You are on page 1of 77

Analysis of Rates for Engineering Appreciation

NAME OF WORK: Construction of Helipad at Harshil under deposit work of civil Aviation Department.

Height Index :- Up to 1800 - Nil


Height of Harshil = 2487 m
height index from 2001 to 2500m = 4% + 3% on every 100m
Hence Height index for Harshil = 4%+3x(2487-2001)/100 18.58 % Say 19%

Sl. Description of Labour Unit Basic Rate Hieght Total Rate


No. rates inclusive Index Rate Round
of 1/6 19% per day of
holiday i/c H.I.

Blacksmith, Mason, Mistry, Painter, Carpenter, Plumber, Amin,


L-01 Rivetter, Welder, Fitter, Turner, Electrician, Driver, Mechanic. day 200.00 233.33 44.33 277.67 278.00

Beldar, Chaukidar, Waterman, Maali, Mazdoor, Helper, Bhisti,


L-01 day 110.00 128.33 24.38 152.72 153.00
Hammer man.
Hole driller, Rock cutter, White washer, Nepali Labour, Khan
L-01 Labour, Lab Assistant, Cleaner, Work Agent, Mate, day 125.00 145.83 27.71 173.54 174.00
Supervisor, Mixtureand
For T&P sundries Oppreator,
lump sumMachine Oppreator,
item in the Pump
skelton for the
L-01 Oppreator, Generator Oppreator, Cook, Care Taker, Blue
analusis of rates the provision will be made as following.
Printer, Photo Stat Machine Oppreator, Winch Oppreator,
Almora Type Stone Cutter/Dresser, Bitumen Beldar, a
Junior Fitter, LS 25.00
RCC Work
Compressor Oppreator. LS 30.00

Junior Engineer Asistant Engineer Executive Engineer


P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari
Analysis of Rates for Engineering Appreciation
NAME OF WORK: Construction of Helipad at Harshil under deposit work of civil
Aviation Department.

Item : Cement/Steel/Lime
Source Rishikesh
Distance 255 Km. Pucca motor road
Cartage

Distance from the No. of Km. Total Approved Rates For Pucca Add extra Total (e+f)
approved Quarry Cartage of Cartage (Rs.) (bxd) (Rs.) for Kutcha
Distance Kms
(km.)

(a) (b) (c) (d) (e) (f) (g)


1 st km. 1 1.00 42.00 42.00 42.00
2-3rd km. 2 3.00 8.50 17.00 17.00
4-5th km. 2 5.00 6.50 13.00 13.00
6-10th km. 5 10.00 5.50 27.50 27.50
11-20th km. 10 20.00 4.25 42.50 42.50
21-30th km. 10 30.00 3.50 35.00 35.00
31-50th km. 20 50.00 3.00 60.00 60.00
Beyond 50th Km. 205 255.00 2.50 512.50 512.50
Total 749.50

Final Rate for Cartage from Rishikesh: 749.50 /MT.


Total 749.50 /MT.
Final Rate for Cartage of Steel, CGI sheet and lime from
Rishikesh : 74.95 /Qtl.
Say Rs. 75.00 /Qtl.
cartage of cement 37.50 /Bag

Item : Coarse Sand, Fine Sand, 20mm & 40 mm s/ballast


Source Local
Distance 1/2 Km. by Mule

Cartage 1/2 km by mule (1x10)x16 160.00


Final cartage for all item 160.00 Per Cum
Item : Chir Wood
Source Gangori Store
Distance 73 Km. Pucca motor road
Cartage

Distance from the No. of Km. Total Approved Rates For Pucca Add extra Total
approved Quarry Cartage of Cartage (Rs.) (bxd) (Rs.) for Kutcha (e+f)
Distance Kms
(km.)

(a) (b) (c) (d) (e) (f) (g)


1 st km. 1 1.00 77.00 77.00 77.00
2-3rd km. 2 3.00 12.00 24.00 24.00
4-5th km. 2 5.00 11.00 22.00 22.00
6-10th km. 5 10.00 10.00 50.00 50.00
11-20th km. 10 20.00 7.80 78.00 78.00
21-30th km. 10 30.00 7.00 70.00 70.00
31st-50th km 20 50.00 6.60 132.00 132.00
51st-73rd km 23 73.00 5.80 133.40 133.40
Total 586.40

Final Rate for Cartage from Gangori: 586.40 / Cum


Say 586.00 Per Cum

Item : Sal wood / Chir wood


Source Uttarkashi
Distance 73 Km. Pucca motor road
Cartage

Distance from the No. of Km. Total Approved Rates For Pucca Add extra Total
approved Quarry Cartage of Cartage (Rs.) (bxd) (Rs.) for Kutcha (e+f)
Distance Kms
(km.)

(a) (b) (c) (d) (e) (f) (g)


1 st km. 1 1.00 55.00 55.00 55.00
2-3rd km. 2 3.00 8.50 17.00 17.00
4-5th km. 2 5.00 8.00 16.00 16.00
6-10th km. 5 10.00 6.80 34.00 34.00
11-20th km. 10 20.00 5.30 53.00 53.00
21-30th km. 10 30.00 4.70 47.00 47.00
31st-50th km 20 50.00 4.00 80.00 80.00
51st-73rd km 23 73.00 3.50 80.50 80.50
Total 382.50

Final Rate for Cartage from Rishikesh: 382.50 / Cum


Say 383.00 Per Cum

Item : Stone for building work


Source local
Distance 1/2 Km by mule
Cartage (1x10)x20 200.00 Per Cum
Item : Bricks
Source Rishikesh
Distance 255 Km. Pucca motor road
Cartage

Distance from the No. of Km. Total Approved Rates For Pucca Add extra Total (e+f)
approved Quarry Cartage of Cartage (Rs.) (bxd) (Rs.) for Kutcha
Distance Kms
(km.)

(a) (b) (c) (d) (e) (f) (g)


1 st km. 1 1.00 55.00 55.00 55.00
2-3rd km. 2 3.00 8.50 17.00 17.00
4-5th km. 2 5.00 8.00 16.00 16.00
6-10th km. 5 10.00 6.80 34.00 34.00
11-20th km. 10 20.00 5.30 53.00 53.00
21-30th km. 10 30.00 4.70 47.00 47.00
31-50th km. 20 50.00 4.00 80.00 80.00
Beyond 50th Km. 205 255.00 3.50 717.50 717.50
Total 1,019.50

Final Rate for Cartage from Rishikesh: 1,019.50 / Cum


Total 1,019.50 / Cum
Final Rate for Cartage for bricks 1,019.50 x 2.40 2,446.80 / 1000 nos
2.45 / No
Say Rs. 2.40 / No

Item : Stone grit


Source Jwalapur
Distance 277 Km. Pucca motor road.
Cartage

Distance from the No. of Km. Total Approved Rates For Pucca Add extra Total (e+f)
approved Quarry Cartage of Cartage (Rs.) (bxd) (Rs.) for Kutcha
Distance Kms
(km.)

(a) (b) (c) (d) (e) (f) (g)


1 st km. 1 1.00 77.00 77.00 77.00
2-3rd km. 2 3.00 12.00 24.00 24.00
4-5th km. 2 5.00 11.00 22.00 22.00
6-10th km. 5 10.00 10.00 50.00 50.00
11-20th km. 10 20.00 7.80 78.00 78.00
21-30th km. 10 30.00 7.00 70.00 70.00
31-50th km. 20 50.00 6.60 132.00 132.00
Beyond 50th Km. 227 277.00 5.80 1,316.60 1,316.60
Total 1,769.60

Final Rate for Cartage from Rishikesh: 1,769.60 / Cum


Total 1,769.60 / Cum

Item : fuel wood


Source Gangori depot
Distance 78 Km. Pucca motor road.
Cartage

Distance from the No. of Km. Total Approved Rates For Pucca Add extra Total (e+f)
approved Quarry Cartage of Cartage (Rs.) (bxd) (Rs.) for Kutcha
Distance Kms
(km.)

(a) (b) (c) (d) (e) (f) (g)


1 st km. 1 1.00 57.00 57.00 57.00
2-3rd km. 2 3.00 11.00 22.00 22.00
4-5th km. 2 5.00 8.00 16.00 16.00
6-10th km. 5 10.00 7.00 35.00 35.00
11-20th km. 10 20.00 6.00 60.00 60.00
21-30th km. 10 30.00 5.40 54.00 54.00
31-50th km. 20 50.00 4.60 92.00 92.00
Beyond 50th Km. 28 78.00 3.70 103.60 103.60
Total 439.60

Final Rate for Cartage from Rishikesh: 439.60 / Cum


Total 439.60 / Cum

Item : Maxphalt
Source Bhatwari store
Distance 47 Km. Pucca motor road.
Cartage

Distance from the No. of Km. Total Approved Rates For Pucca Add extra Total (e+f)
approved Quarry Cartage of Cartage (Rs.) (bxd) (Rs.) for Kutcha
Distance Kms
(km.)

(a) (b) (c) (d) (e) (f) (g)


1 st km. 1 1.00 57.00 57.00 57.00
2-3rd km. 2 3.00 11.00 22.00 22.00
4-5th km. 2 5.00 8.00 16.00 16.00
6-10th km. 5 10.00 7.00 35.00 35.00
11-20th km. 10 20.00 6.00 60.00 60.00
21-30th km. 10 30.00 5.40 54.00 54.00
31-50th km. 17 47.00 4.60 78.20 78.20
Total 322.20

Final Rate for Cartage from Rishikesh: 322.20 / Cum


Total 322.20 / Cum
cartage cost per drum 322.2x100/156 206.54 per drum
206.54 per drum

Item : Stone ballast for road work


Source local
Distance 1/2 Km by mule
Cartage (1x11)x16 176.00 Per Cum
Analysis of Rates for Engineering Appreciation
NAME OF WORK: Construction of Helipad at Harshil under deposit work of civil Aviation Department.
Block :- Bhatwari Distt: Uttarkashi
Name of Description of material Approved rate at Contractor's Unit Cost of Total of Col. Wastage on Total of Col 7 to 8 Rate rounded to
Quarry quarry (Rs.) Profit @ 10% Cartage No. (3 to 6) Col. No. (3) whole Rs.
1 2 3 4 5 6 7 8 9 10
Local Coarse sand 400.00 40.00 per cum 160.00 600.00 8.00 608.00 608.00
Local Fine/Local sand 350.00 35.00 per cum 160.00 545.00 7.00 552.00 552.00
Stone ballast
Local Stone ballast 20 mm 520.00 52.00 per cum 160.00 732.00 10.40 742.40 742.40
Local Stone ballast 40 mm 390.00 39.00 per cum 160.00 589.00 3.90 592.90 592.90
Rishikesh Cement 237.00 23.70 per bag 37.50 298.20 - 298.20 298.20
Rishikesh R/F steel 4,056.00 405.60 per qtl 75.00 4,536.60 - 4,536.60 4,536.60
Rishikesh M.S.Steel 4,300.00 430.00 per qtl 75.00 4,805.00 - 4,805.00 4,805.00
Rishikesh White lime 600.00 60.00 per qtl 75.00 735.00 - 735.00 735.00
Gangori Chir wood 21,580.00 2,158.00 Per Cum 383.00 24,121.00 - 24,121.00 24,121.00
Gangori Sal Wood 44,435.00 4,443.50 Per Cum 383.00 49,261.50 - 49,261.50 49,261.50
Local Stone building work 300.00 30.00 per cum 200.00 530.00 - 530.00 530.00
Stone site work 250.00 25.00 per cum 200.00 475.00 - 475.00 475.00
Rishikesh CGI sheet 4,400.00 440.00 per qtl 75.00 4,915.00 - 4,915.00 4,915.00
Uttarkashi Paint 195.00 21.50 per litre 4.00 220.50 - 220.50 220.50
Uttarkashi Primer 105.00 11.00 per litre 4.00 120.00 - 120.00 120.00
Rishikesh Bricks 2.40 0.24 Per No 2.40 5.04 - 5.04 5.00
Local stone ballast 45-63 310.00 31.00 per cum 176.00 517.00 3.10 520.10 520.10
Local stone ballast 22.5-50 355.00 35.50 per cum 176.00 566.50 3.55 570.05 570.10
Jwalapur stone grit 13.2mm 425.00 42.50 per cum 1,769.60 2,237.10 8.50 2,245.60 2,245.60
Jwalapur stone grit 11.5 mm 425.00 42.50 per cum 1,769.60 2,237.10 8.50 2,245.60 2,245.60
Jwalapur stone grit 6.7 mm 425.00 42.50 per cum 1,769.60 2,237.10 8.50 2,245.60 2,245.60
Gangori Fuel wood 330.00 33.00 per cum 439.60 802.60 - 802.60 802.60
Bhatwari store Maxphalt 6,000.00 600.00 per cum 206.54 6,806.54 - 6,806.54 6,806.50

1- The shortest route has been adopted in R.M.R.


2- The Quarry rates and cartage rates are as per rates approved by the compotent authority.
3- The Minimum rates as compared to other R.M.R. has been adopted.
4- For Chir wood sawing chareges is 10% of cost - not wastage.

Junior Engineer Assistant Engineer Executive Engineer


Pron. Div. P.W.D. Pron. Div. P.W.D. Pron. Div. P.W.D.
Bhatwari Bhatwari Bhatwari
Analysis of Rates

NAME OF WORK: Construction of Helipad at Harshil under deposit work of civil Aviation Department.

SL. No. Description Unit Quantity Rate Cost

1 Excavation in foundation in all type


of soil i/c lift upto 1.5 m & lead
upto 30 meter & i/c filling,
watering, ramming of excavated
earth into the trenches or in it to
the space between the building &
site of foundation trenches or into
the plinth & removal & disposal of
surplus earth as directed by tje
engineer charge up to a distance of
30 meter from the foundation
trenches.

SOR Sl No- 165A As per schedule 50.00 cum


add height index 19% 9.50
Total 59.50
say 60.00 cum

2 Cement, concrete with 40 mm


gauge locally available approved
stone ballast, coarse sand and
cement in proportion of 12:6:1 in
foundation including cost of
materials, labour, T&P etc. required
for proper completion of the work.

A Materials
40 mm. Stone ballast cum. 0.90 592.90 533.61
Coarse sand cum. 0.50 608.00 304.00
cement Bags 3.46 298.20 1031.77
Total 1869.38
B Labour ( 100 cuft.)
Mistry Per day No. 1/8 278.00 34.75
mason Per day No. 1/3 278.00 92.67
Beldar Per day No. 4 153.00 612.00
coolie Per day No. 6 153.00 918.00
bhisti Per day No. 1 153.00 153.00
Black smith Per day No. 1/8 278.00 34.75
T&P & sundries LS Job. 2 25.00 50.00
1895.17

Page 7 of 77
Analysis of Rates
Add 10% for CP 189.52
Total 2084.68
Rate Per cum. 736.64
Total ( Material + Labour ) 2606.02
Add water charges @ 1.50% 39.09
G total 2645.11
Say 2645.00 per cum

3 Class M-100 brick thick work in 1:6


cement sand mortar in super
structure i/c s/o all material, labour
t&p etc required for proper
completion of the work.

A Material
Cement Bags 1.27 298.20 378.71
F/sand cum. 0.27 552.00 149.04
Bricks No 460 5.00 2300.00
Total 2827.75
B Labour
Mistri Per day No. 1/6 278.00 46.33
Mason Per day No. 3 278.00 834.00
Beldar Per day No. 2 153.00 306.00
Coolie Per day No. 3 153.00 459.00
Bhisti Per day No. 1/2 153.00 76.50
T&P Sundries Per day L.S. 2.25 25.00 56.25
Total 1778.08
add 10% C.P. 177.81
Total 1955.89
Labour Rate per Cum 1,955.89 / 2.83 691.13
(Material+Labour) 2827.75 + 691.13 3518.88 Per Cum
Add 1.5% Water Allowance 52.78 Per Cum
G. Total 3571.67 Per Cum
Say 3572.00 Per Cum

4 Same as above item but half brick


thick wall n super structure i/c
cutting & moulding of brick.

