You are on page 1of 30

SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Quantity Calculation of Foundation & Sub-structure

8.67

0.83 Width of Piercap = 2.50


0.2 Width of Pedestal = 0.6
0.7 Number of Pedestal = 8
0.70 Avg. Depth of Excavation = 1.85
Depth of PCC = 0.10

3.45 1.50

Width of Pilecap = 8.00


Depth of Soling = 0.15

1.7

9.00

Sn Particulars No Length Breadth Height Area Volume Unit


FOUNDATION
1 Earthwork in Excavation for foundation of
structure in all type of soil including shoring,
struting, bracing, dewatering and disposal with
necessary haulage and lift, removal of stumps and
other deleterious matter and backfilling with
approved Material all complete as per design
drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 900]

Pier 1 9.00 8.00 1.85 133.2


Total 133.2
Total for 1 Numbers 1 133.2 Cum

2 Providing and placing machine mixed Cement


Concrete M15/40 for Levelling Course, including
compaction, curing, testing and necessary lead,
including necessary form works [F1 Finish] all
complete as per design drawings, technical
specification and to the satisfaction of Engineer.
[SS/SP 1800 and 2000]

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass1


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Pier 1 9.00 8.00 0.1 7.2


Total 7.20
Total for 1 Numbers 1 7.2 Cum

3 Providing and laying of Stone


Soling/Pitching/Packing Works for levelling in
line and level, all complete as per design
drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 2600]

Pier 1 9.00 8.00 0.15 10.8


Total 10.80
Total for 1 Numbers 1 10.8 Cum

4 Providing and placing machine mixed Cement


Concrete M30/20 for Foundation & Footings,
including compaction, curing, testing and
necessary lead, including necessary form works
[F1 Finish] all complete as per design drawings,
technical specification and to the satisfaction of
Engineer. [SS/SP 1800 and 2000]

Pier 1 9.00 8.00 1.70 122.4


Total 122.4
Total for 1 Numbers 1 122.4 Cum

SUB-STRUCTURE
8 Providing and placing machine mixed Cement
Concrete M30/20 for Pier stem, Cap, including
compaction, curing, testing and necessary lead,
including necessary form works [F3 Finish] all
complete as per design drawings, technical
specification and to the satisfaction of Engineer.
[SS/SP 1800/2000]

Pier
Stem 1 1.50 3.45 1.77 6.11
Pier Cap Rectangular 1 8.67 2.50 0.70 15.17
Pier Cap Trapezoidal 1 5.09 2.50 0.70 8.9
Total 30.18
Total for 1 Numbers 1 30.18

9 Providing and placing machine mixed Cement


Concrete M30/20 for Pedestal including
compaction, curing, testing and necessary lead,
including necessary form works [F3 Finish] all
complete as per design drawings, technical
specification and to the satisfaction of Engineer.
[SS/SP 1800/2000]

Pier 8 0.83 0.6 0.20 0.80


Total 0.80
Total for 1 Numbers 1 0.8

10 Providing and placing machine mixed Cement


Concrete M30/20 for Stopper including
compaction, curing, testing and necessary lead,
including necessary form works [F3 Finish] all
complete as per design drawings, technical
specification and to the satisfaction of Engineer.
[SS/SP 1800/2000]

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass2


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Pier 4 0.50 0.4 0.60 0.48


Total 0.48
Total for 1 Numbers 1 0.48

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass3


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Summary of Quantity
Sn Description of Works No Quantity Total Quantity Unit Remarks
1 FOUNDAATION / SUBSTRUCTURE / ABUTEMENT / PIER
FOUNDATION
1.1 Earthwork in Excavation for foundation of structure
in all type of soil including shoring, struting, bracing,
dewatering and disposal with necessary haulage and
lift, removal of stumps and other deleterious matter
and backfilling with approved Material all complete as 2.00 409.60 819.20 Cum
per design drawings, technical specification and to
the satisfaction of Engineer. [SS/SP 900]

1.2 Providing and placing machine mixed Cement


Concrete M15/40 for Levelling Course, including
compaction, curing, testing and necessary lead,
including necessary form works [F1 Finish] all
2.00 22.14 44.28 Cum
complete as per design drawings, technical
specification and to the satisfaction of
Engineer.[SS/SP 1800 and 2000]

1.3 Providing and laying of Stone


Soling/Pitching/Packing Works for levelling in line
and level, all complete as per design drawings,
2.00 33.22 66.44 Cum
technical specification and to the satisfaction of
Engineer. [SS/SP 2600]

