Jul '23 13 Aug '23 Skylights Installation
217 Others Works 14 days 16 Aug '23 29 Aug '23 Others Works
218 MEPF Works 220 days 19 Feb '23 30 Sep '23
219 Earthing system 35 days 20 Feb '23 26 Mar '23 Earthing system
220 Underground Piping/Conduit 35 days 19 Feb '23 25 Mar '23 Underground Piping/Conduit
221 Embeded Conduit 90 days 06 Mar '23 05 Jun '23 Embeded Conduit
222 Tray/Trunking, Piping, Duct works 70 days 31 Mar '23 10 Jun '23 Tray/Trunking, Piping, Duct works
223 Lightning protection and grounding system 40 days 24 May '23 02 Jul '23 Lightning protection and grounding system
224 Cabling and wiring works 30 days 27 May '23 25 Jun '23 Cabling and wiring works
225 Installation of Air Con., Lighting, Camera, etc… 48 days 23 Jun '23 09 Aug '23 Installation of Air Con., Lighting, Camera, etc…

226 Installation of Electrical Panel,UPS 30 days 31 Jul '23 29 Aug '23 Installation of Electrical Panel,UPS
227 Data Center MEP works 30 days 11 Jul '23 09 Aug '23 Data Center MEP works
228 Lift Installation 50 days 21 Jun '23 09 Aug '23 Lift Installation
229 Temporary Substation 500KVA 60 days 31 Jul '23 30 Sep '23 Temporary Substation 500KVA
230 Testing and Commissioning 23 days 30 Aug '23 22 Sep '23 Testing and Commissioning
231 Handover to owner 31 days 30 Aug '23 30 Sep '23
232 Defect rectification 30 days 30 Aug '23 29 Sep '23 Defect rectification
233 Handover to owner 1 day 30 Sep '23 30 Sep '23 Handover to owner
234 LMV Data Centre work (by Others) 96 days 13 Sep '23 18 Dec '23 LMV Data Centre work (by Others)
235 Coordinate with other works 96 days 13 Sep '23 18 Dec '23 Coordinate with other works
236 Parking 164 days 13 Apr '23 26 Sep '23
237 RC Structure 52 days 13 Apr '23 05 Jun '23
238 Excavation including compaction 21 days 13 Apr '23 05 May '23 Excavation including compaction
239 Lean concrete 21 days 16 Apr '23 08 May '23 Lean concrete
240 Rebar, form work, concrete for Foundation 35 days 23 Apr '23 29 May '23 Rebar, form work, concrete for Foundation
241 Rebar, form work, concrete for groundbeam and Stump 35 days 02 May '23 05 Jun '23 Rebar, form work, concrete for groundbeam and Stump column
column
242 Grass concrete Road 56 days 02 Jun '23 27 Jul '23
243 Excavation and remove soil 14 days 02 Jun '23 15 Jun '23 Excavation and remove soil

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 4 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
244 Agregate back fill 14 days 16 Jun '23 29 Jun '23 Agregate back fill
245 Asphalt pavement, light traffic 28 days 30 Jun '23 27 Jul '23 Asphalt pavement, light traffic
246 Steel Structure 60 days 28 Jul '23 26 Sep '23
247 Install Steel Structure 30 days 28 Jul '23 26 Aug '23 Install Steel Structure
248 Metalsheet roof 30 days 27 Aug '23 26 Sep '23 Metalsheet roof
249 MEP works 85 days 01 Jul '23 24 Sep '23
250 Underground Piping/Conduit 18 days 01 Jul '23 18 Jul '23 Underground Piping/Conduit
251 Cable Tray/ Trunking 15 days 28 Jul '23 11 Aug '23 Cable Tray/ Trunking
252 PV Conduit 15 days 01 Sep '23 16 Sep '23 PV Conduit
253 Cabling and wiring works 15 days 18 Aug '23 01 Sep '23 Cabling and wiring works
254 Installation of Lighting, Camera 10 days 03 Sep '23 12 Sep '23 Installation of Lighting, Camera
255 Testing and Commissioning 10 days 15 Sep '23 24 Sep '23 Testing and Commissioning
256 Gate House 1 65 days 06 Jun '23 09 Aug '23
257 RC Structure 38 days 06 Jun '23 13 Jul '23
258 Excavation including compaction 2 days 06 Jun '23 07 Jun '23 Excavation including compaction
259 Lean concrete 1 day 08 Jun '23 08 Jun '23 Lean concrete
260 Pile cut off 1 day 09 Jun '23 09 Jun '23 Pile cut off
261 Rebar, form work, concrete for Foundation 8 days 10 Jun '23 17 Jun '23 Rebar, form work, concrete for Foundation
262 Rebar, form work, concrete for Stump column 5 days 18 Jun '23 22 Jun '23 Rebar, form work, concrete for Stump column
263 Rebar, form work, concrete for Groundbeam and slab 8 days 23 Jun '23 30 Jun '23 Rebar, form work, concrete for Groundbeam and slab

264 Rebar, form work, concrete for column 5 days 01 Jul '23 05 Jul '23 Rebar, form work, concrete for column
265 Rebar, form work, concrete for roof 8 days 06 Jul '23 13 Jul '23 Rebar, form work, concrete for roof
266 Finishing works 27 days 14 Jul '23 09 Aug '23
267 Brickwall and plastering 14 days 14 Jul '23 27 Jul '23 Brickwall and plastering
268 Door & window installation 10 days 21 Jul '23 30 Jul '23 Door & window installation
269 Roof Finishing 10 days 24 Jul '23 02 Aug '23 Roof Finishing
270 Tiling work 7 days 21 Jul '23 27 Jul '23 Tiling work
271 Water proofing 7 days 14 Jul '23 20 Jul '23 Water proofing
272 Painting 10 days 28 Jul '23 06 Aug '23 Painting
273 Other finishings 7 days 03 Aug '23 09 Aug '23 Other finishings
274 MEP works 57 days 06 Jun '23 01 Aug '23
275 Underground Piping/Conduit 2 days 06 Jun '23 07 Jun '23 Underground Piping/Conduit
276 Embeded Conduit 16 days 12 Jun '23 27 Jun '23 Embeded Conduit
277 Cable ladder,Piping, Electric Panel 14 days 09 Jul '23 22 Jul '23 Cable ladder,Piping, Electric Panel
278 Cabling and wiring works 10 days 18 Jul '23 27 Jul '23 Cabling and wiring works
279 Installation of Lighting, Socket 5 days 28 Jul '23 01 Aug '23 Installation of Lighting, Socket
280 Testing 2 days 02 Aug '23 03 Aug '23 Testing
281 Pump House 131 days 14 Jul '23 22 Nov '23
282 Tank Foundation 26 days 14 Jul '23 08 Aug '23
283 Excavation Works 10 days 14 Jul '23 23 Jul '23 Excavation Works
284 Rebar, form work, concrete for Foundation R6250 14 days 17 Jul '23 30 Jul '23 Rebar, form work, concrete for Foundation R6250
285 Rebar, form work, concrete for Foundation R7750 10 days 27 Jul '23 05 Aug '23 Rebar, form work, concrete for Foundation R7750
286 Rebar, form work, concrete for Foundation R4000 7 days 02 Aug '23 08 Aug '23 Rebar, form work, concrete for Foundation R4000
287 Pump House Building 121 days 24 Jul '23 22 Nov '23
288 RC Structure 43 days 24 Jul '23 05 Sep '23
289 Excavation including compaction 2 days 24 Jul '23 25 Jul '23 Excavation including compaction
290 Lean concrete 1 day 26 Jul '23 26 Jul '23 Lean concrete
291 Pile cut off 1 day 27 Jul '23 27 Jul '23 Pile cut off
292 Rebar, form work, concrete for Foundation 10 days 28 Jul '23 06 Aug '23 Rebar, form work, concrete for Foundation
293 Rebar, form work, concrete for Stump column 6 days 07 Aug '23 12 Aug '23 Rebar, form work, concrete for Stump column
294 Rebar, form work, concrete for groundbeam and slab 8 days 13 Aug '23 20 Aug '23 Rebar, form work, concrete for groundbeam and slab

