You are on page 1of 149

Rate Analysis

Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of sainthia -sultanpur
road (SH-11) by rigid & flexible pavement under birbhum division, PWD in the district of birbhum during
the year 2017-18

Lead for Stone material from Panchami Quarry :-


Distance from Panchami quarry to end of this road (16+14+1) = 31.00 Km
Average of work site. = 9.00 Km
Lead 40.00 Km
Say 40.00 Km
Cost of Stone at Work Site per m 3 :-

Carriage cost :- (P-228 , Table -1)


upto 5.00 Km =Rs. 124.00
above 5.00 Km upto 10.00 Km = 5.00 Km @ Rs. 10.90 /Km =Rs. 54.50
above 10.00 Km upto 20.00 Km = 10.00 Km @ Rs. 10.10 /Km =Rs. 101.00
above 20.00 Km upto 40.00 Km = 20.00 Km @ Rs. 9.50 /Km =Rs. 190.00
above 0.00 Km upto 0.00 Km = 0.00 Km @ Rs. 0.00 /Km =Rs. 0.00
above 0.00 Km upto 0.00 Km = 0.00 Km @ Rs. 0.00 /Km =Rs. 0.00
Total= Rs. 469.50

20mm 10 mm
material 22.4mm 13.2mm 11.2mm 5.6mm Stone dust 37.5mm 26.5mm nominal nominal
material
cost 659.00 710.00 494.00 290.00 97.00 545.00 591.00 624.00 433.00
L+Ul 57.75 57.75 57.75 57.75 46.50 57.75 57.75 57.75 57.75
Carriage 469.50 469.50 469.50 469.50 469.50 469.50 469.50 469.50 469.50
Total 1186.25 1237.25 1021.25 817.25 613.00 1072.25 1118.25 1151.25 960.25

Type-B Boulder 225-


material moorum Grade-I Grade -II Screening 150 mm
material
cost 123.00 483.00 545.00 102.00 290.00
L+Ul 46.50 62.25 62.25 57.75 83.00
Carriage 469.50 469.50 469.50 469.50 469.50
Total 639.00 1014.75 1076.75 629.25 842.50

Carriage Cost of V.G 40- 30/40 Grade Bitumen (Bulk) & Cationic Emulsion (M.S. Type) (bulk)
Project Site at : Sainthia
Source at : Haldia Dhulagarh
Lead from source = 333 Km. 240 Km.
Carriage Unit Carriage cost
Carriage cost (Rs.) (Rs.)
Carriage distance Carriage distance Carriage rate
rate

From To Distance From To Distance


0 5 5 - 82.00 0 5 5 - 82.00
Per Metric Ton

5 10 5 7.30 36.50 5 10 5 7.30 36.50


10 20 10 6.70 67.00 10 20 10 6.70 67.00
20 50 30 6.30 189.00 20 50 30 6.30 189.00
50 100 50 5.60 280.00 50 100 50 5.60 280.00
100 200 100 5.30 530.00 100 200 100 5.30 530.00
200 333 133 5.30 704.90 200 240 40 5.30 212.00
Total Carriage Cost = 1889.40 Per MT Total Carriage Cost = Per MT 1396.50
Item Cost at Contractors Cost of
source (A) Carriage profit 10% Container
L/ U overhead charge 5 % on A (less) Total
cost

30/40
Grade bulk
Bitumen 30980.00 42.00 1889.40 1549.00 3252.90 -1000.00 36713.30

MS Type
Bit.
Emulsion 25946.00 42.00 1889.40 1297.30 2724.33 -1000.00 30899.03
(bulk)
60/70
Grade
packed 34344.00 42.00 1889.40 1717.20 3606.12 -1000.00 40598.72
Bitumen

10/20
Grade
packed 37800.00 42.00 1396.50 1890.00 3969.00 -999.00 44098.50
Bitumen

1 Item No.18.02 (b) (i)&(ii) Page No 321 of P.W. (Roads) Schedule of Rates 2015-16
Picking up and removing old bituminous layer or sand sealing coat from old black topped surface and
cleaning the exposed surface by scraping and stacking the material as directed.

b) By mechanical means
(i) From 25 mm to 50 mm thick.
Cost of Labour per sqm. = Rs. 3.80
= Rs. 3.80
Add 1% cess = Rs. 0.038
2
Rate per m = Rs. 3.838
(ii) From 50 mm to 100 mm thick.

Cost of Labour per sqm. = Rs. 7.50


= Rs. 7.50
Add 1% cess = Rs. 0.075
Rate per m2 = Rs. 7.575

2 Item No.3.16 (a) Page No 237 of P.W. (Roads) Schedule of Rates 2015-16
Box cutting or filling in Road embankment in all sorts of soil including spreading the spoils properly over
the flank as necessary or on berm to approximate grade & camber and rolling the sub-grade with power
roller to proper camber and grade as per direction and satisfaction of Engineer-in-charge including
uprooting and removing plants and jungles when and where
necessary.

(a) Depth up to 150 mm.


Cost of Labour per sqm. = Rs. 14.40
= Rs. 14.40
Add 1% cess = Rs. 0.14
Rate per m2 = Rs. 14.54
(b) For each additional Depth of 150mm to 300 mm.
Cost of Labour per sqm. = Rs. 19.00
= Rs. 19.00
Add 1% cess = Rs. 0.19
Rate per m2 = Rs. 19.19

(c) For each additional Depth of 300 mm to 750 mm.


Cost of Labour per sqm. = Rs. 57.00
= Rs. 57.00
Add 1% cess = Rs. 0.57
Rate per m2 = Rs. 57.57

3 Item No.3.04(i) Page No 234 of P.W. (Roads) Schedule of Rates 2015-16


Earthwork in cutting to form road section in correct profile including removal of spoils not exceeding initial
lead of 50m and initial lift of 1.5m (Mode of measurement: pre works and post works)

(i) In ordinary soil


Cost of Labour per sqm. = Rs. 79.90
= Rs. 79.90
Add 1% cess = Rs. 0.80
Rate per m2 = Rs. 80.70

4 Item No. 4.08(A)Page No 243 of P.W. (Roads) Schedule of Rates 2015-2016


Construction of granular sub-base by providing graded material, mixing in Wet Mix Plant at OMC, carriage
of mixed material to work site, spreading in uniform layers with Motor grader on prepared surface in
proper grade and camber, compacting with vibratory power roller to achieve the desired density, including
lighting, guarding, barricading, including cost of all materials, machinery, tools and plants and cost of quality
control complete as per Clause 401 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).

A) Plant Mix method

Grading - V
37.5 mm stone aggregates 0.2560 m3 @ Rs. 1072.25 / m3 = Rs. 274.50
22.4 mm stone aggregates 0.2560 m3 @ Rs. 1186.25 / m3 = Rs. 303.68
11.2 mm stone aggregates 0.1920 m3 @ Rs. 1021.25 / m3 = Rs. 196.08
5.6 mm stone aggregates 0.3200 m3 @ Rs. 817.25 / m3 = Rs. 261.52
Sand (medium) 0.2560 m3 @ Rs. 350.00 / m3 = Rs. 89.60
Add labour rate per m3 = Rs. 391.00
1516.38
Add 1% cess = Rs. 15.16
3
Rate per m = Rs. 1531.54

B) Grading - II
37.5 mm stone aggregates 0.1920 m3 @ Rs. 1072.25 / m3 = Rs. 205.87
22.4 mm stone aggregates 0.1280 m3 @ Rs. 1186.25 / m3 = Rs. 151.84
11.2 mm stone aggregates 0.1280 m3 @ Rs. 1021.25 / m3 = Rs. 130.72
5.6 mm stone aggregates 0.1536 m3 @ Rs. 817.25 / m3 = Rs. 125.53
Sand (medium) 0.6784 m3 @ Rs. 350.00 / m3 = Rs. 237.44
Add labour rate per m3 = Rs. 387.00
1238.40
Add 1% cess = Rs. 12.38
3
Rate per m = Rs. 1250.79
5 Item No. 4.12 Page No 246 of P.W. (Roads) Schedule of Rates 2015-2016
Providing, laying, spreading and compacting graded stone aggregate to Wet Mix Macadam specification
including screening of aggregates and granular materials, premixing the material with water at OMC in Wet
Mix Plant, carriage of mixed material by tipper to site, laying in uniform layers with Paver in Sub- base
/Base course on well prepared surface and compacting with Vibratory Roller to achieve the desired
density,including supply of all materials, machinery, fuel and lubricants, including incidental costs for
lighting,guarding, barricading, making earthen bundh to protect the edges including cost of quality control
complete as per Clause 406 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).cum
338.00 362.00Note Add cost at site of 1.32 m³ of the stone materials as per specified grading to arrive at the
complete rate.

26.5 mm stone aggregates 0.3960 m3 @ Rs. 1118.25 / m3 = Rs. 442.83


13.2 mm stone aggregates 0.2640 m3 @ Rs. 1237.25 / m3 = Rs. 326.63
5.6 mm stone aggregates 0.3564 m3 @ Rs. 817.25 / m3 = Rs. 291.27
Stone dust 0.3036 m3 @ Rs. 613.00 / m3 = Rs. 186.11
Add labour rate per m3 = Rs. 338.00
1584.84
Add 1% cess = Rs. 15.85
3
Rate per m = Rs. 1600.69

6 Item No.5.02 Page No 248 of P.W. (Roads) Schedule of Rates 2015-2016


Providing and applying tack coat with Cationic Bitumen Emulsion of approved grade conforming to IS:
8887-1978 on the prepared surface cleaned with Hydraulic broom, moistening the surface including cost
and carriage of emulsion, hire charges of machinery and labour, cost of fuel and lubricants all complete as
per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).Providing & applying
tack coat using Cationic bituminous emulsion of approved grade conforming to IS: 8887-1978, over
prepared surface includig cleaning of surface with mechanical broom, moistening the surface, applying tack
coat including cost and carriage of emulsion, hire charges of machinaries and labour cost of fuel and
lubricants all complete as per specification and direction of Engineer-in-charge.

(i) On Bituminous Surface (Using Bitumen Emulsion at the rate of 0.20 to 0.30 kg per sqm.)

cost of bitumen emulsion (M.S.) 0.25kg @ Rs. 30899.03 / M.T.


= Rs. 7.72
Add labour rate per m2 = Rs. 1.30
= Rs. 9.02
Add 1% cess = Rs. 0.09
2
Rate per m = Rs. 9.12
(ii) On Granular surfaces treated with primer (Using Bitumen emulsion at the rate of 0.25 to 0.30 kg
per sqm.)

cost of bitumen emulsion (M.S.) 0.275kg @ Rs. 30899.03 / M.T. = Rs. 8.50
Add labour rate per m2 = Rs. 1.30
= Rs. 9.80
Add 1% cess = Rs. 0.10
Rate per m2 = Rs. 9.90
7 Item No.5.01 Page No 248 of P.W. (Roads) Schedule of Rates 2015-2016
Providing and applying primer coat with Cationic Bitumen Emulsion of approved grade conforming to IS:
8887-1978 and requisite quantity on prepared surface of granular base including cleaning of road surface
and spraying primer using Mechanical means including cost and carriage of bitumen emulsion and all other
incidental costs of work complete as per Clause 502 of Specifications for Road & Bridge Works of MoRT&H
(5th Revision).

(i) For WBM / WMM Surface: (with primer @ 0.70-1.0 kg/sqm)


cost of bitumen emulsion (M.S.) 1.05kg @ Rs. 30899.03 / M.T. = Rs. 26.26
2
Add labour rate per m = Rs. 1.50
= Rs. 27.76
Add 1% cess = Rs. 0.28
Rate per m2 = Rs. 28.04
8 Item No.5.14 (b) (ii) Page No 256 of P.W. (Roads) Schedule of Rates 2015-2016
Mastic Ashphalt
Providing and laying Mastic asphalt wearing course with paving grade bitumen meeting the requirements
given in table 500-29 using approved coarse aggregate, fine aggregate, filler material and bitumen, prepared
by using Mastic cooker including cost and carriage of all ingredients, cost of heating aggregates and binder,
mixing in specified proportions conforming to approved Job Mix Formula and laid to required level and
slope after cleaning the surface, compacting, sealing the construction joints and surface finishing
conforming to specifications including providing antiskid surface with bitumen pre-coated fine-grained
hard stone chipping of 13.2 mm nominal size at the rate of 0.005 cum per 10 sqm and at an approximate
spacing of 10 cm center to center in both directions, pressed into surface when the temperature of surfaces
not less than 100°C, protruding 1 mm to 4 mm over mastic surface, including the hire charges of all tools
and plants and machinery, pay of operators, cost of fuel and lubricants and all other incidental charges and
quality control all complete as per Clause 516 of Specifications for Road & Bridge Works of MoRT&H (5th
Revision).

(i) 25 mm thickness
cost of 13.2 mm chips 0.0005 m3 @ Rs. 1237.25 / m3 = Rs. 0.62
cost of 11.2mm chips 0.0079 m3 @ Rs. 1021.25 / m3 = Rs. 8.07
cost of 5.6mm chips 0.0079 m3 @ Rs. 817.25 / m3 = Rs. 6.46
cost of stone dust /medium
sand 0.0111 m3 @ Rs. 350.00 / m3 = Rs. 3.89
cost of lime stone dust 10.29 kg @ Rs. 3.90 / kg = Rs. 40.13
cost of bitumen 10/20 5.71 kg @ Rs. 40598.72 / M.T. = Rs. 231.81869
cost of bitumen 60/70 0.0143 kg @ Rs. 36713.30 / M.T. = Rs. 0.53
Add labour rate per m2 = Rs. 172.00
= Rs. 463.50
Add 1% cess = Rs. 4.64
Rate per m2 = Rs. 468.14

9 Item No.5.05 Page No 250 of P.W. (Roads) Schedule of Rates 2015-2016


Dense Bituminous Macadam
Providing and laying dense bituminous macadam with Hot Mix Plant producing an average output of 75
tonnes per hour using coarse aggregate, fine aggregate, filler and bituminous binder as per design Job Mix
Formula conforming Marshall Method as per specification,including screening, cleaning of chips and
preparing a uniform and quality mix in Hot Mix Plant and ensuring a homogeneous mix, in which all
particles of the mineral aggregates are coated uniformly, transporting the hot mix to work site, laying the
mixed materials at specified laying temperature with a hydrostatic paver finisher with sensor control to the
required grade, level and alignment over prepared surface coated with tack coat, rolling with smooth
wheeled, vibratory and tandem rollers for break down, inter-mediate and finished rolling to achieve the
desired density of at least 98% of that of Laboratory Marshall specimen, hand packing and pinning to give
an even surface including cost and carriage of bitumen, coarse and fine aggregates and filler materials and
hire charges of machinery and equipment for construction and quality control, fuels and lubricants and
wages of operational staff complete as per Clause 505 of Specifications for Road & Bridge Works of
MoRT&H (5th Revision).

A. For Grading 1
(37.5 mm nominal size, 75-100 mm thick.)
(i) Using Batch Type HMP of minimum capacity
100-120 TPH.
cost of 37.5 mm chips 0.2945 / m3 @ Rs. 1072.25 / m3 = Rs. 315.78
cost of 26.5 mm chips 0.1472 / m3 @ Rs. 1118.25 / m3 = Rs. 164.61
cost of 22.4mm chips 0.2208 / m3 @ Rs. 1186.25 / m3 = Rs. 261.92
cost of 11.2mm chips 0.2945 / m3 @ Rs. 1021.25 / m3 = Rs. 300.76
cost of 5.6mm chips 0.1472 / m3 @ Rs. 817.25 / m3 = Rs. 120.30
cost of stone dust 0.3681 / m3 @ Rs. 613.00 / m3 = Rs. 225.65
Filler 2% (lime Stone dust/
cement) 44.00 Kg @ Rs. 3.90 /Kg = Rs. 171.60
cost of bitumen 99.00 kg/m3 @ Rs. 36713.30 / M.T. = Rs. 3634.62
Add labour rate per m3 = Rs. 1307.00
= Rs. 6502.23
Add 1% cess = Rs. 65.02
Rate per m3 = Rs. 6567.25
B. For Grading 2 (26.5 mm nominal size, 50-75 mm thick.)
(i) Using Batch Type HMP of minimum capacity
100-120 TPH.
cost of 26.5 mm chips 0.2197 / m3 @ Rs. 1118.25 / m3 = Rs. 245.68
cost of 22.4 mm chips 0.2197 / m3 @ Rs. 1186.25 / m3 = Rs. 260.62
cost of 11.2mm chips 0.3662 / m3 @ Rs. 1021.25 / m3 = Rs. 373.98
cost of 5.6mm chips 0.2197 / m 3
@ Rs. 817.25 / m 3
= Rs. 179.55
3 3
cost of stone dust 0.4394 / m @ Rs. 613.00 / m = Rs. 269.35
Filler 2% (lime Stone dust/
cement)
44.00 Kg @ Rs. 3.90 /Kg = Rs. 171.60
cost of bitumen 111.00 kg/m3 @ Rs. 36713.30 / M.T. = Rs. 4075.18
Add labour rate per m3 = Rs. 1298.00
= Rs. 6873.96
Add 1% cess = Rs. 68.74
Rate per m3 = Rs. 6942.70

10 Item No.5.08 Page No 252 of P.W. (Roads) Schedule of Rates 2015-2016


Bituminous Concrete
Providing and laying bituminous concrete with Hot Mix Plant using coarse aggregates, fine aggregates, filler
materials and bituminous binder of required specification including screening, cleaning of chips and
preparing a uniform and quality mix in Hot Mix Plant and ensuring a homogeneous mix, in which all
particles of the mineral aggregates are coated uniformly, transporting the hot mix to work site, laying the
mixed materials at specified laying temperature with a hydrostatic paver finisher with sensor control to the
required grade, level and alignment over prepared surface coated with tack coat, rolling with smooth
wheeled, vibratory and tandem rollers for break down, inter-mediate and finished rolling to achieve the
desired density of at least 98% of that of Laboratory Marshall specimen, including cost and carriage of
bitumen, coarse and fine aggregates and filler materials and hire charges of machinery and equipment for
construction and quality control, fuels and lubricants and wages of operational staff complete as per Clause
507 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).

B. For Grading 2
(13.2 mm nominal size, 30-40 mm thick.)
i) Using Batch Type HMP of minimum capacity
100-120 TPH.
cost of 13.2 mm chips 0.2959 / m3 @ Rs. 1237.25 / m3 = Rs. 366.10
cost of 11.2mm chips 0.2959 / m3 @ Rs. 1021.25 / m3 = Rs. 302.19
cost of 5.6mm chips 0.2959 / m 3
@ Rs. 817.25 / m 3
= Rs. 241.82
cost of stone dust 0.5919 / m3 @ Rs. 613.00 / m3 = Rs. 362.83
Filler 2% (lime Stone dust/
cement)
45.00 Kg @ Rs. 3.90 /Kg = Rs. 175.50
cost of bitumen 137.00 kg/m3 @ Rs. 36713.30 / M.T. = Rs. 5029.72
Add labour rate per m3 = Rs. 1249.00
= Rs. 7727.17
Add 1% cess = Rs. 77.27
Rate per m3 = Rs. 7804.44

Junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
Earthen Shouldring

1 Item No.3.14 Page No 236 of P.W. (Roads) Schedule of Rates 2015-2016


Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthen shoulders with
approved material obtained from borrow pits with all lifts and leads, transporting to site, spreading, grading
to required slope and compacted to meet requirement of Table 300.2 with lead upto 1000 m as per
Technical Specification Clause 303.1 for Rural Roads of MORD. (Borrow pit /pre work post work
measurement)

Add labour rate per m3 = Rs. 94.80


= Rs. 94.80
Add 1% cess = Rs. 0.95
Rate per m3 = Rs. 95.75

2 Item No.3.15 Page No 236 of P.W. (Roads) Schedule of Rates 2015-2016


Extra for carriage of all kinds of earth by Mechanical Transport:
b) Carriage up to total lead of 2.0 km.

Add labour rate per m3 = Rs. 106.90


= Rs. 106.90
Add 1% cess = Rs. 1.07
Rate per m3 = Rs. 107.97

3 Item No.3.17 Page No 237 of P.W. (Roads) Schedule of Rates 2015-2016


A. Compacting original ground supporting subgrade Loosening of the ground upto a level of 300 mm below
the subgrade level, watered, graded and compacted in layers to meet requirement of
Tables 300.1 and 300.2 for subgrade construction as per Clause 305.3.4 of Specifications for Road & Bridge
Works of MoRT&H (5th Revision).

Add labour rate per m3 = Rs. 55.50


= Rs. 55.50
Add 1% cess = Rs. 0.56
Rate per m3 = Rs. 56.06

Junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
Cross drainage work
1 Item No.12.01 Page No 278 of P.W. (Roads) Schedule of Rates 2015-2016
Excavation for Structures
Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, removing, spreading or stacking of spoils within a lead of 150 m. as directed and
including trimming the sides of the trenches, leveling, dressing and ramming the bottom, and backfilling
with approved material complete as per direction of the Engineer-in-Charge .

I. In all sorts of soil excluding marshy soil & rocks (soft or hard) by manual means.
a) upto3m depth
(i) With pumping out water including shoring
as required.
Labour rate per m3 = Rs. 124.00
cess 1 % = Rs. 1.24
Rate per m3 = Rs. 125.24

2 Item No.4.05 Page No 242 of P.W. (Roads) Schedule of Rates 2015-2016


Supplying, spreading and compacting Sand to required thickness, in layers not exceeding 150 mm to proper
gradient and camber, inundating each layer by water and packing and ramming layer by layer to achieve
desired compaction, including lighting, guarding, barricading and making adequate earthen bundh where
necessary, curing with water as per direction, mending cracks and depressions by ramming wherever
necessary.

cost of Sand 1.1947 / m3 @ Rs. 350.00 / m3 = Rs. 418.16


Add labour rate per m3 = Rs. 196.00
= Rs. 614.16
Add 1% cess = Rs. 6.14
Rate per m3 = Rs. 620.30

3 Item No. 12.05 Page No 280 of P.W. (Roads) Schedule of Rates 2014-2015
Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any part of
foundation of bridges / culverts with graded stone chips of appropriate nominal sizes, including screening
and cleaning of coarse aggregates, fine aggregate (sand) conforming to proper grading zone,both of
approved quality and cement, as necessary,cost of curing with water, including cost and carriage of all
materials and including preparation of design mix, approval of the same by the Engineer-in-Charge, cost for
quality control, sampling, testing etc. including cost of formwork but excluding reinforcement complete as
per drawing and technical specifications.

15.1 PCC grade M20 conc.


cost of
20 mm stone chips 60 % of 0.90 cum @ Rs. 1151.25 / m3 = Rs. 621.68
10 mm stone chips 40 % of 0.90 cum @ Rs. 960.25 / m3 = Rs. 345.69
Cost of Cement @ Rs. 7364.00 /M.T. = Rs. 2945.60
Add labour rate per m3 = Rs. 2175.00
= Rs. 6087.97
Add 1% cess = Rs. 60.88
Rate per m3 = Rs. 6148.84
15.2 M25 concrete (RCC ) conc. Mixture
cost of
20 mm stone chips 60 % of 0.90 cum @ Rs. 1151.25 / m3 = Rs. 621.68
10 mm stone chips 40 % of 0.90 cum @ Rs. 960.25 / m3 = Rs. 345.69
Cement 420 Kg/m³ @ Rs. 7364.00 /M.T. = Rs. 3092.88
Add labour rate per m3 = Rs. 2306.00
= Rs. 6366.25
Add 1% cess = Rs. 63.66
Rate per m3 = Rs. 6429.91

4 Item No. 13.02 Page No 297 of P.W. (Roads) Schedule of Rates 2015-2016
Supplying, fitting and placing HYSD bar reinforcement in Sub-structure including initial straightening,
straightening of coils bars, removal ofloose rust (if any), cutting to requisite length bending, binding with
annealed wire not less than 1 mm in size and conforming to IS 280 at everyintersection hooked and bent to
correct shape and placed on forms etc. including cost of black annealed wire and cost of loading,
unloading,carriage of all steel materials complete as per drawing and technical specifications and direction
of Engineer-in-charge.