1.4 Providing and placing machine mixed Cement


Concrete M30/20 for Foundation & Footings,
including compaction, curing, testing and necessary
lead, including necessary form works [F1 Finish] all
2.00 353.70 707.40 Cum
complete as per design drawings, technical
specification and to the satisfaction of Engineer.
[SS/SP 1800 and 2000]

1.5 Providing and laying , fitting and placing un-coated


Mild steel / HYSD reinforcement complete in
foundationas all complete as per design drawings,
2.00 28.26 56.52 Mt
technical specification and to the satisfaction of
Engineer. [SS/SP 2000]

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass4


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Summary of Quantity
Sn Description of Works No Quantity Total Quantity Unit Remarks
SUBSTRUCTURE
1.6 Providing and placing machine mixed Cement
Concrete M30/20 for Abutment Stem, Cap,
Approach Slab, Pedestal and Stopper including
compaction, curing, testing and necessary lead,
including necessary form works [F3 Finish] all 2.00 183.82 367.64 Cum
complete as per design drawings, technical
specification and to the satisfaction of Engineer.
[SS/SP 1800/2000]

1.7 Providing and laying , fitting and placing HYSD bar


reinforcement in substructure complete all complete
as per design drawings, technical specification and to 2.00 22.42 44.84 Mt
the satisfaction of Engineer. [SS/SP 2000]

1.8 Providing and filling with graded Pervious Filter


Material behind abutment in layer with necessary
watering and compaction, all complete as per design 2.00 77.86 155.72 Cum
drawings, technical specification and to the
satisfaction of Engineer.[SS/SP 900]

1.9 Providing, laying and fixing of Geotextile (filter


fabric) all complete as per design drawings, technical
specification and to the satisfaction of Engineer. 2.00 129.78 259.56 Sqm
[SS/SP 2400]

1.10 Providing suitable back fill material and Back filling


in layers behind the abutment including compaction
and watering etc. all complete as per design 2.00 814.58 1,629.16 Cum
drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 900]

1.11 Providing and making of Weep Holes with 110mm


HDPE pipe in position all complete as per design
drawings, technical specification and to the 2.00 70.40 140.80 Rm
satisfaction of Engineer. [SS/SP 3100/2000]

2 SUPERSTRUCTURE
2.1 Providing and placing machine mixed Cement
Concrete M30/20 for Deck Slab, including
compaction, curing, testing and necessary lead,
including necessary form works [F3 Finish] all
2.00 79.56 159.12 Cum
complete as per design drawings, technical
specification and to the satisfaction of
Engineer.[SS/SP 1800 and 2000]

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass5


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Summary of Quantity
Sn Description of Works No Quantity Total Quantity Unit Remarks
2.2 Tack coat with Bitumen By Mechanical Means
Providing and applying tack coat with hot Bitumen
(VG-30) at specified rate on the prepared non-
bituminous/bituminous surfaces including cleaning all
2.00 362.44 724.88 Sqm
complete as per design drawings, technical
specification and to the satisfaction of Engineer.
[SS/SP 1300]

2.3 Bituminous Concrete / Asphalt Concrete Providing


and laying Bituminous concrete/ Asphalt concrete
using crushed aggregates of specified grading,
premixed with bituminous binder (VG-30) and filler all
2.00 27.18 54.36 Cum
complete as per design drawings, technical
specification and to the satisfaction of Engineer.
[SS/SP 1300]

2.4 Providing and placing machine mixed Cement


Concrete M45/20 for Post tainsioned Precast
Main Girders, including compaction, curing, testing
and necessary lead, including necessary form works
[F3 Finish] all complete as per design drawings, 2.00 106.48 212.96 Cum
technical specification and to the satisfaction of
Engineer. [SS/SP 1800, 2000 and 2100]

2.5 Providing and placing machine mixed Cement


Concrete M45/20 for Cross Girders, including
compaction, curing, testing and necessary lead,
including necessary form works [F3 Finish] all 2.00 8.90 17.80 Cum
complete as per design drawings, technical
specification and to the satisfaction of Engineer.
[SS/SP 1800 and 2000]

2.6 Providing and placing machine mixed Cement


Concrete M30/20 for Crash Barrier, including
compaction, curing, testing and necessary lead,
including necessary form works [F3 Finish] all 2.00 11.25 22.50 Cum
complete as per design drawings, technical
specification and to the satisfaction of Engineer.
[SS/SP 1800 and 2000]

