Analysis of Rates

Name of work:- Construction of foot track for approaching of Nahri gad bridge
abutment for inspection of Geologist.

Height Index
Height of Site - 2200 m from M.S.L.
hence Height Index 4%+6% = 10%

1) Excavation in hill side cutting in blasting boulder i/c s/o all material, Labour, T&P etc required for
proper completion of the work.
Rate as per SOR SL. No - 156 135.00 Per Cum
Add 10% height Index 13.50
Total 148.50
Say 149.00 Per Cum

2) Excavation in foundation in all type of soil i/c s/o all m/l, t&p etc required for proper completion
of the work.
Rate as per SOR SL no - 165 45 Per Cum
Add 10% height Index 4.50
Total 49.50
Say 50.00 Per Cum

3) RR stone masonary laid dry i/c s/o all m/l, t&p etc required for proper completion of the work.
Rate as per SOR SL no - 518 310.00 Per Cum
Add 10% height Index 31.00
Total 341.00
Add cartage of stone 3x20.00 60.00
G.Total 401.00
Say 401.00 Per Cum

4) Hill side cutting in E&B i/c s/o all m/l, t&p etc required for proper completion of the work.
Rate as per SOR 40.00
add height index 4.00
Total 44.00
Say 44.00

Junior Engineer Assistant Engineer Executive Engineer


P.D.P.W.D. P.D.P.W.D. P.D.P.W.D.
Bhatwari Bhatwari Bhatwari
DETAILS OF MEASUREMENTS
Name of work:- Construction of foot track for approaching of Nahri gad bridge abutment for
inspection of Geologist.

S.No. Item of work Unit No No Length Breadth H/D Quantity


1 Excavation in hill side cutting in blasting
boulder i/c s/o all material, Labour, T&P etc
required for proper completion of the work.
As per attached Sheet Cum 1 1 10.00 10.00
Total 10.00

2 Excavation in foundation in all type of soil i/c


s/o all m/l, t&p etc required for proper
completion of the work.
R/wall Cum 1 2/3 8.00 1.04 1.75 9.68
1 1/3 6.00 1.04 1.75 3.63
1 1/3 6.00 1.01 1.65 3.34
Total 16.66

3
RR stone masonary laid dry i/c s/o all m/l, t&p
etc required for proper completion of the work.

R/wall Cum 1 1 8.00 0.95 1.75 13.23


1 1 6.00 0.84 1.75 8.82
1 1 6.00 1.18 1.65 11.63
Total 33.68

4 Hill side cutting in E&B i/c s/o all m/l, t&p etc
required for proper completion of the work.
As per attached sheet cum 1 1 98.94 98.94
Total 98.94

Junior Engineer Assistant Engineer


P.D.P.W.D. Bhatwari P.D.P.W.D. Bhatwari
BILL OF QUANTITY

Name of work:- Construction of foot track for approaching of Nahri gad bridge abutment for
inspection of Geologist.

S.NO. ITEM OF WORK Qty Unit Rate Per Amount


1 Excavation in hill side cutting in blasting boulder i/c s/o all
material, Labour, T&P etc required for proper completion of the
work. 10.00 Cum 149.00 Cum 1490.00
0 0.00
2 Excavation in foundation in all type of soil i/c s/o all m/l, t&p etc
required for proper completion of the work. 16.66 Cum 50.00 Cum 832.79
0 0.00
3 RR stone masonary laid dry i/c s/o all m/l, t&p etc required for
proper completion of the work. 33.68 Cum 401.00 Cum 13506.68
0 0.00
4 Hill side cutting in E&B i/c s/o all m/l, t&p etc required for
proper completion of the work. 98.94 Cum 44.00 Cum 4353.43
0.00
Total 20182.90
Say 20183.00

Junior Engineer Asssitant Engineer


Pron. Div. P.D. P.W.D. Pron. Div. P.D. P.W.D.
Bhatawri Bhatawri
Hill Side Cutting
Name OF Work :- Lowering of approach road for Nahri gad steel girder bridge at km-1 of Dwari - raithal motor
Raod under Nabard XIV.
Factor Length Width Height Area 3x4x1 Avg.Area Area Area in Sqm Qty in Cum
%E&B % BLB E&B BLB E&B
1 2 3 4 5 6 7 8 9 10 11
0 0.00 1.80 1.200 0.00 0.00 60.00 40.00 0.00 0.00 0.00
0.5 10.00 1.80 1.300 1.17 0.59 75.00 25.00 0.44 0.15 4.39
0.5 20.00 1.80 1.500 1.35 1.26 65.00 35.00 0.82 0.44 16.38
0.5 30.00 1.80 1.300 1.17 1.26 60.00 40.00 0.76 0.50 22.68
0.5 40.00 1.80 1.200 1.08 1.13 50.00 50.00 0.56 0.56 22.50
0.5 47.00 1.80 1.400 1.26 1.17 60.00 40.00 0.70 0.47 32.99
Total 98.94

Junior Engineer Assistant Engineer


Pron. Div. P.W.D. Pron. Div. P.W.D.
Bhatwari Bhatwari
ari - raithal motor

Qty in Cum
BLB
12
0.00
1.46
8.82
15.12
22.50
22.00
69.90
SUMMARY OF ESTIMATED COST

Name of work:- Construction of foot track for approaching of Nahri gad


bridge abutment for inspection of Geologist.

S.NO. PARTICULARS OF ITEAMS ESTIMATED COST


1 Construction of foot track for approaching
of Nahri gad bridge abutment for
inspection of Geologist. 20183.00

TOTAL 20183.00
SAY 20183.00

Junior Engineer Asssitant Engineer


Pron. Div. P.D. P.W.D. Pron. Div. P.D. P.W.D.
Bhatawri Bhatawri