1. Rate of Item 19 (a) for Agency supply @ Rs. 3369.00 / MT = Rs. 3369.00
2. Add basic price at outlet of steel x 1.05 @ Rs. 49900.00 / MT = Rs. 52395.00
3.( carriage+loading+unloading) /1.15 = Rs. 165.65
4. Overhead charge @ 5% = Rs. 2628.03
5. Contarctor's profit @ 10% = Rs. 5518.87
Distance from to work site 2.80 km from Sainthia = Rs. 64076.55
Carriage upto 5.0km per MT =Rs 82.00 Add 1% cess = Rs. 640.77
Carriage 5.0km upto 10 km per MT =Rs 36.5 Rate per M.T. = Rs. 64717.32
Loadind unloading 96.00 x 0.75 =Rs 72.00
=Rs 190.50

5 Item No. 13 Page No 45 of P.W. (Building) Schedule of Rates 2015-2016


Supplying and laying Polythene Sheet (150 gm/sq.m) over damp proof coarse or below flooring or roof
terranching or in foundation or in foundation trenches.
Basic rate Rs 25.00
6 Item No. 13.03 Page No 292 of P.W. (Roads) Schedule of Rates 2015-2016
Providing weep holes (150 x 75 mm.) in abutment or wing wall for the entire thickness, with slope 1:20
towards drainage surface including packing with brick bats or boulders of approved quality and sizes at the
back side as per direction of the Engineer-in-charge

= Rs. 126.00
Add 1% cess = Rs. 1.26
Rate Each = Rs. 127.26
7 Item No. 7 Page No 162 of P.W. (Building) Schedule of Rates 2015-2016
Priming one coat to timber or plastered surface with ready mixed primer of approved quality including
scrapping and smoothening surface

Basic rate Rs 41.00


2
Rate per m Rs 41.00
8 Item No. 8.21 Page No 268 of P.W. (Building) Schedule of Rates 2015-2016
Painting the vertical end faces of posts, wheel guards or railing or parapet with alternate bands of different
colours as directed by the Engineer-in-charge with approved synthetic enamel paint.

Basic rate Rs 99.00


Add. Cess 1.00% Rs 0.99
Rate per m2 Rs 99.99
9 Item No. 18.06 Page No 322 of P.W. (Roads) Schedule of Rates 2015-2016
First class Brick work in cement sand mortar in steining of well, pier, abutment, wing wall, parapets cross
drain. H.P. culverts, guard wall etc. including curing, scaffolding, raking out joints etc. complete including
cost and carriage of all materials.
(a) In 1:4 proportion.
Add labour rate per m3 = Rs. 2590.00
cost of Brick 388 Nos/m³ @ Rs. 6500.00 /1000Nos = Rs. 2522.00
= Rs. 5112.000
Add 1% cess = Rs. 51.120
3
Rate per m = Rs. 5163.12
10 Item No. 2 Page No 164 of P.W. (Building) Schedule of Rates 2015-2016
Plaster with sand and cement mortar including rounding off comers or chamfering comers as directed and
including raking out joints or roughening of concrete surface, curing with cost and carriage of all materials.
(ii) with (4 : 1) cement mortar.(b) 15 mm. thick plaster.

= Rs. 163.00
2
Rate per m = Rs. 163.00
11 Item No. 8 Page No 166 of P.W. (Building) Schedule of Rates 2015-2016
Neat cement punning on cement plaster surface.
= Rs. 38.00
2
Rate per m = Rs. 38.00

Junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
Protective work
1 Item No. 18.30 Page No 326 of P.W. (Building) Schedule of Rates 2015-2016
Weaving wire mattress as directed with wire of 4mm dia. and making sausage crate of required shape after
tying all intersections including joining longitudinal ends, closing ends of sausage, carriage of wire to site of
work complete in all respect as per direction of the Engineer-in-charge including cost of supply of G.I. wire.
(With 100mm x 100mm mesh.)

Basic rate Rs 238.00


Add. Cess 1.00% Rs 2.38
Rate per m3 Rs 240.38

2 Item No. 18.30 Page No 326 of P.W. (Building) Schedule of Rates 2015-2016
Filling properly the empty sausage crates with boulders of any size & shape with hand packing after
preparation of bed of placement, placing the crate in position, carriage of boulders from road stacks with a
lead upto 150m etc. complete in all respect including stitching the rest of the crate with wire (passage for
filling boulders) after filling up the crate with boulders and launching the crate in position if necessary and
as directed by the Engineer-in charge. [Rate provided is exclusive of the cost of stone boulders and sausage
crate

cost of Stone boulder Rs 842.50


Labour rate Rs 454.00
1296.50
Add. Cess 1% Rs 12.97
3
Rate per m Rs 1309.47

3 Item No. 11.01 Page No 276 of P.W. (Building) Schedule of Rates 2015-2016
Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and technical
specification Clause 1104 for Rural Roads of MORD including setting out, construction of shoring and
bracing, removal of stumps and other deleterious matter, dressing of sides and bottom and backfilling with
approved material.

Labour rate Rs 104.00


104.00
Add. Cess 1% Rs 1.04
3
Rate per m Rs 105.04

4 Item No. 12.04 Page No 280 of P.W. (Building) Schedule of Rates 2015-2016
Sand filling in foundation trenches and at the back of abutments, wing-walls etc. with good local sand free
from earth in layers not exceeding 15 cm. including inundating each layer by profuse water and poking and
ramming layer by layer complete including supply of sand. Quality of sand is to be approved by the
Engineer-in-charge.

cost of sand 1.20 m³ @ Rs. 350.00 /m³ = Rs. 420.00


Labour rate = Rs. 177.00
= Rs. 597.00
Add. Cess 1% = Rs. 5.97
Rate per m3 = Rs. 602.97

Junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
Diversion Road works
1 Item No. 3.14 Page No 236 of P.W. (Roads) Schedule of Rates 2015-2016
Construction of Subgrade and Earthen Shoulders with approved material obtained from borrow pits with all
lifts and leads, transporting to site, spreading, grading to required slope and compacted to meet
requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Clause 303.1 for Rural
Roads of MORD. (Borrow pit /pre work post work measurement)
(b) Carriage up to total lead of 2.0 km.
Basic rate Rs 94.80
Carriage up to 2.0 km. 106.90
201.70
Add. Cess 1.00% Rs 0.95
3
Rate per m Rs 202.65

2 Item No. 4.05 Page No 242 of P.W. (Roads) Schedule of Rates 2015-2016
Supplying, spreading and compacting Sand to required thickness, in layers not exceeding 150 mm to proper
gradient and camber, inundating each layer by water and packing and ramming layer by layer to achieve
desired compaction, including lighting, guarding, barricading and making adequate earthen bundh where
necessary, curing with water as per direction, mending cracks and depressions by ramming wherever
necessary.
cost of sand 1.20 m³ @ Rs. 350.00 /m³ = Rs. 420.00
Labour rate = Rs. 196.00
= Rs. 616.00
Add. Cess 1% = Rs. 6.16
Rate per m 3
= Rs. 622.16

3 Item No. 4.06 Page No 242 of P.W. (Roads) Schedule of Rates 2015-2016
Supplying, spreading and consolidating Stone Dust to a depth of 100 mm and above at desired density and
C.B.R. as per Specification with power roller to proper gradient and camber including watering as
necessary, and lighting, guarding, barricading and making adequate earthen bundh where necessary to
protect the edges and curing with water for 2 to 3 days, mending cracks and depressions by rolling where
necessary including all incidental charges of
roller, cost of fuel & lubricants complete as per specification.

Stone dust 1.429 m3 @ Rs. 613.00 / m3 = Rs. 875.71


Add labour rate per m3 = Rs. 209.00
1084.71
Add 1% cess = Rs. 10.85
Rate per m 3
= Rs. 1095.56

4 Item No. 4.11(iii)/(B)Page No 245 of P.W. (Roads) Schedule of Rates 2015-2016


Providing, laying, spreading and compacting stone aggregates of specific sizes to water bound macadam
specification including spreading in uniform thickness, hand packing, rolling with vibratory roller 8-10
tonnes in stages to proper grade and camber, applying and brooming requisite type of screening / binding
materials to fill up the interstices of coarse aggregate, watering including lighting, guarding, barricading and
making necessary earthen bundh of one metre width on each side and preparing the bed by necessary
cutting or filling, including cost of all materials and hire and labour charges of all men and machinery and
compacting to the required density, as per Clause 404 of Specifications for Road & Bridge Works of
MoRT&H (5th Revision).

(ii) Grading-I Aggregate (63 mm to 45 mm) Using Stone Screening Type B (11.2 mm)
A. Mechanical Means
Grading I stone aggregates 1.210 m3 @ Rs. 1014.75 / m3 = Rs. 1227.85
Type B screening 0.240 m3 @ Rs. 629.25 / m3 = Rs. 151.02
Add labour rate per m3 = Rs. 215.00
1593.87
Add 1% cess = Rs. 15.94
Rate per m3 = Rs. 1609.81
5 Item No. 4.04 Page No 242 of P.W. (Roads) Schedule of Rates 2015-2016
Supplying, spreading and consolidating Moorum to a depth of 75 mm at desired density and C.B.R. as per
specification with power roller to proper gradient and camber including watering as necessary, and lighting,
guarding, barricading and making adequate earthen bundh where necessary to protect the edges and curing
with water for 2 to 3 days, mending cracks by rolling where necessary including all incidental charges of
roller, cost of fuel & lubricants etc. complete as per specification.

cost of moorum 1.493 m3 @ Rs. 639.00 / m3 = Rs. 953.73


Add labour rate per m3 = Rs. 167.00
1120.73
Add 1% cess = Rs. 11.21
3
Rate per m = Rs. 1131.94
6 Item No. 14.02 Page No 304 of P.W. (Roads) Schedule of Rates 2015-2016
Providing Sal-bullah / Eucalyptus bullah piles of diameter not less than 150mm, driving upto desired depth
but not less than 4 m and spacing as per approved design and joining each bullah piles with the staging
props by proper arrangement capable to transmit the loads from superstructure, all complete.

= Rs. 2000.00
Add 1% cess = Rs. 20.00
Rate per m2 = Rs. 2020.00

7 Item No. 18.29 Page No 325 of P.W. (Roads) Schedule of Rates 2015-2016
Filling empty Cement bags with dry earth or sand, stitching the bag (cost of thread included) and
carrying and placing them in position and all incidental charges complete but excluding cost of
sand and gunny bags.

cost of sand 0.0280 m³ @ Rs. 350.00 /m³ = Rs. 9.80


cement bag = Rs. 3.30
Labour rate = Rs. 3.50
= Rs. 16.60
Add. Cess 1% = Rs. 0.17
Rate per m3 = Rs. 16.77
8 Item No. 11.03 Page No 276 of P.W. (Roads) Schedule of Rates 2015-2016
Providing and laying reinforced cement concrete pipe NP3 with spigot socket for culverts on first class
bedding of granular material in single row including fixing with cement mortar 1:2 as per Technical
Specification Clause 1106 for Rural Roads of MORD.
(C) 900 mm dia
Labour rate = Rs. 651.00
cost of 900 dia hume pipe = Rs. 3742.00
carriage ( 48 km) = Rs. 326.60
L/UL = Rs. 43.20
= Rs. 4762.80
Add. Cess 1% = Rs. 47.63
Rate per m3 = Rs. 4810.43

Lead from Bolpur = 48.00 km


Carriage upto 5.0km @ Rs / km =Rs 74.00
from 5 km to 10 km @ Rs 6.60 / km =Rs 33.00
from 10 km to 20 km 6.0 / km =Rs 60.00
from 20 km to 48 km 5.70 / km =Rs 159.60
=Rs 326.60

Junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
Box Bridge
1 Item No. 2.05 Page No 230 of P.W. (Roads) Schedule of Rates 2015-2016
Dismantling of existing structures like culverts, bridges, retaining walls and other structure comprising of
masonry, cement concrete, steel work, including T&P and scaffolding wherever necessary, sorting the
dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts
and lead of 1000 m as per Technical Specifications Clause 202 for Rural Roads of MORD.
(II) By Mechanical Means
a) Cement Concrete
Basic rate Rs 470.00
Add. Cess 1.00% Rs 4.70
Rate per m3 Rs 474.70

b) Reinforced Cement Concrete


Basic rate Rs 773.00
Add. Cess 1.00% Rs 7.73
Rate per m3 Rs 780.73

2 Item No. 12.01 Page No 278 of P.W. (Roads) Schedule of Rates 2015-2016
Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, removing, spreading or stacking of spoils within a lead of 150 m. as directed and
including trimming the sides of the trenches, leveling, dressing and ramming the bottom, and backfilling
with approved material complete as per direction of the Engineer-in-Charge .
a) upto 3 m depth
(i) With pumping out water including shoring as required.
Basic rate Rs 124.00
Add. Cess 1.00% Rs 1.24
Rate per m3 Rs 125.24

3 Item No. 12.04 Page No 280 of P.W. (Roads) Schedule of Rates 2015-2016
Sand filling in foundation trenches and at the back of abutments, wing-walls etc. with good local sand free
from earth in layers not exceeding 15 cm. including inundating each layer by profuse water and poking and
ramming layer by layer complete including supply of sand. Quality of sand is to be approved by the
Engineer-in-charge.
cost of sand 1.198 m³ @ Rs. 350.00 /m³ = Rs. 419.16
Labour rate = Rs. 177.00
= Rs. 596.16
Add. Cess 1% = Rs. 5.96
Rate per m3 = Rs. 602.12

4 Item No.12.05 Page No 280 of P.W. (Roads) Schedule of Rates 2015-16


Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any part of
foundation of bridges / culverts with graded stone chips of appropriate nominal sizes, including screening
and cleaning of coarse aggregates, fine aggregate (sand) conforming to proper grading zone, both of
approved quality and cement, as necessary, cost of curing with water, including cost and carriage of all
materials and including preparation of design mix, approval of the same by the Engineer-in-Charge, cost for
quality control, sampling, testing etc. including cost of formwork but excluding reinforcement complete as
per drawing and technical specifications.
A) PCC Grade M20
I) Using concrete mixer
cement (supplied by the contractor)
Vide page no.217 FORMAT - C

Rate of item = Rs 2175.00


Cost of cement = 0.400 x 7364.00 = Rs 2945.60
Overhead charges @ 5% of (B) = Rs 147.28
Contractor profit @ 10% of (B+C) Rs 309.29
Rs 5577.17
stone Aggregate
cost of 20 mm chips
(60% of 0.9 m3) 0.54 m3 @ Rs. 1151.25 / m3 = Rs. 621.68
cost of 10 mm chips
40% of 0.9 m3 0.36 m3 @ Rs. 960.25 / m3 = Rs. 345.69
Rs 967.37

Consolidataed Rate of this Item


Cost of
0.9 m3 crushed stone aggregate = Rs 967.37
Cement = Rs 5577.17
Rs 6544.53

D) RCC Grade M25


I) Using concrete mixer

cement (supplied by the contractor)


Vide page no.217 FORMAT - C

Rate of item = Rs 2306.00


Cost of cement = 0.420 x 7364.00 = Rs 3092.88
Overhead charges @ 5% of (B) = Rs 154.64
Contractor profit @ 10% of (B+C) Rs 324.75
Rs 5878.28

stone Aggregate

cost of 20 mm chips
(60% of 0.9 m3) 0.54 m3 @ Rs. 1151.25 / m3 = Rs. 621.68
cost of 10 mm chips
40% of 0.9 m3 0.36 m3 @ Rs. 960.25 / m3 = Rs. 345.69
Rs 967.37
Consolidataed Rate of this Item
Cost of
0.9 m3 crushed stone aggregate = Rs 967.37
Cement = Rs 5878.28
Rs 6845.64
5 Item No.13.02 Page No 297 of P.W. (Roads) Schedule of Rates 2015-16
Supplying, fitting and placing HYSD bar reinforcement in Sub-structure including initial straightening,
straightening of coils bars, removal of loose rust (if any), cutting to requisite length bending, binding with
annealed wire not less than 1 mm in size and conforming to IS 280 at every intersection hooked and bent to
correct shape and placed on forms etc. including cost of black annealed wire and cost of loading, unloading,
carriage of all steel materials complete as per drawing and technical specifications and direction of
Engineer-in-charge.
carriage Cost of reinforcement
Distance from work site to durgapur = 103 km

Carriage upto 5.0km per MT =Rs 82.00


from 5 km to 10 km @ Rs 7.30 / km =Rs 36.50
from 10 km to 20 km @ Rs 6.70 / km =Rs 67.00
from 20 km to 50 km @ Rs 6.3 / km =Rs 189.00
from 50 km to 100 km @ Rs 5.60 / km =Rs 280.00
from 100 km to 103 km @ Rs 5.30 / km =Rs 15.90
Loading & unloading per MT 0.75 @ 96.0/MT =Rs 72.00
Rs 742.40

A. Item rate = Rs 3369.00


B. Add issue price at outlet of steel
1.05 X 49900.00 / MT = Rs 52395.00

C. carriage+Loading+unloading 742.40 / MT = Rs 779.52

D. Overhead charges @ 5% of (B+C) = Rs 2658.73

E. Contractor Profit @ 10% of (B+C+D) = Rs 5583.32


Rs 64785.57 per MT

6 Item No.13.03 Page No 297 of P.W. (Roads) Schedule of Rates 2015-16


Providing weep holes in Brick masonry / Plain / Reinforced concrete abutment, wing wall / return
wall with 100 mm dia AC pipe, extending through the full width of the structure with slope of 1V:20H
towards drawing face. Complete as per drawing and Technical specifications.

Basic rate Rs 126.00


Add. Cess 1.00% Rs 1.26
Rate per m3 Rs 127.26
7 Item No.14.08 Page No 305 of P.W. (Roads) Schedule of Rates 2015-16
Construction of precast RCC railing of M30 Grade, aggregate size not exceeding 12 mm, true to line
and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing between
vertical post not to exceed 2000 mm, leaving adequate space between vertical post for expansion, complete
as per approved drawings and technical specifications.

Basic rate Rs 1855.00


Add. Cess 1.00% Rs 18.55
Rate per m3 Rs 1873.55
8 Item No.14.09 Page No 305 of P.W. (Roads) Schedule of Rates 2015-16
Drainage Spouts in Superstructure including providing drip mouldings and also including supplying, fitting
and fixing approved type of materials complete as per drawing and Technical
specification vide clause no. 2705 of MoRT&H’s Specification for Road & Bridge Works.

Basic rate Rs 899.00


Add. Cess 1.00% Rs 8.99
Rate per each Rs 907.99
9 Item No.14.04 Page No 304 of P.W. (Roads) Schedule of Rates 2015-16
Providing and laying Cement concrete Wearing coat M-30 grade with graded stone chips 19mm
down including screening and cleaning approved stone chips and sand as necessary laying, finishing
complete to camber and grade, curing with water, including cost and carriage of all materials and hire
charges for form work including reinforcement complete as per drawing and Technical Specifications vide
clause no. 2702 of MoRT&H’s Specification for Road & Bridge Works.

Basic rate Rs 10938.00


Add. Cess 1.00% Rs 109.38
Rate per cum Rs 11047.38
10 Item No.14.06 Page No 306 of P.W. (Roads) Schedule of Rates 2015-16
Providing and laying of asphaltic plug joint to provide for horizontal movement of 25 mm and
vertical movement of 2 mm, depth of joint varying from 75 mm to 100 mm, width varying from 500 mm to
750 mm (in traffic direction), covered with a closure plate of 200mm x 6mm of wieldable
structural steel conforming to IS: 2062, asphaltic plug to consist of polymer modified bitumen binder,
carefully selected single size aggregate of 12.5 mm nominal size and a heat resistant foam
caulking/backer rod, all as per approved drawings and specifications.

Basic rate Rs 9875.00


Add. Cess 1.00% Rs 98.75
Rate per mtr Rs 9973.75

11 Item No.12.03 Page No 279 of P.W. (Roads) Schedule of Rates 2015-16


Earth in filling in foundation trenches and at the back of abutments with good earth (sandy soil) in
layers not exceeding 15 cm. including watering and ramming layer by layer complete with earth
obtained by fresh excavation from land arranged by Department beyond 150 m. but within 300 m.
including all lifts. Earth to be approved by the Engineer-in-charge.

Basic rate Rs 161.00


Add. Cess 1.00% Rs 1.61
Rate per cum Rs 162.61

12 Item No.8.21 Page No 268 of P.W. (Roads) Schedule of Rates 2015-16


Painting the vertical end faces of posts, wheel guards or railing or parapet with alternate bands of different
colours as directed by the Engineer-in-charge with approved synthetic enamel paint.
Two coats

Basic rate Rs 99.00


Add. Cess 1.00% Rs 0.99
Rate per sq m Rs 99.99

Junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
Type -B Cost of Stone moorum at Work Site per m3 :-
materia Grade Grade screenin
l -I -II
g
mat.

cost 483.00 ### 102.00 C arriage cost :- (P-228 , Table -1)


L+Ul 62.25 62.25 46.50 above #REF! Km upto Err:504 Km = Err:504 Km @ Rs.

Carriage 40.00 40.00 40.00 above #REF! Km upto Err:504 Km = Err:504 Km @ Rs.
total 585.25 ### 188.50 above Err:504 Km upto Err:504 Km = Err:504 Km @ Rs.
above #REF! Km upto Err:504 Km = Err:504 Km @ Rs.
above #REF! Km upto #REF! Km = #REF! Km @ Rs.
material sand

L+Ul 0.00 77.00 77.00 77.00 77.00 77.00 77.00 62.00 83.00

Carriage 0.00 374.50 374.50 374.50 374.50 Err:504 Err:504 374.50 Err:504
total 0.00 451.50 451.50 451.50 451.50 Err:504 Err:504 436.50 Err:504

Grade-I Grade-II Grade-III Screening Screening


Stone Stone Stone Type-A Type-B

483.00 545.00 0.00 0.00 102.00

83.00 77.00 0.00 0.00 62.00


0.00 0.00 0.00 0.00 0.00

566.00 622.00 0.00 0.00 164.00


Source at : Kolkata

Lead from sourc 228 Km.


Stone dust with grit (40%)
Filler @ 2% (Lime stone dust)
11 Item No.245 Page No 245 of P.W. (Roads) Schedule of Rates 2015-2016

Providing, laying, spreading and compacting stone aggregates of specific sizes to


water bound Aggregate
ii) Grading-I macadam (63 specification
mm to 45including
mm) Using spreading in uniform
Stone Screening thickness,
Type B
hand packing,
(11.2 mm) rolling with vibratory roller 8-10 tonnes in stages to proper grade
and camber,
B. Manual applying and brooming requisite type of screening / binding
Means
materials to fill up the interstices of3coarse aggregate, watering 3
including lighting,
cost of GradE
guarding, I Aggrega
barricading 1.21 / m
and making @earthen
necessary Rs. 585.25
bundh/m = Rs.width
of one metre 708.15
on
each side and preparing
cost of Screening (Type the bed by
0.24 / m necessary
3 cutting or filling,
@ Rs. 188.50 / m 3 including cost of all
= Rs. 45.24
materials and hire and labour charges of all men and machinery and compacting
to the required density, as per Clause 404 of Specifications for Road & Bridge
Works of MoRT&H (5th Revision).
iii) Grading-II Aggregate (53 mm to 22.4 mm) Using Stone Screening Type B
(11.2 mm)
B. Manual Means
cost of Grading II 1.21 / m3 @ Rs. 647.25 / m3 = Rs. 783.17
cost of Screening 0.24 / m3
@ Rs. 188.50 / m3
= Rs. 45.24
Add labour rate per m3 = Rs. 356.00

= Rs. ###

Add 1% cess = Rs. 11.84


3
Rate per m = Rs. ###
#REF! /Km =Rs. Err:504

#REF! /Km =Rs. #REF!


