You are on page 1of 106

PWD UTTARAKHAND

RATE ANALYSIS REPORT

Name MORD Year 2016-2017

Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Chapter Name CEMENT CONCRETE PAVEMENT


Amount And Rate In (Rs)
Item Description Rate Unit

10974 6-2 Lime Treated Soil for Sub-Base 912.30 cu.m


0 Providing, laying and spreading soil on a prepared sub-grade, pulverising, mixing
the spread soil in place with rotavator with 4 per cent slaked lime with minimum
content of 70 per cent of CaO, grading with motor grader and compacting with the
road roller at OMC to achieve atleast 98 per cent of the max dry density to form a
layer of sub-base as per Technical Specification Clause 403.

S.No Resource Code Resource Quantity Rate Unit Amount


.
Labour Group
1 PL14 Mate 0.48 337.56 day 162.03
2 PL15 Beldar/mazdoor (unskilled) 10.00 306.88 day 3,068.75
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC014 Hydraulic Excavator 0.9/1.0 cum 5.00 1,242.00 hours 6,210.00
2 PMC019 Motor Grader 6.00 3,381.00 hours 20,286.00
3 PMC027 Three wheel 80-100 kN Static Roller 4.30 648.60 hours 2,788.98
4 PMC028 Tipper 5.5 cum/10 ton capacity 14.00 655.50 hours 9,177.00
5 PMC032 Tractor with Rotavator 12.00 496.80 hours 5,961.60
6 PMC035 Water tanker 6 kl capacity (Truck Mounted) 5.00 276.00 hours 1,380.00
Material Group
1 PM0095 Lime 21.00 8,912.80 M.T. 1,87,168.71
2 PM0144 Water 30.00 135.00 Killo Litre 4,050.00
Total Resource Amount 2,41,136.87

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,411.37

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 30,142.11

Total OH Amount 32,553.48

Total Cost for 300.00 cu.m = Resource Cost + Overhead Cost 2,73,690.34

Item Rate Per cu.m 912.30

MORD - 2016-2017 - 01/05/2016 - 6 Page 1 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Notes: The exact quantity of lime shall be as per design.

6-3 Water Bound Macadam (WBM) - Sub-base


10974 6-3-A By Manual Means 879.00 cu.m
1
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.48 337.56 day 162.03
2 PL15 Beldar/mazdoor (unskilled) 10.00 306.88 day 3,068.75
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC014 Hydraulic Excavator 0.9/1.0 cum 5.00 1,242.00 hours 6,210.00
2 PMC019 Motor Grader 6.00 3,381.00 hours 20,286.00
3 PMC027 Three wheel 80-100 kN Static Roller 4.30 648.60 hours 2,788.98
4 PMC028 Tipper 5.5 cum/10 ton capacity 14.00 655.50 hours 9,177.00
5 PMC032 Tractor with Rotavator 12.00 496.80 hours 5,961.60
6 PMC035 Water tanker 6 kl capacity (Truck Mounted) 5.00 276.00 hours 1,380.00
Material Group
1 PM0049 Cement 21.00 8,481.46 tonne 1,78,110.73
2 PM0144 Water 30.00 135.00 Killo Litre 4,050.00
Total Resource Amount 2,32,078.89

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 29,009.86

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,610.89

Total OH Amount 31,620.75

Total Cost for 300.00 cu.m = Resource Cost + Overhead Cost 2,63,699.64

Item Rate Per cu.m 879.00

6-3-B Water Bound Macadam Sub-base/ Base


6-3-B-1 WBM Grading 1
Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness, hand
packing, rolling with three wheel 80-100 kN static roller in stages to proper grade
and camber, applying and brooming, stone screening/binding materials to fill-up the
interstices of coarse aggregate, watering and compacting to the required density
Grading 1 as per Technical Specification Clause 404.

MORD - 2016-2017 - 01/05/2016 - 6 Page 2 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

11254 6-3-B-1-(A) By Manual Means 2,892.30 cu.m


7
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 10.08 337.56 day 3,402.63
2 PL15 Beldar/mazdoor (unskilled) 250.00 306.88 day 76,718.75
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC027 Three wheel 80-100 kN Static Roller 36.00 648.60 hours 23,349.60
2 PMC035 Water tanker 6 kl capacity (Truck Mounted) 24.00 276.00 hours 6,624.00
Material Group
1 PM0021 Aggregate-Grading I 90 mm to 45 mm 435.60 1,099.80 cu.m 4,79,072.88
2 PM0035 Binding Material 28.80 80.00 cu.m 2,304.00
3 PM0138 Stone Screening - Type A 13.2 mm for 97.20 3,133.67 cu.m 3,04,592.43
Grading-1
4 PM0144 Water 144.00 135.00 Killo Litre 19,440.00
Total Resource Amount 9,16,388.09

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,14,548.51

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 10,309.37

Total OH Amount 1,24,857.88

Total Cost for 360.00 cu.m = Resource Cost + Overhead Cost 10,41,245.97

Item Rate Per cu.m 2,892.35

11254 6-3-B-1-(B) By Mechanical Means 2,731.60 cu.m


8
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.68 337.56 day 229.54
2 PL15 Beldar/mazdoor (unskilled) 15.00 306.88 day 4,603.13
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC019 Motor Grader 7.20 3,381.00 hours 24,343.20
2 PMC027 Three wheel 80-100 kN Static Roller 36.00 648.60 hours 23,349.60
3 PMC035 Water tanker 6 kl capacity (Truck Mounted) 24.00 276.00 hours 6,624.00
Material Group
MORD - 2016-2017 - 01/05/2016 - 6 Page 3 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

1 PM0021 Aggregate-Grading I 90 mm to 45 mm 435.60 1,099.80 cu.m 4,79,072.88


2 PM0035 Binding Material 28.80 80.00 cu.m 2,304.00
3 PM0138 Stone Screening - Type A 13.2 mm for 97.20 3,133.67 cu.m 3,04,592.43
Grading-1
4 PM0144 Water 144.00 135.00 Killo Litre 19,440.00
Total Resource Amount 8,65,442.58

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,08,180.32

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 9,736.23

Total OH Amount 1,17,916.55

Total Cost for 360.00 cu.m = Resource Cost + Overhead Cost 9,83,359.13

Item Rate Per cu.m 2,731.55

6-3-B-2 WBM Grading 2


Providing, laying, spreading and compacting stone aggregates of specific sizes to
water bound macadam specification including spreading in uniform thickness, hand
packing, rolling with smooth wheel roller 80-100 kN in stages to proper grade and
camber, applying and brooming, stone screening/binding materials to fill-up the
interstices of coarse aggregate, watering and compacting to the required density
grading 2 as per Technical Specification Clause 405.
11254 6-3-B-2-(A) By Manual Means 2,967.70 cu.m
9
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 10.08 337.56 day 3,402.63
2 PL15 Beldar/mazdoor (unskilled) 250.00 306.88 day 76,718.75
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC027 Three wheel 80-100 kN Static Roller 45.00 648.60 hours 29,187.00
2 PMC035 Water tanker 6 kl capacity (Truck Mounted) 24.00 276.00 hours 6,624.00
Material Group
1 PM0022 Aggregate-Grading II 63 mm to 45 mm 435.60 1,149.80 cu.m 5,00,852.88
2 PM0035 Binding Material 28.80 80.00 cu.m 2,304.00
3 PM0140 Stone Screening - Type B 11.2 mm for 96.01 3,133.67 cu.m 3,00,863.37
Grading-2
4 PM0144 Water 144.00 135.00 Killo Litre 19,440.00
Total Resource Amount 9,40,276.43

MORD - 2016-2017 - 01/05/2016 - 6 Page 4 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,17,534.55

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 10,578.11

Total OH Amount 1,28,112.66

Total Cost for 360.00 cu.m = Resource Cost + Overhead Cost 10,68,389.09

Item Rate Per cu.m 2,967.75

11255 6-3-B-2-(B) By Mechanical Means 2,807.00 cu.m


0
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.68 337.56 day 229.54
2 PL15 Beldar/mazdoor (unskilled) 15.00 306.88 day 4,603.13
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC019 Motor Grader 7.20 3,381.00 hours 24,343.20
2 PMC027 Three wheel 80-100 kN Static Roller 45.00 648.60 hours 29,187.00
3 PMC035 Water tanker 6 kl capacity (Truck Mounted) 24.00 276.00 hours 6,624.00
Material Group
1 PM0022 Aggregate-Grading II 63 mm to 45 mm 435.60 1,149.80 cu.m 5,00,852.88
2 PM0035 Binding Material 28.80 80.00 cu.m 2,304.00
3 PM0140 Stone Screening - Type B 11.2 mm for 96.01 3,133.67 cu.m 3,00,863.37
Grading-2
4 PM0144 Water 144.00 135.00 Killo Litre 19,440.00
Total Resource Amount 8,89,330.92

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,11,166.36

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 10,004.97

Total OH Amount 1,21,171.34

Total Cost for 360.00 cu.m = Resource Cost + Overhead Cost 10,10,502.25

Item Rate Per cu.m 2,806.95

6-3-B-3 WBM Grading 3


11255 6-3-B-3-(A) By Manual Means 2,947.90 cu.m
1
MORD - 2016-2017 - 01/05/2016 - 6 Page 5 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

11255 6-3-B-3-(B) By Mechnical Means 2,787.10 cu.m


2
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.68 337.56 day 229.54
2 PL15 Beldar/mazdoor (unskilled) 15.00 306.88 day 4,603.13
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC019 Motor Grader 7.20 3,381.00 hours 24,343.20
2 PMC027 Three wheel 80-100 kN Static Roller 45.00 648.60 hours 29,187.00
3 PMC035 Water tanker 6 kl capacity (Truck Mounted) 24.00 276.00 hours 6,624.00
Material Group
1 PM0023 Aggregate-Grading III 53 mm to 22.4 mm 435.60 1,209.80 cu.m 5,26,988.88
2 PM0141 Stone Screening - Type B 11.2 mm for 86.40 3,133.67 cu.m 2,70,748.83
Grading-3
3 PM0144 Water 144.00 135.00 Killo Litre 19,440.00
Total Resource Amount 8,83,048.38

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,10,381.05

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 9,934.29

Total OH Amount 1,20,315.34

Total Cost for 360.00 cu.m = Resource Cost + Overhead Cost 10,03,363.72

Item Rate Per cu.m 2,787.12

10974 6-4 Cement Concrete Pavement 7,754.90 cu.m


3 Construction of un-reinforced, dowel jointed at expansion and construction joint
only, plain cement concrete pavement, thickness as per design, over a prepared sub
base, with 43 grade cement or any other type as per Clause 1501.2.2 M30 (Grade),
coarse and fine aggregates conforming to IS:383, maximum size of coarse aggregate
not exceeding 25 mm, mixed in a concrete mixer of not less than 0.2 cum capacity
and appropriate weigh batcher using approved mix design, laid in approved fixed
side formwork (steel channel, laying and fixing of 125 micron thick polythene film,
wedges, steel plates including levelling the formwork as per drawing), spreading the
concrete with shovels, rakes, compacted using needle, screed and plate vibrators and
finished in continuous operation including provision of contraction and expansion,
construction joints, applying debonding strips, primer, sealant, dowel bars, near
approaches to bridge/culvert and construction joints, admixtures as approved, curing
of concrete slabs for 14-days,using curing compound (where specified) and water
finishing to lines and grade as per drawing and Technical Specification Clause 1501

MORD - 2016-2017 - 01/05/2016 - 6 Page 6 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

S.No Resource Code Resource Quantity Rate Unit Amount


.
Labour Group
1 PL01 Bhisti 14.00 306.88 day 4,296.25
2 PL03 Blacksmith 1st class/Electrician 1.00 558.51 day 558.51
3 PL12 Mason (brick layer) 1st class 5.00 558.51 day 2,792.56
4 PL14 Mate 7.00 337.56 day 2,362.94
5 PL15 Beldar/mazdoor (unskilled) 129.00 306.88 day 39,586.88
6 PL16 Mazdoor (Semi skilled) 6.00 337.56 day 2,025.38
7 PL17 Mazdoor/Beldar (Skilled) 6.00 441.90 day 2,651.40
8 PL20 Surveyor 2.00 540.10 day 1,080.20
9 PL35 Mason (for plain stone work) 2nd class) 5.00 540.10 day 2,700.50
Machine Group
1 PMC001 Air Compressor 210 cfm 2.00 414.00 hours 828.00
2 PMC007 Concrete mixer 0.28/0.4 cum 36.00 207.00 hours 7,452.00
3 PMC017 Joint cutting machine with 2-3 blades 4.00 1,242.00 hours 4,968.00
4 PMC020 Vibrator (Needle type 40mm) 9.00 69.00 hours 621.00
5 PMC023 Plate vibrator 9.00 69.00 hours 621.00
6 PMC024 Screed Vibrator Machine 9.00 1,518.00 hours 13,662.00
7 PMC035 Water tanker 6 kl capacity (Truck Mounted) 5.00 276.00 hours 1,380.00
Material Group
1 PM0002 Aggregate - For 37.5 mm Maximum size - 67.50 1,429.80 cu.m 96,511.50
22.4 mm to 5.6 mm
2 PM0043 Bitumen Emulsion (SS-1) 0.01 25,683.51 tonne 128.42
3 PM0044 Bituminous sealant 19.00 53.00 litre 1,007.00
4 PM0049 Cement 26.25 8,481.46 tonne 2,22,638.41
5 PM0067 Curing compound 131.25 125.00 litre 16,406.25
6 PM0068 Debonding strips 90.00 20.00 metre 1,800.00
7 PM0091 Joint filler board 3.00 45.00 sq.m 135.00
8 PM0093 Jute rope 12 mm dia 90.00 80.00 kilogram 7,200.00
9 PM0107 Plasticizer 122.00 55.00 litre 6,710.00
10 PM0108 Polythene sheet (125 micron) 412.50 8.50 sq.m 3,506.25
11 PM0109 Polythene Sheething 483.00 8.50 Nos. 4,105.50
12 PM0123 Sand (Coarse) 33.75 1,302.44 cu.m 43,957.30
13 PM0128 Steel Reinforcement (MS Round Bars) 117.60 37,881.46 tonne/kilogra 4,454.86
m
14 PM0144 Water 18.00 135.00 Killo Litre 2,430.00

Page 7 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Resource Amount 4,98,577.11

Over Heads

16. Formwork Charges 3% on (All Resource) 14,957.31

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 62,322.14

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 5,758.57

Total OH Amount 83,038.02

Total Cost for 75.00 cu.m = Resource Cost + Overhead Cost 5,81,615.13

Item Rate Per cu.m 7,754.87

10974 6-5 Roller Compacted Concrete Pavement 8,665.20 cu.m


4 Construction of Roller Compacted Concrete Pavement (RCCP) with coarse and fine
aggregates conforming to IS:383, the size of coarse aggregate not exceeding 25 mm
with minimum aggregate cement ratio of 5:1 mm and with minimum cemnt content
of 310 kg per cum, aggregate gradation to be as per Table 602.2 after blending,
mixing in concrete mixer at optimum moisture content, transporting to site, laying
with wheel barrows or steel pans or with mechanical paver, compacting with 80-100
kN smooth wheel, tandem vibratory roller, to achieve, the designed flexural
strength, finishing and curing as per drawings and Technical Specification Clause
1502
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL01 Bhisti 14.00 306.88 day 4,296.25
2 PL12 Mason (brick layer) 1st class 4.00 558.51 day 2,234.05
3 PL14 Mate 6.00 337.56 day 2,025.38
4 PL15 Beldar/mazdoor (unskilled) 132.00 306.88 day 40,507.50
5 PL20 Surveyor 2.00 540.10 day 1,080.20
6 PL35 Mason (for plain stone work) 2nd class) 4.00 540.10 day 2,160.40
Machine Group
1 PMC001 Air Compressor 210 cfm 2.00 414.00 hours 828.00
2 PMC007 Concrete mixer 0.28/0.4 cum 36.00 207.00 hours 7,452.00
3 PMC017 Joint cutting machine with 2-3 blades 6.00 1,242.00 hours 7,452.00
4 PMC034 Vibratory roller 80-100 kN 6.00 2,070.00 hours 12,420.00
5 PMC035 Water tanker 6 kl capacity (Truck Mounted) 6.00 276.00 hours 1,656.00
Material Group
1 PM0043 Bitumen Emulsion (SS-1) 0.01 25,683.51 tonne 256.84
2 PM0044 Bituminous sealant 16.80 53.00 litre 890.40
3 PM0049 Cement 23.25 8,481.46 tonne 1,97,194.02
4 PM0066 Crushed Stone Coarse Aggregate Passing 53 67.50 3,133.67 cu.m 2,11,522.52
mm and
MORD - 2016-2017 - 01/05/2016 - 6retained on 2.8 mm Page 8 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

mm and retained on 2.8 mm


5 PM0067 Curing compound 131.25 125.00 litre 16,406.25
6 PM0093 Jute rope 12 mm dia 90.00 80.00 kilogram 7,200.00
7 PM0123 Sand (Coarse) 33.75 1,302.44 cu.m 43,957.30
8 PM0144 Water 18.00 135.00 Killo Litre 2,430.00
Total Resource Amount 5,61,969.11

Over Heads

16. Formwork Charges 2% on (All Resource) 11,239.38

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 70,246.14

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 6,434.55

Total OH Amount 87,920.07

Total Cost for 75.00 cu.m = Resource Cost + Overhead Cost 6,49,889.18

Item Rate Per cu.m 8,665.19

Notes: When curing compound is used 4-days water curing will be done

10974 6-6 Rectangular Concrete Block Pavement 878.20 sq.m


5 Manufacturing, laying of cement concrete blocks of size 0.450 m x 0.300 m x 0.15
m of Cement Concrete (C.C.) M30 garde and spreading 25 mm thick sand under
neath and filling joints with sand on existing W.B.M. base as per Technical
Specification Clause 1503.
Concrete M30 grade for block, 400 x (0.450 x 0.300 x 0.150)
cum 8.10 1,836.2414,873.54

Concrete M30 for edge block, 2 x 50 x (0.300 x 0.300 x 0.150)


cum 1.35 1,836.242,478.92

TOTAL cum 9.45


S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL01 Bhisti 1.40 306.88 day 429.63
2 PL14 Mate 1.70 337.56 day 573.86
3 PL15 Beldar/mazdoor (unskilled) 41.00 306.88 day 12,581.88
4 PL41 Mason (average) 6.00 540.10 day 3,240.60
Machine Group
1 PMC007 Concrete mixer 0.28/0.4 cum 6.00 207.00 hours 1,242.00
2 PMC023 Plate vibrator 12.00 69.00 hours 828.00
3 PMC035 Water tanker 6 kl capacity (Truck Mounted) 2.00 276.00 hours 552.00

MORD - 2016-2017 - 01/05/2016 - 6 Page 9 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Material Group
1 PM0016 Aggregate (Single size) : 20 mm nominal size 7.94 3,133.67 cu.m 24,881.32
2 PM0049 Cement 3.80 8,481.46 tonne 32,229.56
3 PM0123 Sand (Coarse) 5.70 1,302.44 cu.m 7,417.39
4 PM0144 Water 6.00 135.00 Killo Litre 810.00
Total Resource Amount 84,786.22

Over Heads

16. Formwork Charges 3% on (All Resource) 2,543.59

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 873.30

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 10,598.28

Total OH Amount 14,015.16

Total Cost for 112.50 sq.m = Resource Cost + Overhead Cost 98,801.38

Item Rate Per sq.m 878.23

Notes: i.In case curing compound is used in places where there is scarcity of water, the water curing will be used for 4-days and rate analysis will
be amended accordingly

ii.Carriage of C.C. block to site of is payable seperately as per Chapter of carriage of material from manufacturing site to the site of work.