A Material
Cement Bags 1.27 278.00 353.06
F/sand cum. 0.27 552.00 149.04
Bricks No 460 5.00 2300.00
Total 2802.10
B Labour
Mistri Per day No. 1/6 278.00 46.33
Mason Per day No. 4 278.00 1112.00
Beldar Per day No. 2 153.00 306.00
Coolie Per day No. 4 153.00 612.00
Bhisti Per day No. 1/2 153.00 76.50
T&P Sundries Per day L.S. 2.25 25.00 56.25
Total 2209.08
add 10% C.P. 220.91
Total 2429.99
Labour Rate per Cum 2,429.99 / 2.83 858.65
(Material+Labour) 2802.10 + 858.65 3660.75 Per Cum
Add 1.5% Water Allowance 54.91 Per Cum
G. Total 3715.67 Per Cum

Page 8 of 77
Analysis of Rates
Say 3716.00 Per Cum

5 Reinforced cement concrete in


proportion of 1:1.5:3 (M-20) in
cement, coarse sand and 20mm
gauge stone grit as per
specification and drawing including
cost of material, labour, T&P etc.
required for proper completion of
the work. Raft, column & lintel.

Materials for 1.00 cum


20 mm. Stone ballast cum. 0.85 742.40 631.04
Coarse sand cum. 0.425 608.00 258.40
cement Bags 8.68 298.20 2588.38
Total 3477.82
Add 2.5% wastage on cement and
coarse sand 71.17
Total 3548.99
Labour ( 100 cuft.)
Mistry Per day No. 1/10 278.00 27.80
mason Per day No. 1/4 278.00 69.50
Beldar Per day No. 4 153.00 612.00
coolie Per day No. 8 153.00 1224.00
bhisti Per day No. 2 153.00 306.00
Black smith Per day No. 1/10 278.00 27.80
T&P & sundries LS Job. 2 25.00 50.00
Extra labour Black smith for
binding and fixing reinforcement Per day No. 2 562.00 1124.00
cost of binding wire LS Job. 28 30.00 840.00
Cost of centering, etc with extra
labour LS Job. 28 30.00 840.00
5121.10
Add 10% for CP 512.11
Total 5633.21
Rate Per cum. 1990.53
Total ( Material + Labour ) 5539.52
Add water charges @ 1.50% 83.09
G total 5622.61
Say 5623.00 per cum

6 Same as above item no-5 but in


roof slab & roof beams.
rate as per above item 5623.00 per cum
add cost of shuttering & centering
etc LS Job. 14.126 30.00 423.78
Total 6046.78
Say 6047.00 per cum

7 2.5 cm thick 1:2:4 cement concrete


floor with 7.5 cm thick 1:6:12 base
concrete with c/sand & 20 mm
gauge s/ballast i/c s/o all m/l , t&p
etc required for proper completion
of the work.

A Material (for one sqm)

Page 9 of 77
Analysis of Rates
Cement with floating coat Bags 0.195 298.20 58.15
C/sand cum. 0.0110 608.00 6.69
20 mm s/ballast cum. 0.02 742.40 14.85
Total 79.69
B Labour for 100 sqft
Mistri Per Day No 1/8 278.00 34.75
Mason Per Day No 1 278.00 278.00
Beldar Per Day No 1/2 153.00 76.50
Coolie Per Day No 1/2 153.00 76.50
Bhisti Per Day No 1/4 153.00 38.25
t&p sundries L.S. 1.25 25 31.25
Total 535.25
Labour Rate per Sqm 535.25 / 100 x 10.764 57.61
Total of A+B 137.30
Add 10% C.P. 13.73
Total 151.03
Add 7.5 cm thick CC 1:6:12 0.075 Cum @ 2645.00 198.38
Total 349.40
Add 1.5% Water Allowance 5.24
G.Total 354.65 Per Sqm
Say 355.00 Per Sqm

8 Same as above but 4cm thick


without base concrete.
A Material (for one sqm)
Cement with floating coat Bags 0.027 298.20 8.05
C/sand cum. 0.0170 608.00 10.34
20 mm s/ballast cum. 0.034 742.40 25.24
Cement Bag 0.264 298.20 78.72
Total 122.35
B Labour for 100 sqft
Mistri Per Day No 1/8 278.00 34.75
Mason Per Day No 1+1/4 278.00 347.50
Beldar Per Day No 1/2 153.00 76.50
Coolie Per Day No 1/2 153.00 76.50
Bhisti Per Day No 1/3 153.00 51.00
t&p sundries L.S. 1.25 25 31.25

Page 10 of 77
Analysis of Rates
Total 617.50
Labour Rate per Sqm 617.50 / 100 x 10.764 66.47
Total of A+B 188.82
Add 10% C.P. 18.88
Total 207.70
Add 1.5% Water Allowance 3.12
G.Total 210.82 Per Sqm
Say 211.00 Per Sqm

9 20 mm thick plaster with 1:2


cement & fine sand on dado or
skirting laid in panels finished with
3mm floating coat of cement i/c
s/o all material, labour, t&p etc
required for proper completion of
the work.

A Material
Cement Bag 2.25 298.20 670.95
F/sand Cum 0.17 552.00 93.84
Total 764.79
B Labour
Mason Per day No 1-1/4 278.00 347.50
Coolie Per day No 1-1/4 153.00 191.25
Bhisti Per day No 3/8+1/10 153.00 72.68
T&P sundies L.S. 1.00 25.00 25.00
Total 636.43
add 10% C.P. 63.64
Total B Total 700.07
Total of A+B 1464.86
Rate per Sqm 1464.86 / 9.29 157.68
Add 1.5% W.A. 21.97
G.Total 179.65
Say 180.00 Per Sqm

10 P/F of 25mm wide & 4.8 mm thick


glass strip i/c s/o all m/l, t&p etc
required for proper completion of
the work.

A Material (for 144 Rft)


25 mm wide & 3 mm thick glass strip 144 / 3.28 43.90 15.00 658.54
Add brakage 10% 65.85
Add C.P. 10% 65.85
Add cartage L.S. 5.00
Total 795.24
B Labour (for 43.90 Rmt).
Mason Per day No 1 278.00 370.67
Beldar Per day No 1/2 153.00 76.50
T&P sundies L.S. 1.00 25.00 25.00
Total 472.17
Add 10% C.P. 47.22
Total 519.38
Total of A+B 795.24 + 519.38 1314.63
Hence rate per Rmt 1314.63 / 43.90 29.95
G.Total 29.95
Say 30.00 Per Rmt

Page 11 of 77
Analysis of Rates
11 12 mm thick plaster in 1:6 cement,
sand mortar i/c s/o all m/l, t&p etc
required for proper completion of
the work.

A Material
Cement Bag 0.078 298.20 23.26
F/sand Cum 0.0165 552.00 9.11
Total 32.37
B Labour
Mason Per day No 1-1/3 278.00 370.67
Beldar Per day No 1+1/2 153.00 229.50
Coolie Per day No 1+1/3 153.00 204.00
Bhisti Per day No 1/2 153.00 76.50
T&P sundies L.S. 1.00 25.00 25.00
Total 905.67
add 10% C.P. 90.57
Total B Total 996.23
Total of A+B 1028.60
Rate per Sqm 1028.60 / 9.29 110.72
Add 1.5% W.A. 1.66
G.Total 112.38
Say 112.00 Per Sqm

12 Same as above item but extra over


rough face of one brick wall.

A Material
extra cost of cement L.S. 1.15 x 25.00 28.75
B Labour
Mason Per day No 1/8 278.00 34.75
Coolie Per day No 1/8 153.00 19.13
53.88
Add 10% C.P. 5.39
59.26
Total of A+B 28.75 + 59.26 88.01
rate for one Sqm 88.01 / 9.29 9.47 Per Sqm
Say 9.00 Per Sqm
13 Add extra labour & material for
making grooves line in plaster on
outer face of wall & joint between
RCC roof & walls i/c all labour,
material, t&p etc required for
proper completion of the work.

assume that 1 no mason & 1 beldar make 30.00m long groove.


mason per day no 1.00 278.00 278.00
Beldar per day no 1.00 153.00 153.00
Total 431.00
add 10% C.P. 43.10
G.Total 474.10
Rate per Rmt 474.10 / 30 15.80 Per Rmt
Say 16.00 Per Rmt

Page 12 of 77
Analysis of Rates
14 Add extra labour & material for
making of drip course (20x30mm)
in projection of roof & sun shade.
Completion as per direction of EIC.

Assuming that the following labour will make 20 m length.


mason per day no 1 278.00 278.00
beldar per day no 1 153.00 153.00
coolie per day no 1 153.00 153.00
cost of material L.S. 1 30.00 30.00
Total 614.00
Rate per mtr 614.00 / 20 30.70
Say 31.00 Per mtr

15 Rendering of roof slab with 1:3


cement & coarse sand mortar 6
mm thick just after RCC slab i/c all
material, labour, t&p etc required
for proper completion of the work.

A For 6mm thick plaster & 3mm thick floating coat of neat cement
Cement Bag 0.96 298.20 286.27
Coarse sand cum 0.07 608 42.56
Total 328.83
B Labour
Mason Per day No 3/4+1/4 278.00 278.00
Coolie Per day No 3/4+1 153.00 267.75
Bhisti Per day No 3/8+1/4 153.00 95.63
Total 641.38
Add 10% C.P. 64.1375
G.Total 705.51
Total of A+B 328.83 + 705.51 1,034.34
Hence Rate per Sqm 1034.34 / 100 x 10.764 111.34 Per Sqm
Say 111.00 Per Sqm

16 Finishing of walls with water proof


cement paint with two coats to
given shades i/c s/o all m/l, t&p etc
all complete.

A Material
Durocem Kg 3.40 48.50 164.90
B Labour
Painter Per day No 3/10 278.00 83.40
Coolie Per day No 3/10 153.00 45.90
Bhisti Per day No 3/8 153.00 57.38
Sundries, T&P L.S. 0.40 25.00 10.00
Total 196.68
Add 10% C.P. 19.67
Total B 216.34
Total of A+B 381.24
Hence Rate Per Sqm 381.24 / 100 x 10.764 41.04
Say 41.00 Per Sqm

Page 13 of 77
Analysis of Rates
17 Painting on new iron works with
two coats of approved paint
including cost of supply of all
materials, labour, T&P etc. required
for proper completion of the work
as per direction of Engineer-in-
charge.

Painting I & II coat ( 100 Sqft.)


A Material
Anticorosive Metal Primer Liter 0.075 120.00 9.00
Paint (0.066+0.058) = 0.124 Lit Liter 0.124 220.50 27.34
Total 36.34 Per Sqm
Labour (for 100.00 Sqft) :-
Painter Per day No. 1+1/3 278.00 370.67
Coolie Per day No. 1+1/3 153.00 204.00
Total 574.67
Add brushes & T&P L.S. 0.50 25.00 12.50
Total 587.17
add 10% for C.P. 58.72
Total 645.88
Labour for one Sqm 645.88 / 100 x 10.764 69.52 Per Sqm
Total of A+B 105.86 Per Sqm
Say 106.00 Per Sqm

18 Supply & fixing of security grill over


window as per drawing or as per
instruction of engineer in charge i/c
welding & supply of all materails,
labours, t&p etc required for
proper completion of the work.

Taking size 1.20x 1.00 m = 1.20 Sqm


A Material
flat iron 14.80 kg 48.05 711.14
fabrication & welding 1.00 L.S. 150.00 150.00
cartage 1 L.S. 50.00 50.00
Total 911.14
Rate per Sqm 911.14 / 1.20 759.28
Say 759.00 Per Sqm

19 S/F of Galavanized mosquito proof


wire mesh over window with chir
wood beading i/c s/o all m/l t&p
etc required for proper completion
of the work.

Rate of wire gauge as per market 150.00


add 10% C.P. 15.00
Total 165.00
Add fixing charges L.S. 15.00
Total 180.00 Per Sqm
Say 180.00 Per Sqm

Page 14 of 77
Analysis of Rates
20 Supply & fixing of heavy quality
oxidized iron fitting for door &
window with necessary ms hinges,
steel screw, nut, bolts & other
material as per requirement.

Taking size 1.20x2.05m = 2.46 Sqm


10 cm long hing - 3x2 = 6 no market rate 6 no 10.00 60.00
10 cm long tower bolt = 2 no 2 no 15.00 30.00
16 cm long sliding bolt = 1 no 1 no 60.00 60.00
hing for cleat = 1x2 = 2 no 2 no 15.00 30.00
handle with plate - 1x2 = 2 no 2 no 15.00 30.00
nut & bolts 1 L.S. 15.00 15.00
Total 225.00
Add 10% C.P. 22.50
add fitting charges & cartage L.S. 150.00
Total 397.50
Rate per Sqm 397.50 / 2.46 161.59
Say 162.00 Per Sqm

21 RR stone masonary laid 1:6


cement, f/sand material in
foundation of wall i/c s/o all m/l,
t&p etc required for proper
completion of the work.

A Labour - Rate as per schedule 345.00 Per cum


Add HI 19% 65.55
410.55
add cost of stone 530.00
Total 940.55
B Material
Cement Bag 1.41 298.20 420.46
Fine sand Cum 0.3 552.00 165.60
Total 586.06
Total of A+B 1,526.61 Per Cum
Say 1527.00 Per Cum

22 M.S./Tor steel or iron work in plain


work such as in reinforcement
cement concrete brought to
required shape as necessary
including binding for proper shape
including cost of supply of all
materials, labour, T&P etc. required
for proper completion of the work.

A Material
Steel Qtl 0.508 4536.60 2304.59
Add 2.5% wastage 57.61
Total 2362.21
B Labour
B/Smith Per day No 1 278.00 278.00
Coolie Per day No 1-1/2 153.00 229.50
Add t&p, sundries L.S. 0.6 x 25.00 15.00
Total 522.50
Add 10% C.P. 52.25
Total 574.75

Page 15 of 77
Analysis of Rates
Total of A+B 2362.21 + 574.75 2936.96
Rate per Qtl 2936.96 / 0.508 5781.41 Per Qtl
Say 5781.00 Per Qtl

23 Supply & fixing 32 mm thick


commercial ply wood flush door
shutter of approved make including
s/f of wooden cleat & fixing of
hinges locks, bolts, handles & other
fitting required for proper
completion of the work.

A Material
Rate per sqm Sqm 1.00 1,200.00 1,200.00
Add rebet L.S. 1.00 25.00 25.00
Add 10% C.P. 120.00
add cartage L.S. 50.00
Total 1,395.00
B Labour for 100 sqft
Mistri Per Day No 1/24 278.00 11.58
Coolie Per Day No 1/24 153.00 6.38
T&P sundries L.S. 0.25 25.00 6.25
Total 24.21
Add 10% C.P. 2.42
Total 26.63
Rate per Sqm 26.63 / 100 x 10.764 2.87
Total 1397.87 Per Sqm
Say 1,398.00 Per Sqm

24 S/F of 4 cm thick C.P.chir wood


fully glazed door & window shutter
i/c s/f of wooden cleats & stoppers
& fixing od adjustment hinges,
bolts, handles etc all complete.

taking door size 4'x7' size of shutter 3.2/3x6.3/4 = 24.75 Sqft


wood required i/c 10% wastage 3.91 Cft or 0.1124 Cum
A Material
Chir wood Cum 0.1124 27,024.00 3,037.50
B Labour
Mistri Per Day No 1/8 278.00 34.75
Carpenter Per Day No 4 278.00 1112.00
Glazier or Painter Per Day 1/4 278.00 69.50
Beldar Per Day No 1 153.00 153.00
T&P sundries L.S. 0.50 25.00 12.50
Total 1381.75
Add 10% C.P. 138.175
Total 1519.93
Total of A+B 4,557.42
Hence Rate per Sqm 4,557.42 / 24.75 x 10.764 1,982.06 Per Sqm
Say 1,982.00 Per Sqm

25 S/F of sal wood chaukhat & other


framed i/c all material labour, t&p
etc required for proper completion
of the work.