295 Rebar, form work, concrete for column 7 days 21 Aug '23 27 Aug '23 Rebar, form work, concrete for column
296 Rebar, form work, concrete for roof 8 days 28 Aug '23 05 Sep '23 Rebar, form work, concrete for roof
297 Finishing works 41 days 06 Sep '23 16 Oct '23
298 Brickwall and plastering 14 days 06 Sep '23 19 Sep '23 Brickwall and plastering
299 Door & window installation 10 days 20 Sep '23 29 Sep '23 Door & window installation
300 Roof Finishing 14 days 16 Sep '23 29 Sep '23 Roof Finishing
301 Floor Finishing 7 days 20 Sep '23 26 Sep '23 Floor Finishing
302 Wall Finishing 14 days 30 Sep '23 13 Oct '23 Wall Finishing
303 Painting 10 days 27 Sep '23 06 Oct '23 Painting
304 Other finishings 7 days 10 Oct '23 16 Oct '23 Other finishings

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 5 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
305 MEP Works 121 days 24 Jul '23 22 Nov '23
306 MEP Underground works 2 days 24 Jul '23 25 Jul '23 MEP Underground works
307 Earthing & Bonding system 40 days 24 Jul '23 01 Sep '23 Earthing & Bonding system
308 Tray/Trunking, Piping, Duct works 20 days 29 Aug '23 18 Sep '23 Tray/Trunking, Piping, Duct works
309 Cable / Wirring works 15 days 20 Sep '23 04 Oct '23 Cable / Wirring works
310 Installation of Electrical Panel 2 days 05 Oct '23 06 Oct '23 Installation of Electrical Panel
311 Installation of Equipment 10 days 30 Sep '23 09 Oct '23 Installation of Equipment
312 Lightning protection system 3 days 30 Sep '23 02 Oct '23 Lightning protection system
313 Fire Water Tank Installation 30 days 19 Aug '23 18 Sep '23 Fire Water Tank Installation
314 Domestic Tank Installation 30 days 19 Aug '23 18 Sep '23 Domestic Tank Installation
315 Installation of FF Pumps system 30 days 14 Oct '23 12 Nov '23 Installation of FF Pumps system
316 Testing and Commissioning 10 days 13 Nov '23 22 Nov '23 Testing and Commissioning
317 Waste Handling 79 days 06 Sep '23 23 Nov '23
318 RC Structure 38 days 06 Sep '23 13 Oct '23
319 Excavation including compaction 2 days 06 Sep '23 07 Sep '23 Excavation including compaction
320 Lean concrete 1 day 08 Sep '23 08 Sep '23 Lean concrete
321 Pile cut off 1 day 09 Sep '23 09 Sep '23 Pile cut off
322 Rebar, form work, concrete for Foundation 10 days 10 Sep '23 19 Sep '23 Rebar, form work, concrete for Foundation
323 Rebar, form work, concrete for Stump column 5 days 20 Sep '23 24 Sep '23 Rebar, form work, concrete for Stump column
324 Rebar, form work, concrete for groundbeam and slab 8 days 25 Sep '23 02 Oct '23 Rebar, form work, concrete for groundbeam and slab

325 Rebar, form work, concrete for column 5 days 03 Oct '23 07 Oct '23 Rebar, form work, concrete for column
326 Rebar, form work, concrete for roof 6 days 08 Oct '23 13 Oct '23 Rebar, form work, concrete for roof
327 Finishing works 41 days 14 Oct '23 23 Nov '23
328 Brickwall and plastering 14 days 14 Oct '23 27 Oct '23 Brickwall and plastering
329 Door & window installation 10 days 28 Oct '23 06 Nov '23 Door & window installation
330 Roof Finishing 14 days 24 Oct '23 06 Nov '23 Roof Finishing
331 Floor Finishing 7 days 28 Oct '23 03 Nov '23 Floor Finishing
332 Wall Finishing 14 days 28 Oct '23 10 Nov '23 Wall Finishing
333 Painting 10 days 11 Nov '23 20 Nov '23 Painting
334 Other finishings 7 days 17 Nov '23 23 Nov '23 Other finishings
335 MEP Works 77 days 08 Sep '23 23 Nov '23
336 MEP Underground works 2 days 08 Sep '23 09 Sep '23 MEP Underground works
337 Earthing & Bonding system 10 days 08 Sep '23 17 Sep '23 Earthing & Bonding system
338 Tray/Trunking, Piping, Electric Panel works 30 days 04 Oct '23 02 Nov '23 Tray/Trunking, Piping, Electric Panel works
339 Cable/wiring works 10 days 03 Nov '23 12 Nov '23 Cable/wiring works
340 Installation of Equipment 20 days 28 Oct '23 16 Nov '23 Installation of Equipment
341 Lightning protection system 7 days 07 Nov '23 13 Nov '23 Lightning protection system
342 Testing and Commissioning 7 days 17 Nov '23 23 Nov '23 Testing and Commissioning
343 Gate House 2 69 days 06 Sep '23 13 Nov '23
344 RC Structure 38 days 06 Sep '23 13 Oct '23
345 Excavation including compaction 2 days 06 Sep '23 07 Sep '23 Excavation including compaction
346 Lean concrete 1 day 08 Sep '23 08 Sep '23 Lean concrete
347 Pile cut off 1 day 09 Sep '23 09 Sep '23 Pile cut off
348 Rebar, form work, concrete for Foundation 8 days 10 Sep '23 17 Sep '23 Rebar, form work, concrete for Foundation
349 Rebar, form work, concrete for Stump column 5 days 18 Sep '23 22 Sep '23 Rebar, form work, concrete for Stump column
350 Rebar, form work, concrete for Groundbeam and slab 8 days 23 Sep '23 30 Sep '23 Rebar, form work, concrete for Groundbeam and slab