6-7 Interlocking Concrete Block Pavement


Providing and Laying of Interlocking Concrete Block Pavements having thickness
80 mm as per drawings and Technical Specification Clause 1504.
10974 6-7-1 Providing and Laying of Interlocking Concrete Block Pavements having thickness 982.30 sq.m
6 80 mm and compressive strength not less than 30 MPa as per drawings and
Technical Specification Clause 1504.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 1.00 337.56 day 337.56
2 PL15 Beldar/mazdoor (unskilled) 17.00 306.88 day 5,216.88
3 PL41 Mason (average) 8.00 540.10 day 4,320.80
Machine Group
1 PMC035 Water tanker 6 kl capacity (Truck Mounted) 2.00 276.00 hours 552.00
Material Group
1 PM0090 Interlocking Blocks with 80 mm thickness 225.00 774.54 sq.m 1,74,270.50
2 PM0123 Sand (Coarse) 7.23 1,302.44 cu.m 9,416.63
3 PM0144 Water 3.00 135.00 Killo Litre 405.00
Total Resource Amount 1,94,519.37

MORD - 2016-2017 - 01/05/2016 - 6 Page 10 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 24,314.92

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,188.34

Total OH Amount 26,503.26

Total Cost for 225.00 sq.m = Resource Cost + Overhead Cost 2,21,022.63

Item Rate Per sq.m 982.32

10974 6-7-2 Providing and Laying of Interlocking Concrete Blcok Pavements having thickness 963.40 sq.m
7 60 mm and compressive strength not less than 30 MPa as per drawing and Technical
Specification Clause 1504
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.90 337.56 day 303.81
2 PL15 Beldar/mazdoor (unskilled) 15.00 306.88 day 4,603.13
3 PL41 Mason (average) 7.00 540.10 day 3,780.70
Machine Group
1 PMC035 Water tanker 6 kl capacity (Truck Mounted) 2.00 276.00 hours 552.00
Material Group
1 PM0090 Interlocking Blocks with 80 mm thickness 225.00 774.54 sq.m 1,74,270.50
2 PM0123 Sand (Coarse) 5.42 1,302.44 cu.m 7,059.22
3 PM0144 Water 3.00 135.00 Killo Litre 405.00
Total Resource Amount 1,90,974.35

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,909.74

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 23,871.79

Total OH Amount 25,781.54

Total Cost for 225.00 sq.m = Resource Cost + Overhead Cost 2,16,755.88

Item Rate Per sq.m 963.36

Notes: i.Carriage of interlocking blocks is payable seperately as per Chapter of carriage of material from manufacturing site to the site of work.

ii.Edge blocks may be cast-in-situ. Brick masonry toe wall or CC block 300 mm x 300 mm x 150 mm or any other shape can also be used and
their cost shall be analysed/included accordingly

iii.The rates for sub-grade, sub-base and base course can be taken from Chapters 3 and 4

6-1 Granular Sub- base with Wll Graded Material (Table 400.1)

MORD - 2016-2017 - 01/05/2016 - 6 Page 11 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

6-1-A Construction of granular sub- base by providing well graded material, spreading in
uniform layers with motor grader on prepared surface, mixing by mix in place
method with rotavator at OMC and compacting with smooth wheel roller to achieve
the desired density, complete as per technical Specification Clauses 40.1
11254 6-1-A-(i) For Grading I Material 1,798.50 cu.m
0
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.48 337.56 day 162.03
2 PL15 Beldar/mazdoor (unskilled) 10.00 306.88 day 3,068.75
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC027 Three wheel 80-100 kN Static Roller 30.00 648.60 hours 19,458.00
2 PMC032 Tractor with Rotavator 12.00 496.80 hours 5,961.60
3 PMC035 Water tanker 6 kl capacity (Truck Mounted) 5.00 276.00 hours 1,380.00
4 PMC145 Tractor Mounted Grader 12.00 531.30 hours 6,375.60
Material Group
1 PM0144 Water 30.00 135.00 Killo Litre 4,050.00
2 PM2250 Well graded granular sub-base material of 360.00 1,204.23 cu.m 4,33,523.58
Grading - I as per table 400.1 of
Specifications.
Total Resource Amount 4,74,863.36

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 59,357.92

11. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 5,342.21

Total OH Amount 64,700.13

Total Cost for 300.00 cu.m = Resource Cost + Overhead Cost 5,39,563.49

Item Rate Per cu.m 1,798.55

11254 6-1-A-(ii) For Grading II Material 1,864.00 cu.m


1
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.48 337.56 day 162.03
2 PL15 Beldar/mazdoor (unskilled) 10.00 306.88 day 3,068.75
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80

MORD - 2016-2017 - 01/05/2016 - 6 Page 12 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Machine Group
1 PMC027 Three wheel 80-100 kN Static Roller 30.00 648.60 hours 19,458.00
2 PMC032 Tractor with Rotavator 12.00 496.80 hours 5,961.60
3 PMC035 Water tanker 6 kl capacity (Truck Mounted) 5.00 276.00 hours 1,380.00
4 PMC145 Tractor Mounted Grader 12.00 531.30 hours 6,375.60
Material Group
1 PM0144 Water 30.00 135.00 Killo Litre 4,050.00
2 PM2251 Well graded granular sub-base material of 360.00 1,252.23 cu.m 4,50,803.58
Grading - II as per table 400.1 of
Specifications.
Total Resource Amount 4,92,143.36

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 61,517.92

11. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 5,536.61

Total OH Amount 67,054.53

Total Cost for 300.00 cu.m = Resource Cost + Overhead Cost 5,59,197.89

Item Rate Per cu.m 1,863.99

11254 6-1-A-(iii) For Grading III Material 2,016.70 cu.m


3
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.48 337.56 day 162.03
2 PL15 Beldar/mazdoor (unskilled) 10.00 306.88 day 3,068.75
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC027 Three wheel 80-100 kN Static Roller 30.00 648.60 hours 19,458.00
2 PMC032 Tractor with Rotavator 12.00 496.80 hours 5,961.60
3 PMC035 Water tanker 6 kl capacity (Truck Mounted) 5.00 276.00 hours 1,380.00
4 PMC145 Tractor Mounted Grader 12.00 531.30 hours 6,375.60
Material Group
1 PM0144 Water 30.00 135.00 Killo Litre 4,050.00
2 PM2252 Well graded granular sub-base material of 360.00 1,364.23 cu.m 4,91,123.58
Grading - III as per table 400.1 of
Specifications.
Total Resource Amount 5,32,463.36

MORD - 2016-2017 - 01/05/2016 - 6 Page 13 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 66,557.92

11. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 5,990.21

Total OH Amount 72,548.13

Total Cost for 300.00 cu.m = Resource Cost + Overhead Cost 6,05,011.49

Item Rate Per cu.m 2,016.71

6-1-B Plant Mix Method


Construction of granular sub-base by providing well graded material, mixing in a
mechanical mix plant at OMC, carriage of mixed material to work site upto lead of
1000 m spreading in uniform layers with motor grader on prepared surface and
compacting with smooth wheel roller to achieve the desired density, complete as
per Technical Specification Clause 401
11254 6-1-B-(i) For Grading I Material 1,858.70 cu.m
4
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.40 337.56 day 135.03
2 PL15 Beldar/mazdoor (unskilled) 8.00 306.88 day 2,455.00
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC012 Front end-loader 1 cum bucket capacity 9.00 1,242.00 hours 11,178.00
2 PMC019 Motor Grader 4.50 3,381.00 hours 15,214.50
3 PMC027 Three wheel 80-100 kN Static Roller 22.50 648.60 hours 14,593.50
4 PMC028 Tipper 5.5 cum/10 ton capacity 13.60 655.50 hours 8,914.80
5 PMC035 Water tanker 6 kl capacity (Truck Mounted) 4.00 276.00 hours 1,104.00
6 PMC108 Wet Mix Plant 75 TPH 7.50 1,745.70 hours 13,092.75
Material Group
1 PM0144 Water 24.00 135.00 Killo Litre 3,240.00
2 PM0153 Well Graded Material for Sub-Base - Grading I 144.00 1,034.23 cu.m 1,48,929.43
53 mm to 9.5 mm
3 PM0154 Well Graded Material for Sub-Base - Grading I 57.00 1,034.23 cu.m 58,951.23
9.5 mm to 2.36 mm
4 PM0155 Well Graded Material for Sub-Base - Grading 86.40 1,034.23 cu.m 89,357.66
II 2.36 mm below
Total Resource Amount 3,68,049.70

Over Heads

MORD - 2016-2017 - 01/05/2016 - 6 Page 14 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 46,006.21

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 4,140.56

Total OH Amount 50,146.77

Total Cost for 225.00 cu.m = Resource Cost + Overhead Cost 4,18,196.47

Item Rate Per cu.m 1,858.65

11254 6-1-B-(ii) For Grading II Material 1,861.80 cu.m


5
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.40 337.56 day 135.03
2 PL15 Beldar/mazdoor (unskilled) 8.00 306.88 day 2,455.00
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC012 Front end-loader 1 cum bucket capacity 9.00 1,242.00 hours 11,178.00
2 PMC019 Motor Grader 4.50 3,381.00 hours 15,214.50
3 PMC027 Three wheel 80-100 kN Static Roller 22.50 648.60 hours 14,593.50
4 PMC028 Tipper 5.5 cum/10 ton capacity 13.60 655.50 hours 8,914.80
5 PMC035 Water tanker 6 kl capacity (Truck Mounted) 4.00 276.00 hours 1,104.00
6 PMC108 Wet Mix Plant 75 TPH 7.50 1,745.70 hours 13,092.75
Material Group
1 PM0144 Water 24.00 135.00 Killo Litre 3,240.00
2 PM0154 Well Graded Material for Sub-Base - Grading I 72.00 1,034.23 cu.m 74,464.72
9.5 mm to 2.36 mm
3 PM0155 Well Graded Material for Sub-Base - Grading 115.20 1,034.23 cu.m 1,19,143.54
II 2.36 mm below
4 PM0156 Well Graded Material for Sub-Base - Grading 100.80 1,034.23 cu.m 1,04,250.60
II 26.5 mm to 9.5 mm
Total Resource Amount 3,68,670.23

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 46,083.78

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 4,147.54

Total OH Amount 50,231.32

Total Cost for 225.00 cu.m = Resource Cost + Overhead Cost 4,18,901.56

Item Rate Per cu.m 1,861.78

MORD - 2016-2017 - 01/05/2016 - 6 Page 15 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

11254 6-1-B-(iii) For Grading III Material 1,861.80 cu.m


6
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.40 337.56 day 135.03
2 PL15 Beldar/mazdoor (unskilled) 8.00 306.88 day 2,455.00
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC012 Front end-loader 1 cum bucket capacity 9.00 1,242.00 hours 11,178.00
2 PMC019 Motor Grader 4.50 3,381.00 hours 15,214.50
3 PMC027 Three wheel 80-100 kN Static Roller 22.50 648.60 hours 14,593.50
4 PMC028 Tipper 5.5 cum/10 ton capacity 13.60 655.50 hours 8,914.80
5 PMC035 Water tanker 6 kl capacity (Truck Mounted) 4.00 276.00 hours 1,104.00
6 PMC108 Wet Mix Plant 75 TPH 7.50 1,745.70 hours 13,092.75
Material Group
1 PM0144 Water 24.00 135.00 Killo Litre 3,240.00
2 PM0155 Well Graded Material for Sub-Base - Grading 151.20 1,034.23 cu.m 1,56,375.90
II 2.36 mm below
3 PM0159 Well Graded Material for Sub-Base - Grading 36.00 1,034.23 cu.m 37,232.36
III 4.75 mm to 2.36 mm
4 PM0160 Well Graded Material for Sub-Base - Grading 100.80 1,034.23 cu.m 1,04,250.60
III 9.5 mm to 4.75 mm
Total Resource Amount 3,68,670.23

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 46,083.78

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 4,147.54

Total OH Amount 50,231.32

Total Cost for 225.00 cu.m = Resource Cost + Overhead Cost 4,18,901.56

Item Rate Per cu.m 1,861.78

Specification:

Page 16 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Chapter Name CAUSEWAY AND SUBMERSIBLE BRIDGES


Amount And Rate In (Rs)
Item Description Rate Unit

7-1 Construction of Cut-off Walls/Head Walls


10974 7-1-1 Earthwork in excavation for structures as per drawing and technical specification 291.20 cu.m
8 Clause 305.

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 1.00 291.20 cu.m 291.20


& brest walls
Total Child Item Amount 291.20

Total Cost for 1.00 cu.m = Sub Items Cost 291.20

Item Rate Per cu.m 291.20

Notes: Rate as appropriate for the type of soil/rock are to be taken in (i)

10974 7-1-2 Plain cement concrete M15 grade 6,250.90 cu.m


9
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 1.00 6,250.90 cu.m 6,250.90

Total Child Item Amount 6,250.90

Total Cost for 1.00 cu.m = Sub Items Cost 6,250.90

Item Rate Per cu.m 6,250.90

10975 7-1-3 Brick masonry in cement mortar 1:4 8,340.80 cu.m


0
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-5-2 Brick masonry in 1:4 cement mortar 1.00 8,340.80 cu.m 8,340.80

Total Child Item Amount 8,340.80

Total Cost for 1.00 cu.m = Sub Items Cost 8,340.80

Item Rate Per cu.m 8,340.80

10975 7-1-4 Stone masonry in cement mortar 1:4 5,252.00 cu.m


1
S.No. Item Code Item Description Quantity Rate Unit Amount

MORD - 2016-2017 - 01/05/2016 - 7 Page 17 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

1 11-6-1-2 In 1:4 cement mortar 1.00 5,252.00 cu.m 5,252.00

Total Child Item Amount 5,252.00

Total Cost for 1.00 cu.m = Sub Items Cost 5,252.00

Item Rate Per cu.m 5,252.00

10975 7-1-5 Providing P.C.C M20 architectural coping on top of wall 403.50 metre
2
S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-13 Providing PCC M-20 architectural 1.00 403.50 m 403.50


coping on the top of wing wall, return
wall etc.
Total Child Item Amount 403.50

Total Cost for 1.00 metre = Sub Items Cost 403.50

Item Rate Per metre 403.50

10975 7-2 Preparation of Subgrade 65.00 cu.m


3
S.No. Item Code Item Description Quantity Rate Unit Amount

1 3-15-2 Compacting original ground supporting 1.00 65.00 cu.m 65.00


subgrade
Total Child Item Amount 65.00

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 65.00

Item Rate Per cu.m 65.00

10975 7-3 Granular Sub-base 1,798.50 cu.m


4
S.No. Item Code Item Description Quantity Rate Unit Amount

1 4-1-A-1 For Grading I Material 1.00 1,798.50 cu.m 1,798.50

Total Child Item Amount 1,798.50

MORD - 2016-2017 - 01/05/2016 - 7 Page 18 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Cost for 1.00 cu.m = Sub Items Cost 1,798.50

Item Rate Per cu.m 1,798.50

10975 7-4 W.B.M. Base Course 2,892.30 cu.m


5
S.No. Item Code Item Description Quantity Rate Unit Amount

1 4-7-1-A By Manual Means 1.00 2,892.30 cu.m 2,892.30

Total Child Item Amount 2,892.30

Total Cost for 1.00 cu.m = Sub Items Cost 2,892.30

Item Rate Per cu.m 2,892.30

10975 7-5 Cement Concrete Slab 7,754.90 cu.m


6
S.No. Item Code Item Description Quantity Rate Unit Amount

1 6-4 Cement Concrete Pavement 1.00 7,754.90 cu.m 7,754.90

Total Child Item Amount 7,754.90

Total Cost for 1.00 cu.m = Sub Items Cost 7,754.90

Item Rate Per cu.m 7,754.90

7-6 Providing and Laying Apron


10975 7-6-1 Providing and Laying Apron with Stone Boulders as per Drawings & Technical 1,338.10 cu.m
7 Specification Clause 1301