A Material

Page 16 of 77
Analysis of Rates
taking size 4'x7'
wood 1x18x1/3x1/4 = 1.5 Cft
wastage 5% 0.075
total 1.575 Cft say 1.60 @ 1394.92 2231.87
B Labour
Mistri Per Day No 1/16 278.00 17.38
Carpenter Per Day No 1/2 278.00 139.00
Beldar Per Day No 1/4 153.00 38.25
T&P sundries L.S. 3.00 25.00 75.00
Total 269.63
add 10% C.P. 26.96
296.59
Total of A+B 2528.45
Hence Rate per cft 2528.45 / 1.5 1685.64 per Cft
Rate per Cum 1685.64 x 35.315 59528.26
Say 59528.00 Per Cum

26 Two Coat of oil bond Distemper


surface i/c s/o all material, labour,
t&p etc required for proper
completion of the work.

For cost of Material


Cost of material at Uttarkashi Kg 20.00 876.00 43.80
Add cartage L.S. 50.00
Add 10% CP 4.38
Total cost of Material 98.18
A Material
Oil bond distemper Kg 2.27 98.18 222.87
T&P sundries, wall putty L.S. 10.00
Total 232.87
B Labour
Painter Per day No 3/8+1/5 278.00 159.85
Coolie Per day No 3/8+1/5 153.00 87.98
T&P & sundries L.S. (0.30+0.15) 20 9.00
Total 256.83
Total A+B 489.69
Hence rate per Sqm 489.69 / 100 x 10.764 52.71
Say 53.00 Per Sqm

27 Filling work by river bed material


i/c watering, dressing, ramming as
per direction of Engineer in charge.

Rate as per SOR Sl No-161 30.00


add 10% C.P. 3.00
add 19% height index 5.70
Total 38.70
add 1.00 km cartage by mule (1x10+1x5.0) x 16 240.00
G.Total 278.70
Say 279.00 Per Cum
28 Supply & fixing of tiles in flooring &
dado in 1:3 cement, c/sand mortar
i/c s/o all m/l, t&p etc all complete.

Tiles as per market of kajaria make 710.00 Per Sqm

add 10% C.P. 71.00

Page 17 of 77
Analysis of Rates
cartage L.S. 50.00
Total 831.00 Per Sqm
for one Sqft = 831.00/10.764 77.20
Material for 108Sqft
Tile 110.00 Sqft @ 77.20 8492.20
Cement 1.00 Bag @ 298.20 298.20
C/sand 4.00 cft @ 17.22 68.87
Total 8859.26
Labour
Mistri 4.00 No @ 278.00 1112.00
Coolie 2.00 No @ 153.00 306.00
Total 1418.00
Total - Labour + Material 8859.26 + 1418.00 10277.26
for one Sqm 10277.26 / 108 x 10.764 1024.30 per sqm
add 0.075 thick base concrete in 0.075 x 2645.00 198.38 per sqm
1:6:12
Say 198.00 per sqm

29 P/f of white glazed viterious china


wash basin R.S. or C.I. basin
painted white crome polish with
stand of parryware company, piller
tab of Jaquar com. & union
complete.

A Material

Page 18 of 77
Analysis of Rates
55x400 mm flat back basin No 1 980.00 980.00
Pedestal for wash basin No 1 1000.00 1000.00
15 mm crome polish piller cock No 1 600.00 600.00
PVC connection No 1 22.00 22.00
32 mm dia PVC waste pipe No 1 56.00 56.00
32 mm dia union No 1 138.00 138.00
R.S. or C.I. brackets No 1 100.00 100.00
Red lead, white lead etc L.S. 2 x 15 30.00
Cement, Sand etc L.S. 1 x 15 15.00
Cartege of material L.S. 2 x 25 30.00
Painting on brackets & fittings L.S. 2 x 15 30.00
Total 3001.00

B Labour
Fitter Per day No. 0.33 278.00 91.74
Mason Per day No. 0.33 278.00 91.74
Beldar Per day No. 0.67 153.00 102.51
total 285.99
add 10% C.P. 28.60
total 314.59
total of A+B 3001.00 + 314.59 3315.59 Per No
add 1% Water allowance 33.16
G. Total 3348.74 Per No
Say 3349.00 Per No

30 P/F of Soil or Vent pipe 110 mm dia


of approved quality i/c s/o all
complete.
detail of cost for 17.35 m
A Material
110 mm pipe Nos 10 493.00 4930.00
5% allowance for wastage 246.50
Scaffolding L.S. 3 x 15 45.00
cartage of material L.S. 5 x 10 75.00
Total 5296.50
B Labour
Fitter Per day No 0.42 278.00 116.76
Badhani Per day No 0.21 153.00 32.13
Beldar Per day No 0.83 153.00 126.99
Total 275.88
Total of A + B 5572.38
add 1% water allowance 55.72
Total 5628.10
add 10% C.P. 562.81
G.Total 6190.91
hence rate per mtr 6190.91 / 17.35 356.83
Say 357.00 Per Rmt

Page 19 of 77
Analysis of Rates
31 Same as above but 75 mm dia
Market Rate 50.00
Add 10% C.P. 5.00
Cartage L.S. 4.00
Total 59.00 Per Rmt

32 P/F of Nahani trap 110 mm dia


inlet 75 mm dia outlet i/c cost of
cutting hole & making good the
wall i/c s/o all m/l , t&p etc all
complete.

A Material
Cost of Nahani trap 110 x 75 mm dia No 138.00 1.00 138.00
Cement, Sand, grit L.S. 2.50 15.00 37.50
Cartage of material L.S. 0.50 5 2.50
Total 178.00
B Labour
Mason Per day No 0.50 278.00 139.00
Beldar Per day No 0.50 153.00 76.50
Total 215.50
Total of A+B 393.50
Add 10% C.P. 39.35
G.Total 432.85 Per No
Say 433.00 Per No

33 P/F of Manhole cover (45x45)cm or


(60x60) cm inside size double seal
frame of approved quality i/c s/o
all m/l, t&p etc required for proper
completion of the work.

45x45 cm size cover rate as per Each 700.00 1.00 700.00


market
Cartage of material L.S. 2 35.00 70.00
Total 770.00

Page 20 of 77
Analysis of Rates
Add 1% water charges 7.70
Total 777.70
add 10% C.P. 77.77
G. Total 855.47 Per No
Say 855.00 Per No

34 P/f of 15 mm dia 'B' class (jindal


STC marked) GI pipe complete with
GI special such as bends, Tee,
socket, cross, clamps etc cutting &
making good the wall etc i/c s/o all
m/l, t&p etc required for proper
completion of the work.

A Material :-
For 10.00 m length
GI pipe 15 mm dia mtr 10.00 98.00 980
Cartage of pipe for 10.00 m App. Kg 12.10 0.70 8.47
988.47
Add 15% for fitting & wastage on L.S. 15.00 0.88 13.20
white lead, hump oil etc.
Cement, sand & grit L.S. 15.00 0.20 3.00
Total 1004.67
B Labour :-
Fitter Per day No 0.33 278.00 91.74
Helper Per day No 0.66 153.00 100.98
Beldar Per day No 0.66 153.00 100.98
Total 293.70
total of A+B 1298.37
Add 1% Water Charges 12.98
1311.35
Add 10% C.P. 131.14
G.T. 1442.49
Hence Rate per Mtr 1442.49 / 10 144.25 Per Mtr
Say 144.00 Per Mtr

35 S/f of bib cock (1.27cm) 1/2"dia i/c


s/o all m/l, t&p etc required proper
completion of the work. Jaquar
make.

Cost of Brass bib cock (400gm) No 1 760.00 760.00


Add cartage of material L.S. 5.00
Add labour & white lead L.S. 0.70 15.00 10.50
Total 775.50
Add 10% C.P. 77.55

Page 21 of 77
Analysis of Rates
G. Total 853.05
Say 853.00 Per No

36 Same as above but wall mixture of


Jaquar make.
Cost of Mixture No 1 2680.00 2680.00
Add cartage of material L.S. 5.00
Add labour & white lead L.S. 1.00 50.00 50.00
Total 2735.00
Add 10% C.P. 273.5
G. Total 3008.50
Say 3009.00 Per No

37 S/F of indian type W/C sheet of


parryware make with cystern.
Market Rate No 1 1020.00 1020.00
Cistern No 1 1250.00 1250.00
Add Fitting charges L.S. 1 50.00 50.00
Add cartage L.S. 1 100.00 100.00
Total 2420.00
Add 10% C.P. 242.00
G.Total 2662.00 Per No

38 S/F of Towel rod of Stainless steel


with Jaquar make.
Market Rate No 1 1080.00 1080.00
Add Fitting charges L.S. 1 20.00 20.00
Add cartage L.S. 1 20.00 20.00
Total 1120.00
Add 10% C.P. 112.00
G.Total 1232.00 Per No

39 S/F of Soap dish


Market Rate No 1 808.00 808.00
Add Fitting charges L.S. 1 20.00 20.00
Add cartage L.S. 1 20.00 20.00
Total 848.00
Add 10% C.P. 84.80
G.Total 932.80 Per No

40 S/F of angle cock.


Market Rate No 1 600.00 600.00
Add Fitting charges L.S. 1 20.00 20.00
Add cartage L.S. 1 20.00 20.00
Total 640.00
Add 10% C.P. 64.00
G.Total 704.00 Per No

41 S/F of 4" dia C.I.waste pipe i/c s/o


all m/l, t&p etc required for proper
completion of the work.
A Material
4" dia CI waste pipe Rmt 17.35 250.00 4337.50
Add 5% wastage 216.88
Scaffolding L.S. 3.00 15.00 45.00
Cartage L.S. 75.00
Total 4674.38

Page 22 of 77
Analysis of Rates
B Labour
Fitter Per day No 0.42 278.00 116.76
Beldar Per day No 0.21 153.00 32.13
Helper Per day No 0.83 153.00 126.99
Total 275.88
Add 10% C.P. 27.59
Total 303.47
Total of A+B 4674.38 + 303.47 4977.84
Hence rate per Rmt 4977.84 / 17.35 286.91
Add 1.5% w.A. 4.30
G.Total 291.21
Say 291.00 Per Rmt.

42 Providing & fixing of C.I. plain


bends 5 to 10 cm dia i/c s/o all m/l,
t&p etc required for proper
completion of the work.

Bends (5-10 cm dia) Rs. 80.00


Cartage of material & fixing charges 35.00
Total 115.00
Add 1% water charges 1.15
116.15
Add 10% C.P. 11.62
G.total 127.77
Say 128.00 Per No

43 Collection & consolidation of 45-63


mm size stone ballast in 10 mm
loose thick & compaction by 8-10
ton road roller i/c spreading of
bimding material i/c s/o all m/l,
t&p etc required for proper
completion of the work.

Cost of s/ballast 45-63 mm 520.10 Per Cum


roller charges 8/35x308 70.40
labour rate as per SOR 83.00
add 19% height index 15.77
Total 689.27 Per Cum
Say 689.00 Per Cum

44 Collection & consolidation of 22.5-


50 mm size stone ballast in 10 mm
loose thick & compaction by 8-10
ton road roller i/c spreading of
binding material i/c type A seal
coat & s/o all m/l, t&p etc required
for proper completion of the work.

Cost of s/ballast 22.5-50 mm 570.10 Per Cum


roller charges 8/35x308 70.40
labour rate as per SOR 83.00
add 19% height index 15.77
Total 739.27 Per Cum
Say 739.00 Per Cum

Page 23 of 77
Analysis of Rates
45 2 cm thick premix carpet with
bitumen applying tack coat &
graded crushed grit 13.2 mm &
11.2 mm size in proportion of 2:1
and cleaning of premix surface i/c
s/o all m/l, t&p etc required for
proper completion of the work.

For 100 sqm


A 2 cm premix carpet
(i) collection of 13.2 mm @ 0.18/10
sqm 0.18 1.80 2245.60 4042.08
(ii) collection of 11.2 mm @
0.09/10 sqm 0.09 0.90 2245.60 2021.04
(iii) collection of 6.7 mm chips @
0.09/10 sqm 0.09 0.90 2245.60 2021.04
Total 8084.16
B Maxphalt for 100 sqm
Tack coat - 100 kg
Pre coating - 146 kg
Seal coat - 98 kg
Total = 344 kg 344/156 = 2.21
2.21 Qtl @ 6806.50 15042.37
C Fuel wood for 100 sqm
for heating grit @ 0.50 qtl/Cum 3.60 1.80
for heating maxphalt @ 4.50qtl/Mt 0.34 1.55
3.35 @ 802.60 2687.10
D Roller charges for 100 Sqm
For PC 8/4.65 308.00 529.89
For Seal coat 8/9.30 308.00 264.95
Total 794.84
Total of A+B+C+D 26608.47
E Mislleneous items i.e. brushing,
wire pans, brooms, painting kit,
manila rope, basket, gunny bags
etc.
add 2.50% extra on 26608.47 665.21
add labour rate as per SOR - 511+513 (15.00+6.00)x100 2100.00
add 19% height index 399.00
total 3164.21
Total of A+B+C+D+E 29772.68
hence rate for 2cm thick premix carpet 29772.68 / 100 297.73 per sqm
Say 298.00 per sqm

46 S/F of 24 BWG CGI sheet for


roofing i/cs/o all material, labour,
t&p etc all complete.
Considering area of roof - 1982.50 Sqm
A Material

Page 24 of 77
Analysis of Rates
24 gauge CGI sheet Qtl 13.92 4830.00 67233.60
1x1/4 G.I. bolt doz 50.00 50.00 2500.00
6x3/8 G.I.J. hook doz 40.00 150.00 6000.00
Lumpet washer doz 90.00 15.00 1350.00
Bitumen washer doz 90.00 15.00 1350.00
Total 78433.60
B Labour
Carpenter Per day No 12 278.00 3336.00
Beldar Per day No 12 153.00 1836.00
t&p L.S. 15 25.00 375.00
Total 5547.00
add 10% C.P. 554.7
Total 6101.70
Total of A+B 78433.60 + 6101.70 84535.30
Rate per Sqm 84535.30x100/1982.50x9.29 459.00
Say Rs. 459.00 Per Sqm

47 Excavation in foundation in all type


of soil i/c s/o all m/l, t&p etc
required for proper completion of
the work.

Rate as per TS estimate noi=kad


- 2995 Hkou @ 107 Hkou&6 @2008-2009 fnukad 07@06@2008 50.00 Per Cum

48 Filling work by river bed materials


i/c watering dressing, ramming as
per direction of EIC.
Rate as per TS estimate noi=kad
- 2995 Hkou @ 107 Hkou&6 @2008-2009 fnukad 07@06@2008 279.00 Per Cum

49 Concrete with 2cm gauge stone


ballast, c/sand & cement in
proportion of 3:1.5:1 in foundation
i/c s/o all m/l, t&p etc required for
proper completion of the work.

Rate as per TS estimate noi=kad


- 2995 Hkou @ 107 Hkou&6 @2008-2009 fnukad 07@06@2008 4363.82 Per Cum
Say 4364.00 Per Cum

50 RR stone masonary laid in 1:6


cement, sand mortar i/c s/o all m/l,
t&p etc required for proper
completion of the work.

Rate as per TS estimate noi=kad


- 2995 Hkou @ 107 Hkou&6 @2008-2009 fnukad 07@06@2008 1115.00 Per Cum
Say 1115.00 Per Cum

51 RR stone masonary laid dry i/c s/o


all m/l, t&p etc required for proper
completion of the work.
Rate as per TS estimate noi=kad
- 2995 Hkou @ 107 Hkou&6 @2008-2009 fnukad 07@06@2008 533.00 Per Cum
Say 533.00 Per Cum

Page 25 of 77
Analysis of Rates
52 Cement plum masonary with 40%
plum & 60% cement concrete in
proportion of 1:3:6 cement
concrete approved 40 mm gauge
stone ballast i/c s/o all m/l, t&p etc
required for proper completion of
the work.

