ID Task Name Duration Start Finish Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023

Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
1 PLANT-PKS PKE_WAREHOUSE 0 days 7/1/22 7/1/22
2 MILESTONE 0 days 8/31/23 8/31/23
3 PKS PKE export conveyor ‐ On Site 0 days 4/18/23 4/18/23 April 18, 2023
4 PKS PKE export conveyor ‐ Commissioning 0 days 7/29/23 7/29/23 July 29, 2023
5 PKS PKE unloading station conveyor ‐ On Site 0 days 4/18/23 4/18/23 April 18, 2023
6 PKS PKE unloading station conveyor ‐ Commissioning 0 days 7/30/23 7/30/23 July 30, 2023
7 Weighbridge x 4 unit ‐ On Site 0 days 12/17/22 12/17/22 December 17, 2022
8 Truck hydraulic tipper ‐ On Site 0 days 12/17/22 12/17/22 December 17, 2022
9 PKS processing equipment‐De stoner ‐ On Site 0 days 12/17/22 12/17/22 December 17, 2022
10 PKS processing equipment‐De stoner ‐ Commissioning 0 days 8/3/23 8/3/23 August 3, 2023
11 Shiploader supplier ‐ On Site 0 days 7/6/23 7/6/23 July 6, 2023
12 Execute Planning 443 days 7/1/22 8/31/23
13 Phase - Design & Engineering 184 days 7/1/22 12/26/22
14 PKS PKE export conveyor design ‐ AE Auto 21 days 7/1/22 7/20/22
15 PKS PKE unloading station conveyor design ‐ AE Auto 28 days 8/9/22 9/5/22
16 Appointment of Consultant 7 days 8/9/22 8/16/22
17 PKE Warehouse ‐ 145m x 72m 7 days 9/13/22 9/20/22
18 PKS Warehouse ‐ 90m x 105m 7 days 10/10/22 10/17/22
19 PKS Stock Pile Warehouse ‐ 75m x 43m 7 days 11/7/22 11/14/22
20 PKS Truck unloading bay building 7 days 11/21/22 11/27/22
21 PKE Truck unloading bay building 7 days 11/27/22 12/4/22
22 MCC Building ‐ Utility Building 7 days 12/4/22 12/11/22
23 Workshop ‐ Utility Building 7 days 12/11/22 12/18/22
24 Weighbridge 4 unit with office ‐ Utility Building 7 days 12/11/22 12/18/22
25 Toilet ‐ Utility Building 7 days 12/18/22 12/26/22
26 Fire and BWRO ‐ 1 x 1000MT Tank 7 days 10/10/22 10/17/22
27 Conveyor Pedestal 7 days 11/7/22 11/14/22
28 Solid Bulk Jetty sub‐structure ‐ Pilling Works 7 days 7/20/22 7/27/22
29 Solid Bulk Jetty super structure 21 days 7/20/22 8/9/22
30 Phase - Tender 249 days 7/1/22 2/26/23
31 PKS PKE export conveyor supplier 63 days 7/20/22 9/19/22
32 PKS PKE export conveyor installation contractor 42 days 1/16/23 2/26/23
33 PKS PKE unloading station conveyor supplier 42 days 8/23/22 10/2/22
34 PKS PKE unloading station conveyor installation contractor 36 days 1/16/23 2/20/23
35 Weighbridge x 4 unit supplier 28 days 7/27/22 8/23/22
36 Weighbridge x 4 unit installation contractor 28 days 7/1/22 7/27/22
37 Truck hydraulic tipper supplier 28 days 7/27/22 8/23/22
38 Truck hydraulic tipper installation contractor 28 days 7/1/22 7/27/22
39 PKS processing equipment‐De stoner‐Supplier 28 days 7/27/22 8/23/22
40 PKS processing equipment‐De stoner‐installation contractor 28 days 7/1/22 7/27/22
41 Shiploader supplier 28 days 7/27/22 8/23/22
42 Shiploader installation contractor 28 days 7/1/22 7/27/22
43 PKE Warehouse ‐ 145m x 72m 21 days 9/21/22 10/10/22
44 PKS Warehouse ‐ 90m x 105m 21 days 10/17/22 11/7/22
45 PKS Stock Pile Warehouse ‐ 75m x 43m 21 days 11/14/22 12/4/22
46 PKS Truck unloading bay building 21 days 11/27/22 12/18/22
47 PKE Truck unloading bay building 21 days 12/4/22 12/26/22