S.No. Item Code Item Description Quantity Rate Unit Amount

1 14-1 Providing and laying boulder apron for 1.00 1,338.10 cu.m 1,338.10
bed protection with stone boulders
Total Child Item Amount 1,338.10

Total Cost for 1.00 cu.m = Sub Items Cost 1,338.10

Item Rate Per cu.m 1,338.10

10975 7-6-2 Providing and Laying of Boulder Apron Laid in Wire Crates as per Drawing and 2,162.60 cu.m
8 Technnical Specification Clause 1301

S.No. Item Code Item Description Quantity Rate Unit Amount

MORD - 2016-2017 - 01/05/2016 - 7 Page 19 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

1 14-2 Providing and laying of boulder apron 1.00 2,162.60 cu.m 2,162.60
laid in wire crates with 4 mm dia GI
wire
Total Child Item Amount 2,162.60

Total Cost for 1.00 cu.m = Sub Items Cost 2,162.60

Item Rate Per cu.m 2,162.60

10975 7-6-3 Providing and Laying of Apron with Cement Concrete Blocks as per Drawing and 6,375.90 cu.m
9 Technical Specification Clause 1301

S.No. Item Code Item Description Quantity Rate Unit Amount

1 14-3 Providing and laying of apron with 1.00 6,375.90 cu.m 6,375.90
cement concrete blocks
Total Child Item Amount 6,375.90

Total Cost for 1.00 cu.m = Sub Items Cost 6,375.90

Item Rate Per cu.m 6,375.90

10976 7-7 Construction of R.C.C. guide posts of 250 mm dia, M25 grade as per drawing and 64,462.00 cu.m
0 technical specification Clause 1401.6

S.No. Item Code Item Description Quantity Rate Unit Amount

1 8-8-(i) Earth work in excavation for structures 1.00 294.10 cu.m 294.10

2 8-8-(ii) RCC M15 grade 1.00 6,313.40 cu.m 6,313.40

3 8-8-(iii) HYSD steel bars 1.00 57,733.00 tons 57,733.00

4 8-8-(iv) Painting two coats including prime 1.00 121.50 sq.m 121.50
coat on new concrete surface
Total Child Item Amount 64,462.00

Total Cost for 1.00 cu.m = Sub Items Cost 64,462.00

Item Rate Per cu.m 64,462.00

7-8 Bedding for Causeway


10976 7-8-1 Type A (concrete cradle) Bedding Clause 1402.5 6,250.90 cu.m
1
S.No. Item Code Item Description Quantity Rate Unit Amount

1 9-2-(i) Type A (Concrete Cradle) Bedding 1.00 6,250.90 cu.m 6,250.90

MORD - 2016-2017 - 01/05/2016 - 7 Page 20 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Child Item Amount 6,250.90

Total Cost for 1.00 cu.m = Sub Items Cost 6,250.90

Item Rate Per cu.m 6,250.90

10976 7-8-2 Type B (first class) Bedding Clause 1402.5 1,884.30 cu.m
2
S.No. Item Code Item Description Quantity Rate Unit Amount

1 9-2-(ii) Type B (First Class) Bedding 1.00 1,884.30 cu.m 1,884.30

Total Child Item Amount 1,884.30

Total Cost for 1.00 cu.m = Sub Items Cost 1,884.30

Item Rate Per cu.m 1,884.30

10976 7-9 Laying Reinforced Cement Concrete Pipe NP3 as per drawing and technical 8,960.60 metre
3 specification Clause 1402.6

S.No. Item Code Item Description Quantity Rate Unit Amount

1 9-3-A 1200 mm dia 1.00 8,960.60 m 8,960.60

Total Child Item Amount 8,960.60

Total Cost for 1.00 metre = Sub Items Cost 8,960.60

Item Rate Per metre 8,960.60

10976 7-10 Laying Reinforced Cement Concrete Pipe NP4 as per technical specification Clause 10,324.10 metre
4 1402.6

S.No. Item Code Item Description Quantity Rate Unit Amount

1 9-4-A 1200 mm dia 1.00 10,324.10 m 10,324.10

Total Child Item Amount 10,324.10

Total Cost for 1.00 metre = Sub Items Cost 10,324.10

Item Rate Per metre 10,324.10

Specification:

MORD - 2016-2017 - 01/05/2016 - 7 Page 21 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Chapter Name HILL ROADS


Amount And Rate In (Rs)
Item Description Rate Unit

10976 8-1 Site Clearance 0.00 sq.m


5

8-2 Setting Out


10976 8-2-(1) Construction of reference pillars as per Fig. 1600.1 (b) as per drawing and Technical 7,847.50 km
6 Specification Clause 1602.1

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 1.20 291.20 cu.m 349.44


& brest walls
Earthwork in excavation for foundation
as per drawing and technical
specifications.
2 11-6-1-2 In 1:4 cement mortar 1.20 5,252.00 cu.m 6,302.40

Stone masonry work in cement mortar


1:4 in foundation complete as per
drawing and technical specifications
3 12-3 Plastering with cement mortar (1:4), 15 4.00 205.50 sq.m 822.00
mm thick on brickwork in substructure

(as per technical specifications)


Total Child Item Amount 7,473.84

Over Heads

24. White Washing, Lettering and Painting, etc. 5% on ( Resource Cost + Over Head Cost + Child Item Amount) 373.69

Total OH Amount 373.69

Total Cost for 1.00 km = Sub Items Cost + Overhead Cost 7,847.53

Item Rate Per km 7,847.53

10976 8-2-(2) Construction of back piller as per Fig. 1600.1( c) as per drawing and Technical 30,663.20 km
7 Specification Clause 1602.3

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 3.60 291.20 cu.m 1,048.32


& brest walls
Earthwork in excavation for foundation
as per drawing and technical
specifications

MORD - 2016-2017 - 01/05/2016 - 8 Page 22 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016
1 11-1-1-1 3.60 291.20 cu.m 1,048.32
Amount And Rate In (Rs)
Item Description Rate Unit

2 11-6-1-2 In 1:4 cement mortar 3.60 5,252.00 cu.m 18,907.20

Stone masonry work in foundation


complete as per drawing and technical
specifications
3 12-3 Plastering with cement mortar (1:4), 15 45.00 205.50 sq.m 9,247.50
mm thick on brickwork in substructure

(as per technical specifications)


Total Child Item Amount 29,203.02

Over Heads

24. White Washing, Lettering and Painting, etc. 5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,460.15

Total OH Amount 1,460.15

Total Cost for 1.00 km = Sub Items Cost + Overhead Cost 30,663.17

Item Rate Per km 30,663.17

10976 8-2-(3) Construction of Job pillers as per Fig. 1600.1 (d) and Technical Specification Clause 765.90 km
8 1602.4

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.10 291.20 cu.m 27.96


& brest walls
Earthwork in excavation for foundation
as per drawing and technical
specifications.
2 11-6-1-2 In 1:4 cement mortar 0.10 5,252.00 cu.m 504.19

Stone masonry work in cement mortar


1:4 in foundation complete as per
drawing and technical specifications
3 12-3 Plastering with cement mortar (1:4), 15 0.96 205.50 sq.m 197.28
mm thick on brickwork in substructure

(as per technical specifications)


Total Child Item Amount 729.43

Over Heads

24. White Washing, Lettering and Painting, etc. 5% on ( Resource Cost + Over Head Cost + Child Item Amount) 36.47

Total OH Amount 36.47

MORD - 2016-2017 - 01/05/2016 - 8 Page 23 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Cost for 1.00 km = Sub Items Cost + Overhead Cost 765.90

Item Rate Per km 765.90

Notes: (i)The dimensions of reference pillars, back pillars and job pillars are as per figure/site conditions. The above items are covered under
different Chapters of MORD Specifications for payment.

(ii)The marking of centre line, setting out, curves, recording of levels, etc. by the surveyor will be incidental to work and no extra payment shall
be made for the same.

8-3 Earthwork in Hill Road


8-3-1 Excavation in Hilly Areas in Soil by manual means.
10976 8-3-1-A Excavation in soil in Hilly Area by manual means including cutting and trimming of 182.00 cu.m
9 side slopes and disposing of excavated earth with a lift upto 1.5 m and a lead upto 20
m as per drawing and Technical Specification Clause 1603.1
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 2.40 337.56 day 810.15
2 PL15 Beldar/mazdoor (unskilled) 60.00 306.88 day 18,412.50
Total Resource Amount 19,222.65

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 2,402.83

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 216.25

Total OH Amount 2,619.09

Total Cost for 120.00 cu.m = Resource Cost + Overhead Cost 21,841.74

Item Rate Per cu.m 182.01

10977 8-3-1-B Extra for Every Additional Lift of 1.5 m or Part thereof Excavation in Soil 19.20 cu.m
0
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL15 Beldar/mazdoor (unskilled) 0.55 306.88 day 168.78
Total Resource Amount 168.78

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 21.10

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1.90

MORD - 2016-2017 - 01/05/2016 - 8 Page 24 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total OH Amount 23.00

Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 191.78

Item Rate Per cu.m 19.18

8-3-2 Excavation in Hilly Areas in Soil by mechanical means


10977 8-3-2-A Excavation in soil in Hilly Area by mechanical means including cutting and 113.00 cu.m
1 trimming of side slopes and disposing of excavated earth with a lift upto 1.5 m and a
lead upto 20 m as per Technical Specification Clause 1603.1
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.80 337.56 day 270.05
2 PL15 Beldar/mazdoor (unskilled) 20.00 306.88 day 6,137.50
Machine Group
1 PMC009 Dozer D 50 6.00 2,001.00 hours 12,006.00
2 PMC012 Front end-loader 1 cum bucket capacity 6.00 1,242.00 hours 7,452.00
Total Resource Amount 25,865.55

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 3,233.19

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 290.99

Total OH Amount 3,524.18

Total Cost for 260.00 cu.m = Resource Cost + Overhead Cost 29,389.73

Item Rate Per cu.m 113.04

10977 8-3-2-B Extra for Every Additional Lift of 1.5 m or Part thereof Excavation in Soil 19.20 cu.m
2
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL15 Beldar/mazdoor (unskilled) 0.55 306.88 day 168.78
Total Resource Amount 168.78

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 21.10

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1.90

Total OH Amount 23.00

MORD - 2016-2017 - 01/05/2016 - 8 Page 25 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 191.78

Item Rate Per cu.m 19.18

Notes: (i)In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision
of front end loader and tipper shall be deleted as excavated earth shall be disposed off on the valley side.

(ii)For disposal of excavated surplus earth beyond 20 m, the relevant items of carriage be followed

(iii)In case, alternative machine like hydraulic excavator 0.9 cum bucket capacity is necessited because of site conditions, the same can be used.

8-3-3 Excavation in Hilly Area in Ordinary Rock by manual means


10977 8-3-3-A Excavation in ordinary rock using manual means including loading in a truck and 400.40 cu.m
3 carrying of excavated material to embankment site with a lift upto 1.5 m and lead
upto 20 m as per Clause 1603.2.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 5.28 337.56 day 1,782.33
2 PL15 Beldar/mazdoor (unskilled) 132.00 306.88 day 40,507.50
Total Resource Amount 42,289.83

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 5,286.23

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 475.76

Total OH Amount 5,761.99

Total Cost for 120.00 cu.m = Resource Cost + Overhead Cost 48,051.82

Item Rate Per cu.m 400.43

10977 8-3-3-B Extra for Every Additional Lift of 1.5 m or Part thereof For Ordinary Rock 30.00 cu.m
4
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL15 Beldar/mazdoor (unskilled) 0.86 306.88 day 263.91
Total Resource Amount 263.91

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 32.99

MORD - 2016-2017 - 01/05/2016 - 8 Page 26 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 2.97

Total OH Amount 35.96

Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 299.87

Item Rate Per cu.m 29.99

10977 8-3-4 Excavation in Hilly Areas in Ordinary Rock by mechanical means not requiring 170.40 cu.m
5 blasting

Excavation in hilly area in ordinary rock not requiring blasting by mechanical means
including cutting and trimming of slopes and disposal of cut material with a lift upto
1.5 m and lead upto 20 m as per Clause 1603.2.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.68 337.56 day 229.54
2 PL15 Beldar/mazdoor (unskilled) 26.00 306.88 day 7,978.75
Machine Group
1 PMC009 Dozer D 50 6.00 2,001.00 hours 12,006.00
2 PMC014 Hydraulic Excavator 0.9/1.0 cum 4.25 1,242.00 hours 5,278.50
Total Resource Amount 25,492.79

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 3,186.60

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 286.79

Total OH Amount 3,473.39

Total Cost for 170.00 cu.m = Resource Cost + Overhead Cost 28,966.19

Item Rate Per cu.m 170.39

Notes: (i)In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision
of front end loader and tipper shall be deleted as excavated earth shall be disposed off on the valley side.

(ii)In case, alternative machine like hydraulic excavator 0.9 cum bucket capacity is necessited because of site conditions, the same can be used.

8-3-5 Excavation in Hilly Areas in Hard Rock requiring blasting


10977 8-3-5-A Excavation in hilly areas in hard rock requiring blasting, by mechanical means, lift 314.50 cu.m
6 upto 1.5 m and disposal of excavated rock upto a lead of 20 m as per Clause 1603.2.

S.No Resource Code Resource Quantity Rate Unit Amount


.

MORD - 2016-2017 - 01/05/2016 - 8 Page 27 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Labour Group
1 PL04 Blaster 10.00 540.10 day 5,401.00
2 PL09 Rock Hole Driller 2.00 337.56 day 675.13
3 PL14 Mate 1.36 337.56 day 459.09
4 PL15 Beldar/mazdoor (unskilled) 22.00 306.88 day 6,751.25
Machine Group
1 PMC001 Air Compressor 210 cfm 28.00 414.00 hours 11,592.00
2 PMC009 Dozer D 50 3.00 2,001.00 hours 6,003.00
3 PMC014 Hydraulic Excavator 0.9/1.0 cum 5.00 1,242.00 hours 6,210.00
Material Group
1 PM0072 Electric Detonator 235.00 11.00 Nos. 2,585.00
2 PM0081 Gelatine 80 per cent 67.00 110.00 kilogram 7,370.00
Total Resource Amount 47,046.46

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 5,880.81

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 529.27

Total OH Amount 6,410.08

Total Cost for 170.00 cu.m = Resource Cost + Overhead Cost 53,456.54

Item Rate Per cu.m 314.45

10977 8-3-5-B Extra for Every Additional Lift of 1.5 m or Part thereof For Hard Rock 37.70 cu.m
7
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL15 Beldar/mazdoor (unskilled) 1.08 306.88 day 331.43
Total Resource Amount 331.43

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 41.43

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 3.73

Total OH Amount 45.16

Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 376.58

Item Rate Per cu.m 37.66

Notes: (1)In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision
of front end loader and tipper shall be deleted as excavated earth shall be disposed off on the valley side.

(2)In case of hill roads, the altitude effect comes into play. The output of men and machines decreases progressively after 2100 m elevation
MORDto- increase
leading 2016-2017 - 01/05/2016
in cost. - 8 effect has been explained Page
High altitude 28 ofapproach.
in the basic 106 14/05/16 8:14

(3)The arrangement for igniting the detonator is covered under overheads


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

(2)In case of hill roads, the altitude effect comes into play. The output of men and machines decreases progressively after 2100 m elevation
leading to increase in cost. High altitude effect has been explained in the basic approach.