#REF! /Km =Rs. #REF!
#REF! /Km =Rs. Err:504
#REF! /Km =Rs. #REF!
Total= Rs. Err:504 Screening Moorum
Type-B

77.00 0.00 0.00 62.00 0.00

Err:504 0.00 0.00 Err:504 0.00


Err:504 0.00 0.00 Err:504 0.00
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of sainthia -sultanpur
road (SH-11) by rigid & flexible pavement under birbhum division, PWD in the district of birbhum
during the year 2017-18
BILL OF QUANTITY (Rigid Portion)
1 Item No.18.02 (b)(ii) Page No 321 of P.W. (Roads) Schedule of Rates 2015-16
Picking up and removing old bituminous layer or sand sealing coat from old
black topped surface and cleaning the exposed surface by scraping and
stacking the material as directed.

b) By mechanical means
(ii) From 50 mm to 100 mm thick.
30800.00 m2 @ Rs 7.58 /m2 = Rs 233,310.00

2 Item No. 4.12 Page No 246 of P.W. (Roads) Schedule of Rates 2015-2016
Wet Mix Macadam base course
Providing, laying, spreading and compacting graded stone aggregate to Wet
Mix Macadam specification including screening of aggregates and granular
materials, premixing the material with water at OMC in Wet Mix Plant,
carriage of mixed material by tipper to site, laying in uniform layers with
Paver in Sub- base /Base course on well prepared surface and compacting
with Vibratory Roller to achieve the desired density,including supply of all
materials, machinery, fuel and lubricants, including incidental costs for
lighting,guarding, barricading, making earthen bundh to protect the edges
including cost of quality control complete as per Clause 406 of Specifications
for Road & Bridge Works of MoRT&H (5th Revision).cum 338.00 362.00Note
Add cost at site of 1.32 m³ of the stone materials as per specified grading to
arrive at the complete rate.

3142.00 m3 @ Rs 1600.69 /m3 = Rs 5,029,368.00

3 Item No. 13 Page No 46 of P.W.D (BLD.) Schedule of Rates 2015-2016


Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof
course or below flooring or roof terracing or in foundation or in foundation
trenches.
31416.00 m2 @ Rs 25.00 /m2 = Rs 785,400.00
4 Item No.6.01 Page No 259 of P.W. (Roads) Schedule of Rates 2015-2016
Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over a prepared sub-
grade with coarse and fine aggregate conforming to IS: 383, the size of
coarse aggregate not exceeding 25 mm, aggregate cement ratio not to exceed
15:1, aggregate gradation after blending to be as per table 600-1,cement
content not to be less than 150 kg/ cum, optimum moisture content to be
determined during trial length construction, concrete strength not to be less
than 10 Mpa at 7 days, mixed in a batching plant, transported to site, laid
with a paver with electronic sensor, compacting with 8-10 tonnes vibratory
roller, finishing and curing. (As per clause 601 of specifications for Road &
Bridge Works of MoRT&H (5th Revision).
4712.00 m3 @ Rs 2903.97 /m3 = Rs 13,683,507.00
5 Item No.6.02(A) Page No 260 of P.W. (Roads) Schedule of Rates 2015-2016
Construction of un-reinforced, dowel jointed at expansion and construction
joint only, plain cement concrete pavement, thickness as per design, over a
prepared sub base, with cement content as per IRC: 15-2011, coarse and fine
aggregates conforming to IS:383, maximum size of coarse aggregate not
exceeding 25 mm, mixed in a batch mix plant / RMC and appropriate weigh
batcher using approved mix design (as per IRC:44 2008), laid in approved
fixed side formwork (steel channel, laying and fixing of 125 micron thick
polythene film, wedges, steel plates including levelling the formwork as per
drawing, spreading the concrete with shovels, rakes, compacted using
needle, screed and plate vibrators and finished in continuous operation
including provision of contraction and expansion, construction joints,
applying debonding strips, primer, polysulphide sealant, dowel bars, near
approaches to bridge/ culvert and construction joints, admixtures
asapproved, curing of concrete slabs for 14-days, using curing compound
(where specified) and water finishing to lines and grade as per drawing and
Technical Specification Clause 1501 for Rural Roads of MORD.

(i) With Batch mix plant

9425.00 m3 @ Rs 12003.31 /m3 = Rs 113,131,197.00

6 Item No.09 Page No 230 of P.W.D (bld.) Schedule of Rates 2015-2016


Bituminous filler of approved type in expansion joints of dummy joints
including finishing the top surface as directed.

3.00 m3 @ Rs 54737.00 /m3 = Rs 164,211.00

7 Item No.92 Page No 298 of P.W.D (bld.) Schedule of Rates 2015-2016


hire and labour charges for 100mm dia bamboo railing on 150mm dia
Jhau/Eucalyptus or other approved timber 1.4 m above G.L. and 0.60 m
below G.L. including tying strongly with coir ropes and boring holes for posts
in any soil /black top/concrete surface, packing the sides etc. including cost
of carriage of all materials and labour complete and maintaining barricading
for a period beyond 5(five) days after the reported & recorded time of
completion of the entire work to the satisfaction of Engineer-in-Charge,
including restoration to the damages of the ground to its original condition
as per direction of Engineer-in -Charge after removing the barricade. [Cost of
restoration will be paid separately.]

100 mm. dia bamboo railing & 150mm. dia Jhau/Eucalyptus/other


approved
timber posts @ 1.80m apart
(i) Railing with 4 rows.

924.00 mtr @ Rs 103.00 /mtr = Rs 95,172.00


Rs. 133,122,165.00
junior Engineer Assistant Engineer
Section II, PWD Suri Sub-Division PWD
Dowel jointed concrete & DLC Rate Analysis
1 Item No.6.02 A Page No 260 of P.W. (Roads) Schedule of Rates 2015-2016
Construction of un-reinforced, dowel jointed at expansion and construction joint only, plain
cement concrete pavement, thickness as per design, over a prepared sub base, with cement
content as per IRC: 15-2011, coarse and fine aggregates conforming to IS:383, maximum size
of coarse aggregate not exceeding 25 mm, mixed in a batch mix plant / RMC and appropriate
weigh batcher using approved mix design (as per IRC:44 2008), laid in approved fixed side
formwork (steel channel, laying and fixing of 125 micron thick polythene film, wedges, steel
plates including levelling the formwork as per drawing, spreading the concrete with shovels,
rakes, compacted using needle, screed and plate vibrators and finished in continuous
operation including provision of contraction and expansion, construction joints, applying
debonding strips, primer, polysulphide sealant, dowel bars, near approaches to bridge/
culvert and construction joints, admixtures asapproved, curing of concrete slabs for 14-days,
using curing compound (where specified) and water finishing to lines and grade as per
drawing and Technical Specification Clause 1501 for Rural Roads of MORD.

(i) With Batch mix plant


Cost of reinforcement calculated for dowel/Tie bar
Distance from work site to durgapur = 112 km

Carriage upto 5.0 km per MT =Rs 82.00


from 5 km to 10 km @ Rs 7.30 / km =Rs 36.50
from 10 km to 20 km @ Rs 6.70 / km =Rs 67.00
from 20 km to 50 km @ Rs 6.3 / km =Rs 189.00
from 50 km to 100 km @ Rs 8.60 / km =Rs 280.00
from 100 km to 112 km @ Rs 5.30 / km =Rs 63.60
Loading & unloading per MT 0.75 @ 96.0/MT =Rs 72.00
Rs 790.10

Add issue price at outlet of steel 49900.00 / MT = Rs 49900.00


carriage+Loading+unloading 790.10 / MT = Rs 790.10
Rs 50690.10
per MT
Reinforcement required
Vol. of Each slab
5.00 x 4.50 x 0.30 = 6.75 m3

38 mm Dowel bar in Expansion joint = 5/.3 = 17 nos 960

= 17 X 0.90 = 15.30 mtr


@ 8.91 kg/m = 136.32 kg
= 0.1363 MT … (A)

12 mm Tie bar in contraction joint = 4.5/.60 = 8 nos


= 8 X 0.375 = 2.81 mtr
@ 0.88 kg/m = 2.48 kg
= 0.0025 MT ... (B)

Total of (A)+(B) = 0.13880 MT ... (C)


So. Per cum of Conc. Reinforcement required =
0.13880 / 6.75 = 0.0206 MT

Cost of Reinforcement per cum = 0.0206 x 50690.10


= Rs 1042.32

stone Aggregate

cost of 20 mm chips 0.540 m3


(60% of 0.9 m3) @ Rs. 1151.25 / m3 = Rs. 621.68

cost of 10 mm chips 0.360 m3


40% of 0.9 m3 @ Rs. 960.25 / m3 = Rs. 345.69
Rs 967.37

cement
Cost of cement = 0.450 x 7364.00 = Rs 3313.80

Consolidated Rate of this Item


Cost of
Labour Rate = Rs 1627.00
0.9 m3 crushed stone aggregate = Rs 967.37
Cement = Rs 3313.80
Dowel bar & Tie bar = Rs 1042.32
medium sand = Rs 350.00
Silica fume @ 60 kg / m3 = Rs 1500.00
Plastisizer 2% of cement wt. = 9 kg = Rs 1620.00
form work (3% of cost of material) = Rs 263.80
overhead charges (5% of cost of material) = Rs 439.67
contractor profit 10 % = Rs 879.35
Rs 12003.31

2 Item No.6.01 Page No 259 of P.W. (Roads) Schedule of Rates 2015-2016


Dry Lean Cement Concrete Sub- base
Construction of dry lean cement concrete Sub- base over a prepared sub-grade with coarse
and fine aggregate conforming to IS: 383, the size of coarse aggregate not exceeding 25 mm,
aggregate cement ratio not to exceed 15:1, aggregate gradation after blending to be as per
table 600-1,cement content not to be less than 150 kg/ cum, optimum moisture content to be
determined during trial length construction, concrete strength not to be less than 10 Mpa at 7
days, mixed in a batching plant, transported to site, laid with a paver with electronic sensor,
compacting with 8-10 tonnes vibratory roller, finishing and curing. (As per clause 601 of
specifications for Road & Bridge Works of MoRT&H (5th Revision).

cement
Cost of cement = 0.15 x 7364.00 = Rs 1104.60
Rs 1104.60

Consolidated Rate of this Item


Cost of
Labour Rate = Rs 832.00
0.9 m3 crushed stone aggregate = Rs 967.37
Cement = Rs 1104.60
Rs 2903.97
junior Engineer Assistant Engineer
Section II, PWD Suri Sub-Division PWD
6.32098765432

16.666667
4.9450549

450
650 0.8888889

1444
8.9135802 8.9135802

0.0100741
0.0205626667

5673.49
170.20455

9
PREFACE REPORT

1.     
NameNameof theof Proposed
Work:- Maintanance
improvement&ofrepair
the existing
to S.O carriageway
office , sainthia
fromsec.(ii)
1.00 at sainthia unde
work :- kmp to 19.00 kmp of sainthia -sultanpur road (SH-11) by rigid
& flexible pavement under birbhum division, PWD in the
district of birbhum during the year 2017-18

2.     
Preface:-
Name of The
Work:-
primary
Maintanance
scope incorporated
& repair to
in S.O
the DPR
officeis, sainthia
to improved
sec.(ii)
& at sainthia unde
upgrade Sainthia-Sultanpur Road from 0.00 kmp to 1.00 kmp
located in the civil jurisdiction of Suri sadar Sub-division under
Birbhum Division.

Classification
3.      Name of The
Work:-Sainthia-Sultanpur
Maintanance &Roadrepairis atoState
S.O office
highway
, sainthia
having sec.(ii)
length at sainthia unde
& present of 19.00 km in total. The width of the existing carriageway of
condition of this Road is 10.00 m. The length of the stretch of the road under
the road:- consideration of this project is 0.00 kmp to 1.00 kmp and
improvement of Bagdanga more and Taltala more. The length
of stretch under this project is 1202.00m in total. The condition
of the above mentioned chainage is very poor and present
carriageway can not bear the heavy vehicular load. The
Existing composition of road section at middle of carriageway
is 40 mm BC, 75 mm DBM, 250 mm WMM. And below
WMM layer there is another layer of moorum and boulder. The
total depth upto WMM layer is 365 mm. It is found that water
is retained in moorum layer and it is required to be removed.

4.   
Necessity of The Sainthia-Sultanpur road is very important as it connects ihe
the project:- two well kown districts Birbhum and Murshidabad. It is also
used as connecting road for many major places in birbhum
district like Bolpur, Suri, Md bazar and mollarpur on NH. 60,
Rampurhat, Tarapith etc. It is also mentioned have that several
nos nos. of sand Ghat is located on this road. Due to the
connectivity of this road a large nos of public vehicle and truck
carrying stone material and sand ply over this Road everyday to
reach their destination. Water mixed with sand has outleting
from those trucks entire to this chainage in constant mode
round the year. From experience it is observed that bituminous
surfacing is not suitable to overcome this specific problem. So
Rigid pavement is proposed for this stretch of the road
5.   
Proposal :- The chainage from 0.00 kmp to 1.00 kmp of Sainthia -
Sultanpur Road including development of Bagdanga more and
Taltala More is proposed in this work. The total length of this
streach stands at 1.202 km. Rigid pavement as well as flexible
pavement is proposed for the entire chainage. The details
shown in Annexure : A. The length of rigid pavement is
proposed for 772.0 m. In rigid pavement consider M-45 grade
Pavement Quality Concrete, 300 mm thick including dowel bar
and other component shown in Annexure : B. The scope of
work of flexible pavement on the rest portion i.e is only 430.0
m. In this portion resection has been proposed and overall
thichness considered 730 mm. Surface drain is proposed on
both side of the road in stretches for smooth drainout of rain
water.

4.   Schedule:- As per current western circle I schedule rates of P.W.D® &


bld. & 6 th corrigendum & addenda as circulated by P.W.D
Wef 22.06.2016

Estimated
5.    cost:- Rs 518,538,929.00 (including 3% contengency)
( Rupees Five crore Seventy Three Thousand & fifty
four only.)
The work will be executed by the Birbhum division
Execution:-
6.    P.W.D on the basis of availability of fund after NIT by
the appropriate authority.

Tools
7.    & Plant:- No special tools and plants are to be required as usual.

Certificates:-
8.    Certified that

(A) There is no need to cut any existing trees on Road


Embankment.

(B) The said portion of the road is not lying under Defect
Liability period

( C ) This estimate has been Prepared as per detailed site


inspection and items considered for this project is
technically best suited as per site condition.
Junior Engineer Assistant Engineer
sec II.,P.W.D suri sub-division,P.W.D
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of
sainthia -sultanpur road (SH-11) by rigid & flexible pavement under birbhum division,
PWD in the district of birbhum during the year 2017-18
QUANTITY ANALYSIS ( RIGID PAVEMENT PORTION)

Total Road length = 18.000 Km


crust = 10.00 m
width
Length calculation for Rigid Portion
from
1.00 kmp to 1.500 kmp = 500.00 mtr
2.580 kmp to 2.890 kmp = 310.00 mtr
4.530 kmp to 6.800 kmp = 2270.00 mtr
3080.00 mtr …………. MKD (A)

1 Picking up and removing old bituminous layer .


b) By mechanical means
(ii) From 50 mm to 100 mm thick.
Rigid por. Only:- 1 x 3080.00 x 10.00 = 30800.00 M2
Length MKD(A)

30800.00 M2

2 WMM:-
1 x 3080.00 x 10.00 x 0.100 = 3080.00 M3
= 3080.00 M3
2% for bell mouth/ curve = 61.60 M3
= 3141.60
Say 3142.00 M3

3 POLYTHENE SHEET
1 x 3080.00 x 10.00 = 30800.00 M2
30800.00
2% for bell mouth/ curve = 616.00 M2
= 31416.00 M2
Say 31416.00 M2
4 DLC:-
for conc. Por
1 x 3080.00 x 10.00 x 0.150 = 4620.00 M3
= 4620.00 M3
2% for bell mouth/ curve = 92.40 M3
4712.40 M3
Say 4712.00 M3

5 UNREINFORCED DOWEL JOINTED CONC (M-45):-


for conc. Por
1 x 3080.00 x 10.00 x 0.300 = 9240.00 M3
9240.00 M3
2% for bell mouth/ curve = 184.80 M3
9424.80 M3
Say 9425.00 M3
6 BITUMEN FILLER:-

684 x 10.00 x 0.020 x 0.020 = 2.74 M3


1 x 3080.00 x 0.012 x 0.020 = 0.74 M3
3.48 M3
Say 3.00 M3
7 BARRICADING:-

1 x 3080.00 x 30% = 924.00 mtr

Junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
2270

1100

0.87
#REF!

540

3388
222.22222
2.55
5.1
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of sainthia
-sultanpur road (SH-11) by rigid & flexible pavement under birbhum division, PWD in the
district of birbhum during the year 2017-18
Drain Portion
1 Item No.12.01 Page No 278 of P.W. (Roads) Schedule of Rates 2015-2016
Excavation for Structures Earth work in excavation of foundation of
structures as per drawing and technical specification, including setting out,
removing, spreading or stacking of spoils within a lead of 150 m. as directed
and including trimming the sides of the trenches, leveling, dressing and
ramming the bottom, and backfilling with approved material complete as per
direction of the Engineer-in-Charge .

In all sorts of soil excluding marshy soil & rocks


(soft or hard) by manual means.
a) upto 3 m depth
iii) Without pumping out water but including
shoring as required

1312.50 m3 @ Rs 124.23 /m3 = Rs 163,052.00

2 Item No.12.04 Page No 280 of P.W. (Roads) Schedule of Rates 2015-16


Sand filling in foundation trenches and at the back of abutments, wing walls
etc. with good local sand free from earth in layers not exceeding 15 cm
including innundating each layer by profuce water and poking and ramming
layer by layer complete including supply of sand. Quality of sand is to be
approved by EIC.

113.00 m3 @ Rs 602.12 /m3 = Rs 68,040.00

3 Item No. 13 Page No 46 of P.W. (bld) Schedule of Rates 2015-2016


Supplying and laying Polythene Sheet (150gm / sq.m.) over damp proof
course or below flooring or roof terracing or in foundation or in foundation
trenches

1500.00 m2 @ Rs 25.00 /m2 = Rs 37,500.00


4 Item No.12.05 Page No 280 of P.W. (Roads) Schedule of Rates 2015-2016
Plain / Reinforced Cement Concrete in Open foundation with or without
reinforcements, in any part of foundation of bridges / culverts with graded
stone chips of appropriate nominal sizes, including screening and cleaning of
coarse aggregates, fine aggregate (sand) conforming to proper grading zone,
both of approved quality and cement, as necessary, cost of curing with water,
including cost and carriage of all materials and including preparation of
design mix, approval of the same by the Engineer-in-Charge, cost for quality
control, sampling, testing etc. including cost of formwork but excluding
reinforcement complete as per drawing and technical specifications.

A) PCC Grade M20


I) Using concrete mixer

360.00 m3 @ Rs 6459.03 /m3 = Rs 2,325,251.00


D) RCC Grade M25

510.00 m3 @ Rs 6760.14 /m3 = Rs 3,447,671.00


5 Item No.13.02 Page No 297 of P.W. (Roads) Schedule of Rates 2015-2016
Supplying, fitting and placing HYSD bar reinforcement in Sub-structure
including initial straightening, straightening of coils bars, removal of loose
rust (if any), cutting to requisite length bending, binding with annealed wire
not less than 1 mm in size and conforming to IS 280 at every intersection
hooked and bent to correct shape and placed on forms etc. including cost of
black annealed wire and cost of loading, unloading, carriage of all steel
materials complete as per drawing and technical specifications and direction
of Engineer-in-charge.

40.00 MT @ Rs 64785.57 /MT = Rs 2,591,423.00


Total Rs 8,632,937.00

junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
Err:509
Err:509
Err:509
Rate Analysis ( Drain portion)
1 Item No.12.01 Page No 278 of P.W. (Roads) Schedule of Rates 2015-16
Excavation for Structures Earth work in excavation of foundation of structures as per
drawing and technical specification, including setting out, removing, spreading or stacking
of spoils within a lead of 150 m. as directed and including trimming the sides of the
trenches, leveling, dressing and ramming the bottom, and backfilling with approved
material complete as per direction of the Engineer-in-Charge .

In all sorts of soil excluding marshy soil & rocks


(soft or hard) by manual means.
a) upto 3 m depth
(ii) With pumping out water excluding shoring

Cost of Labour per sqm. = Rs. 123.00


= Rs. 123.00
Add 1% cess = Rs. 1.23
Rate per m3 = Rs. 124.23

2 Item No.12.04 Page No 280 of P.W. (Roads) Schedule of Rates 2015-16


Sand filling in foundation trenches and at the back of abutments, wing walls etc. with good
local sand free from earth in layers not exceeding 15 cm including innundating each layer
by profuce water and poking and ramming layer by layer complete including supply of
sand. Quality of sand is to be approved by EIC.

cost of sand 1.1976 / m3 @ Rs. 350.00 / m3 = Rs. 419.16


Add labour rate per m3 = Rs. 177.00
= Rs. 596.16
Add 1% cess = Rs. 5.96
Rate per m3 = Rs. 602.12

3 Item No.12.05 Page No 280 of P.W. (Roads) Schedule of Rates 2015-16


Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in
any part of foundation of bridges / culverts with graded stone chips of appropriate nominal
sizes, including screening and cleaning of coarse aggregates, fine aggregate (sand)
conforming to proper grading zone, both of approved quality and cement, as necessary,
cost of curing with water, including cost and carriage of all materials and including
preparation of design mix, approval of the same by the Engineer-in-Charge, cost for quality
control, sampling, testing etc. including cost of formwork but excluding reinforcement
complete as per drawing and technical specifications.

A) PCC Grade M20


I) Using concrete mixer
cement (supplied by the contractor)
Vide page no.217 FORMAT - C

Rate of item = Rs 2175.00


Cost of cement = 0.400 x 7364.00 = Rs 2945.60
Overhead charges @ 5% of (B) = Rs 147.28
Contractor profit @ 10% of (B+C) Rs 309.29
Rs 5577.17
stone Aggregate
cost of 20 mm chips
(60% of 0.9 m3) 0.54 m3 @ Rs. 1056.25 / m3 = Rs. 570.38
cost of 10 mm chips
40% of 0.9 m3 0.36 m3 @ Rs. 865.25 / m3 = Rs. 311.49
Rs 881.87

Consolidataed Rate of this Item


Cost of
0.9 m3 crushed stone aggregate = Rs 881.87
Cement = Rs 5577.17
Rs 6459.03

D) RCC Grade M25


I) Using concrete mixer

cement (supplied by the contractor)


Vide page no.217 FORMAT - C

Rate of item = Rs 2306.00


Cost of cement = 0.420 x 7364.00 = Rs 3092.88
Overhead charges @ 5% of (B) = Rs 154.64
Contractor profit @ 10% of (B+C) Rs 324.75
Rs 5878.28

stone Aggregate

cost of 20 mm chips
(60% of 0.9 m3) 0.54 m3 @ Rs. 1056.25 / m3 = Rs. 570.38
cost of 10 mm chips
40% of 0.9 m3 0.36 m3 @ Rs. 865.25 / m3 = Rs. 311.49
Rs 881.87
Consolidataed Rate of this Item
Cost of
0.9 m3 crushed stone aggregate = Rs 881.87
Cement = Rs 5878.28
Rs 6760.14

4 Item No.13.02 Page No 297 of P.W. (Roads) Schedule of Rates 2015-16


Supplying, fitting and placing HYSD bar reinforcement in Sub-structure including initial
straightening, straightening of coils bars, removal of loose rust (if any), cutting to requisite
length bending, binding with annealed wire not less than 1 mm in size and conforming to IS
280 at every intersection hooked and bent to correct shape and placed on forms etc.
including cost of black annealed wire and cost of loading, unloading, carriage of all steel
materials complete as per drawing and technical specifications and direction of Engineer-
in-charge.

carriage Cost of reinforcement


Distance from work site to durgap103 km

Carriage upto 5.0km per MT =Rs 82.00


from 5 km to 10 km @ Rs 7.30 / km =Rs 36.50
from 10 km to 20 km @ Rs 6.70 / km =Rs 67.00
from 20 km to 50 km @ Rs 6.3 / km =Rs 189.00
from 50 km to 100 km @ Rs 5.60 / km =Rs 280.00
from 100 km to 103 km @ Rs 5.30 / km =Rs 15.90
Loading & unloading per MT 0.75 @ 96.0/MT =Rs 72.00
Rs 742.40

A. Item rate = Rs 3369.00


B. Add issue price at outlet of steel
1.05 X 49900.00 / MT = Rs 52395.00

C. carriage+Loading+unloading 742.40 / MT = Rs 779.52

D. Overhead charges @ 5% of (B+C) = Rs 2658.73

E. Contractor Profit @ 10% of (B+C+D) = Rs 5583.32


Rs 64785.57 per MT

junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
292.25
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00
kmp of sainthia -sultanpur road (SH-11) by rigid & flexible pavement under
birbhum division, PWD in the district of birbhum during the year 2017-18

QUANTITY ANALYSIS ( DRAIN PORTION)


Length of the drain
1.00 kmp to 1.50 kmp = 2 x 500.00 = 1000.00 mtr
8.00 kmp to 8.50 kmp = 2 x 500.00 = 1000.00 mtr
= 2000.00 mtr

1 Earthwork in Excavation
2 x 1000.00 x 0.750 x 0.875 = 1312.50 M3

2 Sand filling
2 x 1000.00 x 0.750 x 0.075 = 113.00 M3

3 Polythene
2 x 1000.00 x 0.75 = 1500.00 M2

4 M20 conc. (P.C.C Grade)


2 x 1000.00 x 1.20 x 0.15 = 360.00 M3

5 M25 conc. (R.C.C Grade)


base:-
2 x 1000.00 x 1.20 x 0.150 = 360.00 M3

wall:-
2 x 1000.00 x 0.150 x 0.500 = 150.00 M3
2 x 1000.00 x 0.100 x 0.500 = 100.00 M3
510.00 M3
6 Reinforcement

1 % of total conc. Vol.