Project: Task Summary Inactive Task Start-only External Tasks Deadline


01MASTER_PLANT-PKS PKE-WAREHOUSE_220729-R0
Milestone Project Summary Inactive Milestone Finish-only External Milestone Progress
Date: 7/30/22

Page 1
ID Task Name Duration Start Finish Qtr 3, 2022 Qtr 4, 2022 Qtr 1, 2023 Qtr 2, 2023 Qtr 3, 2023
Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
48 MCC Building ‐ Utility Building 21 days 12/11/22 1/1/23
49 Workshop ‐ Utility Building 21 days 12/18/22 1/8/23
50 Weighbridge 4 unit with office ‐ Utility Building 21 days 12/18/22 1/8/23
51 Toilet ‐ Utility Building 21 days 12/26/22 1/15/23
52 Fire and BWRO ‐ 1 x 1000MT Tank 21 days 10/17/22 11/7/22
53 Conveyor Pedestal 21 days 11/14/22 12/4/22
54 Solid Bulk Jetty super structure 36 days 8/9/22 9/13/22
55 Phase - Delivery Equipment 288 days 8/23/22 5/29/23
56 PKS PKE export conveyor supplier 216 days 9/19/22 4/18/23
57 PKS PKE unloading station conveyor supplier 216 days 9/19/22 4/18/23
58 Weighbridge x 4 unit supplier 120 days 8/23/22 12/17/22
59 Truck hydraulic tipper supplier 120 days 8/23/22 12/17/22
60 PKS processing equipment‐De stoner‐Supplier 120 days 8/23/22 12/17/22
61 Shiploader supplier 288 days 8/23/22 5/29/23
62 Phase - Construction 415 days 7/27/22 8/31/23
63 PKE Warehouse ‐ 145m x 72m 224 days 10/13/22 5/20/23
64 PKS Warehouse ‐ 90m x 105m 224 days 11/7/22 6/12/23
65 PKS Stock Pile Warehouse ‐ 75m x 43m 168 days 12/4/22 5/17/23
66 PKS Truck unloading bay building 168 days 12/20/22 6/1/23
67 PKE Truck unloading bay building 168 days 12/28/22 6/8/23
68 MCC Building ‐ Utility Building 168 days 1/3/23 6/14/23
69 Workshop ‐ Utility Building 154 days 1/10/23 6/8/23
70 Weighbridge 4 unit with office ‐ Utility Building 154 days 1/10/23 6/8/23
71 Toilet ‐ Utility Building 84 days 1/16/23 4/9/23
72 Fire and BWRO ‐ 1 x 1000MT Tank 196 days 11/7/22 5/17/23
73 Conveyor Pedestal 112 days 5/17/23 8/31/23
74 Solid Bulk Jetty sub‐structure ‐ Pilling Works 84 days 7/27/22 10/15/22
75 Solid Bulk Jetty super structure 252 days 9/13/22 5/16/23
76 PKS PKE export conveyor installation contractor 133 days 2/22/23 6/30/23
77 PKS PKE unloading station conveyor installation contractor 133 days 2/22/23 6/30/23
78 Weighbridge x 4 unit installation contractor 49 days 12/25/22 2/10/23
79 Truck hydraulic tipper installation contractor 49 days 12/25/22 2/10/23
80 PKS processing equipment‐De stoner‐installation contractor 49 days 12/25/22 2/10/23
81 Shiploader installation contractor 28 days 6/10/23 7/6/23
82 Phase - Commissioning 34 days 7/2/23 8/3/23
83 PKS PKE export conveyor installation contractor 28 days 7/2/23 7/29/23
84 PKS PKE unloading station conveyor installation contractor 28 days 7/4/23 7/30/23
85 PKS processing equipment‐De stoner‐installation contractor 28 days 7/8/23 8/3/23

Project: Task Summary Inactive Task Start-only External Tasks Deadline


01MASTER_PLANT-PKS PKE-WAREHOUSE_220729-R0
Milestone Project Summary Inactive Milestone Finish-only External Milestone Progress
Date: 7/30/22

Page 2