2.7 Providing, fitting and fixing High Tensile Steel


Wires/Strands (Tendons) including all accessories
for stressing opeation and grouting all complete as
per design drawings, technical specification and to 2.00 7.18 14.36 Mt
the satisfaction of Engineer. [SS/SP 2100]

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass6


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Summary of Quantity
Sn Description of Works No Quantity Total Quantity Unit Remarks
2.8 Transportation and Placement: Transportation of
pre-cast bridge girder (from yard to bridge site) and
placement at site with provided line and level, all
complete as per design drawings, technical 2.00 8.00 16.00 No
specification and to the satisfaction of Engineer.
[SS/SP 2100]

2.9 Providing and laying Reinforcement Bars in Super-


Structure, HYSD, TMT, minimum 0.2% prof stress
500 MPA (Fe 500) for RCC works including cutting,
bending, binding, fixing in position and necessary
2.00 36.21 72.42 Mt
lead, all complete as per design drawings, technical
specification and to the satisfaction of Engineer.
[SS/SP 2000]

2.10 Providing and fixing of Expansion Joints (Slab Seal


Type) including necessary assesories,all complete as
per design drawings, technical specification and to 2.00 32.85 65.70 Rm
the satisfaction of Engineer. [SS/SP 1900]

2.11 Providing and fixing of POT-PTEE Bearing all


complete as per design drawings, technical
specification and to the satisfaction of Engineer. 2.00 16.00 32.00 No
[1900]

2.12 Providing and fixing of Drainage Spouts all complete


as per design drawings, technical specification and to
the satisfaction of Engineer. [3100] 2.00 32.00 64.00 No

2.13 Providing and fixing of GI Ralling Pipe all complete


as per design drawings, technical specification and to
the satisfaction of Engineer.[2200 and 3100] 2.00 817.16 1,634.32 Kg

2.14 Providing and fixing of Steel Plates and other parts


all complete as per design drawings, technical
specification and to the satisfaction of 2.00 250.24 500.48 Kg
Engineer.[SS/SP 2200]

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass7


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Quantity Calculation of Foundation & Sub-structure

3.5
0.25 0.40 1.20 0.25
0.25 Width of Abutment = 9.00 m
0.3

1.76 Width of Pedestal = 0.83 m


0.20 Number of Pedestal = 4.00 No
0.60 Avg. Depth of Excavation = 1.85 m
0.6 Depth of PCC = 0.10 m
1.00
1.1
0.50 4.85

5 1.1 2.2 Filter material thickness = 0.60 m


Backfill slope = 62.50 dg
Depth of Soling = 0.15 m
1.1 Depth of Soling = 1.50 m
1.100 0.75

8.30

Sn Particulars No Length Breadth Height Area Volume Unit


FOUNDATION
1 Earthwork in Excavation for foundation of
structure in all type of soil including shoring,
struting, bracing, dewatering and disposal
with necessary haulage and lift, removal of
stumps and other deleterious matter and
backfilling with approved Material all
complete as per design drawings, technical
specification and to the satisfaction of
Engineer. [SS/SP 900]

Left Abutment 1 8.30 9.00 1.85 138.20


Right Abutment 1 8.30 9.00 1.85 138.20
Total 276.40 Cum

2 Providing and placing machine mixed


Cement Concrete M15/40 for Levelling
Course, including compaction, curing,
testing and necessary lead, including
necessary form works [F1 Finish] all
complete as per design drawings, technical
specification and to the satisfaction of
Engineer. [SS/SP 1800 and 2000]

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass8


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Quantity Calculation of Foundation & Sub-structure


Left Abutment 1 8.30 9.00 0.10 7.47
Right Abutment 1 8.30 9.00 0.10 7.47
Total 14.94 Cum

3 Providing and laying of Stone


Soling/Pitching/Packing Works for
levelling in line and level, all complete as per
design drawings, technical specification and
to the satisfaction of Engineer. [SS/SP 2600]

Left Abutment 1 8.30 9.00 0.15 11.21


Right Abutment 1 8.30 9.00 0.15 11.21
Total 22.42 Cum

4 Providing and placing machine mixed


Cement Concrete M30/20 for Foundation
& Footings, including compaction, curing,
testing and necessary lead, including
necessary form works [F1 Finish] all
complete as per design drawings, technical
specification and to the satisfaction of
Engineer. [SS/SP 1800 and 2000]