510.00 X 1.0% X 7.85 = 40.00 MT

junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
ABSTRACT OF COST

Proposed improvement of the existing carriageway from 1.00


kmp to 19.00 kmp of sainthia -sultanpur road (SH-11) by rigid
& flexible pavement under birbhum division, PWD in the
district of birbhum during the year 2017-18

1 Rigid Pavement portion ₹ 133,122,165.00


2 Flexible pavement portion ₹ 314,341,857.00
3 Earthen Shoulder ₹ 6,991,137.00
4 Road Furniture Portion ₹ 6,912,418.00

5 Cross drainage Work


i) Box culvert 2M x 2M ₹ 5,401,230.00
ii) Box Bridge 3M x 3M ₹ 12,769,154.00
iii) Box Bridge 6M x 6M ₹ 13,160,998.00
iv) Widening of Existing Slab Culvert ₹ 0.00
v) Repairing of culvert ₹ 1,845,007.00

6 Diversion work ₹ 11,430,867.00

7 Surface Drain Portion ₹ 8,632,937.00

8 Protective work ₹ 3,931,159.00


Grand Total (A) = ₹ 518,538,929.00

cont……2
(B) Grand Total = ₹ 518,538,929.00

(C) Add 3rd party


supervision/consultancy @2.5%
on Sl no.(B) = ₹ 12,963,473.00

(D) Add 3% Contengency on Sl no.(B)


= ₹ 15,556,168.00

(E) Add utility & Shifting = ₹ 0.00

Project Cost ₹ 547,058,570.00

Rupees Fifty Four Crores Seventy Lacs Fifty Eight Thousand Five hundred &
Seventy Only/-

This Estimate has been prepared after details site inspection.

Junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of sainthia -sultanpur
road (SH-11) by rigid & flexible pavement under birbhum division, PWD in the district of birbhum
during the year 2017-18
BILL OF QUANTITY
1 Item No.18.02 (b)(ii) Page No 321 of P.W. (Roads) Schedule of Rates 2015-16
Picking up and removing old bituminous layer or sand sealing coat from old black topped surface and
cleaning the exposed
b) By mechanical surface by scraping and stacking the material as directed.
means
(i) From 25 mm to 50 mm thick.
57300.00 m2 @ Rs 3.84 /m2 = Rs 219,917.00

(ii) From 50 mm to 100 mm thick.


91900.00 m2 @ Rs 7.58 /m2 = Rs 696,143.00

2 Item No.3.16 Page No 237 of P.W. (Roads) Schedule of Rates 2015-2016


Box cutting or filling in Road embankment in all sorts of soil including spreading
the spoils properly over the flank as necessary or on berm to approximate grade
& camber and rolling the sub-grade with power roller to proper camber and
grade as per direction and satisfaction of Engineer-in-charge including uprooting
and removing plants and jungles when and where necessary.

(A) upto depth 150 mm


91900.00 m2 @ Rs 14.54 /m2 = Rs 1,336,226.00

3 Item No.3.04(i) Page No 234 of P.W. (Roads) Schedule of Rates 2015-16


Earthwork in cutting to form road section in correct profile including removal of
spoils not exceeding initial lead of 50m and initial lift of 1.5m (Mode of
measurement: pre works and post works)
(i) In ordinary soil
45031.00 m3 @ Rs 57.57 /m3 = Rs 2,592,435.00

4 Item No. 4.08(A)Page No 243 of P.W. (Roads) Schedule of Rates 2015-2016


Construction of granular sub-base by providing graded material, mixing in Wet
Mix Plant at OMC, carriage of mixed material to work site, spreading in uniform
layers with Motor grader on prepared surface in proper grade and camber,
compacting with vibratory power roller to achieve the desired density, including
lighting, guarding, barricading, including cost of all materials, machinery, tools
and plants and cost of quality control complete as per Clause 401 of
Specifications for Road & Bridge Works of MoRT&H (5th Revision).

Grade II 22310.00 m3 @ Rs 1250.79 /m3 = Rs 27,905,125.00


Grade V 22947.00 m3 @ Rs 1531.54 /m3 = Rs 35,144,248.00
5 Item No. 4.12 Page No 246 of P.W. (Roads) Schedule of Rates 2015-2016
Wet Mix Macadam base course
Providing, laying, spreading and compacting graded stone aggregate to Wet Mix
Macadam specification including screening of aggregates and granular materials,
premixing the material with water at OMC in Wet Mix Plant, carriage of mixed
material by tipper to site, laying in uniform layers with Paver in Sub- base /Base
course on well prepared surface and compacting with Vibratory Roller to achieve
the desired density,including supply of all materials, machinery, fuel and
lubricants, including incidental costs for lighting,guarding, barricading, making
earthen bundh to protect the edges including cost of quality control complete as
per Clause 406 of Specifications for Road & Bridge Works of MoRT&H (5th
Revision).cum 338.00 362.00Note Add cost at site of 1.32 m³ of the stone
materials as per specified grading to arrive at the complete rate.

29279.00 m3 @ Rs 1600.69 /m3 = Rs 46,866,603.00


6 Item No.5.02 Page No 248 of P.W. (Roads) Schedule of Rates 2015-16
Providing and applying tack coat with Cationic Bitumen Emulsion of approved
grade conforming to IS: 8887-1978 on the prepared surface cleaned with
Hydraulic broom, moistening the surface including cost and carriage of emulsion,
hire charges of machinery and labour, cost of fuel and lubricants all complete as
per Clause 503 of Specifications for Road & Bridge Works of MoRT&H (5th
Revision).Providing & applying tack coat using Cationic bituminous emulsion of
approved grade conforming to IS: 8887-1978, over prepared surface includig
cleaning of surface with mechanical broom, moistening the surface, applying tack
coat including cost and carriage of emulsion, hire charges of machinaries and
labour cost of fuel and lubricants all complete as per specification and direction
of Engineer-in-charge.

(i) On Bituminous Surface (Using Bitumen Emulsion at the rate of 0.20 to


0.30 kg per sqm.)

152184.00 m2 @ Rs 9.12 /m2 = Rs 1,387,918.00


(ii) On Granular surfaces treated with primer (Using Bitumen emulsion at
the rate of 0.25 to 0.30 kg per sqm.)

152184.00 m2 @ Rs 9.90 /m2 = Rs 1,506,622.00

7 Item No.5.01 Page No 248 of P.W. (Roads) Schedule of Rates 2015-16


Providing and applying primer coat with Cationic Bitumen Emulsion of approved
grade conforming to IS: 8887-1978 and requisite quantity on prepared surface of
granular base including cleaning of road surface and spraying primer using
Mechanical means including cost and carriage of bitumen emulsion and all other
incidental costs of work complete as per Clause 502 of Specifications for Road &
Bridge Works of MoRT&H (5th Revision).

(i) For WBM / WMM Surface: (with primer @ 0.70-1.0 kg/sqm)

152184.00 m2 @ Rs 28.04 /m2 = Rs 4,267,239.00


8 Item No.5.05 Page No 250 of P.W. (Roads) Schedule of Rates 2015-16
Dense Bituminous Macadam
Providing and laying dense bituminous macadam with Hot Mix Plant producing
an average output of 75 tonnes per hour using coarse aggregate, fine aggregate,
filler and bituminous binder as per design Job Mix Formula conforming Marshall
Method as per specification,including screening, cleaning of chips and preparing
a uniform and quality mix in Hot Mix Plant and ensuring a homogeneous mix, in
which all particles of the mineral aggregates are coated uniformly, transporting
the hot mix to work site, laying the mixed materials at specified laying
temperature with a hydrostatic paver finisher with sensor control to the
required grade, level and alignment over prepared surface coated with tack coat,
rolling with smooth wheeled, vibratory and tandem rollers for break down, inter-
mediate and finished rolling to achieve the desired density of at least 98% of that
of Laboratory Marshall specimen, hand packing and pinning to give an even
surface including cost and carriage of bitumen, coarse and fine aggregates and
filler materials and hire charges of machinery and equipment for construction
and quality control, fuels and lubricants and wages of operational staff complete
as per Clause 505 of Specifications for Road & Bridge Works of MoRT&H (5th
Revision).

A. For Grading 1
(40 mm nominal size, 80-100 mm thick.)
(i) Using Batch Type HMP of minimum capacity
100-120 TPH.

13901.00 m3 @ Rs 6567.25 /m3 = Rs 91,291,342.00


B. For Grading 2
(i) Using
(26.5 mmBatch Type
nominal HMP
size, of minimum
50-75 capacity
mm thick.)
100-120 TPH.

7609.00 m3 @ Rs 6942.70 /m3 = Rs 52,827,004.00


9 Item No.5.14 (b) (ii) Page No 256 of P.W. (Roads) Schedule of Rates 2015-16
Mastic Ashphalt
Providing and laying Mastic asphalt wearing course with paving grade bitumen
meeting the requirements given in table 500-29 using approved coarse
aggregate, fine aggregate, filler material and bitumen, prepared by using Mastic
cooker including cost and carriage of all ingredients, cost of heating aggregates
and binder, mixing in specified proportions conforming to approved Job Mix
Formula and laid to required level and slope after cleaning the surface,
compacting, sealing the construction joints and surface finishing conforming to
specifications including providing antiskid surface with bitumen pre-coated fine-
grained hard stone chipping of 13.2 mm nominal size at the rate of 0.005 cum per
10 sqm and at an approximate spacing of 10 cm center to center in both
directions, pressed into surface when the temperature of surfaces not less than
100°C, protruding 1 mm to 4 mm over mastic surface, including the hire charges
of all tools and plants and machinery, pay of operators, cost of fuel and lubricants
and all other incidental charges and quality control all complete as per Clause
516 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).

25 mm thick
5100.00 m2 @ Rs 468.14 /m2 = Rs 2,387,514.00

10 Item No.5.08 Page No 252 of P.W. (Roads) Schedule of Rates 2015-2016


Bituminous Concrete
Providing and laying bituminous concrete with Hot Mix Plant using coarse
aggregates, fine aggregates, filler materials and bituminous binder of required
specification including screening, cleaning of chips and preparing a uniform and
quality mix in Hot Mix Plant and ensuring a homogeneous mix, in which all
particles of the mineral aggregates are coated uniformly, transporting the hot
mix to work site, laying the mixed materials at specified laying temperature with
a hydrostatic paver finisher with sensor control to the required grade, level and
alignment over prepared surface coated with tack coat, rolling with smooth
wheeled, vibratory and tandem rollers for break down, inter-mediate and
finished rolling to achieve the desired density of at least 98% of that of
Laboratory Marshall specimen, including cost and carriage of bitumen, coarse
and fine aggregates and filler materials and hire charges of machinery and
equipment for construction and quality control, fuels and lubricants and wages of
operational staff complete as per Clause 507 of Specifications for Road & Bridge
Works of MoRT&H (5th Revision).

B. For Grading 2
(13.2 mm nominal size, 30-40 mm thick.)
i) Using Batch Type HMP of minimum capacity
100-120 TPH.
5883.00 m3 @ Rs 7804.44 /m3 = Rs 45,913,521.00
Rs 314,341,857.00
junior Engineer Assistant Engineer
Section II, PWD Suri Sub-Division PWD
148732570

49127089.00
65289471
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of
sainthia -sultanpur road (SH-11) by rigid & flexible pavement under birbhum division,
PWD in the district of birbhum during the year 2017-18
calculation sheet

Length calculation for Resectioning Portion


from
3.490 kmp to 3.990 kmp = 500.00 mtr 3.490 kmp

6.800 kmp to 7.610 kmp = 810.00 mtr 6.800 kmp t


8.970 kmp to 9.670 kmp = 700.00 mtr 8.970 kmp t
10.107 kmp to 13.640 kmp = 3470.00 mtr 10.107 kmp t
14.160 kmp to 14.770 kmp = 610.00 mtr 14.160 kmp t
15.080 kmp to 16.310 kmp = 1230.00 mtr 15.080 kmp t
17.130 kmp to 19.000 kmp = 1870.00 mtr 17.130 kmp t
9190.00 mtr (MKD- B)

Length calculation for scarifying of bituminous layer only Length


from
1.500 kmp to 2.580 kmp = 1080.00 mtr

2.890 kmp to 3.490 kmp = 600.00 mtr

3.990 kmp to 4.530 kmp = 540.00 mtr

7.610 kmp to 8.970 kmp = 1360.00 mtr

9.610 kmp to 10.170 kmp = 500.00 mtr

16.640 kmp to 14.160 kmp = 520.00 mtr

14.770 kmp to 15.080 kmp = 310.00 mtr

16.310 kmp to 17.130 kmp = 820.00 mtr

5730.00 mtr ….MKD (C)


1 Picking up and removing old
bituminous layer .

b) By mechanical means
(i) From 25 mm to 50 mm thick.
Scarifying por. Only:- 1 x 5730.00 x 10.00 = 57300.00 M2
Length
MKD ©
(ii) From 50 mm to 100 mm thick.
Resectioning por. :- 1 x 9190.00 x 10.00 = 91900.00 M2
Length
91900.00 M2
MKD (B)
2 Box cutting
Resectioning por. :-
1 x 9190.00 x 10.00 = 91900.00 M2
Say 91900.00 M2
3 Earthwork in cutting
1 x 9190.00 x 10.00 X 0.490 = 45031.00 M3

Say 45031.00 M3

4 Granular sub-base:-
Grade-II
1 x 9190.00 x 14.00 x 0.170 = 21872.20 M3

21872.20 M3

2% for bell mouth/ curve = 437.44 M3

22309.64 M3

Say 22310.00 M3

Grade-V
1 x 9190.00 x 13.60 x 0.180 = 22497.12 M3

22497.12 M3

2% for bell mouth/ curve = 449.94 M3

22947.06 M3

Say 22947.00 M3
4 WMM:-
1 x 9190.00 x 10.00 x 0.250 = 22975.00 M3

1 x 5730.00 x 10.00 x 0.100 = 5730.00 M3

28705.00 M3

2% for bell mouth/ curve = 574.10 M3

29279.10 M3
Say 29279.00 M3
5 Primer
1 x 14920.00 x 10.00 = 149200.00 M2
149200.00 M2
2% for bell mouth/ curve = 2984.00 M3

152184.00 M3

Say 152184.00 M3

6 Tack coat on granular surface


1 x 14920.00 x 10.00 = 149200.00 M2
149200.00 M2
2% for bell mouth/ curve = 2984.00 M2
152184.00 M2
Say 152184.00 M2
on bituminous surface
1 x 14920.00 x 10.00 = 149200.00 M2
1 x 500.00 x 10.00 = 5000.00 M2
149200.00 M2
2% for bell mouth/ curve = 2984.00 M2
152184.00 M2
Say 152184.00 M2
7 DBM
Grading - I
1 x 14920.00 x 10.00 x 0.090 = 13428.00 M3

1 x 500.00 x 10.00 x 0.040 = 200.00 M3

13628.00 M3

2% for bell mouth/ curve = 272.56 M3

13900.56 M3

Say 13901.00 M3
Grading - II

1 x 14920.00 x 10.00 x 0.050 = 7460.00 M3

7460.00 M3

2% for bell mouth/ curve = 149.20 M3

7609.20 M3

Say 7609.00 M3
8 BC
1 x 14420.00 x 10.00 x 0.040 = 5768.00 M3

5768.00 M3

2% for bell mouth/ curve = 115.36 M3

5883.36 M3

Say 5883.00 M3

9 Mastic
1 x 500.00 x 10.00 = 5000.00 M2
5000.00 M2
2% for bell mouth/ curve = 100.00 M3

5100.00 M3

Say 5100.00 M3

Junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
New chainage

Length calculation for Resectioning Portion


from
3.490 kmp to 3.990 kmp = 500.00 mtr

6.800 kmp to 7.610 kmp = 810.00 mtr

8.970 kmp to 9.670 kmp = 700.00 mtr

10.107 kmp to 13.640 kmp = 3470.00 mtr

14.160 kmp to 14.770 kmp = 610.00 mtr

15.080 kmp to 16.310 kmp = 1230.00 mtr


17.130 kmp to 19.000 kmp = 1870.00 mtr
9190.00 mtr

Length calculation for scarifying of bituminous layer only


from
1.500 kmp to 2.580 kmp = 1080.00 mtr

2.890 kmp to 3.490 kmp = 600.00 mtr

3.990 kmp to 4.530 kmp = 540.00 mtr

7.610 kmp to 8.970 kmp = 1360.00 mtr

9.610 kmp to 10.170 kmp = 500.00 mtr

16.640 kmp to 14.160 kmp = 520.00 mtr

14.770 kmp to 15.080 kmp = 310.00 mtr

16.310 kmp to 17.130 kmp = 820.00 mtr

5730.00
250

350
100
40
740

18820

32420.00

18000.00
18000.00
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of sainthia
-sultanpur road (SH-11) by rigid & flexible pavement under birbhum division, PWD in the
district of birbhum during the year 2017-18
( ROAD FURNITURE)
1 Item No. 8.17 Page No 267of P.W. (Roads) Schedule of Rates 2015-16
Supply, fitting and fixing R.C. guard post 1.37m. long with c.c 1:2:4 with graded
stone chips of 13.2 mm down casting, curing complete including cost of
providing 4 Nos. of 12mm dia rods of length 1.54m as main reinforcement and 6
nos. of round-shaped 8mm dia rods used as binders; the placing of the 1st binder
should be at 75mm below the top finished surface and the other 5 nos. of binders
should be placed at 245 mm c/c; the guard post is of octagonal section with
inscribed circle of dia 24 cm at the base tapering to corresponding dimen­sions of
16cm. at the top including two coats of painting with best quality synthetic
enamel paint of approved make and brand to form 6 Nos. horizontal alternate
bands in white/tanery yellow and black to 90cm. length standing up above
ground after mending good damages if any during striking or shuttering, making
hole in ground of 47cm. depth and 30cm. minimum dia, fixing the guard post in
the same hole and repacking the earth thoroughly. so as to keep the guard post
standing properly erect in correct position true to line and length including
carriage of R.C. guard post with due care to the site including loading into the
truck and unloading at site complete in all respect.

600.00 NO @ Rs. 872.64 /each = Rs. 523584.00

2 Item No. 8.04 Page No 264 of P.W. (Roads) Schedule of Rates 2004-15
Providing and fixing of retro- reflectorised cautionary, mandatory and
informatory sign as per IRC :67 made of high intensity grade sheeting vide clause
801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of
properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x
60 cm, 60 cm below ground level as perapproved drawing and Clause 801 of
Specifications for Road & Bridge Works of MoRT&H (5th Revision).

i) 90 cm equilateral triangle
0.00 NO @ Rs. 4782.35 /each = Rs. 0.00
iii) 60 cm circular
0.00 NO @ Rs. 4191.50 /each = Rs. 0.00

iv) 80 mm x 60 mm rectangular
0.00 NOS @ Rs. 5930.72 /each = Rs. 0.00

v) 60 cm x 45 cm rectangular
0.00 NOS @ Rs. 4076.36 /each = Rs. 0.00
2 Item No.8.09 Page No 266 of P.W. (Roads) Schedule of Rates 2015-16
Road Marking with Hot Applied Thermoplastic Compound with
Reflectorising Glass Beads on Bituminous Surface
Providing and laying of hot applied thermoplastic compound 2.5 mm thick
including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5
mm is exclusive of surface applied glass beads as per IRC:35. The finished
surface to be level, uniform and free from streaks and holes complete as per
Clause 803 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).

Total road length = 18 km


Two 2 X 18000 x 0.15 = 5400.00 m2
sides
C/L 2571 X 4.00 x 0.10 = 1028.40 m2
6428.40 m2
6428.40 mtr @ Rs. 589.84 /mtr = Rs. 3791727.00

3 Item No.8.15 Page No 267 of P.W. (Roads) Schedule of Rates 2015-16


Road Markers/Road Stud with Lense Reflector
Providing and fixing of road stud 100 x 100 mm, diecast in aluminium, resistant
to corrosive effect of salt and grit, fitted with lens reflectors, installed in concrete
or asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in
a suitable bituminous grout or epoxy mortar, all as per BIS 873 part 4:1973

9947.00 nos @ Rs. 257.55 /nos = Rs. 2561850.00

4 Item No.8.10 Page No 266 of P.W. (Roads) Schedule of Rates 2015-16


Kilometre Stone
Reinforced cement concrete M15 grade kilometre stone of standard design as
per IRC:8-1980, fixing in position including painting and printing etc.

(i) 5th kilometre stone (precast)


3.00 nos @ Rs. 2960.31 /nos = Rs. 8881.00

(ii) Ordinary kilometer stone (precast)


15.00 nos @ Rs. 1758.41 /nos = Rs. 26376.00
Rs. 6912418.00

junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
junior Engineer Assistant Engineer
SainthiaSection, PWD Suri Sub-Division PWD
2571.4286
5000
10400

36000

14920
4973.3333
(Rate Analysis)
( Road Furniture)
1 Item No.8.17 Page No 267 of P.W. (Roads) Schedule of Rates 2015-16
Supply, fitting and fixing R.C. guard post 1.37m. long with c.c 1:2:4 with graded
stone chips of 13.2 mm down casting, curing complete including cost of providing
4 Nos. of 12mm dia rods of length 1.54m as main reinforcement and 6 nos. of
round-shaped 8mm dia rods used as binders; the placing of the 1st binder should
be at 75mm below the top finished surface and the other 5 nos. of binders should
be placed at 245 mm c/c; the guard post is of octagonal section with inscribed
circle of dia 24 cm at the base tapering to corresponding dimen­sions of 16cm. at
the top including two coats of painting with best quality synthetic enamel paint of
approved make and brand to form 6 Nos. horizontal alternate bands in
white/tanery yellow and black to 90cm. length standing up above ground after
mending good damages if any during striking or shuttering, making hole in
ground of 47cm. depth and 30cm. minimum dia, fixing the guard post in the same
hole and repacking the earth thoroughly. so as to keep the guard post standing
properly erect in correct position true to line and length including carriage of R.C.
guard post with due care to the site including loading into the truck and
unloading at site complete in all respect.

