PROPOSED CONSTRUCTION SCHEDULE

XSTRUCTURES ENGINEERING CONSULTANTS


as of 27 Nov '22

ID Task N am e D uration Baseline Start Finish Baseline StartBaseline Finish Act.Start Act.Finish % Com p. PlannCurren N ovem ber2022 D ecem ber2022 January 2023 February 2023
D uration % % 232629010407101316192225280104071013161922252831030609121518212427300205081114172023260
0
PROPOSED CONSTRUCTION  298.2d 298.2d 25 Oct  26 Oct  25 Oct  26 Oct '23 25 Oct NA 7% 7% 6%
SCHEDULE '22 '23 '22 '22
1 PLANNING 53d 52d 25 Oct '22 02 Jan '23 25 Oct '22 29 Dec '22 25 Oct '22 NA 49% 52% 47% 49%

2 Create Site Plans 3.33w 3w 25 Oct '22 18 Nov '22 25 Oct '22 16 Nov '22 25 Oct '22 18 Nov '22 100% 100%100% 100%

3 Submit Plans for Approval 1mo 1mo 18 Nov '22 20 Dec '22 17 Nov '22 19 Dec '22 18 Nov '22 NA 25% 35% 25% 25%

4 Order Materials 8d 8d 21 Dec '22 02 Jan '23 20 Dec '22 29 Dec '22 NA NA 0% 0% 0% 0%

5 Planning Completed 0d 0d 02 Jan '23 02 Jan '23 29 Dec '22 29 Dec '22 NA NA 0% 0% 0% 02/01

6 SITE WORKS 28d 28d 03 Jan '23 03 Feb '23 02 Jan '23 02 Feb '23 NA NA 0% 0% 0% 0%

7 Erect Fencing 3d 0d? 03 Jan '23 05 Jan '23 NA NA NA NA 0% 0% 0%

8 Erect Site Buildings 4d 4d 03 Jan '23 06 Jan '23 02 Jan '23 05 Jan '23 NA NA 0% 0% 0% 0%

9 Clear and Level Site 3w 3w 07 Jan '23 27 Jan '23 06 Jan '23 26 Jan '23 NA NA 0% 0% 0% 0%

10 Prepare Drainage Infrastructure 1w 1w 28 Jan '23 03 Feb '23 27 Jan '23 02 Feb '23 NA NA 0% 0% 0% 0%

11 Prepare Cabling Infrastructure 1w 1w 28 Jan '23 03 Feb '23 27 Jan '23 02 Feb '23 NA NA 0% 0% 0% 0%

Critical Split Finish-only Baseline M ilestone M anualSum m ary Inactive Task Slack
CriticalSplit Task Progress D uration-only M ilestone Project Sum m ary Inactive M ilestone Baseline 1
CriticalProgress M anualTask Baseline Sum m ary Progress ExternalTasks Inactive Sum m ary
Task Start-only Baseline Split Sum m ary ExternalM ilestone D eadline

Prepared by; Page 1