Rate as per TS estimate noi=kad


- 2995 Hkou @ 107 Hkou&6 @2008-2009 fnukad 07@06@2008 2340.00 Per Cum
Say 2340.00 Per Cum

53 Painting & varnishing on iron work


in small area with one coat ready
mixed primer & two coat approved
enamel paint i/c s/o all m/l, t&p etc
required for proper completion of
the work.

Rate as per TS estimate noi=kad


- 2995 Hkou @ 107 Hkou&6 @2008-2009 fnukad 07@06@2008 71.00 Per Cum
Say 71.00 Per Cum

Page 26 of 77
DETAIL OF MEASUREMENTS

NAME OF WORK: Construction of Helipad at Harshil under deposit work of civil Aviation Department.

S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
1 Excavation in foundation in all type of
soil i/c lift upto 1.5 m & lead upto 30
meter & i/c filling, watering, ramming of
excavated earth into the trenches or in
it to the space between the building &
site of foundation trenches or into the
plinth & removal & disposal of surplus
earth as directed by tje engineer charge
up to a distance of 30 meter from the
foundation trenches.

building 1 3 13.80 1.00 1.50 62.10


1 4 5.96 1.00 1.50 35.76
Column 1 16 1.00 1.00 1.50 24.00
Total 121.86 Cum
Say 122.00 Cum

2 Cement, concrete with 40 mm gauge


locally available approved stone ballast,
coarse sand and cement in proportion
of 12:6:1 in foundation including cost of
materials, labour, T&P etc. required for
proper completion of the work.

building 1 3 13.80 1.00 0.15 6.21


1 4 5.96 1.00 0.15 3.58
Column 1 16 1.00 1.00 0.15 2.40
floor meeting hall 1 1 4.00 4.00 16.00
entrance meeting hall 1 1 1.73 1.00 1.73
bath 1 1 1.50 2.70 4.05
vip room 1 1 4.00 4.30 17.20
wc & bath 1 1 1.50 2.50 3.75
lobby vip 1 1 1.73 1.50 2.60
verandah 1 1 2.73 3.23 8.82
wating room 1 1 3.00 3.00 9.00
door sill 1 3 1.20 0.25 0.90
1 2 1.00 0.25 0.50
in stair 1 1 2.50 0.23 0.58
1 3 4.20 0.25 3.15
1 3 3.10 0.25 2.33
Total 82.78 Cum
Say 83.00 Cum

3 Class M-100 brick thick work in 1:6


cement sand mortar in super structure
i/c s/o all material, labour t&p etc
required for proper completion of the
work.

long wall 1 3 8.46 0.23 3.50 20.43


waiting room long wall 1 2 3.23 0.23 3.50 5.20
short wall 1 3 5.96 0.23 3.50 14.39
1 1 3.46 0.23 3.50 2.79
verandah dwarf wall 1 1 3.23 0.23 0.60 0.45
1 1 2.73 0.23 0.60 0.38
Total 43.63 Cum
Deduct- window -1 4 1.50 0.23 1.50 -2.07
door -1 3 1.10 0.23 2.10 -1.59
door -1 2 0.90 0.23 2.10 -0.87
opening -1 1 1.50 0.23 2.10 -0.72
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
-1 1 1.00 0.23 2.10 -0.48
door level bend -1 3 8.46 0.23 0.15 -0.88
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
-1 2 3.23 0.23 0.15 -0.22
-1 3 5.96 0.23 0.15 -0.62
-1 1 3.46 0.23 0.15 -0.12
Total 36.06
Say 36.10 Cum

4 Reinforced cement concrete in


proportion of 1:1.5:3 (M-20) in cement,
coarse sand and 20mm gauge stone grit
as per specification and drawing
including cost of material, labour, T&P
etc. required for proper completion of
the work. Raft, column & lintel.

Raft - long 1 3 12.5 0.60 0.20 4.50


1 1 2.95 0.60 0.20 0.35
short 1 4 6.35 0.60 0.20 3.05
1 2 1.45 0.60 0.20 0.35
plinth bend 1 2 12.50 0.23 0.15 0.86
1 4 5.80 0.23 0.15 0.80
1 1 3.00 0.23 0.15 0.10
1 1 4.30 0.23 0.15 0.15
1 1 4.00 0.23 0.15 0.14
door level bend 1 2 12.50 0.23 0.15 0.86
1 3 5.80 0.23 0.15 0.60
1 1 3.00 0.23 0.15 0.10
1 1 4.30 0.23 0.15 0.15
in lintel 1 1 3.60 0.23 0.15 0.12
1 1 2.80 0.23 0.15 0.10
in column 1 14 0.23 0.23 4.50 3.33
1 2 0.23 0.23 6.50 0.69
in beam 1 1 6.80 0.30 0.40 0.82
Total 17.07 Cum
Say 17.10 Cum

5 Same as above item no-5 but in roof slab


& roof beams.
Beams short 1 4 6.19 0.23 0.23 1.31
long 1 3 12.22 0.23 0.23 1.94
roof 1 1 13.42 7.39 0.15 14.88
Total 18.13
Say 18.00 Cum

6 M.S./Tor steel or iron work in plain


work such as in reinforcement cement
concrete brought to required shape as
necessary including binding for proper
shape including cost of supply of all 1.50% of (17.10+18.00) cum RCC 22.04 Qtl
materials, labour, T&P etc. required for
proper completion of the work.

Say 22.00 Qtl

7 Rendering of roof slab with 1:3 cement


& coarse sand mortar 6 mm thick just
after RCC slab i/c all material, labour,
t&p etc required for proper completion
of the work. 2 1 13.42 7.39 198.35
Total 198.35
say 198.00 Sqm

8 2.5 cm thick 1:2:4 cement concrete floor


with 7.5 cm thick 1:6:12 base concrete
with c/sand & 20 mm gauge s/ballast i/c
s/o all m/l , t&p etc required for proper
completion of the work.
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
around building 1 1 31.30 11.85 370.91
deduct building area -1 1 12.20 6.19 -75.52
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
Total 295.39 Sqm
say 295.00 Sqm

9 20 mm thick plaster with 1:2 cement &


fine sand on dado or skirting laid in
panels finished with 3mm floating coat
of cement i/c s/o all material, labour,
t&p etc required for proper completion
of the work.

around boilding 1 2 11.85 0.60 14.22


1 2 6.19 0.60 7.43
Total 21.65 sqm
Say 22.00 sqm

10 P/F of 25mm wide & 4.8 mm thick glass


strip i/c s/o all m/l, t&p etc required for
proper completion of the work.

around building 2 14 1.50 42.00


2 7 1.50 21.00

Total 63.00 Rmt


say 63.00 Rmt

11 12 mm thick plaster in 1:6 cement, sand


mortar i/c s/o all m/l, t&p etc required
for proper completion of the work.
out side 1 2 11.85 3.75 88.88
1 2 6.19 3.00 37.14
deduct door -1 1 1.10 2.10 -2.31
window -4 1 1.50 1.50 -9.00
Total A 114.71
meeting room 1 4 4.00 3.50 56.00
lobby 1 2 1.73 3.50 12.11
1 1 1.00 3.50 3.50
deduction - door -1 1 0.75 2.10 -1.58
wc bath 1 2 1.50 0.50 1.50
1 2 2.70 0.50 2.70
VIP room 1 2 4.00 3.50 28.00
1 2 4.30 3.50 30.10
deduction - door -1 1 1.10 2.10 -2.31
deduct window -2 1 1.50 1.50 -4.50
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
deduct opening -1 1 1.50 2.10 -3.15
lobby 1 2 1.50 3.50 10.50
1 2 1.73 3.50 12.11
deduction - door -1 1 0.75 2.10 -1.58
opening -1 1 1.50 2.10 -3.15
waiting room 1 4 3.00 3.50 42.00
deduct door -1 2 1.10 2.10 -4.62
window -1 1 1.50 1.50 -2.25
verandah 1 1 2.50 3.50 8.75
1 1 3.00 3.50 10.50
deduct door -1 1 1.10 2.10 -2.31
Total B 192.33
Total A+B 307.04 Sqm
Say 307.00 Sqm

12 Same as above item but extra over rough


face of one brick wall.
same as item - 10 1 1/2 307.00 153.50 Sqm
Say 154.00 sqm

13 Add extra labour & material for making


grooves line in plaster on outer face of
wall & joint between RCC roof & walls
i/c all labour, material, t&p etc required
for proper completion of the work.
long side 2 2 12.50 50.00
short side 1 2 6.40 12.80
roof level 1 2 12.50 25.00
1 2 6.40 12.80
Total 100.60 rmt
say 101.00 rmt

14 Add extra labour & material for making


of drip course (20x30mm) in projection
of roof & sun shade. Completion as per
direction of EIC.

1 2 13.00 26.00
1 2 6.80 13.60
sunshed window 1 4 2.60 10.40
verandah 1 1 8.50 8.50
Total 58.50 Rmt
say 59.00 Rmt

15 Finishing of walls with water proof


cement paint with two coats to given
shades i/c s/o all m/l, t&p etc all
complete.
Same as outer plaster 114.71
Total 114.71 Sqm
Say 115.00 Sqm
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
16 Painting on new iron works with two
coats of approved paint including cost of
supply of all materials, labour, T&P etc.
required for proper completion of the
work as per direction of Engineer-in-
charge.

on door 2 3 1.10 2.10 13.86


2 2 0.90 2.10 7.56
window 2 4 1.50 1.50 18.00
on security grill 4 1/2 1.34 1.34 3.59
wire window 1 4 1.50 1.50 9.00
Total 52.01 sqm
say 52.00 sqm

17 Supply & fixing of security grill over


window as per drawing or as per
instruction of engineer in charge i/c
welding & supply of all materails,
labours, t&p etc required for proper
completion of the work.

1 4 1.34 1.34 7.18


Total 7.18 Sqm
Say 7.20 Sqm

18 S/F of Galavanized mosquito proof wire


mesh over window with chir wood
beading i/c s/o all m/l t&p etc required
for proper completion of the work.

1 4 1.50 1.50 9.00


Total 9.00 Sqm
say 9.00 Sqm
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
19 Supply & fixing of heavy quality
oxidized iron fitting for door & window
with necessary ms hinges, steel screw,
nut, bolts & other material as per
requirement.
same as item no - 16 1 1 7.20 7.20
same as item no - 17 1 1 9.00 9.00
Total 16.20 sqm
say 16.00 sqm

20 RR stone masonary laid 1:6 cement,


f/sand material in foundation of wall i/c
s/o all m/l, t&p etc required for proper
completion of the work.

foundation long wall 1 2 12.35 0.60 1.40 20.75


middle wall 1 1 8.20 0.60 1.40 6.89
1 1 2.95 0.60 1.40 2.48
short wall 1 4 6.35 0.60 1.40 21.34
1 2 1.45 0.60 1.40 2.44
Total 53.89 cum
say 54.00 cum

21 Supply & fixing 32 mm thick


commercial ply wood flush door shutter
of approved make including s/f of
wooden cleat & fixing of hinges locks,
bolts, handles & other fitting required
for proper completion of the work.

door 1 3 1.10 2.10 6.93


1 2 0.90 2.10 3.78
Total 10.71 Sqm
say 11.00 Sqm

22 S/F of 4 cm thick C.P.chir wood fully


glazed door & window shutter i/c s/f of
wooden cleats & stoppers & fixing od
adjustment hinges, bolts, handles etc all
complete.

window 1 4 1.50 1.50 9.00


Total 9.00 Sqm
say 9.00 Sqm

23 S/F of sal wood chaukhat & other


framed i/c all material labour, t&p etc
required for proper completion of the
work.
in door 1 3 5.3 0.075 0.10 0.12
1 2 5.3 0.075 0.10 0.08
window 1 4 6.0 0.075 0.10 0.18
Total 0.38 Cum
Say 0.40 Cum
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
24 Two Coat of oil bond Distemper surface
i/c s/o all material, labour, t&p etc
required for proper completion of the
work.
same as plaster - qty of snowcem + roof
1 1 Same as inner plaster 192.33
ceiling meeting hall 1 1 4.00 4.00 16.00
entrance meeting hall 1 1 1.73 1.00 1.73
bath 1 1 1.50 2.70 4.05
vip room 1 1 4.00 4.30 17.20
wc & bath 1 1 1.50 2.50 3.75
lobby vip 1 1 1.73 1.50 2.60
verandah 1 1 2.73 3.23 8.82
wating room 1 1 3.00 3.00 9.00
Total 255.47 sqm
say 255.00 sqm

25 Supply & fixing of tiles in flooring &


dado in 1:3 cement, c/sand mortar i/c s/o
all m/l, t&p etc all complete.
meeting hall 1 1 4.00 4.00 16.00
skirting 1 4 4.00 0.15 2.40
entrance meeting hall 1 1 1.73 1.00 1.73
skirting 1 2 1.73 0.15 0.52
1 1 1.00 0.15 0.15
bath 1 1 1.50 2.70 4.05
walls 1 2 2.70 2.10 11.34
1 2 1.50 2.10 6.30
deduct door -1 1 0.75 2.10 -1.58
vip room 1 1 4.00 4.30 17.20
skirting 1 2 4.00 0.15 1.20
1 2 4.30 0.15 1.29
deduct door -1 1 1.00 0.15 -0.15
opening -1 1 1.50 0.15 -0.23
wc & bath 1 1 1.50 2.50 3.75
walls 1 2 1.50 2.10 6.30
1 2 2.50 2.10 10.50
deduct door -1 1 0.75 2.10 -1.58
lobby vip 1 1 1.73 1.50 2.60
skirting 1 2 1.73 0.15 0.52
1 1 1.50 0.15 0.23
deduct door -1 1 0.75 0.15 -0.11
verandah 1 1 2.73 3.23 8.82
skirting 1 1 2.73 0.15 0.41
1 1 3.23 0.15 0.48
deduct door -1 1 1.00 0.15 -0.15
wating room 1 1 3.00 3.00 9.00
skirting 1 4 3.00 0.15 1.80
deduct door -1 2 1.00 0.15 -0.30
Total 102.49 Sqm
say 102.50 Sqm

26 P/f of white glazed viterious china wash


basin R.S. or C.I. basin painted white
crome polish with stand of parryware
company, piller tab of Jaquar com. &
union complete.
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
in T1 & T2 2 1 2.00
Total 2.00 No
Say 2.00 No

27 P/F of Soil or Vent pipe 110 mm dia of


approved quality i/c s/o all complete.

for T1 1 1 10.00 10.00


for T2 1 1 11.00 11.00
Total 21.00 Rmt
say 21.00 Rmt

28 Same as above but 75 mm dia


1 1 7.50 7.50
1 1 8.45 8.45
Total 15.95 Rmt
say 16.00 Rmt

29 P/F of Nahani trap 110 mm dia inlet 75


mm dia outlet i/c cost of cutting hole &
making good the wall i/c s/o all m/l ,
t&p etc all complete. 2 2 4.00 No
Total 4.00 Nos

30 P/F of Manhole cover (45x45)cm or


(60x60) cm inside size double seal
frame of approved quality i/c s/o all m/l,
t&p etc required for proper completion
of the work.
4 1 4.00
Total 4.00 Nos

31 P/f of 15 mm dia 'B' class (jindal STC


marked) GI pipe complete with GI
special such as bends, Tee, socket, cross,
clamps etc cutting & making good the
wall etc i/c s/o all m/l, t&p etc required
for proper completion of the work.