351 Rebar, form work, concrete for column 5 days 01 Oct '23 05 Oct '23 Rebar, form work, concrete for column
352 Rebar, form work, concrete for roof 8 days 06 Oct '23 13 Oct '23 Rebar, form work, concrete for roof
353 Finishing works 27 days 14 Oct '23 09 Nov '23
354 Brickwall and plastering 14 days 14 Oct '23 27 Oct '23 Brickwall and plastering
355 Door & window installation 10 days 21 Oct '23 30 Oct '23 Door & window installation
356 Roof Finishing 10 days 24 Oct '23 02 Nov '23 Roof Finishing
357 Tiling work 7 days 21 Oct '23 27 Oct '23 Tiling work
358 Water proofing 7 days 14 Oct '23 20 Oct '23 Water proofing
359 Painting 10 days 28 Oct '23 06 Nov '23 Painting
360 Other finishings 7 days 03 Nov '23 09 Nov '23 Other finishings
361 MEP works 67 days 08 Sep '23 13 Nov '23
362 Underground Piping/Conduit 2 days 08 Sep '23 09 Sep '23 Underground Piping/Conduit
363 Embeded Conduit 16 days 12 Sep '23 27 Sep '23 Embeded Conduit
364 Cable ladder,Piping, Electric Panel 14 days 03 Oct '23 16 Oct '23 Cable ladder,Piping, Electric Panel
365 Cabling and wiring works 10 days 20 Oct '23 29 Oct '23 Cabling and wiring works

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 6 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
366 Installation of Lighting, Socket, Equipments 5 days 30 Oct '23 03 Nov '23 Installation of Lighting, Socket, Equipments
367 Testing 2 days 12 Nov '23 13 Nov '23 Testing
368 External Works 380 days 20 Mar '23 16 Apr '24
369 Storm Drainage System 192 days 13 Apr '23 24 Oct '23
370 Precast manhole 45 days 13 Apr '23 29 May '23 Precast manhole
371 Soil excavation 45 days 13 Apr '23 29 May '23 Soil excavation
372 Install RC pile and manhole 150 days 06 May '23 03 Oct '23 Install RC pile and manhole
373 Backfill and compacted 150 days 27 May '23 24 Oct '23 Backfill and compacted
374 MEPF External Utilities U/G Trench 380 days 20 Mar '23 16 Apr '24
375 Precast manhole, Soil Excavation, Piping, Testing, Backfill 380 days 20 Mar '23 16 Apr '24 Precast manhole, Soil Excavation, Piping, Testing, Backfill and compacted
and compacted
376 Road and Paving 205 days 30 May '23 21 Dec '23
377 Soil excavation and leveling 75 days 30 May '23 12 Aug '23 Soil excavation and leveling
378 Agregate back fill 75 days 14 Jul '23 27 Sep '23 Agregate back fill
379 Road_Heavy traffic 90 days 18 Aug '23 16 Nov '23 Road_Heavy traffic
380 Road_Light traffic 28 days 10 Nov '23 07 Dec '23 Road_Light traffic
381 Concrete Paving Blocks 21 days 01 Dec '23 21 Dec '23 Concrete Paving Blocks
382 Fencing 255 days 30 Mar '23 12 Dec '23
383 RC Structure Works 180 days 30 Mar '23 28 Sep '23 RC Structure Works
384 Install Steel Frame 90 days 14 Aug '23 12 Nov '23 Install Steel Frame
385 Finishing 90 days 14 Sep '23 12 Dec '23 Finishing
386 Tanks for Waste Water Treatment Plant 45 days 05 Jul '23 18 Aug '23 Tanks for Waste Water Treatment Plant
387 Pellet Filter 21 days 19 Aug '23 09 Sep '23 Pellet Filter
388 Pressure Pipe Reception Pit 18 days 10 Sep '23 27 Sep '23 Pressure Pipe Reception Pit
389 Sandtrap 21 days 28 Sep '23 18 Oct '23 Sandtrap
390 Wier 21 days 19 Oct '23 08 Nov '23 Wier
391 Pump Station 30 days 09 Nov '23 08 Dec '23 Pump Station
392 Landscaping 75 days 22 Oct '23 04 Jan '24 Landscaping
393 STREAM 2_Energy Centre & Infra Connection 390 days 02 Mar '23 08 Apr '24
394 Energy 1 390 days 02 Mar '23 08 Apr '24
395 RC Structure 87 days 16 Mar '23 12 Jun '23
396 Excavation including compaction 28 days 16 Mar '23 12 Apr '23 Excavation including compaction
397 Lean concrete 28 days 18 Mar '23 14 Apr '23 Lean concrete
398 Pile cut off 28 days 19 Mar '23 15 Apr '23 Pile cut off
399 Rebar, form work, concrete for Foundation 45 days 25 Mar '23 10 May '23 Rebar, form work, concrete for Foundation
400 Rebar, form work, concrete for Ground beam & Stump 35 days 08 Apr '23 14 May '23 Rebar, form work, concrete for Ground beam & Stump column
column
401 Rebar, form work, concrete for column 1st Floor 28 days 22 Apr '23 21 May '23 Rebar, form work, concrete for column 1st Floor
402 Soil leveling and compacted for ground floor 14 days 25 Apr '23 10 May '23 Soil leveling and compacted for ground floor
403 Rebar, form work, concrete for beam & slab 2nd floor 35 days 09 May '23 12 Jun '23 Rebar, form work, concrete for beam & slab 2nd floor

404 Dry cooler foundation 54 days 13 Jun '23 05 Aug '23


405 Excavation including compaction 14 days 13 Jun '23 26 Jun '23 Excavation including compaction
406 Lean concrete 14 days 15 Jun '23 28 Jun '23 Lean concrete
407 Rebar, form work, concrete for Foundation 28 days 25 Jun '23 22 Jul '23 Rebar, form work, concrete for Foundation
408 Rebar, form work, concrete for Stump column 28 days 09 Jul '23 05 Aug '23 Rebar, form work, concrete for Stump column
409 Steel Structure Erection 83 days 13 Jun '23 04 Sep '23
410 Steel Structure Erected 28 days 13 Jun '23 10 Jul '23 Steel Structure Erected
411 Steel Purlin 28 days 15 Jun '23 12 Jul '23 Steel Purlin
412 Safety Mesh 18 days 30 Jun '23 17 Jul '23 Safety Mesh
413 Metalsheet Roof 14 days 13 Jul '23 26 Jul '23 Metalsheet Roof
414 Fireproof Paint 21 days 14 Aug '23 04 Sep '23 Fireproof Paint
415 Ground Slab 39 days 06 Jul '23 13 Aug '23
416 Soil Leveling and compacted for ground floor 14 days 06 Jul '23 19 Jul '23 Soil Leveling and compacted for ground floor
417 Termite treatment & Lean Concrete 14 days 13 Jul '23 27 Jul '23 Termite treatment & Lean Concrete
418 Rebar, form work, concrete for Groundslab 18 days 27 Jul '23 13 Aug '23 Rebar, form work, concrete for Groundslab
419 Finishing Works 244 days 27 Jun '23 08 Mar '24
420 Mansonry Work 65 days 27 Jun '23 30 Aug '23 Mansonry Work
421 Door and Windown 45 days 22 Jul '23 05 Sep '23 Door and Windown
422 Waterproofing Works 14 days 21 Aug '23 04 Sep '23 Waterproofing Works
423 Roof Finshing 21 days 03 Aug '23 23 Aug '23 Roof Finshing
424 Tiling Works 28 days 31 Aug '23 28 Sep '23 Tiling Works
425 Ceiling Works 24 days 08 Sep '23 01 Oct '23 Ceiling Works
426 Panel Works 45 days 31 Aug '23 15 Oct '23 Panel Works