= Rs. 864.00
Add 1% cess = Rs. 8.64
Rate per No. = Rs. 872.64
2 Item No.8.04 Page No 264 of P.W. (Roads) Schedule of Rates 2015-16
Retro-Reflectorised Traffic Signs
Providing and fixing of retro- reflectorised cautionary, mandatory and
informatory sign as per IRC :67 made of high intensity grade sheeting vide clause
801.3, fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of
properly designed foundation with M15 grade cement concrete 45 cm x 45 cm x
60 cm, 60 cm below ground level as per approved drawing and Clause 801 of
Specifications for Road & Bridge Works of MoRT&H (5th Revision).

i) 90 cm equilateral triangle
= Rs. 4735.00
Add 1% cess = Rs. 47.35
Rate per No. = Rs. 4782.35

iv) 80 mm x 60 mm rectangular
= Rs. 5872.00
Add 1% cess = Rs. 58.72
Rate per No. = Rs. 5930.72
v) 60 cm x 45 cm rectangular
= Rs. 4036.00
Add 1% cess = Rs. 40.36
Rate per No. = Rs. 4076.36

iii) 60 cm circular
= Rs. 4150.00
Add 1% cess = Rs. 41.50
Rate per No. = Rs. 4191.50

3 Item No.8.09 Page No 266 of P.W. (Roads) Schedule of Rates 2015-16


Road Marking with Hot Applied Thermoplastic Compound with
Reflectorising Glass Beads on Bituminous Surface
Providing and laying of hot applied thermoplastic compound 2.5 mm thick
including reflectorising glass beads @ 250 gms per sqm area, thickness of 2.5 mm
is exclusive of surface applied glass beads as per IRC:35. The finished surface to
be level, uniform and free from streaks and holes complete as per Clause 803 of
Specifications for Road & Bridge Works of MoRT&H (5th Revision).

Labour cost per Sqm = Rs. 584.00


Add 1% cess = Rs. 5.84
Rate per Sqm = Rs. 589.84
4 Item No.8.10 Page No 266 of P.W. (Roads) Schedule of Rates 2015-16
Kilometre Stone
Reinforced cement concrete M15 grade kilometre stone of standard design as per
IRC:8-1980, fixing in position including painting and printing etc.

(i) 5th kilometre stone (precast)


= Rs. 2931.00
Add 1% cess = Rs. 29.31
Rate per Each = Rs. 2960.31
(ii) Ordinary kilometer stone (precast)
= Rs. 1741.00
Add 1% cess = Rs. 17.41
Rate per Each = Rs. 1758.41

5 Item No.8.15 Page No 267 of P.W. (Roads) Schedule of Rates 2015-16


Road Markers/Road Stud with Lense Reflector
Providing and fixing of road stud 100x 100 mm, diecast in aluminium, resistant to
corrosive effect of salt and grit, fitted with lens reflectors, installed in concrete or
asphaltic surface by drilling hole 30 mm upto a depth of 60 mm and bedded in a
suitable bituminous grout or epoxy mortar, all as per BIS 873 part 4:1973

= Rs. 255.00
Add 1% cess = Rs. 2.55
Rate per Each = Rs. 257.55
6 Item No.8.18 Page No 268 of P.W. (Roads) Schedule of Rates 2015-16
Painting (one coat) guard posts with 6nos. of 16cm wide horizontal alternate
band in different colours after the scrapping the surface free from old paint etc. as
directed with best quality synthetic enamel paint of approved make and brand
after fixing old existing guard post in correct position true to line and level with
repacking the ground at base properly and mending good damages if necessary
complete in all respect.

= Rs. 120.00
Add 1% cess = Rs. 1.20
Rate per Each = Rs. 121.20

7 Item No.8.19 Page No 268 of P.W. (Roads) Schedule of Rates 2015-16


Painting (one coat) K.M. post with best quality synthetic enamel paint of approved
make and brand of different shades as directed after cleaning and washing the
surface including mending good damages as necessary complete in all respect.

a) 5th K.M. Post


= Rs. 104.00
Add 1% cess = Rs. 1.04
Rate per Each = Rs. 105.04

b) Ordinary K.M. Post


= Rs. 67.00
Add 1% cess = Rs. 0.67
Rate per Each = Rs. 67.67

8 Item No.8.19 Page No 268 of P.W. (Roads) Schedule of Rates 2015-16


Painting the vertical end faces of posts, wheel guards or railing or parapet with
alternate bands of different colours as directed by the Engineer-in-charge with
approved synthetic enamel paint.

b) Two Coats
= Rs. 99.00
Add 1% cess = Rs. 0.99
Rate per Each = Rs. 99.99

junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
Circuit House to Tilpara NH-60 connecting
COST ESTIMATE AND ABSTRACT FOR CONSTRUCTION OF BOX CULVERT
SL Description of Items Nos Measurements
Unit Quantity
NO L(m) B(m) D(m)
1 2 3 4 5 6 7 8
SPAN -2.0 x 2.0 M No 1
Estimate for 1No
Item No. 12.01 Page No 276 of P.W. (Roads) Schedule of Rates 2014-2015
1 Dismantling of existing structures like culverts, bridges,retaining walls and other structures comprising of brick
masonry, including disposal of unserviceable material and stacking the serviceable material with all lift and
lead of 1000 m as per Technical Specifications Clause 202 for Rural Roads of MORD.
Dismantling of Brick
existing Abutment Wall 1 x 12.000 x 0.375 x 1.500 CUM 6.750
Return wall 4 x 2.500 x 0.250 x 1.000 CUM 2.500
Total = 9.250
2 Dismantling of existing structures like culverts, bridges,retaining walls and other structure comprising of
masonry, cement concrete, steel work, including T&P and scaffolding wherever necessary, sorting the
dismantled material, disposal of unserviceable material and stacking the serviceable material with all lifts and
lead of 1000of
Dismantling mRCC
as per Technical Specifications Clause 202 for Rural Roads of MORD.
existing Deck slab 1 x 12.000 x 2.000 x 0.200 CUM 4.800
Total = 4.800

3 Earthwork in excavation for foundation of structures as per drawing and technical specification including
setting out,removing,spreading or stacking spoils with a lead of 150m as directed and including trimming the
sides of trenches, leveling, dressing and ramming the bottom, complete, as per direction of the Engineer - in -
charge.In all sorts of soil excluding marshy soil and rocks ( soft or rock ) by mannual meansDepth upto 3
metre without pumping water and shoring
Abutment Wall 1 x 12.000 x 3.500 x 2.550 cum. 107.100
Return Wall 4 x 2.500 x 0.750 x 0.350 cum. 2.625
Total = 109.725
4 Item No. 12.04 Page No 278 of P.W. (Roads) Schedule of Rates 2014-2015
Sand filling in foundation trenches and at the back of abutments, wingwalls etc. with good local sand free from
earth in layers not exceeding 15 cm. including inundating each layer by profuse water and poking and
ramming layer by layer complete including supply of sand. Quality of sand is to be approved by the Engi­neer-
in-charge.
Sand filling ( Fine sand)
Abutment Wall 1 x 12.000 x 2.900 x 0.100 CUM 3.480
Return wall 2 x 2.500 x 3.500 x 0.100 CUM 1.750
Back Filling 2 x 12.000 x 0.200 x 2.350 CUM 11.280
Total = 16.510
5 Item No. 13 Page No 45 of P.W. (Building) Schedule of Rates 2014-2015
Supplying and laying Polythene Sheet (150 gm/sq.m) over damp proof coarse or below flooring or roof
terranching or in foundation or in foundation trenches.
Abutment Wall 1 x 12.000 x 2.700 Sqm 32.400
Return wall 1 x 3.000 x 2.700 Sqm 8.100
Total= Sqm 40.500
6 Item No. 12.05 Page No 278 of P.W. (Roads) Schedule of Rates 2014-2015
Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any part of
foundation of bridges / culverts with graded stone chips of appropriate nominal sizes, including screening and
cleaning of coarse aggregates, fine aggregate (sand) conforming to proper grading zone,both of approved
quality and cement, as necessary,cost of curing with water, including cost and carriage of all materials and
including preparation of design mix, approval of the same by the Engineer-in-Charge, cost for quality control,
sampling, testing etc. including cost of formwork but excluding reinforcement complete as per drawing and
technical specifications.
6.1 PCC grade M20 conc.
Abutment Wall 1 X 12.000 X 2.700 X 0.100 cum. 3.24

Return wall 2 X 3.000 X 2.700 X 0.100 cum. 1.62


Total= cum. 4.860
6.2 RCC grade M25 conc.
Floor,Wall,Deck slab 4 x 12.000 x 2.250 x 0.250 cum 27.000
Hunch 4 x 12.000 x 0.075 x 0.150 cum 0.540
Return wall, Base 2 x 2.500 x 2.500 x 0.250 cum 3.125
Return wall, U shaped avg. walls 4 x 3.000 x 0.250 x 1.875 cum 5.625
U/S Lugs 1 x 2.500 x 0.200 x 1.000 cum 0.500
D/S Lugs 1 x 2.500 x 0.200 x 1.500 cum 0.750
Parapet wall 2 x 2.500 x 0.250 x 0.900 cum 1.125
Total= cum. 38.665

7 Item No. 14.03 Page No 298 of P.W. (Roads) Schedule of Rates 2014-2015
Supplying bending and binding and laying in position steel reinforcement of different dimensions in cement
concrete work i.e. R.C.C., P.S.C. etc.of different components in foundation and in superstructure including
initial straightening, straightening of coils bars, removal of loose rust (if any), cutting to requisite length
bending, binding with annealed wire not less than 1 mm in size and conforming to IS 280 at every intersection
hooked and bent to correct shape and placed on forms etc. including cost of black annealed wire and cost of
loading, unloading, carriage of all steel materials complete as per drawing and direction of Engineer-in-
charge.(a) For M.S. Rounds/Tor Steel/H.Y.S.D. Bars

@ 1.00% OF Sl.No. 5 ton 3.035


8 Item No. 13.03 Page No 292 of P.W. (Roads) Schedule of Rates 2014-2015
Providing weep holes in brick masonry abutment , return wall with 100 mm dia AC pipe extending through
the full width of the structure with slope of 1(V) : 20(H) towards drawing face complete as per drawing and
technical specification clause 614,709, 1204.3.7of specification of Rural Roads including curing complete.
Abutment wall 2 x 2 x 6.000 Nos 24
Return wall 4 2 2.000 Nos 16
Nos 40
9 Item No. 13Page No 162 of P.W. D Schedule of Rates 2014-2015
Priming one coat to timber or plastered surface with ready mixed primer of approved quality including
scrapping and smoothening surface
Primingin one coats
Parapet, Side wall 4 x 2.500 x 0.900 Sqm 9.000
4 x 0.250 x 0.900 Sqm 0.900
Top 2 x 2.500 x 0.250 Sqm 1.250
Total= Sqm 11.150
10 Item No. 8.21 Page No 266 of P.W. (Roads) Schedule of Rates 2014-2015
Painting the vertical end faces of posts, wheel guards or railing or parapet with alternate bands of different
colours as directed by the Engineer-in-charge with approved synthetic enamel paint.
Painting in two coats
same as priming area Total= Sqm 11.150

Junior Engineer,PWD Assistant Engineer,PWD


Section-II Suri Sub Division
Suri Sub Division
Preparation of DPR for road under Suri SubDivision in West Bengal

COST ESTIMATE FOR CROSS DRAINAGE WORKS: 2.0 m x 2.0 m BOX CULVERT
District Birbhum
Road Sainthia-Sultanpur No of CD= 10 (2.0 x 2.0 m Box )

Sl No. Brief Description of Item Unit Quantity Rate (Rs) Amount (Rs)

1 Dismantling of existing structures like culverts,


bridges,retaining walls and other structures
comprising of brick masonry, including disposal of
unserviceable material and stacking the serviceable
material with all lift and lead of 1000 m as per
Technical Specifications Clause 202 for Rural Roads of
MORD.

cum 6.219 282.80 1758.66


2 Dismantling of existing structures like culverts,
bridges,retaining walls and other structure
comprising of masonry, cement concrete, steel work,
including T&P and scaffolding wherever necessary,
sorting the dismantled material, disposal of
unserviceable material and stacking the serviceable
material with all lifts and lead of 1000 m as per
Technical Specifications Clause 202 for Rural Roads of
MORD.

cum 2.250 780.73 1756.64


3 Earthwork in excavation for foundation of structures cum
as per drawing and technical
specificationincludingsettingout,removing,spreading
or stacking spoils with a lead of 150m as directed and
including trimming the sides of trenches, leveling,
dressing and ramming the bottom, complete, as per
direction of the Engineer - in - charge.In all sorts of
soil excluding marshy soil and rocks ( soft or rock ) by
mannual meansDepth upto 3 metre without pumping
water and shoring .

118.65 125.24 14859.73


4 Sand filling in foundation trenches and at the back of
abutments, wingwalls etc. with good local sand free
from earth in layers not exceeding 15 cm. including
inundating each layer by profuse water and poking
and ramming layer by layer complete including
supply of sand. Quality of sand is to be approved by
the Engi­neer-in-charge.

cum 17.74 620.30 11004.12


5 Supplying and laying Polythene Sheet (150 gm/sq.m)
over damp proof coarse or below flooring or roof
terranching or in foundation or in foundation
trenches.
sqm 43.20 25.00 1080.00
6 Plain / Reinforced Cement Concrete in Open
foundation with or without reinforcements, in any
part of foundation of bridges / culverts with graded
stone chips of appropriate nominal sizes, including
screening and cleaning of coarse aggregates, fine
aggregate (sand) conforming to proper grading
zone,both of approved quality and cement, as
necessary,cost of curing with water, including cost
and carriage of all materials and including preparation
of design mix, approval of the same by the Engineer-
in-Charge, cost for quality control, sampling, testing
etc. including cost of formwork but excluding
reinforcement complete as per drawing and technical
specifications.
6.1 PCC Grade M-20 cum 5.130 6,148.84 31,543.57
6.2 RCC Grade M25
I) Using concrete mixer cum 40.960 6,429.91 263,369.00
7 Supplying bending and binding and laying in position
steel reinforcement of different dimensions in cement
concrete work i.e. R.C.C., P.S.C. etc.of different
components in foundation and in superstructure
including initial straightening, straightening of coils
bars, removal of loose rust (if any), cutting to requisite
length bending, binding with annealed wire not less
than 1 mm in size and conforming to IS 280 at every
intersection hooked and bent to correct shape and
placed on forms etc. including cost of black annealed
wire and cost of loading, unloading, carriage of all
steel materials complete as per drawing and direction
of Engineer-in-charge.(a) For M.S. Rounds/Tor
Steel/H.Y.S.D. Bars

MT 3.215 64,717.32 208,089.00


8 Providing Weep Holes in Brick masonry/ Stone
masonry, Plain/ Reinforced concrete abument, wing
wall, return wall with 100mm dia AC pipe extending
through the full width of the structures with slope of
1(V): 20 (H) towards drawing face complete as per
drawing
nos. 40 127.26 5,090.40
9 Priming one coat to timber or plastered surface with
ready mixed primer of approved quality including
scrapping and smoothening surface
Sqm 11.150 41.00 457.15
10 Painting the vertical end faces of posts, wheel guards
or railing or parapet with alternate bands of different
colours as directed by the Engineer-in-charge with
approved synthetic enamel paint.
Sqm
11.150 99.99 1,114.89
Total (Rs.) for 1No 540,123.00
TOTAL COST OF 10 NOS CULVERTS (Rs.) 5,401,230.00

Junior Engineer,PWD Assistant Engineer,PWD 7867132.4


Section-II Suri Sub Division
Suri Sub Division
468410607.00 28.574

1,700,982.00

13.9

470111589.00 20.85

7.724
139032
-4620
-9240
-14870
-250
-21900
-6160
81992
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of
sainthia -sultanpur road (SH-11) by rigid & flexible pavement under birbhum
division, PWD in the district of birbhum during the year 2017-18
BILL OF QUANTITY (Earthen Shoulder)
1 Item No.3.14 Page No 236 of P.W. (Roads) Schedule of Rates 2015-2016
Construction of Subgrade and Earthen Shoulders Construction of
subgrade and earthen shoulders with approved material obtained
from borrow pits with all lifts and leads, transporting to site,
spreading, grading to required slope and compacted to meet
requirement of Table 300.2 with lead upto 1000 m as per Technical
Specification Clause 303.1 for Rural Roads of MORD. (Borrow pit
/pre work post work measurement)

44962.40 m3 @ Rs 95.75 /m3 = Rs 4,305,150.00

2 Item No.3.15 Page No 236 of P.W. (Roads) Schedule of Rates 2015-2016


Extra for carriage of all kinds of earth by Mechanical Transport:
b) Carriage up to total lead of 2.0 km.
19269.60 m3 @ Rs 107.97 /m3 = Rs 2,080,539.00

3 Item No.3.17 Page No 237 of P.W. (Roads) Schedule of Rates


2015-2016
A. Compacting original ground supporting subgrade Loosening of
the ground upto a level of 300 mm below the subgrade level,
watered, graded and compacted in layers to meet requirement of
Tables 300.1 and 300.2 for subgrade construction as per Clause
305.3.4 of Specifications for Road & Bridge Works of MoRT&H (5th
Revision).

(i) In ordinary soil


10800.00 m3 @ Rs 56.06 /m3 = Rs 605,448.00
6,991,137.00

junior
SectionEngineer
II, Assistant Engineer
PWD Suri Sub-Division PWD
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of
sainthia -sultanpur road (SH-11) by rigid & flexible pavement under birbhum division
PWD in the district of birbhum during the year 2017-18
QUANTITY ANALYSIS
1 Item No.3.14 Page No 236 of P.W. (Roads) Schedule of Rates 2015-2016
Construction of Subgrade and Earthen Shoulders Construction of subgrade and earthe
shoulders with approved material obtained from borrow pits with all lifts and lead
transporting to site, spreading, grading to required slope and compacted to me
requirement of Table 300.2 with lead upto 1000 m as per Technical Specification Claus
303.1 for Rural Roads of MORD. (Borrow pit /pre work post work measurement)

proposed sec.
(12.00+20.00)
X 2.00 (AV.) =
2
ded. For existing sec.
(11.50+17.50)
X 1.70 (AV.) =
2

Total vol. in 18 km =
18000 x 7.35 =
ded. For WMM =
ded. For DBM =
ded. For DLC =
ded. For PQC =

2 Item No.3.15 Page No 236 of P.W. (Roads) Schedule of Rates 2015-2016


Extra for carriage of all kinds of earth by Mechanical Transport:
b) Carriage up to total lead of 2.0 km.

30 % of Total quantity =
3 Item No.3.17 Page No 237 of P.W. (Roads) Schedule of Rates 2015-2016
A. Compacting original ground supporting subgrade Loosening of the ground upto
level of 300 mm below the subgrade level, watered, graded and compacted in layers
meet requirement of Tables 300.1 and 300.2 for subgrade construction as per Claus
305.3.4 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).

Side Shoulder
2 x 18000.00 x 1.00 x 0.300 =
Say

junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
.00 kmp to 19.00 kmp of
nt under birbhum division,
ar 2017-18

tes 2015-2016
on of subgrade and earthen
its with all lifts and leads,
e and compacted to meet
chnical Specification Clause 16
work measurement)

32.00 M2
16.5
14.5

-24.65 M2

7.35 M2

0.2966667
132300.00 M3
-32421.00 M3
-21510.00 M3
-4712.00 M3
-9425.00 M3
64232.00 M3

tes 2015-2016
rt:

19269.60 M3
tes 2015-2016
ning of the ground upto a
and compacted in layers to
construction as per Clause
H (5th Revision).

10800.00 M3
10800.00 M3
Bill of Quantity :
Protective Works

PART E : PROTECTIVE WORK

Item Rate Amount


Ref. to SOR Description of Item Unit Quantity
No. (Rs.) (Rs.)
C-1 Ref .Item # Weaving wire mattress as directed with wire of 4mm dia.
18.30, page-326 and making sausage crate of required shape after tying
of S.O.R of P.W all intersections including joining longitudinal ends, closing
(Roads), 2015- ends of sausage, carriage of wire to site of work complete in
2016 all respect as per direction of the Engineer-in-charge Sqm. 7488.00 240.38 1799965.44
including cost of supply of G.I. wire. (With 100mm x 100mm
mesh.)

C-2 Ref .Item # Filling properly the empty sausage crates with boulders
18.31, page-326 of any size & shape with hand packing after preparation of
of S.O.R of P.W bed of placement, placing the crate in position, carriage of
(Roads), 2015- boulders from road stacks with a lead upto 150m etc.
2016 complete in all respect including stitching the rest of the
crate with wire (passage for filling boulders) after filling up
the crate with boulders and launching the crate in cum 1404.00 1309.47 1838495.88
position if necessary and as directed by the Engineer-in
charge.

C-3 Ref .Item # Earthwork in excavation for foundation of structures upto 3


11.01, Page- m depth as per drawing and technical specification Clause
274 of S.O.R of 1104 for Rural Roads of MORD including setting out,
P.W (Roads), construction of shoring and bracing, removal of stumps and
2015-2016 other deleterious matter, dressing of sides and bottom and cum 832.00 105.04 87393.00
backfilling with approved material.

C-4 Ref Item # Sand filling in foundation trenches and at the back of
12.04, page-278 abutments, wing-walls etc. with good local sand free from
S.O.R of P.W earth in layers not exceeding 15 cm. including inundating
(Roads), 2015- each layer by profuse water and poking and ramming layer
2016 by layer complete including supply of sand. Quality of sand cum 478.40 429.15 205305.00
is to be approved by the Engineer-in-charge.

Total Protective Works : Rs. 3,931,159.00

317,029
Bill of Quantity :
Protective Works

7121.66
Quantity Calculation :
Protective Works

Quantity Estimate of proposed Protective Work

Total Quantity = 624.00 m

ITEM No. C -8 : Weaving wire mattress as directed with wire of 4mm dia. and making sausage crat ……
Length Breadth Width
624.00 2.00 0.50 3120.00 Sqm
624.00 1.50 0.50 2496.00 Sqm
624.00 1.00 0.50 1872.00 Sqm
7488.00 Sqm

ITEM No. C-9 : Filling properly the empty sausage crates with boulders of any size & shape ……

Length Breadth Width


624.00 2.00 0.50 624.00 Cum
624.00 1.50 0.50 468.00 Cum
624.00 1.00 0.50 312.00 Cum
1404.00 Cum

ITEM No. C-10 : Earthwork in excavation for foundation of structures upto 3 m depth as per drawing ……

624.00 2.00 0.80 832.00 cum

ITEM No. C-11 : Sand filling in foundation trenches and at the back of abutments, wing-walls etc ……

624.00 2.00 0.20 208.00 cum


624.00 2.60 0.20 270.40 cum
478.40 cum
Quantity Calculation :
Protective Works

201.6

201.6
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of sainthia
-sultanpur road (SH-11) by rigid & flexible pavement under birbhum division, PWD in the
district of birbhum during the year 2017-18

Diversion of Road work


1 Item No. 3.14 Page No 236 of P.W. (Roads) Schedule of Rates 2015-2016
Construction of Subgrade and Earthen Shoulders with approved material obtained
from borrow pits with all lifts and leads, transporting to site, spreading, grading to
required slope and compacted to meet requirement of Table 300.2 with lead upto 1000
m as per Technical Specification Clause 303.1 for Rural Roads of MORD. (Borrow pit
/pre work post work measurement)

19162.00 M3 @ Rs. 202.65 /m3 = Rs. 3883141.00

2 Item No. 4.05 Page No 242 of P.W. (Roads) Schedule of Rates 2015-2016
Supplying, spreading and compacting Sand to required thickness, in layers not
exceeding 150 mm to proper gradient and camber, inundating each layer by water and
packing and ramming layer by layer to achieve desired compaction, including lighting,
guarding, barricading and making adequate earthen bundh where necessary, curing
with water as per direction, mending cracks and depressions by ramming wherever
necessary.