Left Abutment 1 8.30 9.00 1.05 78.30


Right Abutment 1 8.30 9.00 2.05 153.00
Total 231.30 Cum

SUB-STRUCTURE
5 Providing and placing machine mixed
Cement Concrete M30/20 for Abutment
stem, Cap, including compaction, curing,
testing and necessary lead, including
necessary form works [F3 Finish] all
complete as per design drawings, technical
specification and to the satisfaction of
Engineer. [SS/SP 1800/2000]

Left Abutment
Stem 1 1.10 9.00 4.85 48.02
Abutment Cap 1 1.60 9.00 0.60 8.64
Ballast Wall 1 0.40 9.00 1.76 6.34
Heel side hunch 1 0.50 9.00 1.00 2.25
Corbel rectangular portion 1 0.25 9.00 0.25 0.56
Corbel traingular portion 1 0.25 9.00 0.25 0.28
Right Abutment
Stem 1 1.10 9.00 4.85 48.02

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass9


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Quantity Calculation of Foundation & Sub-structure


Abutment Cap 1 1.60 9.00 0.60 8.64
Ballast Wall 1 0.40 9.00 1.76 6.34
Heel side hunch 1 0.50 9.00 1.00 2.25
Corbel rectangular portion 1 0.25 9.00 0.25 0.56
Corbel traingular portion 1 0.25 9.00 0.25 0.28
Total 132.18 Cum

6 Providing and placing machine mixed


Cement Concrete M30/20 for Approach
Slab including compaction, curing, testing
and necessary lead, including necessary
form works [F3 Finish] all complete as per
design drawings, technical specification and
to the satisfaction of Engineer. [SS/SP
1800/2000]

Left Abutment 1 3.50 9.00 0.30 9.45


Right Abutment 1 3.50 9.00 0.30 9.45
Total 18.90 Cum

7 Providing and placing machine mixed


Cement Concrete M30/20 for Pedestal
including compaction, curing, testing and
necessary lead, including necessary form
works [F3 Finish] all complete as per design
drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 1800/2000]

Left Abutment 4 0.60 0.83 0.20 0.40


Right Abutment 4 0.60 0.83 0.20 0.40
Total 0.80 Cum

8 Providing and placing machine mixed


Cement Concrete M30/20 for Stopper
including compaction, curing, testing and
necessary lead, including necessary form
works [F3 Finish] all complete as per design
drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 1800/2000]

Left Abutment 2 0.50 0.4 0.60 0.24


Right Abutment 2 0.50 0.4 0.60 0.24
Total 0.48 Cum

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass10


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Quantity Calculation of Foundation & Sub-structure


9 Providing and filling with graded Pervious
Filter Material behind abutment in layer with
necessary watering and compaction, all
complete as per design drawings, technical
specification and to the satisfaction of
Engineer. [SS/SP 900]

Left Abutment 1 9.00 0.60 7.21 38.93


Right Abutment 1 9.00 0.60 7.21 38.93
Total 77.86 Cum

10 Providing, laying and fixing of Geotextile


(filter fabric) all complete as per design
drawings, technical specification and to the
satisfaction of Engineer. [SS/SP 2400]

Left Abutment 1 9.00 7.21 64.89


Right Abutment 1 9.00 7.21 64.89
Total 129.78 Sqm

11 Providing suitable back fill material and Back


filling in layers behind the abutment
including compaction and watering etc. all
complete as per design drawings, technical
specification and to the satisfaction of
Engineer. [SS/SP 900]

Left Abutment 1 9.00 6.28 7.21 407.29


Right Abutment 1 9.00 6.28 7.21 407.29
Total 814.58 Cum

12 Providing and making of Weep Holes with


110mm HDPE pipe in position all complete
as per design drawings, technical
specification and to the satisfaction of
Engineer. [SS/SP 3100/2000]

Left Abutment 32 1.10 35.20


Right Abutment 32 1.10 35.20
Total 70.40 Rm

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass11


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Quantity Calculation of Super-structure

Type :- PSC Length :- 22.1 m Width:- 9 m Span :- 2

9.00
0.4 8.20 0.4

0.080 0.155
0.20 0.48
0.81

0.33
0.20
0.205

2.40

0.900 7.20 0.900

Number of Girder : 4 L = 22.100 m


Main Girder Section
0.65 0.65 0.3 0.3

0.275 0.15
0.15
1.20
0.40 1.20 0.9 0.9

0.2
0.30

At Center At End End Cross Girder Intermediate Cross Girder


Numbers 2 Numbers 1
Total Length of Girder = 22.10
Length of Rectangular Section = 0.84
Length of Transition Section = 2.25
Length of I-Section = 15.92
No of Tendons in Girder = 4.00