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 7 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
427 Floor Finishing 21 days 22 Sep '23 12 Oct '23 Floor Finishing
428 Painting Works 30 days 08 Sep '23 07 Oct '23 Painting Works
429 Metal Works 21 days 20 Sep '23 10 Oct '23 Metal Works
430 Sanitary Installation 21 days 15 Sep '23 05 Oct '23 Sanitary Installation
431 Finishing works after chillers complete installation 21 days 14 Feb '24 08 Mar '24 Finishing works after chillers complete installation
432 MEPF Works 389 days 02 Mar '23 07 Apr '24
433 Earthing system 40 days 02 Mar '23 10 Apr '23 Earthing system
434 Underground Piping/Conduit 28 days 02 Mar '23 29 Mar '23 Underground Piping/Conduit
435 Embeded Conduit 18 days 13 Jul '23 30 Jul '23 Embeded Conduit
436 Tray/Trunking, Piping,Trans, Electric Panels,Busway 30 days 31 Jul '23 29 Aug '23 Tray/Trunking, Piping,Trans, Electric Panels,Busway works
works
437 Lightning protection and grounding system 164 days 02 Mar '23 14 Aug '23 Lightning protection and grounding system
438 Cabling and wiring works 30 days 16 Jul '23 14 Aug '23 Cabling and wiring works
439 Installation of Air Con., Lighting, Camera, etc… 30 days 13 Aug '23 12 Sep '23 Installation of Air Con., Lighting, Camera, etc…
440 Installation of Electrical Panel,UPS 30 days 03 Sep '23 02 Oct '23 Installation of Electrical Panel,UPS
441 Data Center MEP works 30 days 13 Aug '23 12 Sep '23 Data Center MEP works
442 Testing and Commissioning 23 days 03 Oct '23 25 Oct '23 Testing and Commissioning
443 Chiller Plan Installation 2sets 30 days 18 Sep '23 17 Oct '23 Chiller Plan Installation 2sets
444 Chiller Plan Installation 4sets 30 days 29 Dec '23 27 Jan '24 Chiller Plan Installation 4sets
445 Dry Coolers (ENC) 30 days 23 Jul '23 21 Aug '23 Dry Coolers (ENC)
446 Air Compressor (ENC) 40 days 08 Jun '23 17 Jul '23 Air Compressor (ENC)
447 MV Switchgears, Transformers, MSB (ENC) 60 days 03 Sep '23 01 Nov '23 MV Switchgears, Transformers, MSB (ENC)
448 BMS Installation 60 days 22 Aug '23 21 Oct '23 BMS Installation
449 First Testing & Commissioning with 2 Chiller 60 days 02 Nov '23 31 Dec '23 First Testing & Commissioning with 2 Chiller
450 Testing and Commissioning 60 days 28 Jan '24 07 Apr '24 Testing and Commissioning
451 Handover to owner 1 day 08 Apr '24 08 Apr '24
452 Handover to Others 1 day 08 Apr '24 08 Apr '24 Handover to Others
453 LMV Data Centre work 79 days 01 Oct '23 18 Dec '23 LMV Data Centre work
454 BMS to be "Online" 21 days 28 Jan '24 28 Feb '24 BMS to be "Online"
455 STREAM 3_Construction & LEGO Equipment 345 days 05 Mar '23 26 Feb '24
456 Moulding Building 344 days 05 Mar '23 25 Feb '24
457 RC Structure 80 days 05 Mar '23 25 May '23
458 Excavation including compaction 42 days 05 Mar '23 15 Apr '23 Excavation including compaction
459 Lean concrete 42 days 07 Mar '23 17 Apr '23 Lean concrete
460 Pile cut off 42 days 09 Mar '23 19 Apr '23 Pile cut off
461 Rebar, form work, concrete for Foundation 65 days 14 Mar '23 19 May '23 Rebar, form work, concrete for Foundation
462 Rebar, form work, concrete for Ground beam & Stump 50 days 04 Apr '23 25 May '23 Rebar, form work, concrete for Ground beam & Stump column
column
463 Silo foundation 37 days 29 Aug '23 05 Oct '23
464 Excavation including compaction 15 days 29 Aug '23 13 Sep '23 Excavation including compaction
465 Lean concrete 7 days 14 Sep '23 20 Sep '23 Lean concrete
466 Rebar, form work, concrete for Foundation 15 days 21 Sep '23 05 Oct '23 Rebar, form work, concrete for Foundation
467 Steel Structure Erection 166 days 05 May '23 18 Oct '23
468 Steel Structure Frame 55 days 05 May '23 28 Jun '23 Steel Structure Frame
469 Steel Purlin 42 days 21 May '23 01 Jul '23 Steel Purlin
470 Safety Mesh 28 days 09 Jun '23 06 Jul '23 Safety Mesh
471 Metalsheet Roof 28 days 02 Jul '23 29 Jul '23 Metalsheet Roof
472 Fireproof Paint 45 days 04 Sep '23 18 Oct '23 Fireproof Paint
473 Steel Structure for crane and racking 30 days 29 Jun '23 28 Jul '23 Steel Structure for crane and racking
474 Ground Slab 77 days 18 Jun '23 03 Sep '23
475 Soil Leveling and compacted for ground floor 21 days 18 Jun '23 09 Jul '23 Soil Leveling and compacted for ground floor
476 Termite treatment & Lean Concrete 21 days 09 Jul '23 30 Jul '23 Termite treatment & Lean Concrete
477 Rebar, form work, concrete for Groundslab 35 days 30 Jul '23 03 Sep '23 Rebar, form work, concrete for Groundslab
478 Penhouse Structure 28 days 21 Jul '23 17 Aug '23
479 Install Metal Sheet 14 days 21 Jul '23 03 Aug '23 Install Metal Sheet
480 Rebar, form work, concrete for Slab 21 days 28 Jul '23 17 Aug '23 Rebar, form work, concrete for Slab
481 Finishing Works 119 days 13 Aug '23 10 Dec '23
482 1.103 material Drying Room 39 days 20 Aug '23 28 Sep '23
483 Mansonry Work 21 days 20 Aug '23 10 Sep '23 Mansonry Work
484 Door and Windown 10 days 08 Sep '23 17 Sep '23 Door and Windown
485 Floor Finishing 7 days 18 Sep '23 24 Sep '23 Floor Finishing
486 Metal Works 14 days 13 Sep '23 26 Sep '23 Metal Works
487 Others Works 7 days 22 Sep '23 28 Sep '23 Others Works