2860.00 M3 @ Rs. 622.16 /m3 = Rs. 1779378.00

3 Item No. 4.06 Page No 242 of P.W. (Roads) Schedule of Rates 2015-2016
Supplying, spreading and consolidating Stone Dust to a depth of 100 mm and above at
desired density and C.B.R. as per Specification with power roller to proper gradient and
camber including watering as necessary, and lighting, guarding, barricading and
making adequate earthen bundh where necessary to protect the edges and curing with
water for 2 to 3 days, mending cracks and depressions by rolling where necessary
including all incidental charges of
roller, cost of fuel & lubricants complete as per specification.
1716.00 M3 @ Rs. 1095.56 /m3 = Rs. 1879981.00

4 Item No. 4.11(iii)/(B)Page No 245 of P.W. (Roads) Schedule of Rates 2015-2016


Providing, laying, spreading and compacting stone aggregates of specific sizes to water
bound macadam specification including spreading in uniform thickness, hand packing,
rolling with vibratory roller 8-10 tonnes in stages to proper grade and camber,
applying and brooming requisite type of screening / binding materials to fill up the
interstices of coarse aggregate, watering including lighting, guarding, barricading and
making necessary earthen bundh of one metre width on each side and preparing the
bed by necessary cutting or filling, including cost of all materials and hire and labour
charges of all men and machinery and compacting to the required density, as per
Clause 404 of Specifications for Road & Bridge Works of MoRT&H (5th Revision).
(ii) Grading-I Aggregate (63 mm to 45 mm) Using Stone Screening Type B (11.2 mm)
A. Mechanical Means

1287.00 M3 @ Rs. 1609.81 /m3 = Rs. 2071825.00

5 Item No. 4.04 Page No 242 of P.W. (Roads) Schedule of Rates 2015-2016
Supplying, spreading and consolidating Moorum to a depth of 75 mm at desired
density and C.B.R. as per specification with power roller to proper gradient and camber
including watering as necessary, and lighting, guarding, barricading and making
adequate earthen bundh where necessary to protect the edges and curing with water
for 2 to 3 days, mending cracks by rolling where necessary including all incidental
charges of roller, cost of fuel & lubricants etc. complete as per specification.
104.00 M3 @ Rs. 1131.94 /m3 = Rs. 117722.00
6 Item No. 14.02 Page No 304 of P.W. (Roads) Schedule of Rates 2015-2016
Providing Sal-bullah / Eucalyptus bullah piles of diameter not less than 150mm,
driving upto desired depth but not less than 4 m and spacing as per approved design
and joining each bullah piles with the staging props by proper arrangement capable to
transmit the loads from superstructure, all complete.

675.00 M2 @ Rs. 2020.00 /m2 = Rs. 1363500.00

7 Item No. 18.29 Page No 325 of P.W. (Roads) Schedule of Rates 2015-2016
Filling empty Cement bags with dry earth or sand, stitching the bag (cost of thread
included) and carrying and placing them in position and all incidental charges
complete but excluding cost of sand and gunny bags.

20000.00 Each @ Rs. 16.77 /each = Rs. 335320.00

8 Item No. 11.03 Page No 276 of P.W. (Roads) Schedule of Rates 2015-2016
Providing and laying reinforced cement concrete pipe NP3 with spigot socket for
culverts on first class bedding of granular material in single row including fixing with
cement mortar 1:2 as per Technical Specification Clause 1106 for Rural Roads of
MORD.
(C) 900 mm dia
500.00 M @ Rs. 4810.43 /M = Rs. 2405214.00

Rs. 11430867.00

junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
QUANTITY CALCULATION FOR DIVERSION ROAD WORK

No. of diversion (type-1) 13 nos


Length of Diversion road (type-1) 13x90.0 m 1040 m
1040 m
Width of carriage way = 5.50 m.

Surface area of carriageway = 5720.00 m2


30 m. surface
Total X 7 + 90area
X (7.0+5.5)/2
of carriage+way
80 X 5.5
5720.00 m2

Item No.1: Earthwork in embakment compacted at OMC…..…..

Diversion road at high level. :-


Length of Diversion road = 1040 m.
Top width of approach at high end = 7.00 m.
Height of embakment at high end = 2.75 m. (Av.)
Bottom width of approach at high end= 15.000 m.
Top width of approach at low end = 10.000 m.
Height of embakment at low end = 0.6 m.
Bottom width of approach at low end= 12.00 m.

Cross
Descripti Dimension(m) section
Item No. on area at Volume
( m3 )
Length Avg.Width Height high end
( m2 )
Diversio
n road at 11.00 2.750 30.3
high end
1 1040.00 19162.00
Diversio
n road at 11.00 0.600 6.6
low end
3
Total 19162.00 m
19162.00 m
3
Say
Item No.2: Sand compaction …..

Diversion road 1 no.


Surface area = 5720.00 m.
Thickness = 0.50 m.

Volume 5720m2 X 0.5m X 2860.00


2860.00 m
3

Item No.3: Stone metal consolidation with Gr.I …..

Diversion road 1 no.


5720.00 m
2
Surface area =
Thickness(in different spell) 0.225 m

Volume 5720m2 X 0.225m. X 1287.00


1287.00 m
3
Item No.5: stone dust ……..
Diversion road 1 no
Surface area = 5720.00 m2.
Thickness 0.300 m

Volume 5720m X 0.3m. 1716


1716.00 m3
1716.00 m3
Item No.4: Moorum compaction …..
Diversion road 2 bothside 1 no
length 1040.00 m
width 0.50 m
Thickness = 0.100 m.
Volume 1040m X 0.5mx0.1m X 2 104
104.00 m3
Item No.6: Providing Sal-bullah / Eucalyptus bullah pile…..

area=90mx2(sides)x3.75m 675 sqm

Item No.7: Supplying and labour for filling empty cement bags with fine sand …..

LS 20000.00 nos.
Item No.8: Supplying of 900 mm. dia NP3 hume pipe…..

Length of each pipe 2.5 m. 2.5 m.


nos. pipes required 200 nos.

Total length 200nos. X 2.5 m. 500 m.


500.00 m.

junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD

,
Suri Sub-Division PWD
Cross Drainage works:(4 Nos 6M X 6M Box Culvert) qty
calculation

1 Item No. 2.05 Page No 230 of P.W. (Roads) Schedule of Rates 2015-2016
Dismantling of existing structures like culverts, bridges,retaining walls and other structures comprising

of brick masonry, including disposal of unserviceable material and stacking the serviceable material with

all lift and lead of 1000 m as per Technical Specifications Clause 202 for Rural Roads of MORD.
Dismantling of PCC
Existing floor appron
1 x 24.00 x 12.00 x 0.5 m3 = 144.00
Abutment 2 x 6.00 x 1.50 x 6.0 m 3
= 108.00
lugs 2 x 6.00 x 0.50 x 6.0 m3 = 36.00
Total quantity for 1 no Culvert 288.000 m3
Dismantling of RCC
existing Deck slab including app.slab
= 1 x 28.00 x 6.00 x 0.5 m3 84.000
RCC Railling
= 2 x 28.00 x 0.25 x 1.5 m3 21.000
Total quantity for 1 no Culvert 105.000 m3
2 Item No. 12.01 Page No 278 of P.W. (Roads) Schedule of Rates 2015-2016
Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, removing, spreading or stacking of spoils within a lead of 150 m. as directed
and including trimming the sides of the trenches, leveling, dressing and ramming the bottom, and
backfilling with approved material complete as per direction of the Engineer-in-Charge .

= 32.600 x 12.6 x 1.50 616.140


Apron U/S 32.000 + 37.0 x 2.5 x 0.3 = 25.88
2
D/S 32.000 + 42.0 x 5.0 x 0.3 = 55.50
2
Curtain Wall
= 1 x 100.0 x 1.500 x 1.700 = 255.000
Dummy Wall
= 2 x 1.000 x 12.00 x 1.600 = 38.400
2 x 2.500 x 12.00 x 0.400 = 24.000
Total quantity for 1 no Culvert 1014.92 m3
3 Item No. 12.04 Page No 280 of P.W. (Roads) Schedule of Rates 2015-2016
Sand filling in foundation trenches and at the back of abutments, wingwalls etc. with good local
sand free from earth in layers not exceeding 15 cm. including inundating each layer by profuse
water and poking and ramming layer by layer complete including supply of sand. Quality of sand is
to be approved by the Engineer-in-charge.

Sand filling ( Fine sand)


Structure
= 32.600 x 12.6 x 0.20 82.152
Intermidiate sand filling
1 x 31.000 x 11.60 x 1.000 = 359.600
Apron U/S 32.000 + 37.0 x 2.5 x 0.2 = 17.25
2
D/S 32.000 + 42.0 x 5.0 x 0.2 = 37.00
2
Dummy Wall
= 2 x 1.000 x 12.00 x 0.20 = 4.800
2 x 2.500 x 12.00 x 0.20 = 12.000
Back filling
= 4 x 3.00 x 12.00 x 3.00 = 432.000
Curtain Wall
= 1 x 100.00 x 1.500 x 0.200 = 30.000
Total quantity for 1 no Culvert = 974.802 m3
4 Item No. 13 Page No 45 of P.W. (Building) Schedule of Rates 2015-2016
Supplying and laying Polythene Sheet (150 gm/sq.m) over damp proof coarse or below flooring or
roof terranching or in foundation or in foundation trenches.
For lugs
[2 x (32-0.2) + 5 (12-0.2)] x 0.20 87.20

Intermidiate of lugs
1 x 31.00 x 11.60 359.60
Apron U/S 32.00 + 37.0 x 2.5 = 78.25
2
D/S 32.00 + 42.0 x 5.0 = 137.00
2
Dummy Wall
2.00 x 1+0.8+0.65+0.5 x 12.00 = 5.45
4
3 x 12.00 x 0.15 5.40
Curtain Wall
= 1 x 100.00 x
0.375+0.875 44.13
2 717.03 m2
Total quantity for 1 no Culvert = 717.03 m2
5 Item No.12.05 Page No 280 of P.W. (Roads) Schedule of Rates 2015-16
Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any
part of foundation of bridges / culverts with graded stone chips of appropriate nominal sizes,
including screening and cleaning of coarse aggregates, fine aggregate (sand) conforming to proper
grading zone,both of approved quality and cement, as necessary,cost of curing with water,
including cost and carriage of all materials and including preparation of design mix, approval of
the same by the Engineer-in-Charge, cost for quality control, sampling, testing etc. including cost of
formwork but excluding reinforcement complete as per drawing and technical specifications.
6.1 PCC grade M20 conc.
For lugs
[2 x (32-0.2) + 5 (12-0.2)] x 0.20 x 0.15 65.37

Intermidiate of lugs
1 x 31.00 x 11.60 x 0.15 53.94
Apron U/S 32.00 + 37.0 x 2.5 x 0.225 = 19.41
2
D/S 32.00 + 42.0 x 5.0 x 0.225 = 41.63
2
Dummy Wall
2.00 x 1+0.8+0.65+0.5 x 12.00 x 1.40 = 99.12
4
3 x 12.00 x 0.15 x 2.00 10.80
Curtain Wall
= 1 x 100.00 x 0.375+0.875 x 1.200 150.00
2
Total quantity for 1 no Culvert = 440.26 m3
6.2 RCC Grade M25
I)
RCCUsing concrete
grade mixer
M25 conc.
Base Slab
= 32.00 x 12.0 x 0.40 153.600
Intermidiate Wall
5 x 6.000 x 12.00 x 0.400 144.000
For
Haunch
20 x 0.5 x 0.225 x 0.225 x 12.00 6.075

Deck Slab
= 1 x 26.00 x 12.00 x 0.40 124.800
Approach Slab
= 2 x 3.0 x 12.000 x 0.400 28.800
Approach SlabSide Wall
= 4 x 3.0 x 5.850 x 0.400 28.080
Total quantity for 1 no Culvert = 485.355 m3
6 Item No.13.02 Page No 297 of P.W. (Roads) Schedule of Rates 2015-16
Supplying bending and binding and laying in position steel reinforcement of different dimensions
in cement concrete work i.e. R.C.C., P.S.C. etc.of different components in foundation and in
superstructure including initial straightening, straightening of coils bars, removal of loose rust (if
any), cutting to requisite length bending, binding with annealed wire not less than 1 mm in size
and conforming to IS 280 at every intersection hooked and bent to correct shape and placed on
forms etc. including cost of black annealed wire and cost of loading, unloading, carriage of all steel
materials complete as per drawing and direction of Engineer-in-charge.(a) For M.S. Rounds/Tor
Steel/H.Y.S.D. Bars
= 485.36 x 0.02 x 7.85 = 76.201 MT
7 Item No.13.03 Page No 297 of P.W. (Roads) Schedule of Rates 2015-16
Providing Weep Holes in Brick masonry/ Stone masonry, Plain/ Reinforced concrete abument,
wing wall, return wall with 100mm dia AC pipe extending through the full width of the structures
with slope of 1(V): 20 (H) towards drawing face complete as per drawing
Return wall = 4 x 3 x 6.00 Nos 72.00
Total quantity for 1 no Culvert = 72.000 Nos
8 Item No.14.08 Page No 305 of P.W. (Roads) Schedule of Rates 2015-16
Construction of precast RCC railing of M30 GRCC post not toexceed 1 in 500, centre to centre spacing
betweenvertical post not to exceed 2000 mm, leavingadequate space between vertical post
forexpansion, complete as per approved drawingsand technical specifications.

32.00 X 2.00 = 64.000 M

9 Item No.14.09 Page No 305 of P.W. (Roads) Schedule of Rates 2015-16


Drainage Spouts in Superstructure includingproviding drip mouldings and also includingsupplying,
fitting and fixing approved type ofmaterials complete as per drawing and Technicalspecification vide
clause no. 2705 of MoRT&H’sSpecification for Road & Bridge Works.
2.00 X 4.00 = 8.000 Nos

10 Item No.14.04 Page No 304 of P.W. (Roads) Schedule of Rates 2015-16


Providing and laying Cement concrete Wearingcoat M-30 grade with graded stone chips 19mmdown
including screening and cleaning approvedstone chips and sand as necessary laying, finishingcomplete
to camber and grade, curing with water,including cost and carriage of all materials and hirecharges for
form work including reinforcementcomplete as per drawing and TechnicalSpecifications vide clause no.
2702 of MoRT&H’sSpecification for Road & Bridge Works.
32.00 x 11.50 X 0.075 = 27.600 M3
11 Item No.14.06 Page No 306 of P.W. (Roads) Schedule of Rates 2015-16
Asphaltic Plug jointProviding and laying of asphaltic plug joint toprovide for horizontal movement of 25
mm andvertical movement of 2 mm, depth of joint varyingfrom 75 mm to 100 mm, width varying from
500 mmto 750 mm (in traffic direction), covered with aclosure plate of 200mm x 6mm of
wieldablestructural steel conforming to IS: 2062, asphalticplug to consist of polymer modified bitumen
binder,carefully selected single size aggregate of 12.5 mmnominal size and a heat resistant
foamcaulking/backer rod, all as per approved drawingsand specifications.
5.00 X 11.50 = 57.500 M
12 Item No.12.03 Page No 279 of P.W. (Roads) Schedule of Rates 2015-16
Earth in filling in foundation trenches and at theback of abutments with good earth (sandy soil) in
layers not exceeding 15 cm. including watering andramming layer by layer complete with earthobtained
by fresh excavation from land arrangedby Department beyond 150 m. but within 300 m.including all
lifts. Earth to be approved by theEngineer-in-charge.
= 338.305 M3
13 Item No.8.21 Page No 268 of P.W. (Roads) Schedule of Rates 2015-16
Painting the vertical end faces of posts, wheel guards or railing or parapet with alternate bands of

different colours as directed by the Engineer-in-charge with approved synthetic enamel paint.
Painting in two coats
same as priming area
2.00 x 32.00 X 1.500 = 96.000 M2
Total Cost R
Junior Engineer Assistant Engineer
Suri Sub-Division
Section II, PWD PWD
m3

288.000 m3 474.70 136714.00

105.000 m3 780.73 81977.00

1014.915 m3 125.24 127108.00


974.802 m3 602.12 586949.00
717.025 m2 25.00 17926.00

440.261 m3 5897.12 2596273.00


485.355 m3 6384.48 3098739.00

76.201 MT 51288.07 3908188.00


72.000 Nos 127.26 9163.00

64.000 m 1873.55 119907.00

8.000 Nos 907.99 7264.00

27.600 m3 11047.38 304908.00

57.500 m 9973.75 573491.00

338.305 m3 162.61 55012.00

96.000 M2 99.99 9599.00


Total Cost Rs.= 11633218.00
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of sainthia
-sultanpur road (SH-11) by rigid & flexible pavement under birbhum division, PWD in the district
of birbhum during the year 2017-18

Box Bridge 6M x 6M
1 Item No. 2.05 Page No 230 of P.W. (Roads) Schedule of Rates 2015-2016
Dismantling of existing structures like culverts, bridges,retaining walls and other
structures comprising of brick masonry, including disposal of unserviceable material and
stacking the serviceable material with all lift and lead of 1000 m as per Technical
Specifications Clause 202 for Rural Roads of MORD.
Dismantling of PCC

288.00 M3 @ Rs. 474.70 /m3 = Rs. 136714.00


Dismantling of RCC

105.00 M3 @ Rs. 780.73 /m3 = Rs. 81977.00

2 Item No. 12.01 Page No 278 of P.W. (Roads) Schedule of Rates 2015-2016
Earth work in excavation of foundation of structures as per drawing and technical
specification, including setting out, removing, spreading or stacking of spoils within a
lead of 150 m. as directed and including trimming the sides of the trenches, leveling,
dressing and ramming the bottom, and backfilling with approved material complete as
per direction of the Engineer-in-Charge .
(i) With pumping out water including shoring as required.

1014.92 M3 @ Rs. 125.24 /m3 = Rs. 127108.00

3 Item No. 12.04 Page No 280 of P.W. (Roads) Schedule of Rates 2015-2016
Sand filling in foundation trenches and at the back of abutments, wingwalls etc. with
good local sand free from earth in layers not exceeding 15 cm. including inundating each
layer by profuse water and poking and ramming layer by layer complete including
supply of sand. Quality of sand is to be approved by the Engineer-in-charge.

974.80 M3 @ Rs. 602.12 /m3 = Rs. 586951.00


4 Item No. 13 Page No 45 of P.W. (Building) Schedule of Rates 2015-2016
Supplying and laying Polythene Sheet (150 gm/sq.m) over damp proof coarse or below
flooring or roof terranching or in foundation or in foundation trenches.

717.03 M2 @ Rs. 25.00 /m2 = Rs. 17926.00


5 Item No.12.05 Page No 280 of P.W. (Roads) Schedule of Rates 2015-16
Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements,
in any part of foundation of bridges / culverts with graded stone chips of appropriate
nominal sizes, including screening and cleaning of coarse aggregates, fine aggregate
(sand) conforming to proper grading zone,both of approved quality and cement, as
necessary,cost of curing with water, including cost and carriage of all materials and
including preparation of design mix, approval of the same by the Engineer-in-Charge,
cost for quality control, sampling, testing etc. including cost of formwork but excluding
reinforcement complete as per drawing and technical specifications.
6.1 PCC grade M20 conc.
440.26 M3 @ Rs. 6544.53 /m3 = Rs. 2881303.00

6.2 RCC Grade M25


I) Using concrete mixer
485.36 M3 @ Rs. 6845.64 /m3 = Rs. 3322566.00
6 Item No. 2.05 Page No 230 of P.W. (Roads) Schedule of Rates 2015-2016
Supplying bending and binding and laying in position steel reinforcement of different
dimensions in cement concrete work i.e. R.C.C., P.S.C. etc.of different components in
foundation and in superstructure including initial straightening, straightening of coils
bars, removal of loose rust (if any), cutting to requisite length bending, binding with
annealed wire not less than 1 mm in size and conforming to IS 280 at every intersection
hooked and bent to correct shape and placed on forms etc. including cost of black
annealed wire and cost of loading, unloading, carriage of all steel materials complete as
per drawing and direction of Engineer-in-charge.(a) For M.S. Rounds/Tor Steel/H.Y.S.D.
Bars

76.20 MT @ Rs. 64785.57 /MT = Rs. 4936708.00

7 Item No.13.03 Page No 297 of P.W. (Roads) Schedule of Rates 2015-16


Providing Weep Holes in Brick masonry/ Stone masonry, Plain/ Reinforced concrete
abument, wing wall, return wall with 100mm dia AC pipe extending through the full
width of the structures with slope of 1(V): 20 (H) towards drawing face complete as per
drawing

72 Nos @ Rs. 127.26 /each = Rs. 9163.00


8 Item No.14.08 Page No 305 of P.W. (Roads) Schedule of Rates 2015-16
Construction of precast RCC railing of M30 GRCC post not toexceed 1 in 500, centre to
centre spacing betweenvertical post not to exceed 2000 mm, leavingadequate space
between vertical post forexpansion, complete as per approved drawingsand technical
specifications.

64.00 M @ Rs. 1873.55 /M = Rs. 119907.00


9 Item No.14.09 Page No 305 of P.W. (Roads) Schedule of Rates 2015-16
Drainage Spouts in Superstructure includingproviding drip mouldings and also
includingsupplying, fitting and fixing approved type ofmaterials complete as per drawing
and Technicalspecification vide clause no. 2705 of MoRT&H’sSpecification for Road &
Bridge Works.

8 Nos @ Rs. 907.99 /each = Rs. 7264.00

10 Item No.14.04 Page No 304 of P.W. (Roads) Schedule of Rates 2015-16


Providing and laying Cement concrete Wearingcoat M-30 grade with graded stone chips
19mmdown including screening and cleaning approvedstone chips and sand as
necessary laying, finishingcomplete to camber and grade, curing with water,including
cost and carriage of all materials and hirecharges for form work including
reinforcementcomplete as per drawing and TechnicalSpecifications vide clause no. 2702
of MoRT&H’sSpecification for Road & Bridge Works.

27.60 M3 @ Rs. 11047.38 /m3 = Rs. 304908.00


11 Item No.14.06 Page No 306 of P.W. (Roads) Schedule of Rates 2015-16
Asphaltic Plug jointProviding and laying of asphaltic plug joint toprovide for horizontal
movement of 25 mm andvertical movement of 2 mm, depth of joint varyingfrom 75 mm
to 100 mm, width varying from 500 mmto 750 mm (in traffic direction), covered with
aclosure plate of 200mm x 6mm of wieldablestructural steel conforming to IS: 2062,
asphalticplug to consist of polymer modified bitumen binder,carefully selected single
size aggregate of 12.5 mmnominal size and a heat resistant foamcaulking/backer rod, all
as per approved drawingsand specifications.
57.50 M @ Rs. 9973.75 /M = Rs. 573491.00
12 Item No.12.03 Page No 279 of P.W. (Roads) Schedule of Rates 2015-16
Earth in filling in foundation trenches and at theback of abutments with good earth
(sandy soil) in layers not exceeding 15 cm. including watering andramming layer by
layer complete with earthobtained by fresh excavation from land arrangedby
Department beyond 150 m. but within 300 m.including all lifts. Earth to be approved by
theEngineer-in-charge.
338.31 M3 @ Rs. 162.61 /m3 = Rs. 55012.00

13 Item No.8.21 Page No 268 of P.W. (Roads) Schedule of Rates 2015-16


Painting the vertical end faces of posts, wheel guards or railing or parapet with alternate
bands of different colours as directed by the Engineer-in-charge with approved synthetic
enamel paint.
Painting in two coats
96.00 M2 @ Rs. 99.99 /m2 = Rs. 9599.00
Rs. 13160998.00

junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
Proposed improvement of the existing carriageway from 1.00 kmp to 19.00 kmp of sainthia
-sultanpur road (SH-11) by rigid & flexible pavement under birbhum division, PWD in the district
of birbhum during the year 2017-18

Box Bridge 3M x 3M
1 Item No. 2.05 Page No 230 of P.W. (Roads) Schedule of Rates 2015-2016
Dismantling of existing structures like culverts, bridges,retaining walls and other
structures comprising of brick masonry, including disposal of unserviceable material and
stacking the serviceable material with all lift and lead of 1000 m as per Technical
Specifications Clause 202 for Rural Roads of MORD.
Dismantling of PCC

189.00 M3 @ Rs. 474.70 /m3 = Rs. 89718.00


Dismantling of RCC

51.00 M3 @ Rs. 780.73 /m3 = Rs. 39817.00

2 Item No. 12.01 Page No 278 of P.W. (Roads) Schedule of Rates 2015-2016
Earth work in excavation of foundation of structures as per drawing and technical
specification, including setting out, removing, spreading or stacking of spoils within a
lead of 150 m. as directed and including trimming the sides of the trenches, leveling,
dressing and ramming the bottom, and backfilling with approved material complete as
per direction of the Engineer-in-Charge .
(i) With pumping out water including shoring as required.