T1 1 1 3.25 3.25
1 1 4.50 4.50
T2 1 1 3.25 3.25
1 1 4.50 4.50
for tank 1 1 10.80 10.80
Total 26.30 Rmt

32 S/f of bib cock (1.27cm) 1/2"dia i/c s/o


all m/l, t&p etc required proper
completion of the work. Jaquar make.
8 1 8.00
Total 8.00 N0

33 Same as above but wall mixture of


Jaquar make. 2 1 2.00
Total 2.00 N0
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
34 S/F of indian type W/C sheet of
parryware make with cystern. 2 1 2.00
Total 2.00 No
Say 2.00 No

35 S/F of Towel rod of Stainless steel with


Jaquar make. 2 1 2.00
Total 2.00 No
Say 2.00 No

36 S/F of Soap dish 2 1 2.00


Total 2.00 No
Say 2.00 No

37 S/F of angle cock. 6 1 6.00


Total 6.00 No
Say 6.00 No

38 S/F of 4" dia C.I.waste pipe i/c s/o all


m/l, t&p etc required for proper
completion of the work.
1 1 14.50 14.50
Total 14.50 Rmt
39 Providing & fixing of C.I. plain bends 5
to 10 cm dia i/c s/o all m/l, t&p etc
required for proper completion of the
work. 5 1 5.00
Total 5.00 Nos

40 Collection & consolidation of 45-63 mm


size stone ballast in 10 mm loose thick
& compaction by 8-10 ton road roller i/c
spreading of bimding material i/c s/o all
m/l, t&p etc required for proper
completion of the work.

approach road 1 1 20.00 10.45 0.10 20.90


infront of building 1 1 80.00 10.00 0.10 80.00
below landing area 2 1 30.00 30.00 0.10 180.00
deduct landing -2 1 10.00 10.00 0.10 -20.00
corner -2 4 3.00 1.00 0.10 -2.40
-2 4 2.00 1.00 0.10 -1.60
total 256.90 cum
say 257.00 cum

41 Collection & consolidation of 22.5-50


mm size stone ballast in 10 mm loose
thick & compaction by 8-10 ton road
roller i/c spreading of binding material
i/c type A seal coat & s/o all m/l, t&p
etc required for proper completion of the
work.
approach road 1 1 20.00 10.45 0.10 20.90
infront of building 1 1 80.00 10.00 0.10 80.00
below landing area 2 1 30.00 30.00 0.10 180.00
deduct landing -2 1 10.00 10.00 0.10 -20.00
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
corner -2 4 3.00 1.00 0.10 -2.40
-2 4 2.00 1.00 0.10 -1.60
Total 256.90 cum
say 257.00 cum

42 2 cm thick premix carpet with bitumen


applying tack coat & graded crushed grit
13.2 mm & 11.2 mm size in proportion
of 2:1 and cleaning of premix surface i/c
s/o all m/l, t&p etc required for proper
completion of the work.

approach road 1 1 20.00 10.45 209.00


infront of building 1 1 80.00 10.00 800.00
deduct landing -2 1 10.00 10.00 -200.00
corner -2 4 3.00 1.00 -24.00
-2 4 2.00 1.00 -16.00
Total 769.00 sqm
say 769.00 sqm

43 Excavation in foundation in all type of


soil i/c s/o all m/l, t&p etc required for
proper completion of the work.
as per qty paid vide mb no - 302/S page
no - 105 516.17 Cum
Side wall of building 1 2/3 11.85 0.805 1.65 10.49
back wall of building 1 2/3 30.7 0.805 1.65 27.18
Total 553.85
say 554.00 Cum
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9

44 Filling work by river bed materials i/c


watering dressing, ramming as per
direction of EIC.
as per qty paid vide mb no - 302/S page
no - 107 11099.19 Cum
inside of building 1 1 11.30 5.50 0.80 49.72
1 1 30.7 11.25 1.5 518.06
Total 11666.97
say 11667.00 Cum

45 Concrete with 2cm gauge stone ballast,


c/sand & cement in proportion of 3:1.5:1
in foundation i/c s/o all m/l, t&p etc
required for proper completion of the
work.
on plateform 2 1 10.00 10.00 0.20 40.00
corners 2 4 3.00 1.00 0.20 4.80
2 4 2.00 1.00 0.20 3.20
Total 48.00
say 48.00 Cum

46 RR stone masonary laid in 1:6 cement,


sand mortar i/c s/o all m/l, t&p etc
required for proper completion of the
work.
as per qty paid vide mb no - 302/S page
no - 106 452.76 Cum
side wall of building bottom band 1 1 11.85 0.935 0.6 6.65
top band 1 1 11.85 0.66 0.5 3.91
vertical band 1 3 0.6 0.79 0.55 0.78
1 1 1.05 0.79 0.55 0.46
back wall of building bottom band 1 1 30.7 0.935 0.6 17.22
top band 1 1 30.7 0.66 0.5 10.13
vertical band 1 6 0.5 0.79 0.55 1.30
1 1 1.25 0.79 0.55 0.54
Total 493.76
say 494.00 Cum

47 RR stone masonary laid dry i/c s/o all


m/l, t&p etc required for proper
completion of the work.
as per qty paid vide mb no - 302/S page
no - 106 151.30 Cum
side wall of building 1 2 3.8 0.79 0.55 3.30
1 1 1.2 0.79 0.55 0.52
back wall of building 1 7 3.8 0.79 0.55 11.56
Total 166.68
say 167.00 Cum
S.No Particulars of Items Nos Nos Length Breadth Height Qty Unit
1 2 3 4 5 6 7 8 9
48 Cement plum masonary with 40% plum
& 60% cement concrete in proportion of
1:3:6 cement concrete approved 40 mm
gauge stone ballast i/c s/o all m/l, t&p
etc required for proper completion of the
work.

as per qty paid vide mb no - 302/S page


no - 106 374.65 Cum
say 374.70 Cum

49 Painting & varnishing on iron work in


small area with one coat ready mixed
primer & two coat approved enamel
paint i/c s/o all m/l, t&p etc required for
proper completion of the work.
on plate form 2 2 6.00 1.00 24.00
2 1 3.00 1.00 6.00
corners 2 4 3.00 1.00 24.00
2 4 2.00 1.00 16.00
Total 70.00
Say 70.00 Sqm
BILL OF QUANTITY
NAME OF WORK: Construction of Helipad at Harshil under deposit work of civil Aviation
Department.
For Halipad
Sr No Particulars of Items Qty Unit Rate as per Rate as per Amount as
Analysis Bond per bond in
Rs.

1 2 3 4 5 6
1 Excavation in foundation in all type of 554.00 Cum 50.00 47.00 26038.00
soil i/c s/o all m/l, t&p etc required for
proper completion of the work.

2 Filling work by river bed materials i/c 11667.00 Cum 279.00 275.00 3208425.00
watering dressing, ramming as per
direction of EIC.

3 Concrete with 2cm gauge stone ballast, 48.00 Cum 4364.00 4200.00 201600.00
c/sand & cement in proportion of 3:1.5:1
in foundation i/c s/o all m/l, t&p etc
required for proper completion of the
work.

4 RR stone masonary laid in 1:6 cement, 494.00 Cum 1115.00 1100.00 543400.00
sand mortar i/c s/o all m/l, t&p etc
required for proper completion of the
work.

5 RR stone masonary laid dry i/c s/o all 167.00 Cum 533.00 530.00 88510.00
m/l, t&p etc required for proper
completion of the work.

6 Cement plum masonary with 40% plum 374.70 Cum 2340.00 2450.00 918015.00
& 60% cement concrete in proportion of
1:3:6 cement concrete approved 40 mm
gauge stone ballast i/c s/o all m/l, t&p
etc required for proper completion of the
work.

7 Painting & varnishing on iron work in 70.00 Sqm 71.00 65.00 4550.00
small area with one coat ready mixed
primer & two coat approved enamel
paint i/c s/o all m/l, t&p etc required for
proper completion of the work.

Total 4990538.00
Below 33.30% as per bond -1661849.15
Total A 3328688.85
Say 3328689.00

Junior Engineer Assistant Engineer Executive Engineer


P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari
BILL OF QUANTITY

NAME OF WORK: Construction of Helipad at Harshil under deposit work of civil Aviation
Department.

Sr No Particulars of Items Qty Unit Rate as per Rate as per Amount as


Analysis Bond per bond in
Rs.

1 2 3 4 5 6
1 Excavation in foundation in all type of 122.00 Cum 60.00 59.00 7198.00
soil i/c lift upto 1.5 m & lead upto 30
meter & i/c filling, watering, ramming
of excavated earth into the trenches or in
it to the space between the building &
site of foundation trenches or into the
plinth & removal & disposal of surplus
earth as directed by tje engineer charge
up to a distance of 30 meter from the
foundation trenches.

2 Cement, concrete with 40 mm gauge 83.00 Cum 2645.00 2150.00 178450.00


locally available approved stone ballast,
coarse sand and cement in proportion of
12:6:1 in foundation including cost of
materials, labour, T&P etc. required for
proper completion of the work.

3 Class M-100 brick thick work in 1:6 36.10 Cum 3572.00 3200.00 115520.00
cement sand mortar in super structure i/c
s/o all material, labour t&p etc required
for proper completion of the work.

4 Reinforced cement concrete in 17.10 Cum 5623.00 4800.00 82080.00


proportion of 1:1.5:3 (M-20) in cement,
coarse sand and 20mm gauge stone grit
as per specification and drawing
including cost of material, labour, T&P
etc. required for proper completion of
the work. Raft, column & lintel.

5 Same as above item no-5 but in roof slab 18.00 Cum 6047.00 5000.00 90000.00
& roof beams.
Sr No Particulars of Items Qty Unit Rate as per Rate as per Amount as
Analysis Bond per bond in
Rs.

1 2 3 4 5 6
6 2.5 cm thick 1:2:4 cement concrete floor 295.00 Sqm 355.00 275.00 81125.00
with 7.5 cm thick 1:6:12 base concrete
with c/sand & 20 mm gauge s/ballast i/c
s/o all m/l , t&p etc required for proper
completion of the work.

7 20 mm thick plaster with 1:2 cement & 22.00 Sqm 180.00 130.00 2860.00
fine sand on dado or skirting laid in
panels finished with 3mm floating coat
of cement i/c s/o all material, labour,
t&p etc required for proper completion
of the work.

8 P/F of 25mm wide & 4.8 mm thick glass 63.00 Rmt 30.00 15.00 945.00
strip i/c s/o all m/l, t&p etc required for
proper completion of the work.

9 12 mm thick plaster in 1:6 cement, sand 307.00 Sqm 112.00 140.00 42980.00
mortar i/c s/o all m/l, t&p etc required
for proper completion of the work.

10 Same as above item but extra over rough 154.00 sqm 9.00 7.00 1078.00
face of one brick wall.

11 Add extra labour & material for making 101.00 rmt 16.00 9.00 909.00
grooves line in plaster on outer face of
wall & joint between RCC roof & walls
i/c all labour, material, t&p etc required
for proper completion of the work.

12 Add extra labour & material for making 59.00 Rmt 31.00 18.00 1062.00
of drip course (20x30mm) in projection
of roof & sun shade. Completion as per
direction of EIC.

13 Finishing of walls with water proof 115.00 Sqm 41.00 35.00 4025.00
cement paint with two coats to given
shades i/c s/o all m/l, t&p etc all
complete.
Sr No Particulars of Items Qty Unit Rate as per Rate as per Amount as
Analysis Bond per bond in
Rs.

1 2 3 4 5 6
14 Painting on new iron works with two 52.00 sqm 106.00 60.00 3120.00
coats of approved paint including cost of
supply of all materials, labour, T&P etc.
required for proper completion of the
work as per direction of Engineer-in-
charge.

15 Supply & fixing of security grill over 7.20 Sqm 759.00 750.00 5400.00
window as per drawing or as per
instruction of engineer in charge i/c
welding & supply of all materails,
labours, t&p etc required for proper
completion of the work.

16 S/F of Galavanized mosquito proof wire 9.00 Sqm 180.00 180.00 1620.00
mesh over window with chir wood
beading i/c s/o all m/l t&p etc required
for proper completion of the work.

17 Supply & fixing of heavy quality 16.00 sqm 162.00 160.00 2560.00
oxidized iron fitting for door & window
with necessary ms hinges, steel screw,
nut, bolts & other material as per
requirement.

18 M.S./Tor steel or iron work in plain 22.00 Qtl 5781.00 4900.00 107800.00
work such as in reinforcement cement
concrete brought to required shape as
necessary including binding for proper
shape including cost of supply of all
materials, labour, T&P etc. required for
proper completion of the work.

19 Supply & fixing 32 mm thick 11.00 Sqm 1398.00 1200.00 13200.00


commercial ply wood flush door shutter
of approved make including s/f of
wooden cleat & fixing of hinges locks,
bolts, handles & other fitting required
for proper completion of the work.
Sr No Particulars of Items Qty Unit Rate as per Rate as per Amount as
Analysis Bond per bond in
Rs.

1 2 3 4 5 6
20 S/F of 4 cm thick C.P.chir wood fully 9.00 Sqm 1982.00 1400.00 12600.00
glazed door & window shutter i/c s/f of
wooden cleats & stoppers & fixing od
adjustment hinges, bolts, handles etc all
complete.

21 S/F of sal wood chaukhat & other 0.40 Cum 59528.00 53000.00 21200.00
framed i/c all material labour, t&p etc
required for proper completion of the
work.

22 Rendering of roof slab with 1:3 cement 198.00 Sqm 111.00 120.00 23760.00
& coarse sand mortar 6 mm thick just
after RCC slab i/c all material, labour,
t&p etc required for proper completion
of the work.

Total 799492.00
Below -266230.84
33.30% as
per bond
Total B 533261.16
Say 533261.00

Junior Engineer Assistant Engineer Executive Engineer


P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari
BILL OF QUANTITY

NAME OF WORK: Construction of Helipad at Harshil under deposit work of civil Aviation
Department.

Sr No Particulars of Items Qty Unit Rate Amount in


Rs.
1 2 3 4 5 6
Extra Items which are necessary but not taken in
aggrement previously.
1 RR stone masonary laid 1:6 cement, f/sand material 54.00 cum 1527.00 82458.00
in foundation of wall i/c s/o all m/l, t&p etc required
for proper completion of the work.

2 Two Coat of oil bond Distemper surface i/c s/o all 255.00 sqm 53.00 13515.00
material, labour, t&p etc required for proper
completion of the work.

3 Supply & fixing of tiles in flooring & dado in 1:3 102.50 Sqm 198.00 20295.00
cement, c/sand mortar i/c s/o all m/l, t&p etc all
complete.

4 P/f of white glazed viterious china wash basin R.S. or 2.00 No 3349.00 6698.00
C.I. basin painted white crome polish with stand of
parryware company, piller tab of Jaquar com. &
union complete.

5 P/F of Soil or Vent pipe 110 mm dia of approved 21.00 Rmt 357.00 7497.00
quality i/c s/o all complete.

6 Same as above but 75 mm dia 16.00 Rmt 59.00 944.00

7 P/F of Nahani trap 110 mm dia inlet 75 mm dia outlet 4.00 Nos 433.00 1732.00
i/c cost of cutting hole & making good the wall i/c s/o
all m/l , t&p etc all complete.

8 P/F of Manhole cover (45x45)cm or (60x60) cm 4.00 Nos 855.00 3420.00


inside size double seal frame of approved quality i/c
s/o all m/l, t&p etc required for proper completion of
the work.

9 P/f of 15 mm dia 'B' class (jindal STC marked) GI 26.30 Rmt 144.00 3787.20
pipe complete with GI special such as bends, Tee,
socket, cross, clamps etc cutting & making good the
wall etc i/c s/o all m/l, t&p etc required for proper
completion of the work.
Sr No Particulars of Items Qty Unit Rate Amount in
Rs.
1 2 3 4 5 6
10 S/f of bib cock (1.27cm) 1/2"dia i/c s/o all m/l, t&p 8.00 N0 853.00 6824.00
etc required proper completion of the work. Jaquar
make.