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 8 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
488 1.106 Equip cleaning Room 49 days 04 Sep '23 22 Oct '23
489 Mansonry Work 28 days 04 Sep '23 01 Oct '23 Mansonry Work
490 Door and Windown 14 days 25 Sep '23 08 Oct '23 Door and Windown
491 Floor Finishing 10 days 09 Oct '23 18 Oct '23 Floor Finishing
492 Metal Works 14 days 07 Oct '23 20 Oct '23 Metal Works
493 Others Works 7 days 16 Oct '23 22 Oct '23 Others Works
494 Mol 1.102 64 days 08 Oct '23 10 Dec '23
495 Mansonry Work 35 days 08 Oct '23 11 Nov '23 Mansonry Work
496 Door and Windown 21 days 01 Nov '23 21 Nov '23 Door and Windown
497 Floor Finishing 14 days 22 Nov '23 05 Dec '23 Floor Finishing
498 Metal Works 14 days 24 Nov '23 07 Dec '23 Metal Works
499 Others Works 7 days 04 Dec '23 10 Dec '23 Others Works
500 All other rooms 98 days 13 Aug '23 19 Nov '23
501 Mansonry Work 55 days 13 Aug '23 07 Oct '23 Mansonry Work
502 Door and Windown 35 days 27 Sep '23 31 Oct '23 Door and Windown
503 Waterproofing Works 30 days 18 Sep '23 17 Oct '23 Waterproofing Works
504 Roof Finshing 45 days 04 Sep '23 18 Oct '23 Roof Finshing
505 Tiling Works 28 days 25 Sep '23 22 Oct '23 Tiling Works
506 Ceiling Works 45 days 20 Sep '23 03 Nov '23 Ceiling Works
507 Panel Works 45 days 24 Sep '23 07 Nov '23 Panel Works
508 Floor Finishing 30 days 10 Oct '23 08 Nov '23 Floor Finishing
509 Painting Works 45 days 30 Sep '23 13 Nov '23 Painting Works
510 Metal Works 30 days 18 Oct '23 16 Nov '23 Metal Works
511 Sanitary Installation 28 days 23 Oct '23 19 Nov '23 Sanitary Installation
512 Others Works 21 days 30 Oct '23 19 Nov '23 Others Works
513 MEPF Works 342 days 07 Mar '23 25 Feb '24
514 Earthing system 175 days 10 Mar '23 03 Sep '23 Earthing system
515 Underground Piping/Conduit 130 days 07 Mar '23 16 Jul '23 Underground Piping/Conduit
516 Tray/Trunking, Piping, Duct works 75 days 20 Jul '23 03 Oct '23 Tray/Trunking, Piping, Duct works
517 Lightning protection system 30 days 30 Jul '23 28 Aug '23 Lightning protection system
518 Cable Laying and Busway 70 days 24 Aug '23 02 Nov '23 Cable Laying and Busway
519 Installation of Air Con, Lighting, Camera, etc… 70 days 04 Sep '23 12 Nov '23 Installation of Air Con, Lighting, Camera, etc…
520 MV Switchgears, Transformers, LV Panels 40 days 13 Oct '23 21 Nov '23 MV Switchgears, Transformers, LV Panels
521 BMS Installation, Programming 60 days 22 Aug '23 21 Oct '23 BMS Installation, Programming
522 PV 1MWp Roof top 90 days 19 Aug '23 17 Nov '23 PV 1MWp Roof top
523 Testing and Commissioning 60 days 17 Dec '23 25 Feb '24 Testing and Commissioning
524 Defect and Minor Works 30 days 11 Dec '23 09 Jan '24 Defect and Minor Works
525 Service Building 304 days 15 Apr '23 26 Feb '24
526 RC Structure 79 days 15 Apr '23 04 Jul '23
527 Excavation including compaction 28 days 15 Apr '23 14 May '23 Excavation including compaction
528 Lean concrete 28 days 17 Apr '23 16 May '23 Lean concrete
529 Pile cut off 28 days 19 Apr '23 18 May '23 Pile cut off
530 Rebar, form work, concrete for Foundation 54 days 24 Apr '23 18 Jun '23 Rebar, form work, concrete for Foundation
531 Rebar, form work, concrete for Ground beam & Stump 49 days 17 May '23 04 Jul '23 Rebar, form work, concrete for Ground beam & Stump column
column
532 Steel Structure Erection 137 days 21 Jun '23 05 Nov '23
533 Steel Structure Frame 45 days 21 Jun '23 04 Aug '23 Steel Structure Frame
534 Steel Purlin 30 days 09 Jul '23 07 Aug '23 Steel Purlin
535 Safety Mesh 28 days 16 Jul '23 12 Aug '23 Safety Mesh
536 Metalsheet Roof 24 days 08 Aug '23 31 Aug '23 Metalsheet Roof
537 Fireproof Paint 30 days 07 Oct '23 05 Nov '23 Fireproof Paint
538 Ground Slab 77 days 21 Jul '23 06 Oct '23
539 Soil Leveling and compacted for ground floor 21 days 21 Jul '23 11 Aug '23 Soil Leveling and compacted for ground floor
540 Termite treatment & Lean Concrete 21 days 11 Aug '23 01 Sep '23 Termite treatment & Lean Concrete
541 Rebar, form work, concrete for Groundslab 35 days 01 Sep '23 06 Oct '23 Rebar, form work, concrete for Groundslab
542 Finishing Works 113 days 16 Sep '23 06 Jan '24
543 Mansonry Work 65 days 16 Sep '23 19 Nov '23 Mansonry Work
544 Door and Windown 45 days 27 Oct '23 10 Dec '23 Door and Windown
545 Waterproofing Works 21 days 21 Oct '23 10 Nov '23 Waterproofing Works
546 Roof Finshing 30 days 07 Oct '23 05 Nov '23 Roof Finshing
547 Tiling Works 28 days 31 Oct '23 27 Nov '23 Tiling Works
548 Ceiling Works 21 days 13 Nov '23 03 Dec '23 Ceiling Works
549 Panel Works 35 days 15 Nov '23 19 Dec '23 Panel Works