Sn Particulars No Length Breadth Height Area Volume Unit


1 Providing and placing machine mixed
Cement Concrete M30/20 for Deck
Slab, including compaction, curing, testing
and necessary lead, including necessary
form works [F3 Finish] all complete as per
design drawings, technical specification
and to the satisfaction of Engineer.
[SS/SP 1800 and 2000]

Central Part 1 22.10 7.20 0.20 31.82


Left End Tapering Part 1 22.10 0.90 0.20 3.98

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass12


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Quantity Calculation of Super-structure


Right End Tapering Part 1 22.10 0.90 0.20 3.98
Total 39.78 Cum
Total for 2 Span 2 79.56 Cum

2 Tack coat with Bitumen By Mechanical


Means Providing and applying tack coat
with hot Bitumen (VG-30) at specified
rate on the prepared
non-bituminous/bituminous surfaces
including cleaning all complete as per
design drawings, technical specification
and to the satisfaction of Engineer.
[SS/SP 1300]

On Carriageway 1 22.10 8.20 181.22


Total 181.22 Sqm
Total for 2 Span 2 362.44 Cum

3 Bituminous Concrete / Asphalt


Concrete Providing and laying
Bituminous concrete/ Asphalt concrete
using crushed aggregates of specified
grading, premixed with bituminous binder
(VG-30) and filler all complete as per
design drawings, technical specification
and to the satisfaction of Engineer.
[SS/SP 1300]

On Carriageway 1 22.10 8.20 0.08 13.59


Total 13.59 Cum
Total for 2 Span 2 27.18 Cum

4 Providing and placing machine mixed


Cement Concrete M45/20 for Post
tensioned Precast Main Girders,
including compaction, curing, testing and
necessary lead, including necessary form
works [F3 Finish] all complete as per
design drawings, technical specification
and to the satisfaction of Engineer.
[SS/SP 1800, 2000 and 2100]

Rectangular Section 2 0.84 0.65 1.20 0.78 1.31


I-Section
Top flange Rectangle 0.65 0.15 0.10
Top flange Trapezium 0.46 0.15 0.07
Bottom flange Rectangle 0.65 0.30 0.20
Bottom flange Trapezium 0.46 0.20 0.09
Central Rectangle 0.28 0.40 0.11
Total I-Section 1 15.92 0.56 8.98
Transition Section 2 2.25 0.67 3.02
Total for One Girder 13.31
For Total Number of Girder 4 53.24 Cum

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass13


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Quantity Calculation of Super-structure


Total for 2 Span 2 106.48 Cum

5 Providing and placing machine mixed


Cement Concrete M45/20 for Cross
Girders, including compaction, curing,
testing and necessary lead, including
necessary form works [F3 Finish] all
complete as per design drawings,
technical specification and to the
satisfaction of Engineer. [SS/SP 1800 and
2000]

End Cross Girder 2 7.20 0.30 0.90 3.89


Deduction 6 0.65 0.30 0.90 -1.05
Intermediate Cross Girder 1 7.20 0.30 0.90 1.94
Deduction 3 0.30 0.37 -0.33
Total 4.45 Cum
Total for 2 Span 2 8.90 Cum

6 Providing and placing machine mixed


Cement Concrete M30/20 for Crash
Barrier, including compaction, curing,
testing and necessary lead, including
necessary form works [F3 Finish] all
complete as per design drawings,
technical specification and to the
satisfaction of Engineer. [SS/SP 1800 and
2000]

Type-I
Upper Trapezoidal Section 1 22.10 0.18 0.48 1.91
Lower Trapezoidal Section 1 22.10 0.30 0.26 1.70
Lower Rectangular Section 1 22.10 0.40 0.08 0.66
Total 4.27 Cum
Total for 2 Span 2 11.25 Cum
Approach Slab Crash Barrier 4 3.50 0.19 2.71

7 Providing, fittingand fixing High Tensile


Steel Wires/Strands (Tendons) including
all accessories for stressing opeation and
grouting all complete as per design
16 24.13 9.30 3.59 Mt
drawings, technical specification and to
the satisfaction of Engineer. [SS/SP 2100]

Total for 2 Span 2 7.18 Cum

8 Transportation and Placement:


Transportation of pre-cast bridge girder
(from yard to bridge site) and placement
at site with provided line and level, all
4 4.00 No
complete as per design drawings,
technical specification and to the
satisfaction of Engineer. [SS/SP 2100]