11 Same as above but wall mixture of Jaquar make. 2.00 No 3009.00 6018.00

12 S/F of indian type W/C sheet of parryware make with 2.00 Nos 2662.00 5324.00
cystern.

13 S/F of Towel rod of Stainless steel with Jaquar make. 2.00 Nos 1232.00 2464.00

14 S/F of Soap dish 2.00 Nos 932.80 1865.60

15 S/F of angle cock. 6.00 Nos 704.00 4224.00

16 S/F of 4" dia C.I.waste pipe i/c s/o all m/l, t&p etc 14.50 Rmt 291.00 4219.50
required for proper completion of the work.

17 Providing & fixing of C.I. plain bends 5 to 10 cm dia 5.00 Nos 128.00 640.00
i/c s/o all m/l, t&p etc required for proper completion
of the work.

Total C 171925.30
Say 171925.00

Junior Engineer Assistant Engineer Executive Engineer


P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari
BILL OF QUANTITY

NAME OF WORK: Construction of Helipad at Harshil under deposit work of civil Aviation
Department.

Sr No Particulars of Items Qty Unit Rate Amount


1 2 3 4 5 6
For Approach Road
1 Collection & consolidation of 45-63 mm size 257.00 cum 689.00 177073.00
stone ballast in 10 mm loose thick &
compaction by 8-10 ton road roller i/c
spreading of bimding material i/c s/o all m/l,
t&p etc required for proper completion of the
work.

2 Collection & consolidation of 22.5-50 mm 257.00 cum 739.00 189923.00


size stone ballast in 10 mm loose thick &
compaction by 8-10 ton road roller i/c
spreading of binding material i/c type A seal
coat & s/o all m/l, t&p etc required for proper
completion of the work.

3 2 cm thick premix carpet with bitumen 769.00 sqm 298.00 229162.00


applying tack coat & graded crushed grit 13.2
mm & 11.2 mm size in proportion of 2:1 and
cleaning of premix surface i/c s/o all m/l, t&p
etc required for proper completion of the
work.

Total D 596158.00
Total of A+B+C+D 4630033.00
Say 4630033.00

Junior Engineer Assistant Engineer Executive Engineer


P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari
SUMMARY OF ESTIMATED COST

NAME OF WORK: Construction of Helipad at Harshil under deposit work of civil Aviation
Department.

Sl no Item of works Estimated Cost in Rs.

Construction of Halipad at Harshil under deposit work


1 4630033.00
of Airport authority.

2 Add contingency 4% 185201.32

3 Add lump-sum for purchasing furniture 150000.00

Grant Total 4965234.32

Say 49.65 Lac

Junior Engineer Assistant Engineer Execuitive Engineer


Pron. Div. PWD Pron. Div. PWD Pron. Div. PWD
Bhatwari Bhatwari Bhatwari
PWA Form No-2
Abstract Of Charges
Name of Work
Rs. P. Rs. P. Rs. P. Rs. P. Rs. P. Rs. P. Rs. P. Rs. P. Rs. P. Rs. P. Rs. P.
PWA Form 2 See chapter VI Paragraph 166 to 172
Form-2 Imprest Cash Account Book
Imprest Cash Book of shree- Pradeep Mamgain
Month & Voucher No. Transactions Amount of each Total Head of Account
Date Payment
1 2 3 4 5 6
List of Quarters
Sl no Type of Building Type of House Name of alloweted Govt. Servent
1 Type - IV RCC roof Executive Engineer
2 Type - I/1 GI roof & walling Raju Chaukidar
3 Type - I/2 GI roof & walling Narottam Chaukidar
4 Type -II/1 GI roof & wall in RR1:6 Y.S. Bisht
5 type - II/2 GI roof & wall in RR1:6 Teeka ram nautiyal
6 Type - I/3 GI roof & wall in RR1:6
7 Type - I/4 GI roof & wall in RR1:6
8 Type - I/5 GI roof & wall in RR1:6
9 Type - I/6 GI roof & wall in RR1:6
10 type - II/3 GI roof & wall in RR1:6 B.S.Mahar
11 type - II/4 GI roof & wall in RR1:6 Dharmender Singh
12 type - II/5 GI roof & wall in RR1:6 Prdadeep Mamgain
13 type - II/6 GI roof & wall in RR1:6 Vikram Singh
14 type - I/7 GI roof & walling Chaukidar Kalibahadur
15 type - I/8 GI roof & walling Kirti chand
16 type - I/9 GI roof & walling Kirti chand
17 type - I/10 GI roof & walling Dev chand
18 type - I/11 GI roof & walling
19 type - I/12 GI roof & walling
20 type - I/13 GI roof & walling Type - D near store
21 type - I/14 GI roof & walling
22 type - I/15 GI roof & walling
23 Type - III/1 GI roof & walling Dinesh Purohit
24 Type - III/2 GI roof & walling Sanjeev kumar
25 Type - III/3 GI roof & walling Dinesh verman
26 Type - III/4 GI roof & walling Bachinath
27 Type - III/5 GI roof & walling Empty
28 Type - III/6 GI roof & walling Charan singh
29 Type - IV/1 GI roof & walling Rajiv Kumar
30 Type - IV/2 GI roof & walling empty
31 Type - IV/3 GI roof & walling Sh. Zafar Ali
32 Type - II/7 GI roof & walling Jeetinder mahar
33 Type - II/8 GI roof & walling Mate sunder singh
34 type - I/16 GI roof & walling
35 type - I/17 GI roof & walling
36 type - I/18 GI roof & walling Rajpal (sweeper) barique - C
37 type - I/19 GI roof & walling
38 type - I/20 GI roof & walling
39 type - I/21 GI roof & walling
40 type - I/22 GI roof & walling
41 type - I/23 GI roof & walling
Barique - D (6 Nos)
42 type - I/24 GI roof & walling
Barique - D (6 Nos)

43 type - I/25 GI roof & walling


44 type - I/26 GI roof & walling
45 type - I/27 GI roof & walling
46 type - I/28 GI roof & walling
47 type - I/29 GI roof & walling
48 type - I/30 GI roof & walling Barique - B (7 Nos)
49 type - I/31 GI roof & walling
50 type - I/32 GI roof & walling
51 type - I/33 GI roof & walling
52 type - I/34 GI roof & walling
53 type - I/35 GI roof & walling
54 type - I/36 GI roof & walling
55 type - I/37 GI roof & walling
56 type - I/38 GI roof & walling
57 type - I/39 GI roof & walling Barique- A
58 type - I/40 GI roof & walling
59 type - I/41 GI roof & walling
60 type - I/42 GI roof & walling
61 type - I/43 GI roof & walling
62 type - I/44 GI roof & walling
Details of House

Sl No House No / Type of House Year of Construction Proposed Repairing


Type

1 Type IV A RCC slab & Brick walls 1993 Not Applicable


2 Type IV/1 GI roof & GI wall 1962 Painting, repairing of floor
3 Type IV/2 GI roof & GI wall 1962 Painting, repairing of floor & apron
4 Type IV/3 GI roof & GI wall 1962 Painting & repairing of floor
5 Type III/1 GI roof & GI wall 1966 Painting, construction of drain, repairing of floor & apron
6 Type III/2 GI roof & GI wall 1966 Painting, construction of drain, repairing of floor & apron
7 Type III/3 GI roof & GI wall 1966 Painting, construction of drain, repairing of floor & apron
8 Type III/4 GI roof & GI wall 1966 Painting, construction of drain, repairing of floor & apron
9 Type III/5 GI roof & GI wall 1966 Painting
10 Type III/6 GI roof & GI wall 1962 Painting & repairing of floor
11 Type III/7 GI roof & GI wall 1962 Painting & repairing of floor
12 Type III/8 GI roof & GI wall 1962 Painting & repairing of floor
13 Type II/1 Brick walls, partiatly GI wall & roof in GI sheet 1970 Painting, white washing, snowcem & flooring
14 Type II/2 Brick walls, partiatly GI wall & roof in GI sheet 1970 Painting, white washing, snowcem & flooring
15 Type II/3 Brick walls, partiatly GI wall & roof in GI sheet 1966 snowcem & construction of drain
16 Type II/4 Brick walls, partiatly GI wall & roof in GI sheet 1966 Snowcem
17 Type II/5 Brick walls, partiatly GI wall & roof in GI sheet 1966 Painting, white washing, snowcem & flooring
18 Type II/6 Brick walls, partiatly GI wall & roof in GI sheet 1993 Painting, white washing, snowcem & flooring
19 Type I/1 GI roof & GI wall 1993 Painting & flooring
20 Type I/2 GI roof & GI wall 1993 Painting & flooring
21 Type I/3 GI roof & brick wall 1966 Painting, flooring,white washing, snowcem & plastering
22 Type I/4 GI roof & brick wall 1966 Painting, flooring,white washing, snowcem & plastering
23 Type I/5 GI roof & brick wall 1966 Painting, flooring,white washing, snowcem & plastering
24 Type I/6 GI roof & brick wall 1966 Painting, flooring,white washing, snowcem & plastering
25 Type I/7 GI roof & GI wall 1970 Painting, flooring, apron & change of GI sheet
26 Type I/8 GI roof & GI wall 1963 Painting, flooring, apron & change of GI sheet
27 Type I/9 GI roof & GI wall 1963 Painting, flooring, apron & change of GI sheet
28 Type I/10 GI roof & GI wall 1963 Painting, flooring, apron & change of GI sheet
29 Type I/11 GI roof & GI wall 1963 Painting, flooring, apron & change of GI sheet
30 Type I/12 GI roof & GI wall 1963 Painting, flooring, apron & change of GI sheet
31 Type I/13 GI roof & GI wall 1963 Painting, flooring, apron & change of GI sheet
Details of House

Sl No House No / Type of House Year of Construction Proposed Repairing


Type

32 Type I/14 GI roof & GI wall 1963 Painting, flooring, apron & change of GI sheet
33 Type I/15 GI roof & GI wall 1963 Painting, flooring, apron & change of GI sheet
34 Type I/16 GI roof & GI wall 1963 Painting, construction of drain, repairing of floor change of GI roof
35 Type I/17 GI roof & GI wall 1963 Painting, construction of drain, repairing of floor change of GI roof
36 Type I/18 GI roof & GI wall 1963 Painting, construction of drain, repairing of floor change of GI roof
37 Type I/19 GI roof & GI wall 1963 Painting, construction of drain, repairing of floor change of GI roof
38 Type I/20 GI roof & GI wall 1963 Painting, construction of drain, repairing of floor change of GI roof
39 Type I/21 GI roof & GI wall 1963 Painting & flooring
40 Type I/22 GI roof & GI wall 1963 Painting & flooring
41 Type I/23 GI roof & GI wall 1963 Painting & flooring
42 Type I/24 GI roof & GI wall 1963 Painting & flooring
43 Type I/25 GI roof & GI wall 1963 Painting & flooring
44 Type I/26 GI roof & GI wall 1963 Painting & flooring
45 Type I/27 GI roof & GI wall 1963 Painting & flooring
46 Type I/28 GI roof & GI wall 1963 Painting & flooring
47 Type I/29 GI roof & GI wall 1963 Painting & flooring
48 Type I/30 GI roof & GI wall 1963 Painting & flooring
49 Type I/31 GI roof & GI wall 1963 Painting & flooring
50 Type I/32 GI roof & GI wall 1963 Painting & flooring
51 Type I/33 GI roof & GI wall 1963 Painting & flooring
52 Type I/34 GI roof & GI wall 1963 Painting & flooring
53 Type I/35 GI roof & GI wall 1963 Painting & flooring
54 Type I/36 GI roof & GI wall 1963 Painting & flooring
55 Type I/37 GI roof & GI wall 1963 Painting & flooring
56 Type I/38 GI roof & GI wall 1963 Painting & flooring
57 Type I/39 GI roof & GI wall 1963 Painting & flooring
58 Type I/40 GI roof & GI wall 1963 Painting & flooring
59 Type I/41 GI roof & GI wall 1963 Painting & flooring
60 Type I/42 GI roof & GI wall 1963 Painting & flooring
61 Type I/43 GI roof & GI wall 1963 Painting & flooring
62 Type I/44 GI roof & GI wall 1963 Painting & flooring
Comparitive Statement

NAME OF WORK: Construction of Helipad at Harshil under deposit work of civil Aviation Department.

Sl Items Unit As per TS estimate As per Bond As per Actual work to be done
no
Qty Rate Amount Qty Rate Amount Qty Rate Amount Qty Rate Amount
1 Excavation in foundation in all type of Cum 730.00 47.60 34748.00 730.00 47.00 34310.00 554.00 47.00 26038.00 -176.00 47.00 -8272.00
soil i/c s/o all m/l, t&p etc required
for proper completion of the work.

2 Filling work by river bed materials i/c Cum 8790.00 279.00 2452410.00 8790.00 275.00 2417250.00 11667.00 275.00 3208425.00 2877.00 275.00 791175.00
watering dressing, ramming as per
direction of EIC.

3 Concrete with 2cm gauge stone Cum 48.00 4364.00 209472.00 48.00 4200.00 201600.00 48.00 4200.00 201600.00 0.00 4200.00 0.00
ballast, c/sand & cement in
proportion of 3:1.5:1 in foundation
i/c s/o all m/l, t&p etc required for
proper completion of the work.

4 RR stone masonary laid in 1:6 Cum 683.00 1115.00 761545.00 683.00 1100.00 751300.00 494.00 1100.00 543400.00 -189.00 1100.00 -207900.00
cement, sand mortar i/c s/o all m/l,
t&p etc required for proper
completion of the work.

5 RR stone masonary laid dry i/c s/o all Cum 190.00 533.00 101270.00 190.00 530.00 100700.00 167.00 530.00 88510.00 -23.00 530.00 -12190.00
m/l, t&p etc required for proper
completion of the work.
6 Cement plum masonary with 40% Cum 230.00 2340.00 538200.00 230.00 2450.00 563500.00 374.70 2450.00 918015.00 144.70 2450.00 354515.00
plum & 60% cement concrete in
proportion of 1:3:6 cement concrete
approved 40 mm gauge stone ballast
i/c s/o all m/l, t&p etc required for
proper completion of the work.
7 Painting & varnishing on iron work in Sqm 70.00 71.00 4970.00 70.00 65.00 4550.00 70.00 65.00 4550.00 0.00 65.00 0.00
small area with one coat ready mixed
primer & two coat approved enamel
paint i/c s/o all m/l, t&p etc required
for proper completion of the work.

8 Excavation in foundation in all type of Cum 0.00 86.00 59.00 5074.00 122.00 59.00 7198.00 36.00 59.00 2124.00
soil i/c lift upto 1.5 m & lead upto 30
meter & i/c filling, watering, ramming
of excavated earth into the trenches
or in it to the space between the
building & site of foundation trenches
or into the plinth & removal &
disposal of surplus earth as directed
by tje engineer charge up to a
distance of 30 meter from the
foundation trenches.

9 Cement, concrete with 40 mm gauge Cum 0.00 11.50 2150.00 24725.00 83.00 2150.00 178450.00 71.50 2150.00 153725.00
locally available approved stone
ballast, coarse sand and cement in
proportion of 12:6:1 in foundation
including cost of materials, labour,
T&P etc. required for proper
completion of the work.

10 Class M-100 brick thick work in 1:6 Cum 0.00 32.50 3200.00 104000.00 36.10 3200.00 115520.00 3.60 3200.00 11520.00
cement sand mortar in super
structure i/c s/o all material, labour
t&p etc required for proper
completion of the work.

11 Same as above but brick masonary in Cum 0.00 35.00 3500.00 122500.00 0.00 3500.00 0.00 -35.00 3500.00 -122500.00
one wall brick in super structure etc
required for proper completion of the
work.
12 Reinforced cement concrete in Cum 0.00 6.00 4800.00 28800.00 17.10 4800.00 82080.00 11.10 4800.00 53280.00
proportion of 1:1.5:3 (M-20) in
cement, coarse sand and 20mm
gauge stone grit as per specification
and drawing including cost of
material, labour, T&P etc. required
for proper completion of the work.
Raft, column & lintel.