(3)The arrangement for igniting the detonator is covered under overheads

8-4 Retaining Walls / Breast Walls

Construction of retaining walls/breast walls in cement mortar 1:5 as per drawing and
technical specifications Clause 1604
10977 8-4-1 Earthwork in excavation for structures 291.20 cu.m
8
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 1.00 291.20 cu.m 291.20


& brest walls
Total Child Item Amount 291.20

Total Cost for 1.00 cu.m = Sub Items Cost 291.20

Item Rate Per cu.m 291.20

10977 8-4-2 Plain cement concrete M 10 grade 6,389.40 cu.m


9
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-1-1 Nominal mix 1:3:6 1.00 6,389.40 cu.m 6,389.40

Total Child Item Amount 6,389.40

Total Cost for 1.00 cu.m = Sub Items Cost 6,389.40

Item Rate Per cu.m 6,389.40

10978 8-4-3 Stone masonry in cement mortar 1:5 3,873.80 cu.m


0
S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-4-3-3 In cement mortar (1:5) 1.00 3,873.80 cu.m 3,873.80

Total Child Item Amount 3,873.80

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

MORD - 2016-2017 - 01/05/2016 - 8 Page 29 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 3,873.80

Item Rate Per cu.m 3,873.80

10978 8-4-4 Pointing with cement mortar 1:3 78.20 sq.m


1
S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-2 Pointing with cement mortar (1:3) on 1.00 78.20 sq.m 78.20
brickwork as per drawing
Total Child Item Amount 78.20

Total Cost for 1.00 sq.m = Sub Items Cost 78.20

Item Rate Per sq.m 78.20

10978 8-4-5 Providing P.C.C. M 20 architectural coping on top of retaining wall/breast wall 4,051.10 metre
2
S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-11 Providing and laying filter media with 1.00 4,051.10 cu.m 4,051.10
granular crushed aggregates as per
specification
Total Child Item Amount 4,051.10

Total Cost for 1.00 metre = Sub Items Cost 4,051.10

Item Rate Per metre 4,051.10

10978 8-4-6 Filter material behind retaining wall / breast wall as per Specification 1204.3.8 in a 199.30 cu.m
3 width of 600 m

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-9 Providing weepholes in brick 1.00 199.30 Nos. 199.30


masonry/stone masonry,
plain/reinforced concrete abutment,
wing wall
Total Child Item Amount 199.30

Total Cost for 1.00 cu.m = Sub Items Cost 199.30

Item Rate Per cu.m 199.30

10978 8-4-7 Back filling behind retaining wall/breast wall 699.80 cu.m
4

MORD - 2016-2017 - 01/05/2016 - 8 Page 30 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-10-5 HP stone filling 1.00 699.80 cu.m 699.80

Total Child Item Amount 699.80

Total Cost for 1.00 cu.m = Sub Items Cost 699.80

Item Rate Per cu.m 699.80

8-5 Construction of Hill Side Drain

Construction of hill side drain in accordance with the requirement of specifications


true to lines and grades. Dimesions and other particulars as per drawing and
Technical Specification Clause 1606.1
10978 8-5-1 Earthwork in excavation for structures as per drawing and technical specification 291.20 cu.m
5
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 1.00 291.20 cu.m 291.20


& brest walls
Total Child Item Amount 291.20

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 291.20

Item Rate Per cu.m 291.20

10978 8-5-2 Plain cement concrete M10 grade 6,414.90 cu.m


6
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-1-2 Nominal mix 1:3.6 (Hand mixing) 1.00 6,414.90 cu.m 6,414.90

Total Child Item Amount 6,414.90

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 6,414.90

Item Rate Per cu.m 6,414.90

MORD - 2016-2017 - 01/05/2016 - 8 Page 31 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

10978 8-5-3 Stone masonry in cement mortar 1:5 3,873.80 cu.m


7
S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-4-3-3 In cement mortar (1:5) 1.00 3,873.80 cu.m 3,873.80

Total Child Item Amount 3,873.80

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 3,873.80

Item Rate Per cu.m 3,873.80

10978 8-5-4 Plain cement concrete M15 grade 6,291.20 cu.m


8
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-2 Nominal mix 1:2.5:5 (Hand mixing) 1.00 6,291.20 cu.m 6,291.20

Total Child Item Amount 6,291.20

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 6,291.20

Item Rate Per cu.m 6,291.20

10978 8-5-5 Cement plaster 15 mm thick 1:4 on stone masonry 205.50 sq.m
9
S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-3 Plastering with cement mortar (1:4), 15 1.00 205.50 sq.m 205.50
mm thick on brickwork in substructure

Total Child Item Amount 205.50

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

MORD - 2016-2017 - 01/05/2016 - 8 Page 32 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Cost for 1.00 sq.m = Sub Items Cost + Overhead Cost 205.50

Item Rate Per sq.m 205.50

10979 8-5-6 Providing P.C.C. M20 architectural coping on top of wall 4,051.10 metre
0
S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-11 Providing and laying filter media with 1.00 4,051.10 cu.m 4,051.10
granular crushed aggregates as per
specification
Total Child Item Amount 4,051.10

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 metre = Sub Items Cost + Overhead Cost 4,051.10

Item Rate Per metre 4,051.10

Notes: (1)Quantities of material/work shall be as per design and drawings


(2)Earth work in excavation may be taken as per site conditions. It may comprise of a number of sub-items depending upon the type of soil/rock
encountered.

8-6 Construction of Catch Water / Intercepting Drain

Construction of catch water/intercepting drain in random rubble masonry in 1:5


cement mortar true to the specified lines grades levels and dimensions as per the
requirement of the specifications Clause 1606.2
10979 8-6-1 Earthwork in excavation for structures as per drawing and technical specification 291.20 cu.m
1
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 1.00 291.20 cu.m 291.20


& brest walls
Total Child Item Amount 291.20

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 291.20

Item Rate Per cu.m 291.20

MORD - 2016-2017 - 01/05/2016 - 8 Page 33 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

10979 8-6-2 Plain cement concrete M10 grade 6,414.90 cu.m


2
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-1-2 Nominal mix 1:3.6 (Hand mixing) 1.00 6,414.90 cu.m 6,414.90

Total Child Item Amount 6,414.90

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 6,414.90

Item Rate Per cu.m 6,414.90

10979 8-6-3 Stone masonry in cement mortor 1:5 3,873.80 cu.m


3
S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-4-3-3 In cement mortar (1:5) 1.00 3,873.80 cu.m 3,873.80

Total Child Item Amount 3,873.80

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 3,873.80

Item Rate Per cu.m 3,873.80

10979 8-6-4 Plain cement concrete M15 grade 6,291.20 cu.m


4
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-2 Nominal mix 1:2.5:5 (Hand mixing) 1.00 6,291.20 cu.m 6,291.20

Total Child Item Amount 6,291.20

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

MORD - 2016-2017 - 01/05/2016 - 8 Page 34 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 6,291.20

Item Rate Per cu.m 6,291.20

10979 8-6-5 Cement plaster 15 mm thick 1:4 on stone masonry 205.50 sq.m
5
S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-3 Plastering with cement mortar (1:4), 15 1.00 205.50 sq.m 205.50
mm thick on brickwork in substructure

Total Child Item Amount 205.50

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 sq.m = Sub Items Cost + Overhead Cost 205.50

Item Rate Per sq.m 205.50

10979 8-6-6 Providing P.C.C. M 20 architectural coping on top of wall 4,051.10 metre
6
S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-11 Providing and laying filter media with 1.00 4,051.10 cu.m 4,051.10
granular crushed aggregates as per
specification
Total Child Item Amount 4,051.10

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 metre = Sub Items Cost + Overhead Cost 4,051.10

Item Rate Per metre 4,051.10

Notes: (1)Quantities of material/work shall be as per design and drawings


(2)Earth work in excavation may be taken as per site conditions.It may comprise of a number of sub-items depending upon the type of soil/rock
encountered.

8-7 Construction of Scupper

Construction of scupper with dry stone masonry as per drawing and technical
specifications as per Clause 1606.5.
MORD - 2016-2017 - 01/05/2016 - 8 Page 35 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

10979 8-7-1 Earthwork in excavation for structures as per drawing and technical specifications 5,581.30 metre
7
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 115.00 291.20 cu.m 33,488.00


& brest walls
Quantity for 6 m formation width of
hill side rock cutting and foundation as
per plate No. 7.27 of Rural Road
Manual
Total Child Item Amount 33,488.00

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 6.00 metre = Sub Items Cost + Overhead Cost 33,488.00

Item Rate Per metre 5,581.33

Notes: Quantity for 6 m formation width of hill side rock cutting and foundation as per plate No. 7.27 of Rural Road Manual

10979 8-7-2 Random rubble dry stone masonry 14,016.00 metre


8
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 38.00 558.51 day 21,223.48
2 PL14 Mate 3.80 337.56 day 1,282.74
3 PL15 Beldar/mazdoor (unskilled) 57.00 306.88 day 17,491.88
Material Group
1 PM0047 Bond stone (400 mm x 150 mm x 150 mm) 266.00 49.70 Nos. 13,219.67
2 PM0136 Stone for Random Rubble Masonry 38.00 370.15 cu.m 14,065.87
Total Resource Amount 67,283.62

Over Heads

2. Water Charges 10% on ( Resource Cost + Over Head Cost + Child Item Amount) 6,728.36

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 9,251.50

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 832.63

Total OH Amount 16,812.50

Total Cost for 6.00 metre = Resource Cost + Overhead Cost 84,096.12

Item Rate Per metre 14,016.02

MORD - 2016-2017 - 01/05/2016 - 8 Page 36 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Notes: Quantity for 6 m formation width = 38 cum

10979 8-7-3 Random course rubble dry stone masonry in corbelling 5,869.10 metre
9
Quantity for 6 m formation width = 10 cum
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 6.00 558.51 day 3,351.08
2 PL14 Mate 0.72 337.56 day 243.05
3 PL15 Beldar/mazdoor (unskilled) 12.00 306.88 day 3,682.50
Material Group
1 PM0055 Corbelling Stones (300 mm x 150 mm x 150 1,335.00 15.65 Nos. 20,898.09
mm)
Total Resource Amount 28,174.71

Over Heads

2. Water Charges 10% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,817.47

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 3,874.02

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 348.66

Total OH Amount 7,040.16

Total Cost for 6.00 metre = Resource Cost + Overhead Cost 35,214.87

Item Rate Per metre 5,869.14

10980 8-7-4 Stone filling in foundation trenches as per drawing and technical specification 682.00 metre
0
Quantity for 6 m formation width = 10 cum
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.12 337.56 day 40.51
2 PL15 Beldar/mazdoor (unskilled) 3.00 306.88 day 920.63
Material Group
1 PM0099 Loose stone 12.00 220.00 cu.m 2,640.00
Total Resource Amount 3,601.13

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 450.14

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 40.51

MORD - 2016-2017 - 01/05/2016 - 8 Page 37 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total OH Amount 490.65

Total Cost for 6.00 metre = Resource Cost + Overhead Cost 4,091.79

Item Rate Per metre 681.96

8-8 Construction of RCC guide posts of 250 mm dia M15 grade cast-in-situ with 20 mm
nominal size aggregate, true to line and grade, tolerance of vertical RCC posts not to
exceed 1 in 500 as per drawing and Technical Specification Clause 1608.2

10980 8-8-(i) Earth work in excavation for structures 294.10 cu.m


2
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 1.00 291.20 cu.m 291.20


& brest walls
Total Child Item Amount 291.20

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 2.91

Total OH Amount 2.91

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 294.11

Item Rate Per cu.m 294.11

10980 8-8-(ii) RCC M15 grade 6,313.40 cu.m


3
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 1.00 6,250.90 cu.m 6,250.90

Total Child Item Amount 6,250.90

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 62.51

Total OH Amount 62.51

Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 6,313.41

Item Rate Per cu.m 6,313.41

10980 8-8-(iii) HYSD steel bars 57,733.00 tonne


4

MORD - 2016-2017 - 01/05/2016 - 8 Page 38 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-6 Supplying, fitting and placing HYSD 1.00 57,161.40 tons 57,161.40
bar reinforcement (Fe 415) in
substructrue
Total Child Item Amount 57,161.40

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 571.61

Total OH Amount 571.61

Total Cost for 1.00 tonne = Sub Items Cost + Overhead Cost 57,733.01

Item Rate Per tonne 57,733.01

10980 8-8-(iv) Painting two coats including prime coat on new concrete surface 121.50 sq.m
5
S.No. Item Code Item Description Quantity Rate Unit Amount

1 10-5 Painting Two Coats on New Concrete 1.00 121.50 sq.m 121.50
Surfaces
Total Child Item Amount 121.50

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00

Total OH Amount 0.00

Total Cost for 1.00 sq.m = Sub Items Cost + Overhead Cost 121.50

Item Rate Per sq.m 121.50

Notes: Quantities are to be taken as per drawing

10980 8-9 Providing edge stones on valley side of formation as per drawing and Technical 253.90 metre
6 Specification Clause 1608.2.6

Taking Output = 45 m (100 no of edge stones of size 450 mm x 300 mm x 100 mm)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL13 Mason (brick layer) 2nd class 1.50 540.10 day 810.15
2 PL14 Mate 0.18 337.56 day 60.76
3 PL15 Beldar/mazdoor (unskilled) 3.00 306.88 day 920.63
Material Group
1 PM0069 Hammer Dressed Edge Stone (450 mm x 350 100.00 58.35 Nos. 5,835.20
mm x 100 mm)

MORD - 2016-2017 - 01/05/2016 - 8 Page 39 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Resource Amount 7,626.74

S.No. Item Code Item Description Quantity Rate Unit Amount

1 10-5 Painting Two Coats on New Concrete 22.50 121.50 sq.m 2,733.75
Surfaces

including priming coat


45 x 0.500 = 22.50
Total Child Item Amount 2,733.75

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 953.34

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 113.14

Total OH Amount 1,066.48

Total Cost for 45.00 metre = Sub Items Cost + Resource Cost + Overhead 11,426.97
Cost
Item Rate Per metre 253.93

10980 8-10 Turfing with Sods 67.60 sq.m


7
Furnishing and laying of the live sods of perennial turf forming grass on
embankment slope, verges or other locations shown on the drawing or as directed by
the Engineer including preparation of ground, stacking the sods and watering as per
Clause 309
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.16 337.56 day 54.01
2 PL15 Beldar/mazdoor (unskilled) 4.00 306.88 day 1,227.50
Machine Group
1 PMC031 Tractor with trolley. 1.00 276.00 hours 276.00
2 PMC035 Water tanker 6 kl capacity (Truck Mounted) 4.00 276.00 hours 1,104.00
Material Group
1 PM0075 Farmyard manure 0.18 300.00 cu.m 54.00
2 PM0144 Water 24.00 135.00 Killo Litre 3,240.00
Total Resource Amount 5,955.51

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 59.56

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 744.44

Total OH Amount 803.99

MORD - 2016-2017 - 01/05/2016 - 8 Page 40 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Cost for 100.00 sq.m = Resource Cost + Overhead Cost 6,759.50

Item Rate Per sq.m 67.60

10980 8-11 Seeding and Mulching 143.30 sq.m


8
Preparation of seed bed on previously laid top soil, furnishing and placing of seeds,
fertilizer, multching material, applying bituminous emulsion at the rate of 0.23 l per
sqm and laying and fixing jute netting, including watering for 3 months all as per
Clause 310.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.60 337.56 day 202.54
2 PL15 Beldar/mazdoor (unskilled) 15.00 306.88 day 4,603.13
Machine Group
1 PMC031 Tractor with trolley. 2.40 276.00 hours 662.40
2 PMC035 Water tanker 6 kl capacity (Truck Mounted) 13.00 276.00 hours 3,588.00
Material Group
1 PM0043 Bitumen Emulsion (SS-1) 0.06 25,683.51 tonne 1,412.59
2 PM0075 Farmyard manure 0.43 300.00 cu.m 129.00
3 PM0092 Jute netting, open weave 25 mm square 264.00 30.00 sq.m 7,920.00
opening
4 PM0125 Seeds 3.60 125.00 kilogram 450.00
5 PM0144 Water 84.00 135.00 Killo Litre 11,340.00
Total Resource Amount 30,307.66

Over Heads

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 303.08

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 3,788.46

Total OH Amount 4,091.53

Total Cost for 240.00 sq.m = Resource Cost + Overhead Cost 34,399.19

Item Rate Per sq.m 143.33

Specification:

MORD - 2016-2017 - 01/05/2016 - 8 Page 41 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Chapter Name PIPE CULVERTS


Amount And Rate In (Rs)
Item Description Rate Unit

9-1 Earthwork in excavation for foundation of structures upto 3 m depth as per drawing
and technical specification Clause 1104 including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material
11255 9-1-1 Excavation in Ordinary Soil 291.20 cu.m
4
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.32 337.56 day 108.02
2 PL15 Beldar/mazdoor (unskilled) 8.00 306.88 day 2,455.00
Total Resource Amount 2,563.02

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 320.38

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 28.83

Total OH Amount 349.21

Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 2,912.23

Item Rate Per cu.m 291.22

11255 9-1-2 Excavation in Ordinary Rock (not requiring blasting) 364.00 cu.m
5
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.40 337.56 day 135.03
2 PL15 Beldar/mazdoor (unskilled) 10.00 306.88 day 3,068.75
Total Resource Amount 3,203.78

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 400.47

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 36.04

Total OH Amount 436.51

Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 3,640.29

Item Rate Per cu.m 364.03

11256 9-1-5 Excavation in Marshy soil 546.00 cu.m


3MORD - 2016-2017 - 01/05/2016 - 9 Page 42 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

3
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.60 337.56 day 202.54
2 PL15 Beldar/mazdoor (unskilled) 15.00 306.88 day 4,603.13
Total Resource Amount 4,805.66

Over Heads

82. Contractor's Profit Including Over Head 12.5% on (All Resource) 600.71

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 54.06

Total OH Amount 654.77

Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 5,460.43

Item Rate Per cu.m 546.04

11262 9-1-3 Hard Rock (Requiring blasting) 0.00 cu.m


2

11262 9-1-4 Hard rock (requiring blasting) 0.00 cu.m


3

11262 9-1-3 Hard rock (requiring blasting) 0.00 cu.m


4

9-2 Bedding for Pipe


10981 9-2-(i) Type A (Concrete Cradle) Bedding 6,250.90 cu.m
0 Laying concrete cradle bedding with M15 Grade Cement Concrete as per Clause
1105 (i)
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 1.00 6,250.90 cu.m 6,250.90

Total Child Item Amount 6,250.90

Total Cost for 1.00 cu.m = Sub Items Cost 6,250.90

Item Rate Per cu.m 6,250.90

MORD - 2016-2017 - 01/05/2016 - 9 Page 43 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

10981 9-2-(ii) Type B (First Class) Bedding 1,884.30 cu.m


1 Laying (First Class) bedding on well compacted sand, moorum or approved granular
material as per Clause 1105 (ii)
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-2-1 Sand filling 1.00 1,884.30 cu.m 1,884.30

Total Child Item Amount 1,884.30

Total Cost for 1.00 cu.m = Sub Items Cost 1,884.30

Item Rate Per cu.m 1,884.30

9-3 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single
Row

Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets Clause 1106.

