Name of work:- Construction of foot track for approaching of Nahri gad bridge
abutment for inspection of Geologist.
Height Index
Height of Site - 2200 m from M.S.L.
hence Height Index 4%+6% = 10%
1) Excavation in hill side cutting in blasting boulder i/c s/o all material, Labour, T&P etc required for
proper completion of the work.
Rate as per SOR SL. No - 156 135.00 Per Cum
Add 10% height Index 13.50
Total 148.50
Say 149.00 Per Cum
2) Excavation in foundation in all type of soil i/c s/o all m/l, t&p etc required for proper completion
of the work.
Rate as per SOR SL no - 165 45 Per Cum
Add 10% height Index 4.50
Total 49.50
Say 50.00 Per Cum
3) RR stone masonary laid dry i/c s/o all m/l, t&p etc required for proper completion of the work.
Rate as per SOR SL no - 518 310.00 Per Cum
Add 10% height Index 31.00
Total 341.00
Add cartage of stone 3x20.00 60.00
G.Total 401.00
Say 401.00 Per Cum
4) Hill side cutting in E&B i/c s/o all m/l, t&p etc required for proper completion of the work.
Rate as per SOR 40.00
add height index 4.00
Total 44.00
Say 44.00
3
RR stone masonary laid dry i/c s/o all m/l, t&p
etc required for proper completion of the work.
4 Hill side cutting in E&B i/c s/o all m/l, t&p etc
required for proper completion of the work.
As per attached sheet cum 1 1 98.94 98.94
Total 98.94
Name of work:- Construction of foot track for approaching of Nahri gad bridge abutment for
inspection of Geologist.
Qty in Cum
BLB
12
0.00
1.46
8.82
15.12
22.50
22.00
69.90
SUMMARY OF ESTIMATED COST
TOTAL 20183.00
SAY 20183.00