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass14


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Quantity Calculation of Super-structure


Total for 2 Span 2 8.00 Cum

9 Providing and fixing of Expansion Joints


(Slab Seal Type) including necessary
assesories,all complete as per design
drawings, technical specification and to 1 10.95 10.95 Rm
the satisfaction of Engineer. [SS/SP 1900]

Total for 2 Span 2 32.85 Cum

10 Providing and fixing of POT-PTEE


Bearing all complete as per design
drawings, technical specification and to
the satisfaction of Engineer. [1900]

Free Bearings 4 4.00


Partially Fixed Bearings 4 4.00
Total 8.00 No
Total for 2 Span 2 16.00 Cum

11 Providing and fixing of Drainage Spouts


all complete as per design drawings,
technical specification and to the 16 16.00 No
satisfaction of Engineer. [3100]

Total for 2 Span 2 32.00 Cum

12 Providing and fixing of GI Ralling Pipe all


complete as per design drawings,
technical specification and to the
satisfaction of Engineer. [2200 and 3100]
GI Pipes Ø 75 mm
On top of Crash Barrier 2 22.10 8.37 369.95
GI Pipes Ø 50 mm
On top of Crash Barrier @ 2m c/c 24 0.32 5.03 38.63
Total 408.58 Kg
Total for 2 Span 2 817.16 Kg

13 Providing and fixing of Steel Plates and


other parts all complete as per design
drawings, technical specification and to
the satisfaction of Engineer. [SS/SP 2200]

Steel plates for Crash Barrier Rails


Base plate 150X100X16 24 1.88 8.37 45.12
Utility Hanger including plates, rods, nuts
16 5.00 80.00
and bolts
Total 125.12 Kg
Total for 2 Span 2 250.24 Kg

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass15


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Summary of Reinforcement
Total
Sn Description of works No Quantity Units Remarks
Quantity

1 Substructure Abutment &


Foundation
Foundation & footing
a) Foundation footing of Abutment
Left abutment 1 6.95 6.95
Right abutment 1 6.95 6.95
Pier(s) 1 14.37 14.37
Total of (a) 28.26 Mt
Total of Foundation Reinfocement 28.26 Mt
Substructre
a) Abutment
Left Abutment 1 8.33 8.33
Right Abutment 1 8.33 8.33
Pier(s) 1 4.97 4.97

Total of (a) 21.63 Mt


d) Pedestal Mesh
Bar for Pedestal Mesh 16 0.03 0.45
Total of ( d ) 0.45 Mt
e ) Stopper
Bar for Stoppers (For four stopper) 8 0.04 0.34
Total of ( e ) 0.34 Mt
Total of Substructure Reinfocement 22.42 Mt

2 Superstructure
2.1 Deck Slab 2 4.50 9.00
2.2 End Cross Girder 2 0.92 1.83
2.3 Intermediate Cross Girder 2 0.27 0.53
2.4 Main Girder 2 9.28 18.56
2.5 RCC Crash Barrier 2 3.14 6.28
Total Reinforcement in Superstructure 36.21 Mt

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass16


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Details of Reinforcement

Bar Bending Schedule of Deck Slab

Length Unit wt.


Sn Sketch Label Dia Nos Weight (kg) Remarks
100 (m) (kg/m)

8920
100

1 S1 12 184 9.12 0.89 1489.82

2 S2 12 178 9.12 0.89 1441.24


100
100

8920

S3 10 46 22.28 0.62 631.88


135

135

22010 S3 10 4 22.28 0.62 54.95

3 S3 10 4 22.28 0.62 54.95

22010
135

4 S4 10 46 22.28 0.62 631.88


135
135

3 2700 S4a 10 46 2.84 0.62 80.40


155

3 2700 S4b 10 46 2.86 0.62 80.97


100

5 S5a 10 41 0.71 0.62 17.95


410
200
100

5 410 S5b 10 41 0.71 0.62 17.95


200

4501.98
Total of Deck Slab 4.50 MT

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass17


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Details of Reinforcement
Bar Bending Schedule of Main Girder

Length Unit wt.