10981 9-3-A 1200 mm dia 8,960.60 metre


2
(3 pipes of 2.5 m length each)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.50 558.51 day 279.26
2 PL14 Mate 0.14 337.56 day 47.26
3 PL15 Beldar/mazdoor (unskilled) 3.00 306.88 day 920.63
Material Group
1 PM0049 Cement 0.07 8,481.46 tonne 593.70
2 PM0111 RCC Pipe NP3 (1200 mm dia) 7.50 7,632.35 metre 57,242.60
3 PM0124 Sand (Fine) 0.05 1,247.44 cu.m 62.37
Total Resource Amount 59,145.82

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 7,393.23

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 665.39

Total OH Amount 8,058.62

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 67,204.43

Item Rate Per metre 8,960.59

MORD - 2016-2017 - 01/05/2016 - 9 Page 44 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Notes: The labour rate for 600 mm dia Hume pipe may be derived from the rates for 750 dia by decreasing 20 per cent

10981 9-3-B 1000 mm dia 7,132.70 metre


3
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.25 558.51 day 139.63
2 PL14 Mate 0.09 337.56 day 30.38
3 PL15 Beldar/mazdoor (unskilled) 2.00 306.88 day 613.75
Material Group
1 PM0049 Cement 0.03 8,481.46 tonne 254.44
2 PM0112 RCC Pipe NP3 (1000 mm dia) 7.50 6,132.35 metre 45,992.60
3 PM0124 Sand (Fine) 0.04 1,247.44 cu.m 49.90
Total Resource Amount 47,080.70

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 5,885.09

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 529.66

Total OH Amount 6,414.75

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 53,495.45

Item Rate Per metre 7,132.73

10981 9-3-C 750 mm dia 4,263.80 metre


4
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.15 558.51 day 83.78
2 PL14 Mate 0.05 337.56 day 16.88
3 PL15 Beldar/mazdoor (unskilled) 1.20 306.88 day 368.25
Material Group
1 PM0049 Cement 0.02 8,481.46 tonne 152.67
2 PM0113 RCC Pipe NP3 (750 mm dia) 7.50 3,665.66 metre 27,492.44
3 PM0124 Sand (Fine) 0.02 1,247.44 cu.m 29.94
Total Resource Amount 28,143.95

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 3,517.99

MORD - 2016-2017 - 01/05/2016 - 9 Page 45 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 316.62

Total OH Amount 3,834.61

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 31,978.56

Item Rate Per metre 4,263.81

9-4 Providing and Laying Reinforced Cement Concrete Pipe NP4 as per design in Single
Row

Providing and laying reinforced cement concrete pipe NP4 for culverts on first class
bedding of granular material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets Clause 1106.

10981 9-4-A 1200 mm dia 10,324.10 metre


5
(3 pipes of 2.5 m length each)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.50 558.51 day 279.26
2 PL14 Mate 0.14 337.56 day 47.26
3 PL15 Beldar/mazdoor (unskilled) 3.00 306.88 day 920.63
Material Group
1 PM0049 Cement 0.07 8,481.46 tonne 593.70
2 PM0116 RCC Pipe NP4 (1200 mm dia) 7.50 8,832.35 metre 66,242.60
3 PM0124 Sand (Fine) 0.05 1,247.44 cu.m 62.37
Total Resource Amount 68,145.82

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 8,518.23

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 766.64

Total OH Amount 9,284.87

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 77,430.68

Item Rate Per metre 10,324.09

10981 9-4-B 1000 mm dia 8,269.00 metre


6
S.No Resource Code Resource Quantity Rate Unit Amount
.
MORD - 2016-2017 - 01/05/2016 - 9 Page 46 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Labour Group
1 PL12 Mason (brick layer) 1st class 0.25 558.51 day 139.63
2 PL14 Mate 0.09 337.56 day 30.38
3 PL15 Beldar/mazdoor (unskilled) 2.00 306.88 day 613.75
Material Group
1 PM0049 Cement 0.03 8,481.46 tonne 254.44
2 PM0117 RCC Pipe NP4 (1000 mm dia) 7.50 7,132.35 metre 53,492.60
3 PM0124 Sand (Fine) 0.04 1,247.44 cu.m 49.90
Total Resource Amount 54,580.70

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 6,822.59

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 614.03

Total OH Amount 7,436.62

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 62,017.32

Item Rate Per metre 8,268.98

10981 9-4-C 750 mm dia 5,059.20 metre


7
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.15 558.51 day 83.78
2 PL14 Mate 0.05 337.56 day 16.88
3 PL15 Beldar/mazdoor (unskilled) 1.20 306.88 day 368.25
Material Group
1 PM0049 Cement 0.02 8,481.46 tonne 152.67
2 PM0118 RCC Pipe NP4 (750 mm dia) 7.50 4,365.66 metre 32,742.44
3 PM0124 Sand (Fine) 0.02 1,247.44 cu.m 29.94
Total Resource Amount 33,393.95

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 4,174.24

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 375.68

Total OH Amount 4,549.93

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 37,943.87

Item Rate Per metre 5,059.18

MORD - 2016-2017 - 01/05/2016 - 9 Page 47 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Notes: The labour rate for 600 mm dia Hume pipe may be derived from the rates for 750 dia by decreasing 20 per cent

9-5 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per Design in
Double Row

Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets as per Clause 1106.

10981 9-5-A 1200 mm dia 17,998.90 metre


8
(6 pipes of 2.5 m length each in two rows)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 1.20 558.51 day 670.22
2 PL14 Mate 0.34 337.56 day 114.77
3 PL15 Beldar/mazdoor (unskilled) 7.20 306.88 day 2,209.50
Material Group
1 PM0049 Cement 0.14 8,481.46 tonne 1,187.40
2 PM0111 RCC Pipe NP3 (1200 mm dia) 15.00 7,632.35 metre 1,14,485.21
3 PM0124 Sand (Fine) 0.11 1,247.44 cu.m 137.22
Total Resource Amount 1,18,804.32

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 14,850.54

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,336.55

Total OH Amount 16,187.09

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 1,34,991.40

Item Rate Per metre 17,998.85

10981 9-5-B 1000 mm dia 14,313.20 metre


9
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.60 558.51 day 335.11
2 PL14 Mate 0.22 337.56 day 74.26
3 PL15 Beldar/mazdoor (unskilled) 4.80 306.88 day 1,473.00

MORD - 2016-2017 - 01/05/2016 - 9 Page 48 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Material Group
1 PM0049 Cement 0.06 8,481.46 tonne 508.89
2 PM0112 RCC Pipe NP3 (1000 mm dia) 15.00 6,132.35 metre 91,985.21
3 PM0124 Sand (Fine) 0.08 1,247.44 cu.m 99.80
Total Resource Amount 94,476.26

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 11,809.53

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,062.86

Total OH Amount 12,872.39

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 1,07,348.65

Item Rate Per metre 14,313.15

10982 9-5-C 750 mm dia 8,526.60 metre


0
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.30 558.51 day 167.55
2 PL14 Mate 0.11 337.56 day 37.13
3 PL15 Beldar/mazdoor (unskilled) 2.40 306.88 day 736.50
Material Group
1 PM0049 Cement 0.04 8,481.46 tonne 305.33
2 PM0113 RCC Pipe NP3 (750 mm dia) 15.00 3,665.66 metre 54,984.88
3 PM0124 Sand (Fine) 0.04 1,247.44 cu.m 49.90
Total Resource Amount 56,281.29

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 7,035.16

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 633.16

Total OH Amount 7,668.33

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 63,949.62

Item Rate Per metre 8,526.62

Notes: The labour rate for 600 mm dia Hume pipe should be decreased by 20 per cent

9-6 Providing and Laying Reinforced Cement Concrete Pipe NP4 as per Design in
Double Row

Providing and laying reinforced cement concrete pipe NP4 for culverts on first class
MORD - 2016-2017 - 01/05/2016 - 9 Page 49 of 106 14/05/16 8:14
bedding of granular material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets as per Clause 1106.
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Providing and laying reinforced cement concrete pipe NP4 for culverts on first class
bedding of granular material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets as per Clause 1106.

10982 9-6-A 1200 mm dia 20,725.90 metre


1
(6 pipes of 2.5 m length each in two rows)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 1.20 558.51 day 670.22
2 PL14 Mate 0.34 337.56 day 114.77
3 PL15 Beldar/mazdoor (unskilled) 7.20 306.88 day 2,209.50
Material Group
1 PM0049 Cement 0.14 8,481.46 tonne 1,187.40
2 PM0116 RCC Pipe NP4 (1200 mm dia) 15.00 8,832.35 metre 1,32,485.21
3 PM0124 Sand (Fine) 0.11 1,247.44 cu.m 137.22
Total Resource Amount 1,36,804.32

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 17,100.54

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,539.05

Total OH Amount 18,639.59

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 1,55,443.90

Item Rate Per metre 20,725.85

10982 9-6-B 1000 mm dia 16,585.70 metre


2
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.60 558.51 day 335.11
2 PL14 Mate 0.22 337.56 day 74.26
3 PL15 Beldar/mazdoor (unskilled) 4.80 306.88 day 1,473.00
Material Group
1 PM0049 Cement 0.06 8,481.46 tonne 508.89
2 PM0117 RCC Pipe NP4 (1000 mm dia) 15.00 7,132.35 metre 1,06,985.21
3 PM0124 Sand (Fine) 0.08 1,247.44 cu.m 99.80

MORD - 2016-2017 - 01/05/2016 - 9 Page 50 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Resource Amount 1,09,476.26

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 13,684.53

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,231.61

Total OH Amount 14,916.14

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 1,24,392.40

Item Rate Per metre 16,585.65

10982 9-6-C 750 mm dia 8,526.60 metre


3
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.30 558.51 day 167.55
2 PL14 Mate 0.11 337.56 day 37.13
3 PL15 Beldar/mazdoor (unskilled) 2.40 306.88 day 736.50
Material Group
1 PM0049 Cement 0.04 8,481.46 tonne 305.33
2 PM0113 RCC Pipe NP3 (750 mm dia) 15.00 3,665.66 metre 54,984.88
3 PM0124 Sand (Fine) 0.04 1,247.44 cu.m 49.90
Total Resource Amount 56,281.29

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 7,035.16

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 633.16

Total OH Amount 7,668.33

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 63,949.62

Item Rate Per metre 8,526.62

Notes: The labour rate for 600 mm dia Hume pipe should be decreased by 20 per cent

10982 9-7 Laying Cement Concrete Pipe NP3 (burried conduits) on first class bedding of 2,998.50 metre
4 granular material including fixing collar with cement sand mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonary work in head wall
and parapets
(3 pipes of 2.5 m length each)
S.No Resource Code Resource Quantity Rate Unit Amount
.

MORD - 2016-2017 - 01/05/2016 - 9 Page 51 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Labour Group
1 PL12 Mason (brick layer) 1st class 0.11 558.51 day 61.44
2 PL14 Mate 0.04 337.56 day 13.50
3 PL15 Beldar/mazdoor (unskilled) 0.90 306.88 day 276.19
Material Group
1 PM0049 Cement 0.01 8,481.46 tonne 84.81
2 PM0115 RCC Pipe NP3 (500 mm dia) 7.50 2,577.45 metre 19,330.87
3 PM0124 Sand (Fine) 0.02 1,247.44 cu.m 24.95
Total Resource Amount 19,791.76

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,473.97

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 222.66

Total OH Amount 2,696.63

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 22,488.38

Item Rate Per metre 2,998.45

Notes: The labour rate for 300 mm dia shall be decreased by 20 per cent

10982 9-8 Laying Cement Concrete Pipe NP4 (burried conduits) on first class bedding of 2,998.50 metre
5 granular material including fixing collar with cement sand mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonary work in head wall
and parapets
(3 pipes of 2.5 m length each)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.11 558.51 day 61.44
2 PL14 Mate 0.04 337.56 day 13.50
3 PL15 Beldar/mazdoor (unskilled) 0.90 306.88 day 276.19
Material Group
1 PM0049 Cement 0.01 8,481.46 tonne 84.81
2 PM0120 RCC Pipe NP4 (500 mm dia) 7.50 2,577.45 metre 19,330.87
3 PM0124 Sand (Fine) 0.02 1,247.44 cu.m 24.95
Total Resource Amount 19,791.76

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,473.97

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 222.66

MORD - 2016-2017 - 01/05/2016 - 9 Page 52 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total OH Amount 2,696.63

Total Cost for 7.50 metre = Resource Cost + Overhead Cost 22,488.38

Item Rate Per metre 2,998.45

Notes: The labour rate for 300 mm dia shall be decreased by 20 per cent

10982 9-9 Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course below open 6,389.40 cu.m
6 foundation of Head walls as per drawings & Technical Specification Clause 1109

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-1-1 Nominal mix 1:3:6 1.00 6,389.40 cu.m 6,389.40

Total Child Item Amount 6,389.40

Total Cost for 1.00 cu.m = Sub Items Cost 6,389.40

Item Rate Per cu.m 6,389.40

9-10 Brick Masonry Work in cement mortar in foundation of Head walls complete
exculding pointing and plastering as per drawing and technical specification Clause
1109
10982 9-10-A Brick Masonry in 1:4 cement mortar 8,340.80 cu.m
7
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-5-2 Brick masonry in 1:4 cement mortar 1.00 8,340.80 cu.m 8,340.80

Total Child Item Amount 8,340.80

Total Cost for 1.00 cu.m = Sub Items Cost 8,340.80

Item Rate Per cu.m 8,340.80

10982 9-10-B Brick Masonry in cement-lime mortar (1:0.5:4.5) 8,874.00 cu.m


8
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-5-3 Brick masonry in cement-lime-mortar 1.00 8,874.00 cu.m 8,874.00


(1:0.5:4.5)
Total Child Item Amount 8,874.00

Total Cost for 1.00 cu.m = Sub Items Cost 8,874.00

Item Rate Per cu.m 8,874.00

MORD - 2016-2017 - 01/05/2016 - 9 Page 53 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

9-11 Stone Masonry Work in cement mortar in foundation of Head walls complete as per
drawing and technical specification Clasue 1109
10982 9-11-A In 1:4 cement mortar 4,989.60 cu.m
9
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-6-2-2 In 1:4 cement mortar 1.00 4,989.60 cu.m 4,989.60

Total Child Item Amount 4,989.60

Total Cost for 1.00 cu.m = Sub Items Cost 4,989.60

Item Rate Per cu.m 4,989.60

10983 9-11-B In cement-lime mortar (1:0.5:4.5) 5,738.20 cu.m


0
S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-6-2-3 In cement-lime-mortar (1:0.5:4.5) 1.00 5,738.20 cu.m 5,738.20

Total Child Item Amount 5,738.20

Total Cost for 1.00 cu.m = Sub Items Cost 5,738.20

Item Rate Per cu.m 5,738.20

10983 9-12 Pointing with Cement Mortar (1:3) on brickwork as per technical specification 78.20 sq.m
1 Clause 613.3

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-2 Pointing with cement mortar (1:3) on 1.00 78.20 sq.m 78.20
brickwork as per drawing
Total Child Item Amount 78.20

Total Cost for 1.00 sq.m = Sub Items Cost 78.20

Item Rate Per sq.m 78.20

10983 9-13 Plastering with Cement Mortar (1:4), 15 mm thick on brickwork in substructure as 2,055.00 sq.m
2 per technical specification

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-3 Plastering with cement mortar (1:4), 15 10.00 205.50 sq.m 2,055.00
mm thick on brickwork in substructure

MORD - 2016-2017 - 01/05/2016 - 9 Page 54 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Child Item Amount 2,055.00

Total Cost for 1.00 sq.m = Sub Items Cost 2,055.00

Item Rate Per sq.m 2,055.00

10983 9-14 Backfilling in Foundation Trenches as per drawing and technical specification 187.10 cu.m
3 Clause 1108

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-2-2 Earth filling (For marshy soil) 1.00 187.10 cu.m 187.10

Total Child Item Amount 187.10

Total Cost for 1.00 cu.m = Sub Items Cost 187.10

Item Rate Per cu.m 187.10

10983 9-15 Providing PCC M20 Architectural Coping on the top of wing wall, return wall etc. 403.50 metre
4 complete as per drawing and technical specification Clause 615

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-13 Providing PCC M-20 architectural 1.00 403.50 m 403.50


coping on the top of wing wall, return
wall etc.
Total Child Item Amount 403.50

Total Cost for 1.00 metre = Sub Items Cost 403.50

Item Rate Per metre 403.50

Specification:

MORD - 2016-2017 - 01/05/2016 - 9 Page 55 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Chapter Name TRAFFIC SIGNS, MARKINGS AND OTHER ROAD APPURTENANCES

Amount And Rate In (Rs)


Item Description Rate Unit

10-1 Printing New Letters and Figures of any Shade

Printing new letter and figures of any shade with synthetic enamel paint black or any
other approved colour to give an even shade as per drawings and Technical
Specification Clause 1701
10983 10-1-1 Hindi (Matras commas and the like not to be measured and paid for. Half letters 1.20 cm
5 shall be counted as half only)

Details for 100 letters of 160 mm height, i.e., 1600 cm


S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.12 337.56 day 40.51
2 PL15 Beldar/mazdoor (unskilled) 1.00 306.88 day 306.88
3 PL18 Painter (Ist class) 2.00 540.10 day 1,080.20
Material Group
1 PM0106 Paint (Synthetic Enamel) 0.70 278.00 litre 194.60
Total Resource Amount 1,622.18

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 202.77

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 18.25

Total OH Amount 221.02

Total Cost for 1,600.00 cm = Resource Cost + Overhead Cost 1,843.20

Item Rate Per cm 1.15

10983 10-1-B English and Roman 0.70 cm


6 Hyphens, commas and the like not to be measured and paid for. Detail for 100
letters of 160 mm height, i.e., 1600 cm
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.07 337.56 day 23.63
2 PL15 Beldar/mazdoor (unskilled) 0.50 306.88 day 153.44
3 PL18 Painter (Ist class) 1.25 540.10 day 675.13
Material Group
1 PM0106 Paint (Synthetic Enamel) 0.50 278.00 litre 139.00
Total Resource Amount 991.19

MORD - 2016-2017 - 01/05/2016 - 10 Page 56 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 123.90

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 11.15

Total OH Amount 135.05

Total Cost for 1,600.00 cm = Resource Cost + Overhead Cost 1,126.24

Item Rate Per cm 0.70

10-2 Traffic Signs


10-2-A Retro-reflectorised Traffic Signs
10-2-A-(1) Providing and fixing of retro-reflectorised cautionary, mandatory and informatory
sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause
1701.2.3 fixed over aluminium sheeting, 1.5 mm thick supported on a mild steel
angle iron post 75 mm x 75 mm x 6 mm firmly fixed to the ground by means of
properly designed foundation with M15 grade cement concrete 450 mm x 450 mm x
600 mm, 600 mm below ground level as per drawings and Technical Specification
Clause 801
10983 10-2-A-(1)-(i) 900 mm equilateral triangle 2,704.50 each
7
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.35 1,805.28 sq.m 631.85
2 PM0101 MS Flat / Structural Steel 20.00 41,781.46 M.T. 835.63
/kilogram
Total Resource Amount 1,569.65

