Assignment 2 Classic Schedule Layout 21-Jul-22 16:45

Activity ID Activity Name Original Duration Remaining Schedule % Start


Duration Complete

SHANKESHWAR ROYALE BUILDING Assignment 2 781 781 0% 01-Jan-21

1 G+11 0 0 0%
41 Completion 781 781 40.46% 01-Jan-21
SHANKESHWAR ROYALE BUILDING.2 Project Design Stage 87 87 0% 20-Mar-22

2 Project Design Stage 30 30 0% 21-Mar-22


3 Site Visit 2 2 0% 21-Mar-22
4 Working Drawings 1 1 0% 23-Mar-22
5 Conceptual Presentation 60 60 0% 27-Apr-22*
6 Design Changes 3 3 0% 04-Apr-22
7 Design Confirmation 2 2 0% 07-Apr-22
8 Structural Designing 55 55 0% 11-Apr-22
9 Drawing Permits 0 0 0% 11-Apr-22*
10 Client Meeting 45 45 0% 11-Apr-22
44 New Activity 5 5 0% 20-Mar-22
SHANKESHWAR ROYALE BUILDING.3 Execution 265 265 0% 16-May-22

11 Execution 190 190 0% 29-Aug-22


SHANKESHWAR ROYALE BUILDING.3.3.1 Sub - structure 135 135 0% 16-May-22
12 Sub - structure 66 66 0% 02-Jun-22
13 Site Cleaning 122 122 0% 02-Jun-22
14 Centerline marking 45 45 0% 13-Jun-22
15 Excavation 59 59 0% 14-Jun-22
SHANKESHWAR ROYALE BUILDING.3.3.1.3.1.4 Footing 40 40 0% 16-May-22
16 Footing 19 19 0% 16-May-22
17 PCC 3 3 0% 21-Jun-22
18 RCC 7 7 0% 14-Jun-22
19 Casting 12 12 0% 23-Jun-22
SHANKESHWAR ROYALE BUILDING.3.3.1.3.1.5 Plinth Beam 18 18 0% 30-Jun-22
20 Plinth Beam 18 18 0% 30-Jun-22
21 RCC 7 7 0% 30-Jun-22
22 Casting 12 12 0% 08-Jul-22
SHANKESHWAR ROYALE BUILDING.3.3.2 Super - Structure 152 152 0% 26-Jul-22
23 Super - Structure 152 152 0% 26-Jul-22
24 Earthwork Filling 2 2 0% 26-Jul-22*
25 PCC for Ground Floor 5 5 0% 28-Jul-22
26 RCC for Ground Floor Columns 15 15 0% 04-Aug-22*
27 Terrace Floor Beam 15 15 0% 25-Aug-22
28 Terrace Floor Slab 21 21 0% 15-Sep-22
29 Masonary work 30 30 0% 19-Aug-22
SHANKESHWAR ROYALE BUILDING.3.3.2.3.2.7 Finish work 104 104 0% 30-Sep-22
30 Finish work 104 104 0% 30-Sep-22
31 Plumbing 15 15 0% 14-Oct-22
32 Electrical 15 15 0% 30-Sep-22
33 Plastering 30 30 0% 04-Nov-22
34 Tiling and granite work 30 30 0% 16-Dec-22
35 Door and Windows 15 15 0% 27-Jan-23
36 False ceiling 15 15 0% 16-Dec-22

Page 1 of 4 TASK filter: All Activities


© Oracle Corporation
Assignment 2 Classic Schedule Layout 21-Jul-22 16:45
Start Finish Total Float

01-Jan-21 29-Dec-23 0

0
01-Jan-21 29-Dec-23 0
20-Mar-22 20-Jul-22 0

21-Mar-22 29-Apr-22 0
21-Mar-22 22-Mar-22 0
23-Mar-22 23-Mar-22 0
27-Apr-22* 20-Jul-22 0
04-Apr-22 06-Apr-22 0
07-Apr-22 08-Apr-22 0
11-Apr-22 24-Jun-22 0
11-Apr-22* 11-Apr-22 0
11-Apr-22 10-Jun-22 0
20-Mar-22 25-Mar-22
16-May-22 19-May-23 0

29-Aug-22 19-May-23 0
16-May-22 18-Nov-22 1
02-Jun-22 01-Sep-22 0
02-Jun-22 18-Nov-22 0
13-Jun-22 12-Aug-22 0
14-Jun-22 02-Sep-22 0
16-May-22 08-Jul-22 0
16-May-22 09-Jun-22 0
21-Jun-22 23-Jun-22 0
14-Jun-22 22-Jun-22* 0
23-Jun-22 08-Jul-22 0
30-Jun-22 25-Jul-22 1
30-Jun-22 25-Jul-22 0
30-Jun-22 08-Jul-22* 0
08-Jul-22 25-Jul-22 0
26-Jul-22 22-Feb-23 0
26-Jul-22 22-Feb-23 0
26-Jul-22* 27-Jul-22 0
28-Jul-22 03-Aug-22 0
04-Aug-22* 24-Aug-22 0
25-Aug-22 14-Sep-22 0
15-Sep-22 13-Oct-22 0
19-Aug-22 29-Sep-22 0
30-Sep-22 22-Feb-23 0
30-Sep-22 22-Feb-23 0
14-Oct-22 03-Nov-22 0
30-Sep-22 20-Oct-22 0
04-Nov-22 15-Dec-22 0
16-Dec-22 26-Jan-23 0
27-Jan-23 16-Feb-23 0
16-Dec-22 05-Jan-23 0

Page 2 of 4 TASK filter: All Activities


© Oracle Corporation
Assignment 2 Classic Schedule Layout 21-Jul-22 16:45
Activity ID Activity Name Original Duration Remaining Schedule % Start
Duration Complete

37 Painting 0 0 0% 27-Jan-23
38 Electrical Fixing 4 4 0% 17-Feb-23

Page 3 of 4 TASK filter: All Activities


© Oracle Corporation
Assignment 2 Classic Schedule Layout 21-Jul-22 16:45
Start Finish Total Float

27-Jan-23 27-Jan-23 0
17-Feb-23 22-Feb-23 0

Page 4 of 4 TASK filter: All Activities