Sn Sketch Label Dia Nos Weight (kg) Remarks
(m) (kg/m)

179

1 2*100 N1a 16 44 3.88 1.58 269.59


860

270
N1b 10 84 3.88 0.62 201.05
255

554

554
70

1 N1c 10 128 1.57 0.62 124.22


440

179 to 554
2*100
760 to
960

1 N2 16 36 4.19 1.58 237.91


0 to 270
255

554

554
70

1 N2c 10 36 1.13 0.62 25.17


220

2*100
120

1 16 16 3.92 1.58 98.89


1304

N3

554 10 16 0.65 0.62 6.45

2 L1 10 5 22.02 0.62 67.88


22020

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass18


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Details of Reinforcement

3 22020 L2 10 5 22.22 0.62 68.50


100

100

4 15920 L3 10 16 15.92 0.62 157.04

800
2260
5 L4 10 32 4.21 0.62 83.06
550

600

350

Ø
6 280 A1 16 8 5.29 1.58 66.80

Pitch 70

420

Pitch 1050
7 93.3 A2 12 10 13.49 0.89 119.77
avg

600

Pitch - 75
7 A3 10 4 8.10 0.62 19.98
420

bothway
s
2 layers

1546.29
Total of One Main Girder 1.55 MT
Total of Six Main Girder 9.28 MT

Bar Bending Schedule of End Cross Girder

Length Unit wt.


SN Sketch Label Dia Nos Weight (kg) Remarks
(m) (kg/m)
400

400

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass19


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Details of Reinforcement

7745
400

400
1 EC1 25 4 8.55 3.85 131.71

7745
400
400

2 EC2 25 6 8.55 3.85 197.56

2*75

3 EC3 12 40 2.58 0.89 91.69


1008

208

4 7420 EC4 10 8 7.42 0.62 36.60

457.56
Total of One Cross Girder 0.46 MT
Total of Two End Cross Girder 0.92 MT

Bar Bending Schedule of Intermediate Cross Girder

Length Unit wt.


Sn Sketch Label Dia Nos Weight (kg) Remarks
(m) (kg/m)
400

400

1 EC1 25 4 8.55 3.85 131.71


7745

7745
400

2 EC2 20 2 8.55 2.47 42.15


400

2*60
1010

3 EC3 10 36 2.56 0.62 56.82


210

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass20


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Details of Reinforcement

4 EC4 10 8 7.42 0.62 36.60


7420
267.27
Total of One Cross Girder 0.27 MT
Total of One Intermediate Cross Girder 0.27 MT

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass21


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Details of Reinforcement
Bar Bending Schedule of Crash Barrier (Type-1)

Length Unit wt.


Sn Sketch Label Dia Nos Weight (kg) Remarks
(m) (kg/m)

575
928

1 C1 16 81 2.03 1.58 259.78


225

304
915

2 C2 16 81 1.42 1.58 180.90

500

4 9960 C3 16 11 9.96 1.58 172.92

613.61
Total of 10 m 0.61 MT
Total of 1 m 0.061 MT

Bar Bending Schedule of Abutment Pilecap

(mm) Length Unit wt.


Sn Sketch Label Dia Weight (kg) Remarks
Nos (m) (kg/m)

1 AF1 32 24 9.36 6.313 1,417.927


500
740

8118

3 AF1a 32 24 4.28 6.313 648.507


300

500

3480

3 AF2 20 24 7.04 2.466 416.681


740

200

6100
180

5 6025
AF3 32 46 6.95 6.313 2,016.924
740

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass22


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass
740

Details of Reinforcement
0

5 AF4 20 46 3.76 2.466 425.978


3255
500

3 AF5 20 15 10.03 2.466 371.032


600

600

8830

2 AF6 16 13 10.03 1.578 205.799


600

8830
600

3 AF7 16 29 10.03 1.578 459.091


600

600

8830

8830
4 AF8 20 26 10.03 2.466 643.123
600

600
L varies 870

Curve Length-130
5 Curve Radius-40 AF9 16 133 1.12 1.578 234.059
to 520

Hook Length-80

8150
8850

7 AF10 16 2 34.00 1.578 107.327

6,946.448
Total of One Abutment Foundation 6.95 MT

Bar Bending Schedule of One Abutment

(mm) Length Unit wt.


