Rate Analysis

RATE ANALYSIS

DEFINITION
“ The determination of rate per unit of a particular Item of Work,
From the cost of Quantity of Material, the cost of Labour, cost
of Machinery and other misc. petty expense required for its
complete execution as per specification is known as analysis of
Rate.
RATE ANALYSIS

RATE ANALYSIS DEPENDS ON…


• Specification of works and material, quantity of Material, Method of
construction and operation.
• Quantities of materials and their rates, number of Different Type of
Labour and Machinary and their Rate.
• Location of site of work and its distance from the source of
materials and the rates of transport, and availability of water etc.
• Profit, miscellaneous expenses of contractor
RATE ANALYSIS

OVERHEAD COSTS
A)- General Overheads :- B)- Job Overheads :-
• Establishment (Office Staff) • Supervision staff / Engineer
• Stationery, Printing, Postage Salary
etc. • Handling of Material
• Travelling Expenses • Amenities of Labour
• Rent and Taxes • Workman’s compensation and
insurance
• Interest on Investment
• Loss of Advances
RATE ANALYSIS

Labour Basic Rate + Index

Machinery Basic Rate + Index

Material Basic Rate + Cartage Cost


CP & Overhead Fix
Taxes (Labour Cess etc.) Fix
Rates of Labour
Index 9%
ID Name Unit Basic Rate Index Cost Total Rate
PL01 Bhisti Day 250.00 23.25 273.25
PL02 Sprayer (for bitumen, tar etc.) Day 275.00 25.58 300.58
PL03 Blacksmith 1st class/Electrician Day 455.00 42.32 497.32
PL04 Blaster Day 440.00 40.92 480.92
PL11 Fitter (grade 1) Day 440.00 40.92 480.92
PL12 Mason (brick layer) 1st class Day 455.00 42.32 497.32
PL13 Mason (brick layer) 2nd class Day 440.00 40.92 480.92
PL14 Mate Day 275.00 25.58 300.58
PL15 Beldar/mazdoor (unskilled) Day 250.00 23.25 273.25
PL16 Mazdoor (Semi skilled) Day 275.00 25.58 300.58
PL17 Mazdoor/Beldar (Skilled) Day 360.00 33.48 393.48
PL18 Painter (Ist class) Day 440.00 40.92 480.92
PL19 Plumber Day 440.00 40.92 480.92
Rates of Machines & Plants
Index 33%
ID Name Unit Basic Rate Index Cost Total Rate

PMC001 Air Compressor 210 cfm hours 300.00 99.00 399.00


PMC002 Batch mix HMP 40-60 TPH hours 15008.00 4952.64 19960.64
PMC003 Batch type HMP 30/40 TPH hours 11188.00 3692.04 14880.04
PMC004 Bitumen boiler oil fired 200 litre hours 120.00 39.60 159.60
PMC005 Bitumen boiler oil fired 1000 litre hours 120.00 39.60 159.60
PMC006 Bitumen emulsion pressure distributor hours 880.00 290.40 1170.40
PMC007 Concrete mixer 0.28/0.4 cum hours 150.00 49.50 199.50
PMC008 Crane upto 8T hours 430.00 141.90 571.90
PMC009 Dozer D 50 hours 1450.00 478.50 1928.50
PMC010 Electric generator set, 125 KVA hours 950.00 313.50 1263.50
PMC011 Emulsion Sprayer with Tractor hours 1100.00 363.00 1463.00
PMC012 Front end-loader 1 cum bucket capacity hours 900.00 297.00 1197.00
RATE ANALYSIS
Material
Lead Distance from Source of Material