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Excavation for foundation
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

Cement concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 0.89 97.70 sq.m 86.66
with Epoxy
MORD - 2016-2017 - 01/05/2016 - 10 Page 57 of 106 14/05/16 8:14
Painting Angle Iron Post with Primer
and two coats of Epoxy Paint as per
specifications
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit
3 10-7 0.89 97.70 sq.m 86.66

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
Total Child Item Amount 785.46

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0101) 25.07

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 297.52

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 26.78

Total OH Amount 349.37

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,704.48
Cost
Item Rate Per each 2,704.48

10983 10-2-A-(1)-(ii) 600 mm equilateral triangle 2,306.50 each


8
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.16 1,805.28 sq.m 281.62
2 PM0101 MS Flat / Structural Steel 20.00 41,781.46 M.T. 835.63
/kilogram
Total Resource Amount 1,219.43

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Excavation for foundation
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

Cement concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 0.89 97.70 sq.m 86.66
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
MORD - 2016-2017 - 01/05/2016 - 10 Page 58 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016
3 10-7 0.89 97.70 sq.m 86.66
Amount And Rate In (Rs)
Item Description Rate Unit

specifications
Total Child Item Amount 785.46

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0101) 25.07

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 253.74

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 22.84

Total OH Amount 301.65

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,306.54
Cost
Item Rate Per each 2,306.54

10983 10-2-A-(1)-(iii) 600 mm circular 2,567.00 each


9
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.28 1,805.28 sq.m 510.90
2 PM0101 MS Flat / Structural Steel 20.00 41,781.46 M.T. 835.63
/kilogram
Total Resource Amount 1,448.70

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Excavation for foundation
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

Cement concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 0.89 97.70 sq.m 86.66
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
Total Child Item Amount 785.46

MORD - 2016-2017 - 01/05/2016 - 10 Page 59 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0101) 25.07

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 282.40

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 25.42

Total OH Amount 332.89

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,567.05
Cost
Item Rate Per each 2,567.05

10984 10-2-A-(1)-(iv) 800 mm x 600 mm rectangular 2,972.20 each


0
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.48 1,805.28 sq.m 866.54
2 PM0101 MS Flat / Structural Steel 20.00 41,781.46 M.T. 835.63
/kilogram
Total Resource Amount 1,804.34

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Excavation for foundation
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

Cement concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 0.89 97.70 sq.m 86.66
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
Total Child Item Amount 785.46

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0026) 26.00

MORD - 2016-2017 - 01/05/2016 - 10 Page 60 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 326.97

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 29.43

Total OH Amount 382.40

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,972.20
Cost
Item Rate Per each 2,972.20

10984 10-2-A-(1)-(v) 600 mm x 450 mm rectangular 2,528.50 each


1
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.27 1,805.28 sq.m 487.43
2 PM0101 MS Flat / Structural Steel 20.00 41,781.46 M.T. 835.63
/kilogram
Total Resource Amount 1,425.23

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Excavation for foundation
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

Cement concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 0.89 97.70 sq.m 86.66
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
Total Child Item Amount 785.46

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0026) 14.62

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 278.16

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 25.03

MORD - 2016-2017 - 01/05/2016 - 10 Page 61 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total OH Amount 317.82

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,528.51
Cost
Item Rate Per each 2,528.51

10984 10-2-A-(1)-(vi) 600 mm x 600 mm square 2,718.70 each


2
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.36 1,805.28 sq.m 649.90
2 PM0101 MS Flat / Structural Steel 20.00 41,781.46 M.T. 835.63
/kilogram
Total Resource Amount 1,587.71

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Excavation for foundation
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

Cement concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 0.89 97.70 sq.m 86.66
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
Total Child Item Amount 785.46

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0026) 19.50

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 299.08

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 26.92

Total OH Amount 345.50

MORD - 2016-2017 - 01/05/2016 - 10 Page 62 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,718.66
Cost
Item Rate Per each 2,718.66

10984 10-2-A-(1)-(vii) 900 mm side octagon 3,365.00 each


3
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.67 1,805.28 sq.m 1,213.15
2 PM0101 MS Flat / Structural Steel 20.00 41,781.46 M.T. 835.63
/kilogram
Total Resource Amount 2,150.95

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Excavation for foundation
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

Cement concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 0.89 97.70 sq.m 86.66
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
Total Child Item Amount 785.46

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0101) 25.07

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 370.19

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 33.32

Total OH Amount 428.57

MORD - 2016-2017 - 01/05/2016 - 10 Page 63 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 3,364.99
Cost
Item Rate Per each 3,364.99

10-2-A-(2) Providing and fixing of retro-reflectorised cautionary, mandatory and informatory


sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 1.5 mm thick supported on GI pipe 50 mm
dia firmly fixed to the ground by means of properly designed foundation with M-15
grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below ground level
as per drawings and Technical Specification Clause 1701
10984 10-2-A-(2)-(i) 900 mm equilateral triangle 2,662.20 each
4
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.35 1,805.28 sq.m 631.85
2 PM0083 GI Pipe 50 mm dia 3.00 297.05 metre 891.14
Total Resource Amount 1,625.17

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

2 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Total Child Item Amount 698.80

Over Heads

13. Fitting and Wastage 3% on (PM0026) 18.96

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 292.87

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 26.36

Total OH Amount 338.18

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,662.15
Cost
Item Rate Per each 2,662.15

10984 10-2-A-(2)-(ii) 600 mm equilateral triangle 2,252.30 each


5
MORD - 2016-2017 - 01/05/2016 - 10 Page 64 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

5
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.16 1,805.28 sq.m 281.62
2 PM0083 GI Pipe 50 mm dia 3.00 297.05 metre 891.14
Total Resource Amount 1,274.94

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

2 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Total Child Item Amount 698.80

Over Heads

13. Fitting and Wastage 3% on (PM0026) 8.45

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 247.77

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 22.30

Total OH Amount 278.52

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,252.27
Cost
Item Rate Per each 2,252.27

10984 10-2-A-(2)-(iii) 600 mm circular 2,520.60 each


6
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.28 1,805.28 sq.m 510.90

MORD - 2016-2017 - 01/05/2016 - 10 Page 65 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

2 PM0083 GI Pipe 50 mm dia 3.00 297.05 metre 891.14


Total Resource Amount 1,504.21

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

2 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Total Child Item Amount 698.80

Over Heads

13. Fitting and Wastage 3% on (PM0026) 15.33

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 277.29

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 24.96

Total OH Amount 317.58

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,520.60
Cost
Item Rate Per each 2,520.60

10984 10-2-A-(2)-(iv) 800 mm x 600 mm rectangular 2,936.80 each


7
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.48 1,805.28 sq.m 866.54
2 PM0083 GI Pipe 50 mm dia 3.00 297.05 metre 891.14
Total Resource Amount 1,859.86

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

2 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Total Child Item Amount 698.80

Over Heads

13. Fitting and Wastage 3% on (PM0026) 26.00

MORD - 2016-2017 - 01/05/2016 - 10 Page 66 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 323.08

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 29.08

Total OH Amount 378.16

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,936.82
Cost
Item Rate Per each 2,936.82

10984 10-2-A-(2)-(v) 600 mm x 450 mm rectangular 2,493.10 each


8
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.27 1,805.28 sq.m 487.43
2 PM0083 GI Pipe 50 mm dia 3.00 297.05 metre 891.14
Total Resource Amount 1,480.75

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

2 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Total Child Item Amount 698.80

Over Heads

13. Fitting and Wastage 3% on (PM0026) 14.62

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 274.27

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 24.68

Total OH Amount 313.58

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,493.13
Cost
Item Rate Per each 2,493.13

10984 10-2-A-(2)-(vi) 600 mm x 600 mm square 2,683.30 each


9

MORD - 2016-2017 - 01/05/2016 - 10 Page 67 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

S.No Resource Code Resource Quantity Rate Unit Amount


.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.36 1,805.28 sq.m 649.90
2 PM0083 GI Pipe 50 mm dia 3.00 297.05 metre 891.14
Total Resource Amount 1,643.22

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

2 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Total Child Item Amount 698.80

Over Heads

13. Fitting and Wastage 3% on (PM0026) 19.50

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 295.19

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 26.57

Total OH Amount 341.25

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,683.28
Cost
Item Rate Per each 2,683.28

10985 10-2-A-(2)-(vii) 900 mm sides octagon 3,342.50 each


0
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.67 1,805.28 sq.m 1,213.15
2 PM0083 GI Pipe 50 mm dia 3.00 297.05 metre 891.14

MORD - 2016-2017 - 01/05/2016 - 10 Page 68 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Resource Amount 2,206.47

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 5,289.77 cu.m 666.51

2 11-1-1-1 Excavation in foundation for retaining 0.13 256.30 cu.m 32.29


& brest walls
Total Child Item Amount 698.80

Over Heads

13. Fitting and Wastage 3% on (PM0026) 36.39

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 367.71

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 33.09

Total OH Amount 437.20

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 3,342.47
Cost
Item Rate Per each 3,342.47

10-2-A-(3) Providing and fixing of retro-reflectorised cautionary, mandatory and informatory


sign as per IRC:67 made of encapsulated lens type reflective sheeting vide Clause
1701.2.3, fixed over aluminium sheeting, 1.5 mm thick supported on RCC Post 100
mm x 100 mm firmly fixed to the ground by means of properly designed foundation
with M15 grade cement concrete 450 mm x 450 mm x 600 mm, 600 mm below
ground level as per approved drawing Clause 1701
10985 10-2-A-(3)-(i) 900 mm equilateral triangle 2,389.30 each
1
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.35 1,805.28 sq.m 631.85
Total Resource Amount 734.02

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade

MORD - 2016-2017 - 01/05/2016 - 10 Page 69 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

2 12-5-1-1 Nominal mix (1:2.5:5) 0.03 6,684.60 cu.m 190.51

3 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
4 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
5 10-7 Painting on Concrete/Steel Surfaces 0.90 111.50 sq.m 100.35
with Epoxy
Total Child Item Amount 1,555.31

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 91.75

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 8.26

Total OH Amount 100.01

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,389.34
Cost
Item Rate Per each 2,389.34

10985 10-2-A-(3)-(ii) 600 mm equilateral triangle 1,991.40 each


2
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.16 1,805.28 sq.m 281.62
Total Resource Amount 383.80

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 0.90 111.50 sq.m 100.35
with Epoxy

MORD - 2016-2017 - 01/05/2016 - 10 Page 70 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

4 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69


& brest walls
Excavation for foundation
5 12-5-1-1 Nominal mix (1:2.5:5) 0.03 6,684.60 cu.m 190.51

Total Child Item Amount 1,555.31

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 47.97

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 4.32

Total OH Amount 52.29

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 1,991.40
Cost
Item Rate Per each 1,991.40

10985 10-2-A-(3)-(iii) 600 mm circular 2,251.90 each


3
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.28 1,805.28 sq.m 510.90
Total Resource Amount 613.07

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 0.90 111.50 sq.m 100.35
with Epoxy
4 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
5 12-5-1-1 Nominal mix (1:2.5:5) 0.03 6,684.60 cu.m 190.51

MORD - 2016-2017 - 01/05/2016 - 10 Page 71 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Child Item Amount 1,555.31

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 76.63

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 6.90

Total OH Amount 83.53

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,251.91
Cost
Item Rate Per each 2,251.91

10985 10-2-A-(3)-(iv) 800 mm x 600 mm rectangular 2,656.00 each


4
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.48 1,805.28 sq.m 866.54
Total Resource Amount 968.71

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


2 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
3 10-7 Painting on Concrete/Steel Surfaces 0.90 111.50 sq.m 100.35
with Epoxy
4 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
5 12-5-1-1 Nominal mix (1:2.5:5) 0.03 6,684.60 cu.m 190.51

Total Child Item Amount 1,555.31

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 121.09

MORD - 2016-2017 - 01/05/2016 - 10 Page 72 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 10.90

Total OH Amount 131.99

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,656.01
Cost
Item Rate Per each 2,656.01

10985 10-2-A-(3)-(v) 600 mm x 450 mm rectangular 2,400.90 each


5
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.27 1,805.28 sq.m 487.43
Total Resource Amount 744.16

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69


& brest walls
Excavation for foundation
2 12-5-1-1 Nominal mix (1:2.5:5) 0.03 6,684.60 cu.m 190.51

3 10-7 Painting on Concrete/Steel Surfaces 0.90 111.50 sq.m 100.35


with Epoxy
4 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
5 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


Total Child Item Amount 1,555.31

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 93.02

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 8.37

Total OH Amount 101.39

MORD - 2016-2017 - 01/05/2016 - 10 Page 73 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,400.86
Cost
Item Rate Per each 2,400.86

10985 10-2-A-(3)-(vi) 600 mm x 600 mm square 2,585.50 each


6
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.36 1,805.28 sq.m 649.90
Total Resource Amount 906.64

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


2 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
3 10-7 Painting on Concrete/Steel Surfaces 0.90 111.50 sq.m 100.35
with Epoxy
4 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
5 12-5-1-1 Nominal mix (1:2.5:5) 0.03 6,684.60 cu.m 190.51

Total Child Item Amount 1,555.31

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 113.33

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 10.20

Total OH Amount 123.53

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,585.47
Cost
Item Rate Per each 2,585.47

MORD - 2016-2017 - 01/05/2016 - 10 Page 74 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

10985 10-2-A-(3)-(vii) 900 mm sides octagon 3,225.50 each


7
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.67 1,805.28 sq.m 1,213.15
Total Resource Amount 1,469.89

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 0.90 111.50 sq.m 100.35
with Epoxy
4 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
5 12-5-1-1 Nominal mix (1:2.5:5) 0.03 6,684.60 cu.m 190.51

Total Child Item Amount 1,555.31

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 183.74

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 16.54

Total OH Amount 200.27

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 3,225.47
Cost
Item Rate Per each 3,225.47

Notes: 1 Any one area of aluminium sheeting given at (i) to (vii) may be adopted as per site requirement and in accordance with IRC:67.
2 The rate for excavation, cement concrete M-15, RCC M-15 in Sub-structure, steel re-inforcement and painting may be taken from
respective Chapters.
3 The depth of foundation and quantity of cement concrete in the foundation are indicative. These may be increased for areas having
higher wind velocities like in coastal areas. This is applicable to all road signs and directions boards.

MORD - 2016-2017 - 01/05/2016 - 10 Page 75 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

10-2-B Semi Reflective Traffic Signs

Providing and fixing of semi reflective cautionary, mandatory and informatory sign
board as per IRC:67 made of 1.5 mm thick MS Sheet duly stove white colour in
front and gray colour on back with red reflective border of 65 mm width and
required letters and figures with reflective tape engineering grade as per Clause
1701.3.9 of MORD for Rural Roads of required shade and colour supported and
welded on 47mm x 47 mm x 12 SWG sheet tube firmly fixed to the ground by mean
of properly designed foundations with M-15 grade cement concrete 450x450x600
mm, 600 mm below ground level as per approved drawing Clause 1701.2.2
10985 10-2-B-(i) 900 mm equilateral & triangle 2,391.00 each
8
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0101 MS Flat / Structural Steel 1.06 41,781.46 M.T. 44.29
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 12.40 61.38 kilogram 761.13
Sheet)
3 PM0103 MS Sheet 1.5 mm thick 0.35 686.17 sq.m 240.16
Total Resource Amount 1,302.31

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


2 10-7 Painting on Concrete/Steel Surfaces 0.46 111.50 sq.m 51.29
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
3 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
Total Child Item Amount 875.59

Over Heads

MORD - 2016-2017 - 01/05/2016 - 10 Page 76 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 31.37

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 166.71

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 15.00

Total OH Amount 213.08

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,390.99
Cost
Item Rate Per each 2,390.99

10985 10-2-B-(ii) 600 mm equilateral & triangle 2,238.40 each


9
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0101 MS Flat / Structural Steel 1.06 41,781.46 M.T. 44.29
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 12.40 61.38 kilogram 761.13
Sheet)
3 PM0103 MS Sheet 1.5 mm thick 0.16 686.17 sq.m 109.79
Total Resource Amount 1,171.94

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


2 10-7 Painting on Concrete/Steel Surfaces 0.46 111.50 sq.m 51.29
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
3 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
Total Child Item Amount 875.59

Over Heads

MORD - 2016-2017 - 01/05/2016 - 10 Page 77 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 27.46

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 149.92

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 13.49

Total OH Amount 190.87

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,238.41
Cost
Item Rate Per each 2,238.41

10986 10-2-B-(iii) 600 mm circular 2,337.20 each


0
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0101 MS Flat / Structural Steel 1.06 41,781.46 M.T. 44.29
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 12.40 61.38 kilogram 761.13
Sheet)
3 PM0103 MS Sheet 1.5 mm thick 0.28 686.17 sq.m 194.19
Total Resource Amount 1,256.34

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69


& brest walls
Excavation for foundation
2 10-7 Painting on Concrete/Steel Surfaces 0.46 111.50 sq.m 51.29
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
3 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


Total Child Item Amount 875.59

Over Heads

MORD - 2016-2017 - 01/05/2016 - 10 Page 78 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 29.99

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 160.79

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 14.47

Total OH Amount 205.25

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,337.18
Cost
Item Rate Per each 2,337.18