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 9 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
550 Floor Finishing 28 days 16 Nov '23 13 Dec '23 Floor Finishing
551 Painting Works 30 days 24 Nov '23 23 Dec '23 Painting Works
552 Metal Works 21 days 10 Dec '23 30 Dec '23 Metal Works
553 Sanitary Installation 21 days 28 Nov '23 18 Dec '23 Sanitary Installation
554 Others Works 14 days 24 Dec '23 06 Jan '24 Others Works
555 MEPF Works 219 days 11 Jul '23 26 Feb '24
556 Earthing system 100 days 11 Jul '23 19 Oct '23 Earthing system
557 Underground Piping/Conduit 30 days 01 Aug '23 30 Aug '23 Underground Piping/Conduit
558 Tray/Trunking, Piping, Duct works 60 days 01 Sep '23 31 Oct '23 Tray/Trunking, Piping, Duct works
559 Lightning protection system 20 days 01 Sep '23 21 Sep '23 Lightning protection system
560 Cable Laying and Busway 50 days 07 Oct '23 25 Nov '23 Cable Laying and Busway
561 Installation of Air Con., Lighting, Camera, etc… 60 days 01 Nov '23 30 Dec '23 Installation of Air Con., Lighting, Camera, etc…
562 MV Switchgears, Transformers, LV Panels 45 days 03 Nov '23 17 Dec '23 MV Switchgears, Transformers, LV Panels
563 Data Center MEP Works 32 days 01 Nov '23 02 Dec '23 Data Center MEP Works
564 BMS Installation, Programming 60 days 01 Nov '23 30 Dec '23 BMS Installation, Programming
565 Testing and Commissioning 60 days 18 Dec '23 26 Feb '24 Testing and Commissioning
566 Handover 1 day 03 Dec '23 03 Dec '23
567 Data Center handover 1 day 03 Dec '23 03 Dec '23 Data Center handover
568 LMV Data Centre work 64 days 04 Dec '23 06 Feb '24 LMV Data Centre work
569 Mould Bunka 1 day 07 Oct '23 07 Oct '23 Mould Bunka
570 MEPF running on manual control 15 days 14 Feb '24 02 Mar '24 MEPF running on manual control
571 Running on full "online" BMS control 15 days 20 Feb '24 05 Mar '24 Running on full "online" BMS control
572 Coordinate with Process Equipment Installation 76 days 04 Dec '23 28 Feb '24 Coordinate with Process Equipment Installation
573 Complete and handover Stream 1, 2, 3 160 days 13 Oct '23 31 Mar '24
574 Fire Fighting inspection 113 days 13 Oct '23 02 Feb '24
575 Submit all documents for invitation 1 day 13 Oct '23 13 Oct '23 Submit all documents for invitation
576 1st inspection from authority 1 day 28 Nov '23 28 Nov '23 1st inspection from authority
577 Final inspection from authority 1 day 29 Dec '23 29 Dec '23 Final inspection from authority
578 Fire Fireting Certificate 35 days 30 Dec '23 02 Feb '24 Fire Fireting Certificate
579 Occupation certificate 120 days 22 Nov '23 31 Mar '24 Occupation certificate
580 Close out (cleaning, punch list/ defects) 45 days 06 Feb '24 31 Mar '24 Close out (cleaning, punch list/ defects)
581 Complete Construction (project handover) 30 days 02 Mar '24 31 Mar '24 Complete Construction (project handover)
582 Complete As-Built Documentation 21 days 15 Jan '24 05 Feb '24 Complete As-Built Documentation
583 Signing Taking-Over Certificate 10 days 22 Mar '24 31 Mar '24 Signing Taking-Over Certificate
584 STREAM 4_Construction Works 395 days 13 Mar '23 24 Apr '24
585 Piling Works 84 days 13 Mar '23 06 Jun '23
586 Pile Test 21 days 13 Mar '23 02 Apr '23
587 Pile Driving 5 days 13 Mar '23 17 Mar '23 Pile Driving
588 Pile Test 14 days 20 Mar '23 02 Apr '23 Pile Test
589 Mast Pile Works 63 days 03 Apr '23 06 Jun '23
590 Handling Building 21 days 03 Apr '23 23 Apr '23 Handling Building
591 Manual Warehouse 45 days 03 Apr '23 19 May '23 Manual Warehouse
592 Final Pack 21 days 24 Apr '23 16 May '23 Final Pack
593 Pre Pack 21 days 17 May '23 06 Jun '23 Pre Pack
594 Packing Area PP1, PP2, FP1 332 days 17 May '23 24 Apr '24
595 RC Structure PP1 83 days 17 May '23 07 Aug '23
596 Excavation including compaction 18 days 17 May '23 03 Jun '23 Excavation including compaction
597 Lean concrete 18 days 19 May '23 05 Jun '23 Lean concrete
598 Pile cut off 18 days 21 May '23 07 Jun '23 Pile cut off
599 Rebar, form work, concrete for Foundation 28 days 26 May '23 22 Jun '23 Rebar, form work, concrete for Foundation
600 Rebar, form work, concrete for Ground beam & Stump column 28 days 09 Jun '23 06 Jul '23 Rebar, form work, concrete for Ground beam & Stump column

601 Rebar, form work, concrete for 1st column 14 days 01 Jul '23 14 Jul '23 Rebar, form work, concrete for 1st column
602 Rebar, form work, concrete for 1st floor 10 days 15 Jul '23 24 Jul '23 Rebar, form work, concrete for 1st floor
603 Rebar, form work, concrete for 2nd column 7 days 25 Jul '23 31 Jul '23 Rebar, form work, concrete for 2nd column
604 Rebar, form work, concrete for 2nd floor 7 days 01 Aug '23 07 Aug '23 Rebar, form work, concrete for 2nd floor
605 RC Structure PP2 83 days 07 Jul '23 28 Sep '23
606 Excavation including compaction 18 days 07 Jul '23 24 Jul '23 Excavation including compaction
607 Lean concrete 18 days 09 Jul '23 26 Jul '23 Lean concrete
608 Pile cut off 18 days 11 Jul '23 28 Jul '23 Pile cut off
609 Rebar, form work, concrete for Foundation 28 days 16 Jul '23 12 Aug '23 Rebar, form work, concrete for Foundation
610 Rebar, form work, concrete for Ground beam & Stump column 28 days 30 Jul '23 26 Aug '23 Rebar, form work, concrete for Ground beam & Stump column

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 10 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
611 Rebar, form work, concrete for 1st column 14 days 21 Aug '23 04 Sep '23 Rebar, form work, concrete for 1st column
612 Rebar, form work, concrete for 1st floor 10 days 05 Sep '23 14 Sep '23 Rebar, form work, concrete for 1st floor
613 Rebar, form work, concrete for 2nd column 7 days 15 Sep '23 21 Sep '23 Rebar, form work, concrete for 2nd column
614 Rebar, form work, concrete for 2nd floor 7 days 22 Sep '23 28 Sep '23 Rebar, form work, concrete for 2nd floor
615 RC Structure FP1 51 days 27 Aug '23 17 Oct '23
616 Excavation including compaction 18 days 27 Aug '23 14 Sep '23 Excavation including compaction
617 Lean concrete 18 days 29 Aug '23 16 Sep '23 Lean concrete
618 Pile cut off 18 days 31 Aug '23 18 Sep '23 Pile cut off
619 Rebar, form work, concrete for Foundation 28 days 06 Sep '23 03 Oct '23 Rebar, form work, concrete for Foundation
620 Rebar, form work, concrete for Ground beam & Stump column 28 days 20 Sep '23 17 Oct '23 Rebar, form work, concrete for Ground beam & Stump column