13 2.5 cm thick 1:2:4 cement concrete Sqm 0.00 50.00 275.00 13750.00 295.00 275.00 81125.00 245.00 275.00 67375.00
floor with 7.5 cm thick 1:6:12 base
concrete with c/sand & 20 mm gauge
s/ballast i/c s/o all m/l , t&p etc
required for proper completion of the
work.

14 Same as above but floor 4cm thick Sqm 0.00 7.50 150.00 1125.00 0.00 150.00 0.00 -7.50 150.00 -1125.00
without base concrete.
15 20 mm thick plaster with 1:2 cement Sqm 0.00 7.50 130.00 975.00 22.00 130.00 2860.00 14.50 130.00 1885.00
& fine sand on dado or skirting laid in
panels finished with 3mm floating
coat of cement i/c s/o all material,
labour, t&p etc required for proper
completion of the work.

16 P/F of 25mm wide & 4.8 mm thick Rmt 0.00 125.00 15.00 1875.00 63.00 15.00 945.00 -62.00 15.00 -930.00
glass strip i/c s/o all m/l, t&p etc
required for proper completion of the
work.

17 12 mm thick plaster in 1:6 cement, Sqm 0.00 353.00 140.00 49420.00 307.00 140.00 42980.00 -46.00 140.00 -6440.00
sand mortar i/c s/o all m/l, t&p etc
required for proper completion of the
work.

18 Same as above item but extra over Sqm 0.00 176.50 7.00 1235.50 154.00 7.00 1078.00 -22.50 7.00 -157.50
rough face of one brick wall.
19 Add extra labour & material for Rmt 0.00 101.00 9.00 909.00 101.00 9.00 909.00 0.00 9.00 0.00
making grooves line in plaster on
outer face of wall & joint between
RCC roof & walls i/c all labour,
material, t&p etc required for proper
completion of the work.

20 Add extra labour & material for Rmt 0.00 58.00 18.00 1044.00 59.00 18.00 1062.00 1.00 18.00 18.00
making of drip course (20x30mm) in
projection of roof & sun shade.
Completion as per direction of EIC.

21 Finishing of walls with water proof Sqm 0.00 353.00 35.00 12355.00 115.00 35.00 4025.00 -238.00 35.00 -8330.00
cement paint with two coats to given
shades i/c s/o all m/l, t&p etc all
complete.

22 Painting on new iron works with two Sqm 0.00 54.00 60.00 3240.00 52.00 60.00 3120.00 -2.00 60.00 -120.00
coats of approved paint including cost
of supply of all materials, labour, T&P
etc. required for proper completion
of the work as per direction of
Engineer-in-charge.

23 Supply & fixing of security grill over Sqm 0.00 7.20 750.00 5400.00 7.20 750.00 5400.00 0.00 750.00 0.00
window as per drawing or as per
instruction of engineer in charge i/c
welding & supply of all materails,
labours, t&p etc required for proper
completion of the work.

24 S/F of Galavanized mosquito proof Sqm 0.00 9.00 180.00 1620.00 9.00 180.00 1620.00 0.00 180.00 0.00
wire mesh over window with chir
wood beading i/c s/o all m/l t&p etc
required for proper completion of the
work.

25 Supply & fixing of heavy quality Sqm 0.00 17.00 160.00 2720.00 16.00 160.00 2560.00 -1.00 160.00 -160.00
oxidized iron fitting for door &
window with necessary ms hinges,
steel screw, nut, bolts & other
material as per requirement.
26 Rendering of roof slab with 1:3 Sqm 0.00 96.00 120.00 11520.00 198.00 120.00 23760.00 102.00 120.00 12240.00
cement & coarse sand mortar 6 mm
thick just after RCC slab i/c all
material, labour, t&p etc required for
proper completion of the work.

27 Reinforced cement concrete in Sqm 0.00 13.00 5000.00 65000.00 18.00 5000.00 90000.00 5.00 5000.00 25000.00
proportion of 1:1.5:3 (M-20) in
cement, coarse sand and 20mm
gauge stone grit as per specification
and drawing including cost of
material, labour, T&P etc. required
for proper completion of the work.
For roof slab & roof beams.

28 M.S./Tor steel or iron work in plain Qtl 0.00 21.00 4900.00 102900.00 22.00 4900.00 107800.00 1.00 4900.00 4900.00
work such as in reinforcement
cement concrete brought to required
shape as necessary including binding
for proper shape including cost of
supply of all materials, labour, T&P
etc. required for proper completion
of the work.

29 Cement concrete with cement, Cum 0.40 3500.00 1400.00 0.00 3500.00 0.00 -0.40 3500.00 -1400.00
c/sand & 20 mm gauge s/ballast in
proportion of 1:2:4 in hold fast i/c s/o
all m/l, t&p etc required for proper
completion of the work.

30 Supply & fixing 32 mm thick Sqm 0.00 9.70 1200.00 11640.00 11.00 1200.00 13200.00 1.30 1200.00 1560.00
commercial ply wood flush door
shutter of approved make including
s/f of wooden cleat & fixing of hinges
locks, bolts, handles & other fitting
required for proper completion of the
work.
31 S/F of 4 cm thick C.P.chir wood fully Sqm 0.00 7.20 1400.00 10080.00 9.00 1400.00 12600.00 1.80 1400.00 2520.00
glazed door & window shutter i/c s/f
of wooden cleats & stoppers & fixing
od adjustment hinges, bolts, handles
etc all complete.

32 S/F of sal wood chaukhat & other Cum 0.00 0.40 53000.00 21200.00 0.40 53000.00 21200.00 0.00 53000.00 0.00
framed i/c all material labour, t&p etc
required for proper completion of the
work.

4677717.50 5790030.00 1112312.50


deduct 33.30% as per bond -1557679.93 -1928079.99 -370400.06
Total 3120037.57 3861950.01 741912.44
33 RR stone masonary laid 1:6 cement, Cum 0.00 0.00 54.00 1527.00 82458.00 54.00 1527.00 82458.00
f/sand material in foundation of wall
i/c s/o all m/l, t&p etc required for
proper completion of the work.

34 Two Coat of oil bond Distemper Sqm 0.00 0.00 255.00 53.00 13515.00 255.00 53.00 13515.00
surface i/c s/o all material, labour,
t&p etc required for proper
completion of the work.

35 Supply & fixing of tiles in flooring & Sqm 0.00 0.00 102.50 198.00 20295.00 102.50 198.00 20295.00
dado in 1:3 cement, c/sand mortar i/c
s/o all m/l, t&p etc all complete.

36 P/f of white glazed viterious china No 0.00 0.00 2.00 3349.00 6698.00 2.00 3349.00 6698.00
wash basin R.S. or C.I. basin painted
white crome polish with stand of
parryware company, piller tab of
Jaquar com. & union complete.

37 P/F of Soil or Vent pipe 110 mm dia Rmt 0.00 0.00 21.00 357.00 7497.00 21.00 357.00 7497.00
of approved quality i/c s/o all
complete.
38 Same as above but 75 mm dia Rmt 0.00 0.00 16.00 59.00 944.00 16.00 59.00 944.00
39 P/F of Nahani trap 110 mm dia inlet No 0.00 0.00 4.00 433.00 1732.00 4.00 433.00 1732.00
75 mm dia outlet i/c cost of cutting
hole & making good the wall i/c s/o
all m/l , t&p etc all complete.

40 P/F of Manhole cover (45x45)cm or No 0.00 0.00 4.00 855.00 3420.00 4.00 855.00 3420.00
(60x60) cm inside size double seal
frame of approved quality i/c s/o all
m/l, t&p etc required for proper
completion of the work.

41 P/f of 15 mm dia 'B' class (jindal STC Rmt 0.00 0.00 26.30 144.00 3787.20 26.30 144.00 3787.20
marked) GI pipe complete with GI
special such as bends, Tee, socket,
cross, clamps etc cutting & making
good the wall etc i/c s/o all m/l, t&p
etc required for proper completion of
the work.

42 S/f of bib cock (1.27cm) 1/2"dia i/c No 0.00 0.00 8.00 853.00 6824.00 8.00 853.00 6824.00
s/o all m/l, t&p etc required proper
completion of the work. Jaquar make.

43 Same as above but wall mixture of No 0.00 0.00 2.00 3009.00 6018.00 2.00 3009.00 6018.00
Jaquar make.
44 S/F of indian type W/C sheet of No 0.00 0.00 2.00 2662.00 5324.00 2.00 2662.00 5324.00
parryware make with cystern.
45 S/F of Towel rod of Stainless steel No 0.00 0.00 2.00 1232.00 2464.00 2.00 1232.00 2464.00
with Jaquar make.
46 S/F of Soap dish No 0.00 0.00 2.00 932.80 1865.60 2.00 932.80 1865.60
47 S/F of angle cock. No 0.00 0.00 6.00 704.00 4224.00 6.00 704.00 4224.00
48 S/F of 4" dia C.I.waste pipe i/c s/o all Rmt 0.00 0.00 14.50 291.00 4219.50 14.50 291.00 4219.50
m/l, t&p etc required for proper
completion of the work.
49 Providing & fixing of C.I. plain bends 5 No 0.00 0.00 5.00 128.00 640.00 5.00 128.00 640.00
to 10 cm dia i/c s/o all m/l, t&p etc
required for proper completion of the
work.
50 Collection & consolidation of 45-63 Cum 0.00 0.00 257.00 739.00 189923.00 257.00 739.00 189923.00
mm size stone ballast in 10 mm loose
thick & compaction by 8-10 ton road
roller i/c spreading of bimding
material i/c s/o all m/l, t&p etc
required for proper completion of the
work.

51 Collection & consolidation of 22.5-50 Cum 0.00 0.00 257.00 689.00 177073.00 257.00 689.00 177073.00
mm size stone ballast in 10 mm loose
thick & compaction by 8-10 ton road
roller i/c spreading of binding
material i/c type A seal coat & s/o all
m/l, t&p etc required for proper
completion of the work.

52 2 cm thick premix carpet with Sqm 0.00 0.00 769.00 298.00 229162.00 769.00 298.00 229162.00
bitumen applying tack coat & graded
crushed grit 13.2 mm & 11.2 mm size
in proportion of 2:1 and cleaning of
premix surface i/c s/o all m/l, t&p etc
required for proper completion of the
work.

Grant Total 4102615.00 3120037.57 4630033.31 1509995.74


Contingency 164104.60 Contingency 185201.33
Total 4266719.60 Total 4815234.64
Say 42.67 lac Say 48.15 lac
EXTRA ITEM SLIP
Name of Work :-Construction of Helipad at Harshil under deposit of Civil Aviation department. CB no with date :- 06/SE dated 24.07.2008
Name of Contractor - Sri Kalam Singh Rana. CB amount :-
Sanctioned Amount :- Rs. 49.65 Lac Expenditure upto submit this Extra item :- Rs. 31.86 Lac
Total Expenditure against of work sanction :- Rs. 31.86 Lac
Sl Items of Work Unit As per sanctioned estimate AS per current S.O.R. As per agree contractor As per recommendation by E.E. on sanction cost Remarks
No Qty Rate Amount Qty Rate Amount Qty Rate Amount Qty Rate Amount Excess saving %
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
1 RR stone masonary laid 1:6 mDr lHkh enksa
cement, f/sand material in dk vkx.ku esa
foundation of wall i/c s/o all m/l, ikzfo/kku j[kk
t&p etc required for proper x;k gS tks fd
completion of the work. Cum 54.00 1527.00 82458.00 54.00 1527.00 82458.00 54.00 1527.00 82458.00 54.00 1527.00 82458.00 nil nil nil
vkids dk;kZy; ds
i=kad 2684
Hkou@107
lh0ch0 6@2010
2 Two Coat of oil bond Distemper fnukad
surface i/c s/o all material, labour,
t&p etc required for proper 02@07@2010 }
completion of the work. Sqm 255.00 53.00 13515.00 255.00 53.00 13515.00 255.00 53.00 13515.00 255.00 53.00 13515.00 nil nil nil kjk Lohd`r gSaA
mDr enksa dk
vuqcz/k esa
izkfo/kku u
3 Supply & fixing of tiles in flooring gksus ds dkj.k
& dado in 1:3 cement, c/sand Lohd`fr gsrq
mortar i/c s/o all m/l, t&p etc all Sqm 102.50 198.00 20295.00 102.50 198.00 20295.00 102.50 198.00 20295.00 102.50 198.00 20295.00 nil nil nil vkidks izsf"kr
complete. fd;s tk jgsa gSA

4 P/f of white glazed viterious china


wash basin R.S. or C.I. basin
painted white crome polish with
stand of parryware company,
piller tab of Jaquar com. & union No 2.00 3349.00 6698.00 2.00 3349.00 6698.00 2.00 3349.00 6698.00 2.00 3349.00 6698.00 nil nil nil
complete.

5 P/F of Soil or Vent pipe 110 mm


dia of approved quality i/c s/o all Mtr 21.00 357.00 7497.00 21.00 357.00 7497.00 21.00 357.00 7497.00 21.00 357.00 7497.00 nil nil nil
complete.

6 Same as above but 75 mm dia Mtr 16.00 59.00 944.00 16.00 59.00 944.00 16.00 59.00 944.00 16.00 59.00 944.00 nil nil nil
7 P/F of Nahani trap 110 mm dia
inlet 75 mm dia outlet i/c cost of
cutting hole & making good the
wall i/c s/o all m/l , t&p etc all No 4.00 433.00 1732.00 4.00 433.00 1732.00 4.00 433.00 1732.00 4.00 433.00 1732.00 nil nil nil
complete.
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19
8 P/F of Manhole cover (45x45)cm
or (60x60) cm inside size double
seal frame of approved quality i/c
s/o all m/l, t&p etc required for
proper completion of the work. No 4.00 855.00 3420.00 4.00 855.00 3420.00 4.00 855.00 3420.00 4.00 855.00 3420.00 nil nil nil

9 P/f of 15 mm dia 'B' class (jindal


STC marked) GI pipe complete
with GI special such as bends, Tee,
socket, cross, clamps etc cutting &
making good the wall etc i/c s/o all
m/l, t&p etc required for proper
completion of the work. Mtr 26.30 144.00 3787.20 26.30 144.00 3787.20 26.30 144.00 3787.20 26.30 144.00 3787.20 nil nil nil &rnSo&

10 S/f of bib cock (1.27cm) 1/2"dia i/c


s/o all m/l, t&p etc required
proper completion of the work. No 8.00 853.00 6824.00 8.00 853.00 6824.00 8.00 853.00 6824.00 8.00 853.00 6824.00 nil nil nil &rnSo&
Jaquar make.

11 Same as above but wall mixture of


Jaquar make. No 2.00 3009.00 6018.00 2.00 3009.00 6018.00 2.00 3009.00 6018.00 2.00 3009.00 6018.00 nil nil nil &rnSo&

12 S/F of indian type W/C sheet of


parryware make with cystern. No 2.00 2662.00 5324.00 2.00 2662.00 5324.00 2.00 2662.00 5324.00 2.00 2662.00 5324.00 nil nil nil &rnSo&

13 S/F of Towel rod of Stainless steel


with Jaquar make. No 2.00 1232.00 2464.00 2.00 1232.00 2464.00 2.00 1232.00 2464.00 2.00 1232.00 2464.00 nil nil nil &rnSo&

14 S/F of Soap dish No 2.00 932.80 1865.60 2.00 932.80 1865.60 2.00 932.80 1865.60 2.00 932.80 1865.60 nil nil nil &rnSo&
15 S/F of angle cock. No 6.00 704.00 4224.00 6.00 704.00 4224.00 6.00 704.00 4224.00 6.00 704.00 4224.00 nil nil nil &rnSo&
167065.80 167065.80 167065.80 167065.80

Contractor Junior Engineer Assistant Engineer Executive Engineer


Schedule 'B'
Name of Work: - Construction of foundation & painting of
waiting room at Harshil Halipad under
deposit of Civil aviation department.