10986 10-2-B-(iv) 800 mm x 600 mm rectangular 2,495.40 each


1
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0101 MS Flat / Structural Steel 1.06 41,781.46 M.T. 44.29
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 12.40 61.38 kilogram 761.13
Sheet)
3 PM0103 MS Sheet 1.5 mm thick 0.48 686.17 sq.m 329.36
Total Resource Amount 1,391.51

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


2 10-7 Painting on Concrete/Steel Surfaces 0.46 111.50 sq.m 51.29
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
3 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
Total Child Item Amount 875.59

Over Heads

MORD - 2016-2017 - 01/05/2016 - 10 Page 79 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 34.04

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 178.19

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 16.04

Total OH Amount 228.28

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,495.38
Cost
Item Rate Per each 2,495.38

10986 10-2-B-(v) 600 mm x 450 mm rectangular 2,326.70 each


2
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0101 MS Flat / Structural Steel 1.06 41,781.46 M.T. 44.29
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 12.40 61.38 kilogram 761.13
Sheet)
3 PM0103 MS Sheet 1.5 mm thick 0.27 686.17 sq.m 185.27
Total Resource Amount 1,247.42

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


2 10-7 Painting on Concrete/Steel Surfaces 0.46 111.50 sq.m 51.29
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
3 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
Total Child Item Amount 875.59

Over Heads

MORD - 2016-2017 - 01/05/2016 - 10 Page 80 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 29.72

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 159.64

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 14.37

Total OH Amount 203.73

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,326.74
Cost
Item Rate Per each 2,326.74

10986 10-2-B-(vi) 600 mm x 600 mm 2,399.00 each


3
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0101 MS Flat / Structural Steel 1.06 41,781.46 M.T. 44.29
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 12.40 61.38 kilogram 761.13
Sheet)
3 PM0103 MS Sheet 1.5 mm thick 0.36 686.17 sq.m 247.02
Total Resource Amount 1,309.17

S.No. Item Code Item Description Quantity Rate Unit Amount

1 10-7 Painting on Concrete/Steel Surfaces 0.46 111.50 sq.m 51.29


with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
2 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
3 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


Total Child Item Amount 875.59

Over Heads

MORD - 2016-2017 - 01/05/2016 - 10 Page 81 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 31.57

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 167.59

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 15.08

Total OH Amount 214.25

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,399.02
Cost
Item Rate Per each 2,399.02

10986 10-2-B-(vii) 900 mm side octagon 2,648.00 each


4
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0101 MS Flat / Structural Steel 1.06 41,781.46 M.T. 44.29
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 12.40 61.38 kilogram 761.13
Sheet)
3 PM0103 MS Sheet 1.5 mm thick 0.67 686.17 sq.m 459.73
Total Resource Amount 1,521.89

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


2 10-7 Painting on Concrete/Steel Surfaces 0.46 111.50 sq.m 51.29
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
3 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
Total Child Item Amount 875.59

Over Heads

MORD - 2016-2017 - 01/05/2016 - 10 Page 82 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 37.95

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 194.98

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 17.55

Total OH Amount 250.48

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,647.96
Cost
Item Rate Per each 2,647.96

Notes: 1 Any one area of M.S. Sheet given at (i) to (viii) may be adopted as per site requirement and in accordance with IRC-67.
2 The rate for excavation, cement concrete M-15, and painting may be taken from respective Chapters.
3 The depth of foundation and quantity of cement in the foundation are indicative. These may be increased for areas having higher wind
velocities like in coastal area. This is applicable to all road signs and direction boards.

10-3 Direction and Place Identification signs upto 0.9 sqm size board
10-3-A Retro-reflectorised Traffic Signs
10986 10-3-A-(i) Providing and erecting direction and place identification retro-reflectorised sign as 4,549.30 sq.m
5 per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the
ground by means of properly designed foundation with M-15 grade cement concrete
450 x 450 x 600 mm, 600 mm below ground level as per approved drawing and
Technical Specification Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.90 1,805.28 sq.m 1,624.76
2 PM0101 MS Flat / Structural Steel 20.00 41,781.46 M.T. 835.63
/kilogram
Total Resource Amount 2,717.12

S.No. Item Code Item Description Quantity Rate Unit Amount

1 10-7 Painting on Concrete/Steel Surfaces 0.89 111.50 sq.m 98.90


with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications

MORD - 2016-2017 - 01/05/2016 - 10 Page 83 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

2 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69


& brest walls
Excavation for foundation
3 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


Total Child Item Amount 923.21

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 73.81

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 348.87

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 31.40

Total OH Amount 454.08

Total Cost for 0.90 sq.m = Sub Items Cost + Resource Cost + Overhead 4,094.40
Cost
Item Rate Per sq.m 4,549.33

10986 10-3-A-(ii) Providing and erecting direction and place identification retro-reflectorised sign as 4,255.00 sq.m
6 per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on 2 inch dia GI Pipe firmly fixed to the ground by means of properly
designed foundation with M-15 grade cement concrete 450 x 450 x 600 mm, 600
mm below ground level as per approved drawing and Tehnical Specification Clause
1701.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.90 1,805.28 sq.m 1,624.76
2 PM0083 GI Pipe 50 mm dia 3.00 297.05 metre 891.14
Total Resource Amount 2,618.07

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


2
11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
MORD - 2016-2017 - 01/05/2016 - 10 Page 84 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit
2 11-1-1-1 0.13 291.20 cu.m 36.69

Excavation for foundation


Total Child Item Amount 824.30

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0083) 26.73

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 330.60

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 29.75

Total OH Amount 387.09

Total Cost for 0.90 sq.m = Sub Items Cost + Resource Cost + Overhead 3,829.47
Cost
Item Rate Per sq.m 4,254.97

10986 10-3-A-(iii) Providing and erecting direction and place identification retro-reflectorised sign as 3,967.30 sq.m
7 per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on RCC Post 100 mm x 100 mm firmly fixed to the ground by means of
properly designed foundation with M-15 grade cement concrete 450 x 450 x 600
mm, 600 mm below ground level as per approved drawing and Technical
Specification Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.90 1,805.28 sq.m 1,624.76
Total Resource Amount 1,726.93

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


2 10-7 Painting on Concrete/Steel Surfaces 0.90 111.50 sq.m 100.35
with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
3 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
MORD - 2016-2017 - 01/05/2016 - 10 Page 85 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit
3 11-1-1-1 0.13 291.20 cu.m 36.69

Excavation for foundation


4 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
5 12-5-1-1 Nominal mix (1:2.5:5) 0.03 6,684.60 cu.m 190.51

RCC M-15 Grade in Sub-structure


Total Child Item Amount 1,555.31

Over Heads

26. Fixing and Installation 3% on (All Item) 46.66

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 221.70

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 19.95

Total OH Amount 288.31

Total Cost for 0.90 sq.m = Sub Items Cost + Resource Cost + Overhead 3,570.55
Cost
Item Rate Per sq.m 3,967.28

Notes: (1)Lettering and arrow markings on sign board to be provided separately as per actual requirement. Rates for these items have been
analysed separately.
(2)The rate for excavation, cement concret M15, RCC M15 in Sub-structure, steel re-inforcement and painting may be taken from respective
Chapters.
(3)The depth of foundation and quantity of cement concrete in the foundation are indicative. These may be increased for areas having higher
wind velocities like in coastal areas. This is applicable to all road signs and directions boards.

10986 10-3-B Semi-Reflective Traffic signs 3,179.00 metre


8 Direction and place indentification signs up to 0.9 sqm size board
Providing and erecting direction and place identifications of semi reflective sign
boards as per IRC:67 made of 2 mm thick M.S. Sheet duly stove enameled paint in
white colour in front and grey colour on back with red reflective border of 70 mm
width and required message, letters, figures with reflective engineering grade tape as
per MORD specifications of required shade and colour. Supported and welded on
47 mm x 47mm of 12 SWG Square tube of 3050 mm height duly strengthened by
25 mm x 5 mm M/s flat iron on edges on back firmly fixed to the ground by means
of properly designed foundations with M-15 grade cement concrete 450 mm x 450
mm x 600 mm, 600 mm below ground level as per approved drawing and Technical
Specification Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08

MORD - 2016-2017 - 01/05/2016 - 10 Page 86 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Material Group
1 PM0101 MS Flat / Structural Steel 1.06 41,781.46 M.T. 44.29
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 12.40 61.38 kilogram 761.13
Sheet)
3 PM0104 MS Sheet 2 mm thick 0.90 866.17 sq.m 779.55
Total Resource Amount 1,687.14

S.No. Item Code Item Description Quantity Rate Unit Amount

1 10-7 Painting on Concrete/Steel Surfaces 0.59 111.50 sq.m 65.79


with Epoxy

Painting Angle Iron Post with Primer


and two coats of Epoxy Paint as per
specifications
2 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
3 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61

Cement concrete M15 grade


Total Child Item Amount 890.09

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 47.55

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 216.84

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 19.52

Total OH Amount 283.90

Total Cost for 0.90 metre = Sub Items Cost + Resource Cost + Overhead 2,861.13
Cost
Item Rate Per metre 3,179.04

Notes: Rate for excavation, cement concrete M15 and painting may be taken from respective Chapters.

10-4 Direction and Place Identification signs with size more than 0.9 sqm size board

10-4-A Retro-reflectorised Traffic Signs


10986 10-4-A-1 Providing and erecting direction and place identification retro-reflectorised sign as 4,732.60 sq.m
9 per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported
on a mild steel single angle iron post 75 x 75 x 6 mm, 2 No.s firmly fixed to the
ground by means of properly designed foundation with M-15 grade cement concrete
450 x 450 x 600 mm, 600 mm below ground level as per approved drawing and
Technical
- 10 Specification Clause 1701Page 87 of 106
MORD - 2016-2017 - 01/05/2016 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Technical Specification Clause 1701


S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.02 337.56 day 6.75
2 PL15 Beldar/mazdoor (unskilled) 0.50 306.88 day 153.44
Machine Group
1 PMC031 Tractor with trolley. 0.12 276.00 hours 33.12
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 1.50 1,805.28 sq.m 2,707.93
2 PM0101 MS Flat / Structural Steel 40.00 41,781.46 M.T. 1,671.26
/kilogram
Total Resource Amount 4,572.49

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.25 291.20 cu.m 73.38


& brest walls
Excavation for foundation
2 11-4-2-1 Nominal mix (1:2.5:5) 0.25 6,250.90 cu.m 1,575.23

Cement concrete M-15 grade


3 10-7 Painting on Concrete/Steel Surfaces 1.77 111.50 sq.m 197.80
with Epoxy
Total Child Item Amount 1,846.41

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0101) 50.14

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 577.83

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 52.00

Total OH Amount 679.97

Total Cost for 1.50 sq.m = Sub Items Cost + Resource Cost + Overhead 7,098.87
Cost
Item Rate Per sq.m 4,732.58

10987 10-4-A-2 Providing and erecting direction and place identification retro-reflectorised sign as 4,687.30 sq.m
0 per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported
on 2 inch dia GI Pipe firmly fixed to the ground by means of properly designed
foundation with M-15 grade cement concrete 450 x 450 x 600 mm, 600 mm below
ground level as per approved drawing and Tehnical Specification Clause 1701.
S.No Resource Code Resource Quantity Rate Unit Amount
.
MORD - 2016-2017 - 01/05/2016 - 10 Page 88 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Labour Group
1 PL14 Mate 0.02 337.56 day 6.75
2 PL15 Beldar/mazdoor (unskilled) 0.50 306.88 day 153.44
Machine Group
1 PMC031 Tractor with trolley. 0.12 276.00 hours 33.12
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 1.50 1,805.28 sq.m 2,707.93
2 PM0083 GI Pipe 50 mm dia 6.00 297.05 metre 1,782.29
Total Resource Amount 4,683.52

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.25 291.20 cu.m 73.38


& brest walls
Excavation for foundation
2 11-4-2-1 Nominal mix (1:2.5:5) 0.25 6,250.90 cu.m 1,575.23

Cement concrete M15 grade


Total Child Item Amount 1,648.61

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0083) 53.47

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 592.12

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 53.29

Total OH Amount 698.88

Total Cost for 1.50 sq.m = Sub Items Cost + Resource Cost + Overhead 7,031.02
Cost
Item Rate Per sq.m 4,687.35

10987 10-4-A-3 Providing and erecting direction and place identification retro-reflectorised sign as 4,345.20 sq.m
1 per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported
on RCC Post 100 mm x 100 mm firmly fixed to the ground by means of properly
designed foundation with M-15 grade cement concrete 450 x 450 x 600 mm, 600
mm below ground level as per approved drawing and Technical Specification
Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.02 337.56 day 6.75
2 PL15 Beldar/mazdoor (unskilled) 0.50 306.88 day 153.44
Machine Group

MORD - 2016-2017 - 01/05/2016 - 10 Page 89 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

1 PMC031 Tractor with trolley. 0.12 276.00 hours 33.12


Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 1.50 1,805.28 sq.m 2,707.93
Total Resource Amount 2,901.23

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.25 291.20 cu.m 73.38


& brest walls
Excavation for foundation
2 11-4-2-1 Nominal mix (1:2.5:5) 0.25 6,250.90 cu.m 1,575.23

Cement concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 1.84 111.50 sq.m 205.16
with Epoxy

two coats including prime coat as per


specifications
4 12-6 Supplying, fitting and placing HYSD 0.02 57,161.40 tons 880.29
bar reinforcement (Fe 415) in
substructrue
5 12-5-1-1 Nominal mix (1:2.5:5) 0.06 6,684.60 cu.m 381.02

RCC M-15 Grade in Sub-structure


Total Child Item Amount 3,115.08

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (All Item) 93.45

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 374.34

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 33.69

Total OH Amount 501.48

Total Cost for 1.50 sq.m = Sub Items Cost + Resource Cost + Overhead 6,517.79
Cost
Item Rate Per sq.m 4,345.19

Notes: (1)Lettering and arrow markings on sign boards to be provided separately as per actual requirement. Rates for these items have been
analysed separately.
(2)The rate for excavation, cement concrete M15, RCC M15 in Sub-structure, steel re-inforcement and painting may be taken from respective
Chapters.
(3)The depth of foundation and quantity of cement concrete in the foundation are indicative. These may be increased for areas having higher
wind velocities like in coastal areas. This is applicable to all road signs and directions boards.

10987 10-4-B Semi-Reflective Traffic signs 3,592.80 each


2
Direction and place identification signs more than 0.90 sqm sign board
MORD - 2016-2017 - 01/05/2016 - 10 Page 90 of 106 14/05/16 8:14
Providing and erecting direction and place identification of semi reflective sign
boards as per IRC-67 made of 2 mm thick M.S. Sheet duly stove enameled paint
white colour in front and grey colour on back with reflective border of 70 mm width
and required message, letters, figures with reflective tape of engineering grade as per
MORD specifications of required shade and colour. Supported and welded on two
nos. 47 mm x 47 mm of 12 SWG square tube of 3050 mm height duly strengthened
by 25 mm x 5 mm MS flat iron on edges on back firmly fixed to the ground by
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Providing and erecting direction and place identification of semi reflective sign
boards as per IRC-67 made of 2 mm thick M.S. Sheet duly stove enameled paint
white colour in front and grey colour on back with reflective border of 70 mm width
and required message, letters, figures with reflective tape of engineering grade as per
MORD specifications of required shade and colour. Supported and welded on two
nos. 47 mm x 47 mm of 12 SWG square tube of 3050 mm height duly strengthened
by 25 mm x 5 mm MS flat iron on edges on back firmly fixed to the ground by
means of properly designed foundations with M-15 grade cement concrete 450 mm
x 450 mm x 600 mm, 600 mm below ground level as per approved drawing and
Technical Specification Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.02 337.56 day 6.75
2 PL15 Beldar/mazdoor (unskilled) 0.50 306.88 day 153.44
Machine Group
1 PMC031 Tractor with trolley. 0.16 276.00 hours 44.16
Material Group
1 PM0101 MS Flat / Structural Steel 2.12 41,781.46 M.T. 88.58
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 24.80 61.38 kilogram 1,522.26
Sheet)
3 PM0104 MS Sheet 2 mm thick 1.50 866.17 sq.m 1,299.25
Total Resource Amount 3,114.44

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.25 291.20 cu.m 73.38


& brest walls
Excavation for foundations
2 11-4-2-1 Nominal mix (1:2.5:5) 0.25 6,250.90 cu.m 1,575.23

Cement Concrete M15 grade


3 10-7 Painting on Concrete/Steel Surfaces 0.92 111.50 sq.m 102.58
with Epoxy

on M.S. tube posts with primer and two


coats as per specification
Total Child Item Amount 1,751.19

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 87.30

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 400.22

Page 91 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 36.02

Total OH Amount 523.54

Total Cost for 1.50 each = Sub Items Cost + Resource Cost + Overhead 5,389.17
Cost
Item Rate Per each 3,592.78

Notes: Rate for excavation cement concrete M15 and painting may be taken from respective chapter

10987 10-5 Painting Two Coats on New Concrete Surfaces 121.50 sq.m
3
Painting two coats including primer coat after filling the surface with synthetic
enamel paint in all shades on new, plastered / concrete surfaces as per drawing and
Technical Specification Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.20 337.56 day 67.51
2 PL15 Beldar/mazdoor (unskilled) 2.00 306.88 day 613.75
3 PL18 Painter (Ist class) 3.00 540.10 day 1,620.30
Material Group
1 PM0050 Cement Primer 3.00 95.00 litre 285.00
2 PM0106 Paint (Synthetic Enamel) 6.00 278.00 litre 1,668.00
Total Resource Amount 4,254.56

Over Heads

18. Scaffolding 1% on (Labour Group) 23.02

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 534.70

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 48.12

Total OH Amount 605.84

Total Cost for 40.00 sq.m = Resource Cost + Overhead Cost 4,860.40

Item Rate Per sq.m 121.51

10987 10-6 Painting on Steel Surfaces 111.90 sq.m


4
Providing and applying two coats of ready mix paint including primer coat of
approved brand on steel surface after through cleaning of surface to give an even
shade as per drawing and Technical Specification Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group