621 Steel Structure Erection 147 days 27 Aug '23 21 Jan '24
622 Steel Structure Frame 65 days 27 Aug '23 31 Oct '23 Steel Structure Frame
623 Steel Purlin 45 days 20 Sep '23 03 Nov '23 Steel Purlin
624 Safety Mesh 28 days 12 Oct '23 08 Nov '23 Safety Mesh
625 Metalsheet Roof 28 days 04 Nov '23 01 Dec '23 Metalsheet Roof
626 Fireproof Paint 30 days 23 Dec '23 21 Jan '24 Fireproof Paint
627 RC Work for upper floor 30 days 01 Nov '23 30 Nov '23 RC Work for upper floor
628 Ground Slab 77 days 07 Oct '23 22 Dec '23
629 Soil Leveling and compacted for ground floor 21 days 07 Oct '23 28 Oct '23 Soil Leveling and compacted for ground floor
630 Termite treatment & Lean Concrete 21 days 28 Oct '23 18 Nov '23 Termite treatment & Lean Concrete
631 Rebar, form work, concrete for Groundslab 35 days 18 Nov '23 22 Dec '23 Rebar, form work, concrete for Groundslab
632 Finishing Works 209 days 18 Sep '23 24 Apr '24
633 Mansonry Work 120 days 18 Sep '23 15 Jan '24 Mansonry Work
634 Door and Windown 60 days 17 Dec '23 25 Feb '24 Door and Windown
635 Waterproofing Works 21 days 06 Jan '24 26 Jan '24 Waterproofing Works
636 Roof Finshing 30 days 23 Dec '23 21 Jan '24 Roof Finshing
637 Tiling Works 21 days 16 Jan '24 06 Feb '24 Tiling Works
638 Ceiling Works 35 days 30 Jan '24 15 Mar '24 Ceiling Works
639 Panel Works 35 days 16 Jan '24 01 Mar '24 Panel Works
640 Floor Finishing 40 days 05 Feb '24 25 Mar '24 Floor Finishing
641 Painting Works 30 days 06 Mar '24 04 Apr '24 Painting Works
642 Metal Works 21 days 22 Mar '24 11 Apr '24 Metal Works
643 Others Works 14 days 11 Apr '24 24 Apr '24 Others Works
644 MEP Works 297 days 17 May '23 20 Mar '24
645 Earthing system 120 days 17 May '23 14 Sep '23 Earthing system
646 Underground Piping/Conduit 120 days 17 May '23 14 Sep '23 Underground Piping/Conduit
647 Tray/Trunking, Piping, Duct works 50 days 04 Nov '23 23 Dec '23 Tray/Trunking, Piping, Duct works
648 Lightning protection system 20 days 02 Dec '23 21 Dec '23 Lightning protection system
649 Cable Laying and Busway 50 days 29 Nov '23 17 Jan '24 Cable Laying and Busway
650 Installation of Air Con., Lighting, Camera, etc… 60 days 24 Dec '23 03 Mar '24 Installation of Air Con., Lighting, Camera, etc…
651 MV Switchgears, Transformers, LV Panels 45 days 26 Dec '23 19 Feb '24 MV Switchgears, Transformers, LV Panels
652 Data Center MEP Works 32 days 24 Dec '23 24 Jan '24 Data Center MEP Works
653 Testing and Commissioning 30 days 20 Feb '24 20 Mar '24 Testing and Commissioning
654 LEGO Handling Equipment 134 days 17 Apr '24 28 Aug '24 LEGO Handling Equipment
655 Manual Warehouse 281 days 07 Jul '23 24 Apr '24
656 RC Structure 80 days 07 Jul '23 25 Sep '23
657 Excavation including compaction 45 days 07 Jul '23 20 Aug '23 Excavation including compaction
658 Lean concrete 45 days 09 Jul '23 22 Aug '23 Lean concrete
659 Pile cut off 45 days 11 Jul '23 24 Aug '23 Pile cut off
660 Rebar, form work, concrete for Foundation 65 days 16 Jul '23 19 Sep '23 Rebar, form work, concrete for Foundation
661 Rebar, form work, concrete for Ground beam & Stump column 50 days 06 Aug '23 25 Sep '23 Rebar, form work, concrete for Ground beam & Stump column

662 Steel Structure Erection 176 days 05 Sep '23 09 Mar '24
663 Steel Structure Frame 55 days 05 Sep '23 29 Oct '23 Steel Structure Frame
664 Steel Purlin 42 days 21 Sep '23 01 Nov '23 Steel Purlin
665 Safety Mesh 28 days 10 Oct '23 06 Nov '23 Safety Mesh
666 Metalsheet Roof 28 days 02 Nov '23 29 Nov '23 Metalsheet Roof
667 Fireproof Paint 45 days 14 Jan '24 09 Mar '24 Fireproof Paint
668 Steel Structure for crane and racking 30 days 30 Oct '23 28 Nov '23 Steel Structure for crane and racking
669 Ground Slab 105 days 01 Oct '23 13 Jan '24
670 Soil Leveling and compacted for ground floor 30 days 01 Oct '23 31 Oct '23 Soil Leveling and compacted for ground floor
671 Termite treatment & Lean Concrete 30 days 31 Oct '23 30 Nov '23 Termite treatment & Lean Concrete

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 11 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
672 Rebar, form work, concrete for Groundslab 45 days 30 Nov '23 13 Jan '24 Rebar, form work, concrete for Groundslab
673 Upper Structure floor 37 days 23 Nov '23 29 Dec '23
674 Install Metal Deck 21 days 23 Nov '23 13 Dec '23 Install Metal Deck
675 Rebar, form work, concrete for upper slab 30 days 30 Nov '23 29 Dec '23 Rebar, form work, concrete for upper slab
676 Finishing Works 206 days 21 Sep '23 24 Apr '24
677 Mansonry Work 120 days 21 Sep '23 18 Jan '24 Mansonry Work
678 Door and Windown 60 days 20 Dec '23 28 Feb '24 Door and Windown
679 Waterproofing Works 21 days 06 Jan '24 26 Jan '24 Waterproofing Works
680 Roof Finshing 30 days 23 Dec '23 21 Jan '24 Roof Finshing
681 Tiling Works 21 days 16 Jan '24 06 Feb '24 Tiling Works
682 Ceiling Works 35 days 02 Feb '24 18 Mar '24 Ceiling Works
683 Panel Works 35 days 02 Feb '24 18 Mar '24 Panel Works
684 Floor Finishing 28 days 01 Mar '24 28 Mar '24 Floor Finishing
685 Painting Works 30 days 09 Mar '24 07 Apr '24 Painting Works
686 Metal Works 21 days 28 Mar '24 17 Apr '24 Metal Works
687 Sanitary Installation 21 days 31 Mar '24 20 Apr '24 Sanitary Installation
688 Others Works 14 days 11 Apr '24 24 Apr '24 Others Works
689 MEP Works 281 days 07 Jul '23 24 Apr '24
690 Earthing system 120 days 07 Jul '23 04 Nov '23 Earthing system
691 Underground Piping/Conduit 120 days 07 Jul '23 04 Nov '23 Underground Piping/Conduit
692 Tray/Trunking, Piping, Duct works 60 days 02 Nov '23 31 Dec '23 Tray/Trunking, Piping, Duct works
693 Lightning protection system 20 days 30 Nov '23 19 Dec '23 Lightning protection system
694 Cable Laying and Busway 60 days 07 Dec '23 05 Feb '24 Cable Laying and Busway
695 Installation of Air Con., Lighting, Camera, etc… 60 days 11 Jan '24 21 Mar '24 Installation of Air Con., Lighting, Camera, etc…
696 MV Switchgears, Transformers, LV Panels 45 days 13 Jan '24 08 Mar '24 MV Switchgears, Transformers, LV Panels
697 Data Center MEP Works 32 days 11 Jan '24 22 Feb '24 Data Center MEP Works
698 Testing and Commissioning 50 days 06 Mar '24 24 Apr '24 Testing and Commissioning
699 LEGO Handling Equipment 138 days 03 Apr '24 18 Aug '24 LEGO Handling Equipment
700 Handling Building and Corridor 279 days 25 Jun '23 10 Apr '24
701 RC Structure 60 days 25 Jun '23 23 Aug '23
702 Excavation including compaction 35 days 25 Jun '23 29 Jul '23 Excavation including compaction
703 Lean concrete 35 days 27 Jun '23 31 Jul '23 Lean concrete
704 Pile cut off 35 days 29 Jun '23 02 Aug '23 Pile cut off
705 Rebar, form work, concrete for Foundation 40 days 04 Jul '23 12 Aug '23 Rebar, form work, concrete for Foundation
706 Rebar, form work, concrete for Ground beam & Stump column 30 days 25 Jul '23 23 Aug '23 Rebar, form work, concrete for Ground beam & Stump column