658.65 M3 @ Rs. 125.24 /m3 = Rs. 82489.00

3 Item No. 12.04 Page No 280 of P.W. (Roads) Schedule of Rates 2015-2016
Sand filling in foundation trenches and at the back of abutments, wingwalls etc. with
good local sand free from earth in layers not exceeding 15 cm. including inundating each
layer by profuse water and poking and ramming layer by layer complete including
supply of sand. Quality of sand is to be approved by the Engineer-in-charge.

787.10 M3 @ Rs. 602.12 /m3 = Rs. 473931.00


4 Item No. 13 Page No 45 of P.W. (Building) Schedule of Rates 2015-2016
Supplying and laying Polythene Sheet (150 gm/sq.m) over damp proof coarse or below
flooring or roof terranching or in foundation or in foundation trenches.

585.90 M2 @ Rs. 25.00 /m2 = Rs. 14647.00


5 Item No.12.05 Page No 280 of P.W. (Roads) Schedule of Rates 2015-16
Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements,
in any part of foundation of bridges / culverts with graded stone chips of appropriate
nominal sizes, including screening and cleaning of coarse aggregates, fine aggregate
(sand) conforming to proper grading zone,both of approved quality and cement, as
necessary,cost of curing with water, including cost and carriage of all materials and
including preparation of design mix, approval of the same by the Engineer-in-Charge,
cost for quality control, sampling, testing etc. including cost of formwork but excluding
reinforcement complete as per drawing and technical specifications.
6.1 PCC grade M20 conc.
440.26 M3 @ Rs. 6544.53 /m3 = Rs. 2881303.00

6.2 RCC Grade M25


I) Using concrete mixer
218.93 M3 @ Rs. 6845.64 /m3 = Rs. 1498682.00
6 Item No. 2.05 Page No 230 of P.W. (Roads) Schedule of Rates 2015-2016
Supplying bending and binding and laying in position steel reinforcement of different
dimensions in cement concrete work i.e. R.C.C., P.S.C. etc.of different components in
foundation and in superstructure including initial straightening, straightening of coils
bars, removal of loose rust (if any), cutting to requisite length bending, binding with
annealed wire not less than 1 mm in size and conforming to IS 280 at every intersection
hooked and bent to correct shape and placed on forms etc. including cost of black
annealed wire and cost of loading, unloading, carriage of all steel materials complete as
per drawing and direction of Engineer-in-charge.(a) For M.S. Rounds/Tor Steel/H.Y.S.D.
Bars

34.37 MT @ Rs. 64785.57 /MT = Rs. 2226759.00

7 Item No.13.03 Page No 297 of P.W. (Roads) Schedule of Rates 2015-16


Providing Weep Holes in Brick masonry/ Stone masonry, Plain/ Reinforced concrete
abument, wing wall, return wall with 100mm dia AC pipe extending through the full
width of the structures with slope of 1(V): 20 (H) towards drawing face complete as per
drawing

54 Nos @ Rs. 127.26 /each = Rs. 6872.00


8 Item No.14.08 Page No 305 of P.W. (Roads) Schedule of Rates 2015-16
Construction of precast RCC railing of M30 GRCC post not toexceed 1 in 500, centre to
centre spacing betweenvertical post not to exceed 2000 mm, leavingadequate space
between vertical post forexpansion, complete as per approved drawingsand technical
specifications.

32.00 M @ Rs. 1873.55 /M = Rs. 59954.00


9 Item No.14.09 Page No 305 of P.W. (Roads) Schedule of Rates 2015-16
Drainage Spouts in Superstructure includingproviding drip mouldings and also
includingsupplying, fitting and fixing approved type ofmaterials complete as per drawing
and Technicalspecification vide clause no. 2705 of MoRT&H’sSpecification for Road &
Bridge Works.

4 Nos @ Rs. 907.99 /each = Rs. 3632.00

10 Item No.14.04 Page No 304 of P.W. (Roads) Schedule of Rates 2015-16


Providing and laying Cement concrete Wearingcoat M-30 grade with graded stone chips
19mmdown including screening and cleaning approvedstone chips and sand as
necessary laying, finishingcomplete to camber and grade, curing with water,including
cost and carriage of all materials and hirecharges for form work including
reinforcementcomplete as per drawing and TechnicalSpecifications vide clause no. 2702
of MoRT&H’sSpecification for Road & Bridge Works.

13.80 M3 @ Rs. 11047.38 /m3 = Rs. 152454.00


11 Item No.14.06 Page No 306 of P.W. (Roads) Schedule of Rates 2015-16
Asphaltic Plug jointProviding and laying of asphaltic plug joint toprovide for horizontal
movement of 25 mm andvertical movement of 2 mm, depth of joint varyingfrom 75 mm
to 100 mm, width varying from 500 mmto 750 mm (in traffic direction), covered with
aclosure plate of 200mm x 6mm of wieldablestructural steel conforming to IS: 2062,
asphalticplug to consist of polymer modified bitumen binder,carefully selected single
size aggregate of 12.5 mmnominal size and a heat resistant foamcaulking/backer rod, all
as per approved drawingsand specifications.
11.50 M @ Rs. 9973.75 /M = Rs. 114698.00
12 Item No.12.03 Page No 279 of P.W. (Roads) Schedule of Rates 2015-16
Earth in filling in foundation trenches and at theback of abutments with good earth
(sandy soil) in layers not exceeding 15 cm. including watering andramming layer by
layer complete with earthobtained by fresh excavation from land arrangedby
Department beyond 150 m. but within 300 m.including all lifts. Earth to be approved by
theEngineer-in-charge.
219.55 M3 @ Rs. 162.61 /m3 = Rs. 35701.00

13 Item No.8.21 Page No 268 of P.W. (Roads) Schedule of Rates 2015-16


Painting the vertical end faces of posts, wheel guards or railing or parapet with alternate
bands of different colours as directed by the Engineer-in-charge with approved synthetic
enamel paint.
Painting in two coats
48.00 M2 @ Rs. 99.99 /m2 = Rs. 4800.00
Rs. 7680657.00

junior Engineer Assistant Engineer


Section II, PWD Suri Sub-Division PWD
Cross Drainage works:(3 Nos 3M X 3M Box Culvert) qty
calculation

1 Item No. 2.05 Page No 230 of P.W. (Roads) Schedule of Rates 2015-2016
Dismantling of existing structures like culverts, bridges,retaining walls and other structures comprising

of brick masonry, including disposal of unserviceable material and stacking the serviceable material with

all lift and lead of 1000 m as per Technical Specifications Clause 202 for Rural Roads of MORD.
Dismantling of PCC
Existing floor appron
1 x 9.00 x 10.00 x 0.5 m3 = 45.00
Abutment 2 x 6.00 x 1.50 x 6.0 m3 = 108.00
lugs 2 x 6.00 x 0.50 x 6.0 m3 = 36.00
Total quantity for 1 no Culvert 189.000 m3
Dismantling of RCC
existing Deck slab including app.slab
= 1 x 9.00 x 9.00 x 0.5 m3 40.500
RCC Railling
= 2 x 14.00 x 0.25 x 1.5 m3 10.500
Total quantity for 1 no Culvert 51.000 m3
2 Item No. 12.01 Page No 278 of P.W. (Roads) Schedule of Rates 2015-2016
Earth work in excavation of foundation of structures as per drawing and technical specification,
including setting out, removing, spreading or stacking of spoils within a lead of 150 m. as directed
and including trimming the sides of the trenches, leveling, dressing and ramming the bottom, and
backfilling with approved material complete as per direction of the Engineer-in-Charge .

= 15.000 x 12.6 x 1.50 283.500


Apron U/S 22.000 + 28.0 x 2.5 x 0.3 = 18.75
2
D/S 24.000 + 28.0 x 5.0 x 0.3 = 39.00
2
Curtain Wall
= 1 x 100.0 x 1.500 x 1.700 = 255.000
Dummy Wall
= 2 x 1.000 x 12.00 x 1.600 = 38.400
2 x 2.500 x 12.00 x 0.400 = 24.000
Total quantity for 1 no Culvert 658.65 m3
3 Item No. 12.04 Page No 280 of P.W. (Roads) Schedule of Rates 2015-2016
Sand filling in foundation trenches and at the back of abutments, wingwalls etc. with good local
sand free from earth in layers not exceeding 15 cm. including inundating each layer by profuse
water and poking and ramming layer by layer complete including supply of sand. Quality of sand is
to be approved by the Engineer-in-charge.

Sand filling ( Fine sand)


Structure
= 15.000 x 12.6 x 0.20 37.800
Intermidiate sand filling
1 x 20.000 x 11.60 x 1.000 = 232.000
Apron U/S 22.000 + 28.0 x 2.5 x 0.2 = 12.50
2
D/S 24.000 + 28.0 x 5.0 x 0.2 = 26.00
2
Dummy Wall
= 2 x 1.000 x 12.00 x 0.20 = 4.800
2 x 2.500 x 12.00 x 0.20 = 12.000
Back filling
= 4 x 3.00 x 12.00 x 3.00 = 432.000
Curtain Wall
= 1 x 100.00 x 1.500 x 0.200 = 30.000
Total quantity for 1 no Culvert = 787.100 m3
4 Item No. 13 Page No 45 of P.W. (Building) Schedule of Rates 2015-2016
Supplying and laying Polythene Sheet (150 gm/sq.m) over damp proof coarse or below flooring or
roof terranching or in foundation or in foundation trenches.
For lugs
[2 x (18-0.2) + 5 (12-0.2)] x 0.20 18.92

Intermidiate of lugs
1 x 20.00 x 11.60 232.00
Apron U/S 22.00 + 28.0 x 2.5 = 90.00
2
D/S 24.00 + 28.0 x 5.0 = 190.00
2
Dummy Wall
2.00 x 1+0.8+0.65+0.5 x 12.00 = 5.45
4
3 x 12.00 x 0.15 5.40
Curtain Wall
= 1 x 100.00 x
0.375+0.875 44.13
2 585.90 m2
Total quantity for 1 no Culvert = 585.90 m2
5 Item No.12.05 Page No 280 of P.W. (Roads) Schedule of Rates 2015-16
Plain / Reinforced Cement Concrete in Open foundation with or without reinforcements, in any
part of foundation of bridges / culverts with graded stone chips of appropriate nominal sizes,
including screening and cleaning of coarse aggregates, fine aggregate (sand) conforming to proper
grading zone,both of approved quality and cement, as necessary,cost of curing with water,
including cost and carriage of all materials and including preparation of design mix, approval of
the same by the Engineer-in-Charge, cost for quality control, sampling, testing etc. including cost of
formwork but excluding reinforcement complete as per drawing and technical specifications.
6.1 PCC grade M20 conc.
For lugs
[2 x (32-0.2) + 5 (12-0.2)] x 0.20 x 0.15 65.37

Intermidiate of lugs
1 x 31.00 x 11.60 x 0.15 53.94
Apron U/S 32.00 + 37.0 x 2.5 x 0.225 = 19.41
2
D/S 32.00 + 42.0 x 5.0 x 0.225 = 41.63
2
Dummy Wall
2.00 x 1+0.8+0.65+0.5 x 12.00 x 1.40 = 99.12
4
3 x 12.00 x 0.15 x 2.00 10.80
Curtain Wall
= 1 x 100.00 x 0.375+0.875 x 1.200 150.00
2
Total quantity for 1 no Culvert = 440.26 m3
6.2 RCC Grade M25
I) Using
RCC concrete
grade mixer
M25 conc.
Base Slab
= 17.00 x 12.0 x 0.40 81.600
Intermidiate Wall
2 x 3.000 x 12.00 x 0.400 28.800
For
Haunch
12 x 0.5 x 0.225 x 0.225 x 12.00 3.645

Deck Slab
= 1 x 10.00 x 12.00 x 0.40 48.000
Approach Slab
= 2 x 3.0 x 12.000 x 0.400 28.800
Approach SlabSide Wall
= 4 x 3.0 x 5.850 x 0.400 28.080
Total quantity for 1 no Culvert = 218.925 m3
6 Item No.13.02 Page No 297 of P.W. (Roads) Schedule of Rates 2015-16
Supplying bending and binding and laying in position steel reinforcement of different dimensions
in cement concrete work i.e. R.C.C., P.S.C. etc.of different components in foundation and in
superstructure including initial straightening, straightening of coils bars, removal of loose rust (if
any), cutting to requisite length bending, binding with annealed wire not less than 1 mm in size
and conforming to IS 280 at every intersection hooked and bent to correct shape and placed on
forms etc. including cost of black annealed wire and cost of loading, unloading, carriage of all steel
materials complete as per drawing and direction of Engineer-in-charge.(a) For M.S. Rounds/Tor
Steel/H.Y.S.D. Bars
= 218.93 x 0.02 x 7.85 = 34.371 MT
7 Item No.13.03 Page No 297 of P.W. (Roads) Schedule of Rates 2015-16
Providing Weep Holes in Brick masonry/ Stone masonry, Plain/ Reinforced concrete abument,
wing wall, return wall with 100mm dia AC pipe extending through the full width of the structures
with slope of 1(V): 20 (H) towards drawing face complete as per drawing
Return wall = 3 x 3 x 6.00 Nos 54.00
Total quantity for 1 no Culvert = 54.000 Nos
8 Item No.14.08 Page No 305 of P.W. (Roads) Schedule of Rates 2015-16
Construction of precast RCC railing of M30 GRCC post not toexceed 1 in 500, centre to centre spacing
betweenvertical post not to exceed 2000 mm, leavingadequate space between vertical post
forexpansion, complete as per approved drawingsand technical specifications.

16.00 X 2.00 = 32.000 M

9 Item No.14.09 Page No 305 of P.W. (Roads) Schedule of Rates 2015-16


Drainage Spouts in Superstructure includingproviding drip mouldings and also includingsupplying,
fitting and fixing approved type ofmaterials complete as per drawing and Technicalspecification vide
clause no. 2705 of MoRT&H’sSpecification for Road & Bridge Works.
2.00 X 2.00 = 4.000 Nos

10 Item No.14.04 Page No 304 of P.W. (Roads) Schedule of Rates 2015-16


Providing and laying Cement concrete Wearingcoat M-30 grade with graded stone chips 19mmdown
including screening and cleaning approvedstone chips and sand as necessary laying, finishingcomplete
to camber and grade, curing with water,including cost and carriage of all materials and hirecharges for
form work including reinforcementcomplete as per drawing and TechnicalSpecifications vide clause no.
2702 of MoRT&H’sSpecification for Road & Bridge Works.
16.00 x 11.50 X 0.075 = 13.800 M3
11 Item No.14.06 Page No 306 of P.W. (Roads) Schedule of Rates 2015-16
Asphaltic Plug jointProviding and laying of asphaltic plug joint toprovide for horizontal movement of 25
mm andvertical movement of 2 mm, depth of joint varyingfrom 75 mm to 100 mm, width varying from
500 mmto 750 mm (in traffic direction), covered with aclosure plate of 200mm x 6mm of
wieldablestructural steel conforming to IS: 2062, asphalticplug to consist of polymer modified bitumen
binder,carefully selected single size aggregate of 12.5 mmnominal size and a heat resistant
foamcaulking/backer rod, all as per approved drawingsand specifications.
1.00 X 11.50 = 11.500 M
12 Item No.12.03 Page No 279 of P.W. (Roads) Schedule of Rates 2015-16
Earth in filling in foundation trenches and at theback of abutments with good earth (sandy soil) in
layers not exceeding 15 cm. including watering andramming layer by layer complete with earthobtained
by fresh excavation from land arrangedby Department beyond 150 m. but within 300 m.including all
lifts. Earth to be approved by theEngineer-in-charge.
= 219.550 M3
13 Item No.8.21 Page No 268 of P.W. (Roads) Schedule of Rates 2015-16
Painting the vertical end faces of posts, wheel guards or railing or parapet with alternate bands of

different colours as directed by the Engineer-in-charge with approved synthetic enamel paint.
Painting in two coats
same as priming area
2.00 x 16.00 X 1.500 = 48.000 M2
Total Cost Rs
Junior Engineer Assistant Engineer
Suri Sub-Division
Section II, PWD PWD
m3

189.000 m3 474.70 89718.00

51.000 m3 780.73 39817.00

658.650 m3 125.24 82489.00


787.100 m3 602.12 473930.00
94.6

585.895 m2 25.00 14647.00

440.261 m3 5897.12 2596273.00


218.925 m3 6384.48 1397722.00

34.371 MT 51288.07 1762834.00


54.000 Nos 127.26 6872.00

32.000 m 1873.55 59954.00

4.000 Nos 907.99 3632.00

13.800 m3 11047.38 152454.00

11.500 m 9973.75 114698.00

219.550 m3 162.61 35701.00

48.000 M2 99.99 4800.00


Total Cost Rs.= 6835541.00
Abstract of cost

Bill of Qty of all Boxes/Culverts :


3M x 3M
Item
Ref SOR Item Description Unit Quantity Rate (Rs) Amount (Rs)
No.

C-1 Item # 2.06(b), Dismantling of existing structures like culverts, bridges,


page - 230, retaining walls and other structures comprising of brick
S.O.R of P.W masonry, including disposal of unserviceable material
(Roads), 2015- and stacking the serviceable material with all lift and
16
lead of 1000 m as per Technical Specifications Clause
202 for Rural Roads of MORD.

iii) Brick masonry in cement mortar cum 3.20 282.80 905.00

C-2 Item # 2.05 II(b), Dismantling of existing structures like culverts, bridges,
page - 230, retaining walls and other structures comprising of brick
S.O.R of P.W masonry, including disposal of unserviceable material
(Roads), 2015- and stacking the serviceable material with all lift and
16
lead of 1000 m as per Technical Specifications Clause
202 for Rural Roads of MORD.

i) Reinforced Cement Concrete


cum 38.80 780.73 30,292.00
C-3 Earthwork in excavation for foundation of structures upto
Ref .Item # 3 m depth as per drawing and technical specification
11.01, Page- Clause 1104 for Rural Roads of MORD including setting
276 of S.O.R of out, construction of shoring and bracing, removal of
P.W (Roads),
stumps and other deleterious matter, dressing of sides
2015-16
and bottom and backfilling with approved material.

I. Ordinary Soil
a) Manual means
i) Depth upto 3.0 metre cum 444.72 105.04 46,713.00

C-4 Ref .Item # Earthwork in filling in foundation trenches with good


12.02, Page- earth in layers not exceeding 15cm. including watering
277 of S.O.R of and ramming layer by layer complete with earth
P.W (Roads), obtained from excavation of foundation or from fresh
2015-16 excavation of land arranged by Department within a lead
of 150 m.
cum 125.10 92.92 11,624.00

C-5 Ref .Item # Sand filling in foundation trenches and at the back of
12.04, Page- abutments, wing-walls etc. with good local sand free
280 of S.O.R of from earth in layers not exceeding 15 cm. including
P.W (Roads), inundating each layer by profuse water and poking and
2015-16
ramming layer by layer complete including supply of
sand. Quality of sand is to be approved by the Engineer-
in-charge.

cum 269.62 602.97 162,570.00


Abstract of cost

Item
Ref SOR Item Description Unit Quantity Rate (Rs) Amount (Rs)
No.

C-6 It- 18.07(a), P- Providing and laying Design Mix concrete for plain
322, Chapter 18 concrete work in any part of bridge (excluding bottom
of SOR, 2015- plugging) with coarse aggregates of appropriate nominal
16-15 size and grading, fine aggregate (sand) conforming to
proper grading zone, both of approved quality and
cement, as necessary, including labour, cost and
carriage of all materials and including preparation of
design mix, approval of the same by the Engineer-in-
Charge and cost for quality control, sampling, testing
etc. all complete but excluding cost of labour and
materials for formwork & reinforcement works.

A . PCC Grade M15 cum 53.92 5,060.73 272,897.00


C-7 Ref .Item # Hire and labour charges for Shuttering with or without
18.05, Page- staging upto 4.0 m height using approved stout props
322 of S.O.R with wooden planks/ply wood/steel sheet plate with
of P.W required bracing for any kind of plain or reinforced
(Roads), 2015- concrete works in all sorts of minor structure including
2016 culvert, box culvert, cross-drain etc. The rate is inclusive
of fitting, fixing and striking out after completion of work Sqm 16.94 216.14 3660.00
as per specification and direction. Where staging is not
required.

C-8 Ref .Item # Plain Cement Concrete in Substructure with coarse


13.01 A (i), aggregates of appropriate nominal size and grading, fine
page-295 of aggregate (sand) conforming to proper grading zone,
S.O.R of P.W both of approved quality, cement and water reducing
(Roads) D,
admixtures, as necessary, including labour, cost and
2015-16
carriage of all materials and including preparation of
design mix, approval of the same by the Engineer-in-
Charge and cost for quality control, sampling, testing
etc. all complete as per drawing and technical
specification including the cost of necessary form work
and staging complete as per drawing and technical
specifications.

A . PCC Grade M20 cum 62.16 6,510.28 404,650.00


Abstract of cost

Item
Ref SOR Item Description Unit Quantity Rate (Rs) Amount (Rs)
No.

C-9 Ref .Item # Furnishing and Placing Reinforced Cement concrete in


14.01B II (i) (a), Super-structure with pakur coarse aggregates of
page-301 of appropriate nominal size and grading, fine aggregate
S.O.R of P.W (coarse sand) conforming to proper grading zone, both
(Roads) D,
of approved quality and cement and admixtures, as
2015-16
necessary, including labour, cost and carriage of all
materials and including preparation of design mix,
approval of the same by the Engineer-in-Charge and
cost for quality control, sampling, testing etc. all
complete as per drawing and technical specification
including the cost of necessary form work and staging
complete. as per drawing and technical specifications.

cum 306.78 7,109.50 2,181,069.00


RCC Grade M25 (Using Batching Plant)

C-10 Ref Item # 8.13, Provision of an Reinforced cement concrete crash


page-266 S.O.R barrier at the edges of the road, approaches to bridge
of P.W (Roads), structures and medians, constructed with reinforced
2015-16 cement concrete with HYSD reinforcement conforming
to IRC:21 and dowel bars 25 mm dia, 450 mm long at
expansion joints filled with pre-moulded asphalt filler
board, keyed to the structure on which it is built and
installed as per design given in the enclosure to MOST
circular No. RW/NH - 33022/1/94-DO III dated 24 June
1994 as per dimensions in the approved drawing and at
locations directed by the Engineer-in-Charge, all as
specified.

R/M 35.48 3,831.56 135,944.00


RCC Grade M30 (Using Batching Plant )

C-11 Ref .Item # Supplying, fitting and placing HYSD bar reinforcement in
14.03, page-304 Bridge Super-structure including initial straightening,
of S.O.R of P.W straightening of coils bars, removal of loose rust (if any),
(Roads), 2015- cutting to requisite length bending, binding with
16
annealed wire not less than 1 mm in size and
conforming to IS 280 at every intersection hooked and
bent to correct shape and placed on forms etc. including
cost of black annealed wire and cost of loading,
unloading, carriage of all steel materials complete as per
drawing and technical specifications.
iii) Superstructure MT 46.02 65,311.39 3,005,456.00

C-12 Ref Item # Providing weep holes in Brick masonry / Plain /


13.03, page-297 Reinforced concrete abutment, wing wall / return wall
S.O.R of P.W with 100 mm dia AC pipe, extending through the full
(Roads), 2015- width of the structure with slope of 1V:20H towards
16
drawing face. Complete as per drawing and Technical
specifications.
Nos 46.00 127.26 5,854.00
Abstract of cost

Item
Ref SOR Item Description Unit Quantity Rate (Rs) Amount (Rs)
No.