Sn Sketch Label Dia Weight (kg) Remarks
Nos (m) (kg/m)

300
6324

1 AB1 25 45 7.12 3.85 1235.31


500

500
6324

2 AB2 32 90 7.32 6.31 4161.50 Bundled

500

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass23


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Details of Reinforcement
6324

2 AB2c 16 8 6.82 1.58 86.16


500

8835

3 AB3 16 34 19.97 1.58 1071.66


1150

2*100
515

7 AB4 12 61 4.11 0.89 222.58


1440

4 8850 AB5 12 27 8.85 0.89 212.14

970
5 AB6 16 169 1.30 1.58 345.43
Hook Length-100

260
2360

1 AB7 16 46 2.92 1.58 212.00

300

260
2290

6 AB8 16 46 3.97 1.58 288.09


1118
300

8850
10 AB8a 10 7 8.85 0.62 38.19

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass24


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Details of Reinforcement

8850

3 268 AB9 10 10 18.24 0.62 112.43

510
300
110

7 655 AB10 16 41 1.78 1.58 114.86

200

510
5 Hook Length-200 AB11 12 82 0.91 0.89 66.25

255
5 AB11a 12 82 0.66 0.89 47.68
Hook Length-200

8860
8 AB12 20 1 8.86 2.47 21.85

8860
8 AB13 16 2 8.86 1.58 27.97
400

9 AB14 20 30 0.90 2.47 66.59


500

8330.71
Total in One Abutment 8.33 MT

Bar Bending Schedule of Approach Slab (For ONE )

(mm) Length Unit wt.


Sn Sketch Label Dia Weight (kg) Remarks
Nos (m) (kg/m)

1 3400 AS1 12 148 3.40 0.89 446.75

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass25


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Details of Reinforcement

2 10850 AS2 12 48 10.85 0.89 462.37

Total of One Approach Slab 909.12


0.91
Total of Two Approach Slabs 1.82 MT

Bar Bending Schedule of Pedestal Mesh (For One)

Length Unit wt.


Sn Sketch Label Dia Nos Weight (kg) Remarks
(m) (kg/m)

730
1 560 PED1 12 5 2.25 0.89 9.99
200

500
1 560 PED2 12 6 2.02 0.89 10.76
200
488

1 PED3 12 1 8.47 0.89 7.52

718

Total of One Pedestal Mesh 28.27


0.03 MT

Bar Bending Schedule of Stopper (For One)

Length Unit wt.


Sn Sketch Label Dia Nos Weight (kg) Remarks
(m) (kg/m)

300
1260
600

2 ST1 16 8 2.76 1.58 34.85


300
300

2*100
400

3 ST2 10 6 1.64 0.62 6.07


320

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass26


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Details of Reinforcement

1 400 ST3 10 4 0.40 0.62 0.99


Total of one stopper 41.90
0.04 MT

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass27


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

Itahari Overpass

Bar Bending Schedule of Pier Pilecap

Length Unit wt.


SN Sketch Label Dia Nos Weight (kg) Remarks
(m) (kg/m)
1140
1140

1 7818 PF1 32 50 10.10 6.31 3187.61


1140

1140

2 8818 PF2 32 54 11.10 6.31 3783.54


1140

1140

3 7818 PF3 32 50 10.10 6.31 3187.61

8818
4 PF4 32 54 11.10 6.31 3783.54
1140

1140

Curve Length-126
1454

5 Curve Radius-40 PF5 16 90 1.87 1.58 265.07


Hook Length-80

8830
7830

7 PF6 16 3 33.32 1.58 157.77

14365.13
Total of One Abutment Foundation 14.365 MT

Bar Bending Schedule of Pier


Length Unit wt.
SN Sketch Label Dia Nos Weight (kg) Remarks
(m) (kg/m)

32 18 9.53 6.31 1082.76


520

1 8488 P1
520

0 0 0.00 0.00 0.00

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass28


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

2 625 P2 20 24 9.91 2.47 586.55


3580
1500

6 Legs
3 H varies P3 16 44 7.12 1.58 494.46
600-1450

5085
2334

4 400 P4 16 10 13.30 1.58 209.98

5085

3293
2334

5 400 P5 16 10 9.72 1.58 153.41

3293

6 P6 32 2 2.35 6.31 29.67


2350
6285

7 P7 32 44 6.69 6.31 1857.01

400

Dia-1434,
Pitch-75
At critical
8 zone P8 16 1 148.31 1.58 234.08

Dia-1434,
Pitch-150
9 At non- P9 16 1 88.35 1.58 139.45
critical
zone

150 mm c/c
at critical
zones
9 500 mm c/c P10 16 14 8.21 1.58 181.41
at non- critical
zones

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass29


SHIP-PPC East - West Highway Kakarbhitta - Laukahi Section

4968.79
Total in One Pier 4.97 MT

SOOSUNG/ERMC/TSE Cost Estimate/Bridge_Overpass30

You might also like