Cartage Cost Per Trip Per Trip Cost of Lead Distance


Resource Capacity Qty. of Material Per Trip
Cartage Cost of Material = Cartage Cost Per Trip
Resource Capacity
Material Rate at Site = Basic Rate + Cartage Cost
Mechanical Cartage Calculation
Litres of Cost of Hire
Litres of Cost of Cost of
No. of Trips No. of Km Mobil oil Beldars Charges of
Lead Avg. Diesel Diesel @ Mobil oil Total cost Cost per
N = 8/(2L/S) Done consumed Nos= 6 Truck
Km L Speed S consumed 52.79 @ 270 (6+8+9+10) Trip (11/ 3)
+1 (2NL+6) @140 @250 @1700
@5 Km/Litre Rs/Litre Rs/Litre
Km/Litre Rs/day Rs/day
1 16 7.11 20.22 4.04 213.51 0.14 39.00 1500.00 1700.00 3452.51 485.51
2 17 6.48 31.90 6.38 336.85 0.23 61.53 1500.00 1700.00 3598.38 555.63
3 17.5 5.96 41.74 8.35 440.74 0.30 80.51 1500.00 1700.00 3721.25 624.64
4 18 5.54 50.31 10.06 531.15 0.36 97.02 1500.00 1700.00 3828.17 691.20
5 18.5 5.19 57.93 11.59 611.62 0.41 111.72 1500.00 1700.00 3923.34 755.51
6 19 4.90 64.84 12.97 684.57 0.46 125.05 1500.00 1700.00 4009.61 817.75
7 19.5 4.66 71.19 14.24 751.67 0.51 137.30 1500.00 1700.00 4088.97 878.08
8 20 4.44 77.11 15.42 814.14 0.55 148.71 1500.00 1700.00 4162.85 936.64
9 20.5 4.26 82.68 16.54 872.89 0.59 159.45 1500.00 1700.00 4232.33 993.57
10 21 4.10 87.95 17.59 928.59 0.63 169.62 1500.00 1700.00 4298.21 1048.97
11 21.5 3.95 92.99 18.60 981.77 0.66 179.33 1500.00 1700.00 4361.11 1102.95
12 22 3.83 97.83 19.57 1032.85 0.70 188.66 1500.00 1700.00 4421.51 1155.62
13 22.5 3.71 102.49 20.50 1082.14 0.73 197.67 1500.00 1700.00 4479.81 1207.06
14 23 3.61 107.02 21.40 1129.91 0.76 206.39 1500.00 1700.00 4536.31 1257.35
RECOURCE CAPACITY for Cartage of Material        
 ID Name Unit Mechanical Manual Mule
Aggregate - For 37.5 mm Maximum size - 22.4 mm to
PM0002 cu.m 6.50 28 18
5.6 mm

PM0024 Aggregates 22.4 mm to 2.36 mm for wet mix macadam cu.m 6.50 28 16

PM0025 Aggregates 45 mm to 22.4 mm for wet mix macadam cu.m 6.50 28 18

PM0026 Aluminum sheeting (1.5 mm thick) sq.m 2,353 12,026 0.04


Aluminum Studs 100 mm x 100 mm fitted with lenses
PM0027 Nos. 0 0 0
reflectors
PM0034 Barbed wire kilogram 9,000 27,000 0.01
PM0048 Brick 1st/2nd Class 1000 Nos 3 15 42
PM0049 Cement tonne 9 57.99 10
PM0055 Corbelling Stones (300 mm x 150 mm x 150 mm) Nos. 1,090 3,837 0.14
PM0056 Corrosion Resistant Structural Steel Grating kilogram 9,000 27,000 0.01
Material Rates for MORI Block
Lead Lead Lead Cost Cost Cost Total
ID Name Rate Unit
Mechanical Manual Mule Mechanical Manual Mule Rate
Aggregate - For 37.5 mm Maximum size
PM0002 960.00 cu.m 249.00 0.00 0.00 2031.37 0.00 0.00 2991.37
- 22.4 mm to 5.6 mm

Aggregates 22.4 mm to 2.36 mm for wet


PM0024 960.00 cu.m 332.00 0.00 0.00 2687.50 0.00 0.00 3647.50
mix macadam
Aggregates 45 mm to 22.4 mm for wet
PM0025 960.00 cu.m 332.00 0.00 0.00 2687.50 0.00 0.00 3647.50
mix macadam
PM0026 Aluminium sheeting (1.5 mm thick) 1800.00 sq.m 332.00 0.00 0.00 2687.50 0.00 0.00 3317.50
Aluminium Studs 100 mm x 100 mm
PM0027 65.00 Nos. 0.00 0.00 0.00 0.00 0.00 0.00 680.00
fitted with lense reflectors
PM0034 Barbed wire 90.00 kilogram 0.00 0.00 0.00 0.00 0.00 0.00 740.00
PM0048 Brick 1st/2nd Class 6100.00 1000 Nos 249.00 0.00 0.00 2031.37 0.00 0.00 2991.37
PM0049 Cement 7100.00 tonne 249.00 0.00 0.00 2031.37 0.00 0.00 2991.37
Corbelling Stones (300 mm x 150 mm x
PM0055 12.00 Nos. 0.00 0.00 0.00 0.00 0.00 0.00 1800.00
150 mm)
Corrosion Resistant Structural Steel
PM0056 70.00 kilogram 0.00 0.00 0.00 0.00 0.00 0.00 65.00
Grating
RATE ANALYSIS
Example