707 Steel Structure Erection 152 days 24 Aug '23 23 Jan '24
708 Steel Structure Frame 65 days 24 Aug '23 28 Oct '23 Steel Structure Frame
709 Steel Purlin 21 days 15 Oct '23 04 Nov '23 Steel Purlin
710 Safety Mesh 14 days 27 Oct '23 09 Nov '23 Safety Mesh
711 Metalsheet Roof 14 days 05 Nov '23 18 Nov '23 Metalsheet Roof
712 Fireproof Paint 45 days 10 Dec '23 23 Jan '24 Fireproof Paint
713 Steel Structure for crane and racking 30 days 29 Oct '23 27 Nov '23 Steel Structure for crane and racking
714 Ground Slab 49 days 22 Oct '23 09 Dec '23
715 Soil Leveling and compacted for ground floor 14 days 22 Oct '23 05 Nov '23 Soil Leveling and compacted for ground floor
716 Termite treatment & Lean Concrete 14 days 05 Nov '23 19 Nov '23 Termite treatment & Lean Concrete
717 Rebar, form work, concrete for Groundslab 21 days 19 Nov '23 09 Dec '23 Rebar, form work, concrete for Groundslab
718 Upper Structure floor 67 days 29 Oct '23 03 Jan '24
719 Install Metal Deck 45 days 29 Oct '23 12 Dec '23 Install Metal Deck
720 Rebar, form work, concrete for upper slab 60 days 05 Nov '23 03 Jan '24 Rebar, form work, concrete for upper slab
721 Finishing Works 133 days 19 Nov '23 10 Apr '24
722 Mansonry Work 60 days 19 Nov '23 17 Jan '24 Mansonry Work
723 Door and Windown 45 days 03 Jan '24 27 Feb '24 Door and Windown
724 Waterproofing Works 21 days 06 Jan '24 26 Jan '24 Waterproofing Works
725 Roof Finshing 30 days 23 Dec '23 21 Jan '24 Roof Finshing
726 Ceiling Works 21 days 01 Feb '24 03 Mar '24 Ceiling Works
727 Panel Works 21 days 01 Feb '24 03 Mar '24 Panel Works
728 Floor Finishing 21 days 22 Feb '24 13 Mar '24 Floor Finishing
729 Painting Works 28 days 25 Feb '24 23 Mar '24 Painting Works
730 Metal Works 21 days 10 Mar '24 30 Mar '24 Metal Works
731 Others Works 14 days 28 Mar '24 10 Apr '24 Others Works
732 MEP Works 181 days 05 Aug '23 02 Feb '24
733 Underground Piping/Conduit 35 days 05 Aug '23 09 Sep '23 Underground Piping/Conduit

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 12 of 13


PROPOSED MASTER CONSTRUCTION SCHEDULE
Project: LEGO GROUP MANUFACTURING VIETNAM PROJECT
Package: General Contractor
Location: VSIP3 IP, Bac Tan Uyen, Binh Duong, Vietnam
Date: 24 Jun 2022, Revision: 1
ID Task Name Duration Start Finish
Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023 Qtr 4, 2023 Qtr 1, 2024 Qtr 2, 2024 Qtr 3, 2024 Qtr 4, 2024 Qtr 1, 2025 Qtr 2, 2025
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May
734 Tray/Trunking, Piping, Duct, Electric Panels works 40 days 10 Nov '23 19 Dec '23 Tray/Trunking, Piping, Duct, Electric Panels works
735 Cabling and wiring works 20 days 15 Dec '23 03 Jan '24 Cabling and wiring works
736 Installation of Lighting, Socket, Equipments 20 days 04 Jan '24 23 Jan '24 Installation of Lighting, Socket, Equipments
737 Testing and Commissioning 10 days 24 Jan '24 02 Feb '24 Testing and Commissioning
738 LEGO Handling Equipment 136 days 02 Apr '24 15 Aug '24 LEGO Handling Equipment
739 Complete and handover STREAM 4 158 days 25 May '24 29 Oct '24
740 Fire Fighting inspection 113 days 25 May '24 14 Sep '24
741 Submit all documents for authority 1 day 25 May '24 25 May '24 Submit all documents for authority
742 1st inspection from authority 1 day 10 Jul '24 10 Jul '24 1st inspection from authority
743 Final inspection from authority 1 day 10 Aug '24 10 Aug '24 Final inspection from authority
744 Fire Fighting Certificate 35 days 11 Aug '24 14 Sep '24 Fire Fighting Certificate
745 Occupation certificate 120 days 02 Jul '24 29 Oct '24 Occupation certificate
746 Close out (cleaning, punch list/ defects) 45 days 15 Sep '24 29 Oct '24 Close out (cleaning, punch list/ defects)
747 Complete Construction (project handover) 30 days 30 Sep '24 29 Oct '24 Complete Construction (project handover)
748 Complete As-Built Documentation 21 days 25 Aug '24 14 Sep '24 Complete As-Built Documentation
749 Signing Taking-Over Certificate 10 days 20 Oct '24 29 Oct '24 Signing Taking-Over Certificate

Task Rolled Up Task Split Inactive Task Duration-only Finish-only

Project: LEGO GROUP MANUFACTU Critical Task Rolled Up Critical Task External Tasks Inactive Milestone Manual Summary Rollup Baseline
Date: 24 Jun 2022
Milestone Rolled Up Milestone Project Summary Inactive Summary Manual Summary Progress

Summary Rolled Up Progress Group By SummTask Manual Task Start-only Critical Task

Prepared by: Tuan Le Construction Co. Ltd. Page 13 of 13