Date of calling Tender 8/30/2010 Earnest Money 70000.00


Date of receiving Tender 9/25/2010 Cost of Tender 75+13.5% VAT
Form
Date of Opening Tender 27-09-210 Time of Completion 03 Months
Validity Period 45 days

SN Item of work Quantity Unit Rate


In figure In words
1 2 3 4 5 6
1 RR stone masonary laid 1:6 cement, f/sand 54.00 Cum 1527.00 Rs One thousand five
material in foundation of wall i/c s/o all m/l, t&p hundred twenty
etc required for proper completion of the work. seven only.

2 Two Coat of oil bond Distemper surface i/c s/o 255.00 Sqm 53.00 Rs Fifty three only.
all material, labour, t&p etc required for proper
completion of the work.

3 Supply & fixing of tiles in flooring & dado in 1:3 102.50 Sqm 198.00 Rs One hundred
cement, c/sand mortar i/c s/o all m/l, t&p etc all ninty eight only.
complete.

4 P/f of white glazed viterious china wash basin 2.00 No 3349.00 Rs three thousand
R.S. or C.I. basin painted white crome polish with three hundred forty
stand of parryware company, piller tab of Jaquar nine only.
com. & union complete.

5 P/F of Soil or Vent pipe 110 mm dia of approved 21.00 Mtr 357.00 Rs Three hundred
quality i/c s/o all complete. fifty seven only.
6 Same as above but 75 mm dia 16.00 Mtr 59.00 Rs Fifty nine only.
7 P/F of Nahani trap 110 mm dia inlet 75 mm dia 4.00 No 433.00 Rs four hundred
outlet i/c cost of cutting hole & making good the thirty three only.
wall i/c s/o all m/l , t&p etc all complete.

8 P/F of Manhole cover (45x45)cm or (60x60) cm 4.00 No 855.00 Rs Eight hundred


inside size double seal frame of approved quality fifty five only.
i/c s/o all m/l, t&p etc required for proper
completion of the work.

9 P/f of 15 mm dia 'B' class (jindal STC marked) GI 26.30 Mtr 144.00 Rs One hundred
pipe complete with GI special such as bends, forty four only.
Tee, socket, cross, clamps etc cutting & making
good the wall etc i/c s/o all m/l, t&p etc required
for proper completion of the work.

10 S/f of bib cock (1.27cm) 1/2"dia i/c s/o all m/l, 8.00 No 853.00 Rs Eight hundred
t&p etc required proper completion of the work. fifty three only.
Jaquar make.

Page 70 of 77
11 Same as above but wall mixture of Jaquar make. 2.00 No 3009.00 Rs Three thousand
nine only.
12 S/F of indian type W/C sheet of parryware make 2.00 No 2662.00 Rs Two thousand six
with cystern. hundred sixty two
only.

13 S/F of Towel rod of Stainless steel with Jaquar 2.00 No 1232.00 Rs One thousand
make. two hundred thirty
two only.

14 S/F of Soap dish 2.00 No 932.00 Rs Nine hundred


thirty two only.
15 S/F of angle cock. 6.00 No 704.00 Rs Seven hundred
four only.

1 I/we hereby agree to execute the above work..............……………….....................% above/below/at par the rates
filled as above.
2
I/We tender my/our rates as above after taking fully into consideration the specification, special condition of
the department for the above work and rate quoted above are inclusive of all leads, lifts, royalty, municipal
octroi and toll charges and other incident expenses.
3

I/we given below my/our permanent address. Any change in the address shall be intimated by me/us from time
to time in writing to the engineer in charge. We shall make necessary arrangements at all times to receive any
notes, orders and communication that will be issued and sent to me/us at this address. If any letter
communication is received back to sender undelivered, it will be deemed to have been delivered to me/us and
the department will be free to take action in view of the same without entitling me/us for any claim what so
ever on this account.

contractor
(Name and full address)

Officer issuing tender Officer opening tender

Page 71 of 77
1 2 3 4 5 6 7 8 9
1/1
Excavation in foundation in all type of soil i/c
0.00 516.17 516.17 s/o all m/l, t&p etc required for proper 47.00 24259.99 24259.99 0.00
completion of the work.
2/2

Cement plum masonary with 40% plum & 60%


0.00 374.65 374.65 cement concrete in proportion of 1:3:6 cement 2450.00 917892.50 917892.50 0.00
concrete approved 40 mm gauge stone ballast
i/c s/o all m/l, t&p etc required for proper
completion of the work.
3/3

0.00 452.76 452.76 RR stone masonary laid in 1:6 cement, sand 1100.00 498036.00 498036.00 0.00
mortar i/c s/o all m/l, t&p etc required for
proper completion of the work.
4/4
RR stone masonary laid dry i/c s/o all m/l, t&p
0.00 151.30 151.30 etc required for proper completion of the 530.00 80189.00 80189.00 0.00
work.
5/5
0.00 11099.19 11099.19 Filling work by river bed materials i/c watering 275.00 3052277.25 3052277.25 0.00
dressing, ramming as per direction of EIC.
6/6 Concrete with 2cm gauge stone ballast, c/sand
& cement in proportion of 3:1.5:1 in
foundation i/c s/o all m/l, t&p etc required for
48.00 0.00 48.00 proper completion of the work. 4200.00 201600.00 0.00 201600.00

For Building work


1/1 Excavation in foundation in all type of soil i/c
lift upto 1.5 m & lead upto 30 meter & i/c
filling, watering, ramming of excavated earth
into the trenches or in it to the space between
the building & site of foundation trenches or
into the plinth & removal & disposal of surplus
94.43 0.00 94.43 earth as directed by tje engineer charge up to 59.00 5571.37 0.00 5571.37
a distance of 30 meter from the foundation
trenches.

2/2 Cement, concrete with 40 mm gauge locally


available approved stone ballast, coarse sand
and cement in proportion of 12:6:1 in
foundation including cost of materials, labour,
9.42 0.00 9.42 T&P etc. required for proper completion of the 2150.00 20253.00 0.00 20253.00
work.

3/4 Class M-100 brick thick work in 1:6 cement


sand mortar in super structure i/c s/o all
material, labour t&p etc required for proper
22.10 0.00 22.10 completion of the work. 3500.00 77350.00 0.00 77350.00

4/5 Reinforced cement concrete in proportion of


1:1.5:3 (M-20) in cement, coarse sand and
20mm gauge stone grit as per specification and
drawing including cost of material, labour, T&P
16.22 0.00 16.22 etc. required for proper completion of the 4800.00 77856.00 0.00 77856.00
work. Raft, column & lintel.

5/7 M.S./Tor steel or iron work in plain work such


as in reinforcement cement concrete brought
to required shape as necessary including
binding for proper shape including cost of
17.44 0.00 17.44 supply of all materials, labour, T&P etc. 4900.00 85456.00 0.00 85456.00
required for proper completion of the work.

6/11 S/F of sal wood chaukhat & other framed i/c all
material labour, t&p etc required for proper
0.438 0.00 0.438 completion of the work. 53000.00 23214.00 0.00 23214.00

Total 5063955.11 4572654.74 491300.37


33.3% below as per bond condition -1686297.05 -1522694.03 -163603.02
Total 3377658.06 3049960.71 327697.35
G. Total 3377658.06 3049960.71 327697.35
Royality Statement
4th Running Bill

Name of Work :- Construction of Harshil helipad under deposit of Civil Aviation department.
Agency :- CB No 06/SE-6th dated 24-07-2008 Name of Contractor :- Sri Jagmohan Singh
Rawat.
Sl no Item of Work Now to Stone Sand Stone / Ballast
pay Qty Norms Qty Norms Qty Norms Qty

1 PCC 1:6:12 9.42 0.00 0.00 0.50 4.71 0.90 8.48


2 Brick work in 1:6 22.10 0.00 0.00 0.00 0.00 0.27 5.97
3 RCC 1:1.5:3 16.22 0.00 0.00 0.425 6.89 0.85 13.79
4 PCC 1:1.5:3 48.00 0.00 0.00 0.425 20.40 0.85 40.80

Total 0.00 32.00 69.03


Cum @ Cum @ Cum @
45.00 45.00 45.00
0.00 1440.16 3106.44
Total Rs. 4546.60
Say Rs. 4547.00

Now to pay Royality Rs. 4547.00

Junior Engineer Assistant Engineer


P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari
Variation Below 20%
Road Work Regarding contract Bond
Name of Sanctioned work:-Construction of Harshil Helipad under deposit of Civil Aviation Department. Name of work as written in Contract Bond Construction of foundation & Painting of waiting room at Harshil Helipad
under deposit of Civil Aviation department.

sanctioned Cost of work (Asper A.A./E.S.):- Rs. Lac Contract Bond :- 08/AE-III dated 01.10.10 C.B. Amount:-167064.20

Total upto Date Ex. Incurred on the Sanctioned work:-Rs. Lac Name Of Contractor :- Sri Jagmohan Singh Rawat

Total upto Date Ex. Against this work befor this variation:- Rs. Lac Total Ex. Against this C.B. after including this variation:- Rs. 78946.00
Sl.no Name of Item unit As per T.S. Estimate As per C.B. As per Actual Variation over C.B. Variation over T.S. Actual Remark

Qty. Rate Amount Qty. Rate Amount Qty. Rate Amount Excess Saving % Excess Saving %

1 2 3 4 5 6 7 8 9 13 14 15 16 17 18 22 23 24 25
1/1 RR stone masonary Bsdsnkj }kjk
laid 1:6 cement, dk;Z u fd;s
f/sand material in tkus ds dkj.k
foundation of wall i/c vfUreh dj.k dj
s/o all m/l, t&p etc
required for proper Cum 54.00 1,527.00 82,458.00 54.00 1,527.00 82,458.00 51.70 1,527.00 78,945.90 - 3,512.10 4.27 - 3,512.10 4.27 fn;k x;k] ftl
completion of the dkj.k mDr en
work. es fopyu
vk;kA

Total 82,458.00 82,458.00 78,945.90 - 3,512.10 - 3,512.10

1- The first lowest tender remain lowest after this variation.


2- The item f saving in this varriation and other varriation will not be executed at higher rate in further . Saving over bond 3,512.10
3- The item of all varriation have been inspected E.E. &A.E. and will not hamper the safety of work . Saving over Estimate 3,512.10
The Total cost of work due to this varriation and other approved varriation will not exceed the sanctioned amount of work by Govt .
Variation Above 20%
Road Work Regarding contract Bond
Name of Sanctioned work:-Construction of Harshil Helipad under deposit of Civil Aviation Department. Name of work as written in Contract Bond Construction of foundation & Painting of waiting room at Harshil Helipad
under deposit of Civil Aviation department.

sanctioned Cost of work (Asper A.A./E.S.):- Rs. Lac Contract Bond :- 08/AE-III dated 01.10.10 C.B. Amount:-167064.20

Total upto Date Ex. Incurred on the Sanctioned work:-Rs. Lac Name Of Contractor :- Sri Jagmohan Singh Rawat

Total upto Date Ex. Against this work befor this variation:- Rs. Lac Total Ex. Against this C.B. after including this variation:- Rs.
Sl.no Name of Item unit As per T.S. Estimate As per C.B. As per Actual Variation over C.B. Variation over T.S. Actual
Remark
Qty. Rate Amount Qty. Rate Amount Qty. Rate Amount Excess Saving % Excess Saving %

1 2 3 4 5 6 7 8 9 13 14 15 16 17 18 22 23 24 25
1/2 Two Coat of oil bond Bsdsnkj }kjk
Distemper surface i/c s/o dk;Z u fd;s
all material, labour, t&p etc tkus ds dkj.k
required for proper vfUreh dj.k dj
completion of the work.
Sqm 255.00 53.00 13,515.00 255.00 53.00 13,515.00 - 53.00 - - 13,515.00 100.00 - 13,515.00 100 fn;k x;k] ftl
dkj.k mDr en
es fopyu
vk;kA

2/3 Supply & fixing of tiles in & rnSo&


flooring & dado in 1:3
cement, c/sand mortar i/c
s/o all m/l, t&p etc all Sqm 102.50 198.00 20,295.00 102.50 198.00 20,295.00 - 198.00 - - 20,295.00 100.00 - 20,295.00 100
complete.

3/4 P/f of white glazed & rnSo&


viterious china wash basin
R.S. or C.I. basin painted
white crome polish with
stand of parryware
company, piller tab of
Jaquar com. & union No 2.00 3,349.00 6,698.00 2.00 3,349.00 6,698.00 - 3,349.00 - - 6,698.00 100.00 - 6,698.00 100
complete.

4/5 P/F of Soil or Vent pipe 110 & rnSo&


mm dia of approved
quality i/c s/o all complete. Mtr 21.00 357.00 7,497.00 21.00 357.00 7,497.00 - 357.00 - - 7,497.00 100.00 - 7,497.00 100

5/6 Same as above but 75 mm


dia Mtr 16.00 59.00 944.00 16.00 59.00 944.00 - 59.00 - - 944.00 100.00 - 944.00 100 &rnSo&

6/7 P/F of Nahani trap 110 mm


dia inlet 75 mm dia outlet
i/c cost of cutting hole &
making good the wall i/c
s/o all m/l , t&p etc all No 4.00 433.00 1,732.00 4.00 433.00 1,732.00 - 433.00 - - 1,732.00 100.00 - 1,732.00 100 &rnSo&
complete.
1 2 3 4 5 6 7 8 9 13 14 15 16 17 18 22 23 24 25
7/8 P/F of Manhole cover
(45x45)cm or (60x60) cm
inside size double seal
frame of approved quality
i/c s/o all m/l, t&p etc
required for proper No 4.00 855.00 3,420.00 4.00 855.00 3,420.00 - 855.00 - - 3,420.00 100.00 - 3,420.00 100 &rnSo&
completion of the work.

8/9 P/f of 15 mm dia 'B' class


(jindal STC marked) GI pipe
complete with GI special
such as bends, Tee, socket,
cross, clamps etc cutting &
making good the wall etc
i/c s/o all m/l, t&p etc
required for proper
completion of the work. Mtr 26.30 144.00 3,787.20 26.30 144.00 3,787.20 - 144.00 - - 3,787.20 100.00 - 3,787.20 100 &rnSo&

9/10 S/f of bib cock (1.27cm)


1/2"dia i/c s/o all m/l, t&p
etc required proper
completion of the work. No 8.00 853.00 6,824.00 8.00 853.00 6,824.00 - 853.00 - - 6,824.00 100.00 - 6,824.00 100 &rnSo&
Jaquar make.

10/11 Same as above but wall


mixture of Jaquar make. No 2.00 3,009.00 6,018.00 2.00 3,009.00 6,018.00 - 3,009.00 - - 6,018.00 100.00 - 6,018.00 100 &rnSo&

11/12 S/F of indian type W/C


sheet of parryware make No 2.00 2,662.00 5,324.00 2.00 2,662.00 5,324.00 - 2,662.00 - - 5,324.00 100.00 - 5,324.00 100 &rnSo&
with cystern.

12/13 S/F of Towel rod of


Stainless steel with Jaquar No 2.00 1,232.00 2,464.00 2.00 1,232.00 2,464.00 - 1,232.00 - - 2,464.00 100.00 - 2,464.00 100 &rnSo&
make.

13/14 S/F of Soap dish No 2.00 932.00 1,864.00 2.00 932.00 1,864.00 - 932.00 - - 1,864.00 100.00 - 1,864.00 100 &rnSo&
14/15 S/F of angle cock. No 6.00 704.00 4,224.00 6.00 704.00 4,224.00 - 704.00 - - 4,224.00 100.00 - 4,224.00 100 &rnSo&

Total 84,606.20 84,606.20 - - 84,606.20 - 84,606.20

1- The first lowest tender remain lowest after this variation.


2- The item f saving in this varriation and other varriation will not be executed at higher rate in further . Saving over bond 84,606.20
3- The item of all varriation have been inspected E.E. &A.E. and will not hamper the safety of work . Saving over Estimate 84,606.20
The Total cost of work due to this varriation and other approved varriation will not exceed the sanctioned amount of work by Govt .

You might also like