C-13 Item. 8.21 (b), Painting the vertical end faces of posts, wheel guards or
page-268 of P railing or parapet with alternate bands of different
W (Roads) colours as directed by the Engineer-in-charge with
SOR, 2015-16 approved synthetic enamel paint.
sq m 86.50 99.99 8,649.00

C-14 Item. 15.09, Construction of flexible apron 0.75 m thick comprising of


page-309 of P loose stone boulders weighing not less than 40 kg
W (Roads) beyond curtain wall.
SOR, 2015-16 cum 54.45 2,099.18 114,294.00

Total Cost of Culvert = Rs. 6,384,577.00

for 2 nos culvert = 12769154.00


3 x 3.00 x 3.00 RCC Box Culvert

Width of Culvert = 12.900 m


No. of Cells in the Culvert = 3 nos
Span of culvert (a) = 3.000 m
Clear Height of Culvert (b) = 3.000 m
Haunch width = 0.250 m
Haunch height = 0.250 m
Thickness of top slab (d) = 0.450 m
Thickness of bottom slab (e) = 0.500 m
Thickness of internal wall (g) = 0.400 m
Thickness of outer wall (f) = 0.470 m
Thickness of PCC = 0.150 m
Extended length of base slab (c) = 0.300 m
Length of Return Wall (M) = 2.980 m
Height of Return Wall (overall) (H) = 2.774 m
Base width of Return Wall (W) = 2.600 m
Breadth/
Sl. Length Height Unit
Description of Item Nos. Thickness Quantity
No. (m) (m) (cum)
(m)
Dismantling of existing structures like culverts, bridges, retaining walls and other structures
comprising of brick masonry, including disposal of unserviceable material and stacking the
C-1
serviceable material with all lift and lead of 1000 m as per Technical Specifications Clause 202 for
Rural Roads of MORD.

Masonary Work (Head wall &


a)
Perapet Wall) 2 2 0.4 2 cum 3.20

Dismantling of existing structures like culverts, bridges, retaining walls and other structure
comprising of masonry, cement concrete, steel work, including T&P and scaffolding wherever
C-2 necessary, sorting the dismantled material, disposal of unserviceable material and stacking the
serviceable material with all lifts and lead of 1000 m as per Technical Specifications Clause 202
for Rural Roads of MORD.
By Mechanical Means
b) Reinforced Cement Concrete 2 8.5 1.5 0.9 cum
22.95
2 6.6 6.9 0.3 cum
27.32
50.27
Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and
technical specification Clause 1104 for Rural Roads of MORD including setting out, construction
C-3
of shoring and bracing, removal of stumps and other deleterious matter, dressing of sides and
bottom and backfilling with approved material.

(i) Box 1 10.50 10.94 cum1.300 149.33


(ii) Lugs 2 (0.75+1.2)/2 10.94 cum1.270 27.09
(iii) Return Wall 4 2.980 2.60 cum2.750 85.23
(iv) Below Curtain Wall D/S 1 7.50 1.85 cum2.65 36.77
U/S 1 7.10 1.85 cum2.65 34.81
(v) Toe Wall D/S 2 4.00 1.50 cum1.65 19.80
U/S 2 4.50 1.50 cum1.65 22.28
Total cum 375.30
Earthwork in filling in foundation trenches with good earth in layers not exceeding 15cm.
including watering and ramming layer by layer complete with earth obtained from excavation of
C-4 foundation or from fresh excavation of land arranged by Department within a lead of 150 m.

1/3 th of earthwork in excavation


= (1/3) x 375.30 = 125.10
vide Item No.3
Total cum 125.10

527760572.xlsx / Qty_3x3.0x3.0
Breadth/
Sl. Length Height Unit
Description of Item Nos. Thickness Quantity
No. (m) (m) (cum)
(m)
Sand filling in foundation trenches and at the back of abutments, wing-walls etc. with good local
sand free from earth in layers not exceeding 15 cm. including inundating each layer by profuse
C-5
water and poking and ramming layer by layer complete including supply of sand. Quality of sand
is to be approved by the Engineer-in-charge.
Back of outer vertical wall 3 12.90 1.50 2.50 cum 145.13
In foundation of Box 1 15.10 10.94 0.50 cum 82.60
In foundation of Rigid Apron D/S 1 (6.3+7.5)/2 2.00 0.45 cum 6.21
U/S 1 (6.3+7.1)/2 1.00 0.45 cum 3.02
In foundation of Flexiable Apron
1 (7.5+13.5)/2 2.995 0.45 cum 14.15
D/S
U/S 1 (7.1+13.5)/2 3.995 0.45 cum 18.52
Total cum 269.62

Providing and laying Design Mix concrete for plain concrete work in any part of bridge (excluding
bottom plugging) with pakur coarse aggregates of appropriate nominal size and grading, fine
aggregate (coarse sand) conforming to proper grading zone, both of approved quality and
C-6 cement, as necessary, including labour, cost and carriage of all materials and including
preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality
control, sampling, testing etc. all complete but excluding cost of labour and materials for
formwork & reinforcement works.
PCC M-15 grade concrete.
Below the box 1 15.10 10.94 0.15 cum 24.78
Below the Return Wall 4 2.980 2.60 0.15 cum 4.65
Below approach Slab 2 12.90 3.50 0.15 cum 13.55
Below Curtain Wall D/S 1 7.50 1.85 0.15 cum 2.08
U/S 1 7.10 1.85 0.15 cum 1.97
For Bottom of Rigid Apron D/S 1 (6.3+7.5)/2 2.00 0.15 cum 2.07
U/S 1 (6.3+7.1)/2 1.00 0.15 cum 1.01
Below Toe Wall D/S 2 4.00 1.50 0.15 cum 1.80
U/S 2 4.50 1.50 0.15 cum 2.03
Total cum 53.92
Hire and labour charges for Shuttering with or without staging upto 4.0 m height using approved
stout props with wooden planks/ply wood/steel sheet plate with required bracing for any kind of
C-7 plain or reinforced concrete works in all sorts of minor structure including culvert, box culvert,
cross-drain etc. The rate is inclusive of fitting, fixing and striking out after completion of work as
per specification and direction. Where staging is not required.

Nos Length (m) Width (m)


Depth (m) Area
Below the box 2 15.10 0.15 4.53
2 10.94 0.15 3.28
Below the Return Wall 4 2.98 0.15 1.79
Below approach Slab 2 12.90 0.15 3.87
Below Curtain Wall D/S 1 7.50 0.15 1.13
U/S 1 7.10 0.15 1.07
Below Toe Wall D/S 1 4.00 0.15 0.60
U/S 1 4.50 0.15 0.68
Total Area Sqm 16.94
Plain Cement Concrete in Substructure with coarse aggregates of appropriate nominal size and
grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality,
cement and water reducing admixtures, as necessary, including labour, cost and carriage of all
C-8 materials and including preparation of design mix, approval of the same by the Engineer-in-
Charge and cost for quality control, sampling, testing etc. all complete as per drawing and
technical specification including the cost of necessary form work and staging complete as per
drawing and technical specifications.
PCC M-20 grade Using concrete mixture
PCC for Curtain Wall D/S 1 7.50 1.65 0.55 cum 6.81
1 7.50 1.30 0.85 cum 8.29
1 7.50 0.75 0.75 cum 4.22
1 7.50 0.45 0.75 cum 2.53
1 7.50 0.20 0.45 cum 0.68
U/S 1 7.10 1.65 0.55 cum 6.44
1 7.10 1.30 0.85 cum 7.85
1 7.10 0.75 0.75 cum 3.99
1 7.10 0.45 0.75 cum 2.40
2 7.10 0.20 0.45 cum 1.28
527760572.xlsx / Qty_3x3.0x3.0
Breadth/
Sl. Length Height Unit
Description of Item Nos. Thickness Quantity
No. (m) (m) (cum)
(m)
For Toe Wall D/S 2 4.00 1.30 0.50 cum 5.20
2 4.00 0.45 0.60 cum 2.16
2 4.00 0.30 0.40 cum 0.96
U/S 2 4.50 1.30 0.50 cum 5.85
2 4.50 0.45 0.60 cum 2.43
2 4.50 0.30 0.40 cum 1.08
Total cum 62.16

527760572.xlsx / Qty_3x3.0x3.0
Breadth/
Sl. Length Height Unit
Description of Item Nos. Thickness Quantity
No. (m) (m) (cum)
(m)
Furnishing and Placing Reinforced Cement concrete in Super-structure with pakur coarse
aggregates of appropriate nominal size and grading, fine aggregate (coarse sand) conforming to
proper grading zone, both of approved quality and cement and admixtures, as necessary,
C-9 including labour, cost and carriage of all materials and including preparation of design mix,
approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing
etc. all complete as per drawing and technical specification including the cost of necessary form
work and staging complete. as per drawing and technical specifications.

RCC M-25 Grade Using concrete mixture


Box Culvert
Base Slab 1 10.50 14.19 0.50 cum 74.50
Lugs 2 (1.2+0.3)/2 14.19 0.82 cum 17.45
Vertical Walls 2 12.90 0.47 3.00 cum 36.38
2 12.90 0.40 2.00 cum 20.64
Top Slab 1 12.90 10.74 0.45 cum 62.35
2 12.90 0.30 0.30 cum 2.32
2 12.90 0.30 0.15 cum 1.16
Haunch 8 12.90 0.25 0.25 cum 6.45
Footpath 2 17.74 0.75 0.20 cum 5.32
Approach Slab 2 12.90 3.50 0.30 cum 27.09
Return Wall 4 2.980 0.60 (0.3+0.6)/2 cum 3.22
4 2.980 1.65 (0.3+0.6)/2 cum 8.85
4 2.980 0.25 0.60 cum 1.79
4 2.980 (0.2+0.25)/2 2.524 cum 6.77
Total cum 306.78
Supplying, fitting and placing HYSD bar reinforcement in Bridge Super-structure including initial
straightening, straightening of coils bars, removal of loose rust (if any), cutting to requisite
length bending, binding with annealed wire not less than 1 mm in size and conforming to IS 280
C-10 at every intersection hooked and bent to correct shape and placed on forms etc. including cost of
black annealed wire and cost of loading, unloading, carriage of all steel materials complete as per
drawing and technical specifications.

Reinforcement @ 150 kg/cum for 306.78 Cum RCC MT 46.02

527760572.xlsx / Qty_3x3.0x3.0
Breadth/
Sl. Length Height Unit
Description of Item Nos. Thickness Quantity
No. (m) (m) (cum)
(m)
Providing weep holes in Brick masonry / Plain / Reinforced concrete abutment, wing wall /
C-11 return wall with 100 mm dia AC pipe, extending through the full width of the structure with slope
of 1V:20H towards drawing face. Complete as per drawing and Technical specifications.
Abutment Wall 1 x 2 x 11 No. 22.00
Return Wall 4x2x3 No. 24.00
No. 46.00
Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches to
bridge structures and medians, constructed with M-30 grade concrete with HYSD reinforcement
conforming to IRC:21 and dowel bars 25 mm dia, 450 mm long at expansion joints filled with
C-12 pre-moulded asphalt filler board, keyed to the structure on which it is built and installed as per
design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June
1994 as per dimensions in the approved drawing and at locations directed by the Engineer-in-
Charge, all as specified.
2 17.74 m 35.48
Painting the vertical end faces of posts, wheel guards or railing or parapet with alternate bands
C-13
of different colours as directed by the Engineer-in-charge with approved synthetic enamel paint.
2x2 17.74 0.90 sqm 63.86
1x2 17.74 0.30 sqm 21.29
2 x 2 (0.30+0.90)/2 0.90 sqm 1.35
Total sqm 86.50
Construction of flexible apron 0.75 m thick comprising of loose Laterite boulders weighing not
C-14
less than 40 kg beyond curtain wall.
D/S 1 (7.5+13.5)/2 2.995 0.75 cum 23.59
U/S 1 (7.1+13.5)/2 3.995 0.75 cum 30.86
Total cum 54.45

527760572.xlsx / Qty_3x3.0x3.0
Analysis of Rate :
Bridge Works

C-0 Rate Analysis : Bridge Works


ITEM
ITEM DESCRIPTION
NO.
C-1 Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry, including
disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical
Specifications Clause 202 for Rural Roads of MORD.
Unit : cum Item # 2.06(b), page - 230, S.O.R of P.W (Roads), 2015-16
iii) Brick masonry in cement mortar
i) Basic cost Rs.280.00
ii) Labour Wellfare Cess @ 1% of (i) Rs.2.80
Total (i+ii) = Rs.282.80

C-2 Dismantling of existing structures like culverts, bridges, retaining walls and other structures comprising of brick masonry, including
disposal of unserviceable material and stacking the serviceable material with all lift and lead of 1000 m as per Technical
Specifications Clause 202 for Rural Roads of MORD.

Unit : cum Item # 2.05 II(b), page - 230, S.O.R of P.W (Roads), 2015-16
i) Reinforced Cement Concrete
i) Basic cost Rs.773.00
ii) Labour Wellfare Cess @ 1% of (i) Rs.7.73
Total (i+ii) = Rs.780.73

C-3 Earthwork in excavation for foundation of structures upto 3 m depth as per drawing and technical specification Clause 1104 for
Rural Roads of MORD including setting out, construction of shoring and bracing, removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with approved material.
Ref .Item # 11.01, Page-276 of S.O.R of P.W (Roads), 2015-16
(a) Depth of excavation upto 3m
(iii) Without pumping out water but including shoring as required.
a) Rate per cum = Rs.104.00
b) Wellfare Cess @ 1% of (d) Rs.1.04
Total (a+b) = Rs.105.04

C-4 Earthwork in filling in foundation trenches with good earth in layers not exceeding 15cm. including watering and ramming layer by
layer complete with earth obtained from excavation of foundation or from fresh excavation of land arranged by Department within a
lead of 150 m.
Ref .Item # 12.02, Page-277 of S.O.R of P.W (Roads), 2015-16
a) Rate per cum = Rs.92.00
b) Wellfare Cess @ 1% of (d) Rs.0.92
Total (a+b) = Rs.92.92

C-5 Sand filling in foundation trenches and at the back of abutments, wing-walls etc. with good local sand free from earth in layers not
exceeding 15 cm. including inundating each layer by profuse water and poking and ramming layer by layer complete including
supply of sand. Quality of sand is to be approved by the Engineer-in-charge.…..
Ref .Item # 12.04, Page-280 of S.O.R of P.W (Roads), 2015-16
a) Cost of Labour. 177.00
b) Cost of material (ref carriage analysis)
Description Unit Qty. Rate (Rs.) Cost (Rs.)
Fine Sand cum 1.20 350.00 420.00
Total cost of material = Rs.420.0
c) Sub Total (a+b) = Rs.597.0
d) Wellfare Cess @ 1% of (c) Rs.5.97
Total (c+d) = Rs.602.97
Say , Rs.602.97
Analysis of Rate :
Bridge Works

ITEM
ITEM DESCRIPTION
NO.
C-6 Providing and laying Design Mix concrete for plain concrete work in any part of bridge (excluding bottom plugging) with coarse
aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved
quality and cement, as necessary, including labour, cost and carriage of all materials and including preparation of design mix,
approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete but excluding cost
of labour and materials for formwork & reinforcement works.

PCC M-15 grade concrete.


Unit : cum
It- 18.07(a), P-322, Chapter 18 of SOR, 2015-16-15
a) Cost of Labour , T& P Machineries etc. Rs.1,425.00
b) Cost of material (ref carriage analysis)
Description Unit Qty. Rate (Rs.) Cost (Rs.)
22.4 mm stone chips cum 0.54 1186.25 640.58
11.2 mm stone chips cum 0.36 1021.25 367.65
Cement Kg 350 7.364 2577.40
Total cost of material = Rs.3,585.63
c) Sub Total (a+b) = Rs.5,010.63
d) Wellfare Cess @ 1% of (c) Rs.50.11
Total (c+d) = Rs.5,060.73
Say , Rs.5,060.73

Hire and labour charges for Shuttering with or without staging upto 4.0 m height using approved stout props with wooden
planks/ply wood/steel sheet plate with required bracing for any kind of plain or reinforced concrete works in all sorts of minor
C-7
structure including culvert, box culvert, cross-drain etc. The rate is inclusive of fitting, fixing and striking out after completion of work
as per specification and direction. Where staging is not required.
Unit : Sqm
Ref .Item # 18.05, Page-322 of S.O.R of P.W (Roads), 2015-2016
i) Basic cost including cost of material & labour = Rs.214.0
ii) Welfare Cess @ 1% Rs.2.14
Total (I + ii) = Rs.216.14

C-8 Plain Cement Concrete in Substructure with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand)
conforming to proper grading zone, both of approved quality, cement and water reducing admixtures, as necessary, including
labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge
and cost for quality control, sampling, testing etc. all complete as per drawing and technical specification including the cost of
necessary form work and staging complete as per drawing and technical specifications.…..

A . PCC Grade M20


Unit : cum
Ref .Item # 13.01 A (i), page-295 of S.O.R of P.W (Roads) D, 2015-16
a) Cost of Labour , T& P Machineries etc. Rs.2,492.00
b) Cost of material (ref carriage analysis)
Description Unit Qty. Rate (Rs.) Cost (Rs.)
22.4 mm stone chips cum 0.54 1186.25 640.58
11.2 mm stone chips cum 0.36 1021.25 367.65
Cement Kg 400 7.364 2945.60
Total cost of material = Rs.3,953.8
c) Sub Total (a+b) = Rs.6,445.83
d) Wellfare Cess @ 1% of (c) Rs.64.46
Total (c+d) = Rs.6,510.28
Say , Rs.6,510.28

C-9 Furnishing and Placing Reinforced Cement concrete in Super-structure with pakur coarse aggregates of appropriate nominal size
and grading, fine aggregate (coarse sand) conforming to proper grading zone, both of approved quality and cement and
admixtures, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of
the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete as per drawing and technical
Unit :
specification cum the cost of necessary form work and staging complete. as per drawing and technical specifications.
including
Ref .Item # 14.01B II (i) (a), page-301 of S.O.R of P.W (Roads) D, 2015-16
RCC Grade M25 (Using Batching Plant)
a) Cost of Labour , T& P Machineries etc. Rs.2,938.00
b) Cost of material (ref carriage analysis)
Description Unit Qty. Rate (Rs.) Cost (Rs.)
22.4 mm stone chips cum 0.54 1186.25 640.58
11.2 mm stone chips cum 0.36 1021.25 367.65
Cement Kg 420 7.364 3092.88
Total cost of material = Rs.4,101.11
c) Sub total (a+d) = Rs.7,039.11
d) Wellfare Cess @ 1% of (c) Rs.70.39
Total (c + d) = Rs.7,109.50
say , Rs.7,109.50
Analysis of Rate :
Bridge Works

ITEM
ITEM DESCRIPTION
NO.
Analysis of Rate :
Bridge Works

ITEM
ITEM DESCRIPTION
NO.
C-10 Provision of an Reinforced cement concrete crash barrier at the edges of the road, approaches to bridge structures and medians,
constructed with reinforced cement concrete with HYSD reinforcement conforming to IRC:21 and dowel bars 25 mm dia, 450 mm
long at expansion joints filled with pre-moulded asphalt filler board, keyed to the structure on which it is built and installed as per
design given in the enclosure to MOST circular No. RW/NH - 33022/1/94-DO III dated 24 June 1994 as per dimensions in the
approved drawing and at locations directed by the Engineer-in-Charge, all as specified.
RCC Grade M30 (Using Batching Plant )
Unit : metre Ref Item # 8.13, page-266 S.O.R of P.W (Roads), 2015-16
a) Basic cost of labour = Rs.1,649.00
b) Cost of material
Description Unit Qty. Rate (Rs.) Cost (Rs.)

RCC M-30 grade concrete cum 0.30 7148.75 2144.62


Total cost of material = Rs.2,144.62
c) Sub total (a+b) = Rs.3,793.62
d) Welfare Cess @ 1% Rs.37.94
Total (I + ii) = Rs.3,831.56

Sub Furnishing and Placing Reinforced Cement concrete in Super-structure with pakur coarse aggregates of appropriate nominal size
Analysis and grading, fine aggregate (coarse sand) conforming to proper grading zone, both of approved quality and cement and
admixtures, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of
the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete as per drawing and technical
specification including the cost of necessary form work and staging complete. as per drawing and technical specifications.

Unit : cum
Ref .Item # 14.01C II (i) (a), page-301 of S.O.R of P.W (Roads) D, 2015-16
RCC Grade M30 (Using Batching Plant)
a) Cost of Labour , T& P Machineries etc. Rs.2,974.00
b) Cost of material (ref carriage analysis)
Description Unit Qty. Rate (Rs.) Cost (Rs.)
22.4 mm stone chips cum 0.54 1186.25 640.58
11.2 mm stone chips cum 0.36 1021.25 367.65
Cement Kg 430 7.364 3166.52
Total cost of material = Rs.4,174.75
Sub total (a+d) = Rs.7,148.75

C-11 Supplying, fitting and placing HYSD bar reinforcement in Bridge Super-structure including initial straightening, straightening of coils
bars, removal of loose rust (if any), cutting to requisite length bending, binding with annealed wire not less than 1 mm in size and
conforming to IS 280 at every intersection hooked and bent to correct shape and placed on forms etc. including cost of black
annealed wire and cost of loading, unloading, carriage of all steel materials complete as per drawing and technical specifications.

Ref .Item # 14.03, page-304 of S.O.R of P.W (Roads), 2015-16


Rate per MT supplied by Contractor:
Basic price (Table-1, 2 (ii), P-214 of S.O.R of P.W (Roads), 2015-16) 39750 x 1.05 = 52395.00
Carriage cost 103 km lead from Durgapur (Table-1, P-227 of S.O.R of
P.W (Roads), 2015-2016) excl. 5% Overhead Charges and 10% 559.3 x 1.05 /1.155 = 609.45
Contractor Profit
Loading & Unloading excl. stacking* (It 1.03 (h), P-224 of SOR P.W (R),
(96x75%)x1.05/1.155 = 65.45
2015-16)
* 75% of the rate is considered as stacking is not required 53069.90
add 5% Overhead Charges 2653.50
add 10% Contractor Profit 5572.34
Item Rate excl. material cost = Rs. 3369.00
64664.74
Add: Labour welfare cess @1% = 646.65
Hence cost per MT = 65311.39
Analysis of Rate :
Bridge Works

ITEM
ITEM DESCRIPTION
NO.
C-12 Providing weep holes in Brick masonry / Plain / Reinforced concrete abutment, wing wall / return wall with 100 mm dia AC pipe,
extending through the full width of the structure with slope of 1V:20H towards drawing face. Complete as per drawing and
Technical specifications.
Unit : each Ref Item # 13.03, page-297 S.O.R of P.W (Roads), 2015-16
i) Basic cost including cost of material & labour = Rs.126.00
ii) Welfare Cess @ 1% 1.26
Total (I + ii) = Rs.127.26

C-13 Painting the vertical end faces of posts, wheel guards or railing or parapet with alternate bands of different colours as directed by
the Engineer-in-charge with approved synthetic enamel paint.
Unit : sqm Item. 8.21 (b), page-268 of P W (Roads) SOR, 2015-16
i) Basic cost including cost of material & labour = Rs.99.00
ii) Welfare Cess @ 1% 0.99
Total (I + ii) = Rs.99.99

C-14 Construction of flexible apron 0.75 m thick comprising of loose stone boulders weighing not less than 40 kg beyond curtain wall.
Unit : metre Item. 15.09, page-309 of P W (Roads) SOR, 2015-16
a) Cost of Labour , T& P Machineries etc. Rs.556.00
b) Cost of material (ref carriage analysis)
Description Unit Qty. Rate (Rs.) Cost (Rs.)
Stone Boulder cum 1.00 1231.75 1231.75
Stone Spulls (37.5 mm) cum 0.20 1453.25 290.65
Total cost of material = Rs.1,522.4
c) Sub Total (a+b) = Rs.2,078.4
d) Wellfare Cess @ 1% of (c) Rs.20.78
Total (c+d) = Rs.2,099.18
Say , Rs.2,099.18