MORD - 2016-2017 - 01/05/2016 - 10 Page 92 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

1 PL14 Mate 0.25 337.56 day 84.39


2 PL15 Beldar/mazdoor (unskilled) 0.40 306.88 day 122.75
3 PL18 Painter (Ist class) 0.60 540.10 day 324.06
Material Group
1 PM0106 Paint (Synthetic Enamel) 1.25 278.00 litre 347.50
2 PM0121 Red-oxide Primer 0.60 170.00 litre 102.00
Total Resource Amount 980.70

Over Heads

18. Scaffolding 1% on (Material Group) 4.50

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 123.15

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 11.08

Total OH Amount 138.73

Total Cost for 10.00 sq.m = Resource Cost + Overhead Cost 1,119.43

Item Rate Per sq.m 111.94

10987 10-7 Painting on Concrete/Steel Surfaces with Epoxy 111.50 sq.m


5
Painting two coats including prime coat with epoxy paint of approved brand on
concrete/steel surfaces after through cleaning of surface to give an even shade as per
drawing and Technical Specification Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.25 337.56 day 84.39
2 PL15 Beldar/mazdoor (unskilled) 0.40 306.88 day 122.75
3 PL18 Painter (Ist class) 0.60 540.10 day 324.06
Material Group
1 PM0073 Epoxy Paint 1.25 275.00 litre 343.75
2 PM0121 Red-oxide Primer 0.60 170.00 litre 102.00
Total Resource Amount 976.95

Over Heads

18. Scaffolding 1% on (Material Group) 4.46

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 122.68

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 11.04

Total OH Amount 138.17

MORD - 2016-2017 - 01/05/2016 - 10 Page 93 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Total Cost for 10.00 sq.m = Resource Cost + Overhead Cost 1,115.12

Item Rate Per sq.m 111.51

10987 10-8 Painting lines, Dashes, Arrows, etc. on Road in Two Coats on New Work 114.00 sq.m
6
Painting lines, dashes, arrows, etc. on roads in two coats on new work with ready
mixed road marking paint conforming to IS:164 on bituminous/concrete surface,
including cleaning the surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control as per drawing and Technical Specification Clause 1702

Assuming 100 mm width


S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.09 337.56 day 30.38
2 PL15 Beldar/mazdoor (unskilled) 1.55 306.88 day 475.66
3 PL18 Painter (Ist class) 0.55 540.10 day 297.06
Material Group
1 PM0122 Road marking paint 1.48 135.00 litre 199.80
Total Resource Amount 1,002.89

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 125.36

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 11.28

Total OH Amount 136.64

Total Cost for 10.00 sq.m = Resource Cost + Overhead Cost 1,139.54

Item Rate Per sq.m 113.95

10-10 Kilometre Stone

Reinforced cement concrete M15 grade kilometre stone/local stone of standard


design as per IRC:8 fixing in position including painting and printing, etc as per
drawing and Technical Specification Clause 1703
10987 10-10-(i) 5th Kilometre Stone (precast) 4,211.90 each
7
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.60 558.51 day 335.11

MORD - 2016-2017 - 01/05/2016 - 10 Page 94 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

2 PL14 Mate 0.26 337.56 day 87.77


3 PL15 Beldar/mazdoor (unskilled) 6.00 306.88 day 1,841.25
Machine Group
1 PMC031 Tractor with trolley. 6.00 276.00 hours 1,656.00
Total Resource Amount 3,920.12

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-5-1-1 Nominal mix (1:2.5:5) 2.35 6,684.60 cu.m 15,708.81

M-15 grade of concrete


2 12-6 Supplying, fitting and placing HYSD 0.02 57,161.40 tons 1,262.12
bar reinforcement (Fe 415) in
substructrue
3 11-1-1-1 Excavation in foundation for retaining 1.68 291.20 cu.m 489.22
& brest walls
Excavation in soil for foundation
4 10-5 Painting Two Coats on New Concrete 9.85 121.50 sq.m 1,196.78
Surfaces
5 10-1-1 Hindi (Matras commas and the like not 1,800.00 1.20 cm 2,160.00
to be measured and paid for.
lettering on km post (average 30 letters
of 10 cm height each)
Total Child Item Amount 20,816.92

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 490.02

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 44.10

Total OH Amount 534.12

Total Cost for 6.00 each = Sub Items Cost + Resource Cost + Overhead 25,271.17
Cost
Item Rate Per each 4,211.86

10987 10-10-(ii) Ordinary Kilometer Stone (Precast) 3,565.90 each


8
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 1.00 558.51 day 558.51
2 PL14 Mate 0.32 337.56 day 108.02
3 PL15 Beldar/mazdoor (unskilled) 7.00 306.88 day 2,148.13
Machine Group

MORD - 2016-2017 - 01/05/2016 - 10 Page 95 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

1 PMC031 Tractor with trolley. 6.00 276.00 hours 1,656.00


Total Resource Amount 4,470.66

S.No. Item Code Item Description Quantity Rate Unit Amount

1 10-5 Painting Two Coats on New Concrete 11.41 121.50 sq.m 1,386.32
Surfaces
2 12-6 Supplying, fitting and placing HYSD 0.27 57,161.40 tons 15,433.58
bar reinforcement (Fe 415) in
substructrue
@ 5 kg per sqm
3 11-1-1-1 Excavation in foundation for retaining 2.77 291.20 cu.m 806.62
& brest walls
Excavation in soil for foundation
4 10-1-1 Hindi (Matras commas and the like not 1,680.00 1.20 cm 2,016.00
to be measured and paid for.
lettering on km post (average 12 letters
of 10 cm height each)
5 12-5-1-1 Nominal mix (1:2.5:5) 3.77 6,684.60 cu.m 25,200.94

M15 grade of concrete


Total Child Item Amount 44,843.46

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 558.83

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 50.29

Total OH Amount 609.13

Total Cost for 14.00 each = Sub Items Cost + Resource Cost + Overhead 49,923.24
Cost
Item Rate Per each 3,565.95

10987 10-10-(iii) 200 m stone (precast) 645.50 each


9
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 1.50 558.51 day 837.77
2 PL14 Mate 0.34 337.56 day 114.77
3 PL15 Beldar/mazdoor (unskilled) 7.00 306.88 day 2,148.13
Machine Group
1 PMC031 Tractor with trolley. 6.00 276.00 hours 1,656.00
Total Resource Amount 4,756.67

MORD - 2016-2017 - 01/05/2016 - 10 Page 96 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

S.No. Item Code Item Description Quantity Rate Unit Amount

1 10-5 Painting Two Coats on New Concrete 6.27 121.50 sq.m 761.81
Surfaces
2 12-6 Supplying, fitting and placing HYSD 0.07 57,161.40 tons 3,772.65
bar reinforcement (Fe 415) in
substructrue
@ 5 kg per sqm
3 11-1-1-1 Excavation in foundation for retaining 1.39 291.20 cu.m 404.77
& brest walls
Excavation in soil for foundation
4 10-1-1 Hindi (Matras commas and the like not 330.00 1.20 cm 396.00
to be measured and paid for.
lettering on km post (average 1 letter of
10 cm height each)
5 12-5-1-1 Nominal mix (1:2.5:5) 1.58 6,684.60 cu.m 10,561.67

M15 grade of concrete


Total Child Item Amount 15,896.89

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 594.58

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 53.51

Total OH Amount 648.10

Total Cost for 33.00 each = Sub Items Cost + Resource Cost + Overhead 21,301.65
Cost
Item Rate Per each 645.50

Notes: (1)The rate for excavation, cement concrete, steel reinforcement, painting and lettering may be taken from respective Chapters.
(2)In case local stone is to be used in place of precast RCC stones, then rate of cement concrete and steel reinforcement may be deleted.

10988 10-9 Painting lines, Dashes, Arrows, etc. on Roads in Two Coats on Old Work 78.10 sq.m
0
Painting lines, dashes, arrows, etc. on roads in two coats on old work with ready
mixed road marking paint conforming to IS:164 on bituminous/concrete surface,
including cleaning the surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control as per drawing and technical specification Clause 1702

Assuming 100 cm width


S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.06 337.56 day 20.25

MORD - 2016-2017 - 01/05/2016 - 10 Page 97 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

2 PL15 Beldar/mazdoor (unskilled) 1.25 306.88 day 383.59


3 PL18 Painter (Ist class) 0.30 540.10 day 162.03
Material Group
1 PM0122 Road marking paint 0.90 135.00 litre 121.50
Total Resource Amount 687.38

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 85.92

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 7.73

Total OH Amount 93.66

Total Cost for 10.00 sq.m = Resource Cost + Overhead Cost 781.03

Item Rate Per sq.m 78.10

10988 10-11 Boundary Pillar 477.30 each


1
Reinforced cement concrete M15 grade boundary pillars/local stone of standard
design as per IRC:25, fixed in position including finishing and lettering but
excluding painting as per drawing and Technical Specification Clause 1704

S.No Resource Code Resource Quantity Rate Unit Amount


.
Labour Group
1 PL14 Mate 0.57 337.56 day 192.41
2 PL15 Beldar/mazdoor (unskilled) 14.25 306.88 day 4,372.97
Machine Group
1 PMC031 Tractor with trolley. 6.00 276.00 hours 1,656.00
Material Group
1 PM0142 Stone spall 11.97 100.00 cu.m 1,197.00
Total Resource Amount 7,418.38

S.No. Item Code Item Description Quantity Rate Unit Amount

1 10-1-1 Hindi (Matras commas and the like not 2,280.00 1.20 cm 2,736.00
to be measured and paid for.
lettering, each 10 cm high
2 11-1-1-1 Excavation in foundation for retaining 10.72 291.20 cu.m 3,121.66
& brest walls
Excavation in soil
3 12-5-1-1 Nominal mix (1:2.5:5) 1.25 6,684.60 cu.m 8,355.75

M-15 grade of Concrete

MORD - 2016-2017 - 01/05/2016 - 10 Page 98 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

4 12-6 Supplying, fitting and placing HYSD 0.08 57,161.40 tons 4,561.48
bar reinforcement (Fe 415) in
substructrue
Total Child Item Amount 18,774.89

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 927.30

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 83.46

Total OH Amount 1,010.75

Total Cost for 57.00 each = Sub Items Cost + Resource Cost + Overhead 27,204.03
Cost
Item Rate Per each 477.26

Notes: (1)In case of soft ground, a proper foundation may be provided as per approved design. In case foundation is required to be provided, the
items of excavation and foundation concrete are required to be measured and paid separately.

(2)In case local stone is to be used in place of precast RCC stones, then rate of cement concrete and steel reinforcement may be deleted.

10988 10-12 G.I Barbed Wire Fencing 1.2 m high 424.60 metre
2
Providing and fixing 1.2 m high GI barbed wire fencing with 1.8 m RCC posts 150
mm x 150 mm placed every 3 m centre-to-centre founded in M15 grade cement
concrete, 0.6 m below ground level, every 15th post, last but one end post and
corner post shall be strutted on both sides and end post on one side only and
provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires,
fixed with GI staples, turn buckles etc. complete as per Clause 1705.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL03 Blacksmith 1st class/Electrician 0.25 558.51 day 139.63
2 PL14 Mate 0.09 337.56 day 30.38
3 PL15 Beldar/mazdoor (unskilled) 2.00 306.88 day 613.75
Material Group
1 PM0034 Barbed wire 31.42 90.00 kilogram 2,827.80
Total Resource Amount 3,611.56

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-5-1-1 Nominal mix (1:2.5:5) 0.53 5,348.23 cu.m 2,813.17

R.C.C. Post 150 mm x 150 mm x 1.80


m
M15 Grade concrete
13 x 150 mm x 150 mm x 1.8 m

MORD - 2016-2017 - 01/05/2016 - 10 Page 99 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

2 12-6 Supplying, fitting and placing HYSD 0.07 50,307.02 tons 3,722.72
bar reinforcement (Fe 415) in
substructrue
Supply of HYSD Bars including
cutting, bending, tying & placing in
position.
10 mm dia HYSD bars for posts

13 x 4 x 1.8 = 93.6 m @ 0.62 kg/mt


=43.60 kg
8 mm dia HYSD bars for rings
13 x 10 x 0.6 = 78 m @ 0.39 kg/mt
=30.42 kg

Total =74.02
kg
3 10-5 Painting Two Coats on New Concrete 8.14 106.36 sq.m 865.80
Surfaces
Total Child Item Amount 7,401.69

Over Heads

16. Formwork Charges 5% on (12-5-1-1) 140.66

38. Labour Cost for Drilling Holes etc. 2% on (Material Group) 56.56

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,401.31

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 126.12

Total OH Amount 1,724.64

Total Cost for 30.00 metre = Sub Items Cost + Resource Cost + Overhead 12,737.89
Cost
Item Rate Per metre 424.60

Notes: Cost of excavation for foundation and foundation concrete to be added separately in the cost estimate as per approved design. The rate for
these items may be taken from respective Chapters.

10988 10-13 G.I Barbed Wire Fencing 1.8 m high 585.50 metre
3
Providing and fixing 1.8 m high GI barbed wire fencing with 2.4 m RCC M15 grade
150 mm x 150 mm concrete post placed every 3 m centre-to-centre founded in M15
grade cement concrete, 0.6 m below ground level, every 15th post, last but one end
post and corner post shall be strutted on both sides and end post on one side only
and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal
wires, fixed with GI staples, turn buckles etc. complete as per Clause 1705.

S.No Resource Code Resource Quantity Rate Unit Amount


.

MORD - 2016-2017 - 01/05/2016 - 10 Page 100 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

Labour Group
1 PL03 Blacksmith 1st class/Electrician 0.40 558.51 day 223.41
2 PL14 Mate 0.12 337.56 day 40.51
3 PL15 Beldar/mazdoor (unskilled) 2.50 306.88 day 767.19
Material Group
1 PM0034 Barbed wire 40.15 90.00 kilogram 3,613.50
Total Resource Amount 4,644.60

S.No. Item Code Item Description Quantity Rate Unit Amount

1 12-5-1-1 Nominal mix (1:2.5:5) 0.70 5,348.23 cu.m 3,754.46

R.C.C. Post 150 mm x 150 mm x 2.4


m
High M-15 Grade
13 x 150 mm x 150 mm x 2.4 m
2 10-5 Painting Two Coats on New Concrete 12.10 106.36 sq.m 1,287.00
Surfaces

exposed surface of RCC posts


3 12-6 Supplying, fitting and placing HYSD 0.11 50,307.02 tons 5,584.08
bar reinforcement (Fe 415) in
substructrue
Supply of HYSD Bars including
cutting, bending, tying & placing in
position
10 mm dia HYSD bars for posts
13 x 4 x 2.4 = 124.80 m
@ 0.62 kg/mt = 77.38 kg
8 mm dia HYSD bars for rings
13 x 11 x 0.6 = 85.80 m
@ 0.39 kg/m = 33.46 kg
Total = 110.84 kg
Total Child Item Amount 10,625.54

Over Heads

16. Formwork Charges 5% on (12-5-1-1) 187.72

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,932.23

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 173.90

Total OH Amount 2,293.86

Total Cost for 30.00 metre = Sub Items Cost + Resource Cost + Overhead 17,564.00
Cost
Item Rate Per metre 585.47

Notes: Cost of excavation for foundation and foundation concrete to be added separately in the cost estimate as per approved design. The rate for
these items may be taken from respective Chapters.
Page 101 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

these items may be taken from respective Chapters.

10988 10-14 Tubular Steel Railing on Medium Weight Steel Channel (ISMC series) 100 mm x 50 2,056.60 metre
4 mm

Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on
medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 m high above
ground, 2 m centre-to-centre, complete as per approved drawings Clause 1706

S.No Resource Code Resource Quantity Rate Unit Amount


.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
3 PL19 Plumber 0.01 540.10 day 5.40
Machine Group
1 PMC031 Tractor with trolley. 0.06 276.00 hours 16.56
Material Group
1 PM0083 GI Pipe 50 mm dia 30.00 297.05 metre 8,911.45
2 PM0101 MS Flat / Structural Steel 104.33 41,781.46 M.T. 4,359.06
/kilogram
Total Resource Amount 13,372.56

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 1.30 291.20 cu.m 377.40


& brest walls
Excavation for foundation (6 Nos.) 6 x
0.6 x 0.6 x 0.6
2 11-4-2-2 Nominal mix 1:2.5:5 (Hand mixing) 0.65 6,291.20 cu.m 4,076.70

Foundation concrete M-15 grade PCC


6 x 0.6 x 0.6 x 0.3
3 10-6 Painting on Steel Surfaces 6.87 111.90 sq.m 768.75

Painting of pipe
Painting of channel section (6 nos.) 1.8
m each 0.2 x 1.8 x 1.6 = 2.16
Total Child Item Amount 5,222.85

Over Heads

30. Electricity Charges, Welding and Drilling Equipment, Electrodes and Other Consumables 3% on (PM0101) 130.77

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,687.92

MORD - 2016-2017 - 01/05/2016 - 10 Page 102 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 151.91

Total OH Amount 1,970.60

Total Cost for 10.00 metre = Sub Items Cost + Resource Cost + Overhead 20,566.01
Cost
Item Rate Per metre 2,056.60

10988 10-15 Tubular Steel Railing on Precast RCC posts, 1.2 m high above Ground Level 2,007.40 metre
5
Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on
precast M-20 grade RCC vertical posts 175 mm x 175 mm x 1.8 m high (1.2 m
above Gl) with 3 holes 50 mm dia for pipe, fixed 2 m centre-to- centre complete as
per approved drawings Clause 1706

S.No Resource Code Resource Quantity Rate Unit Amount


.
Labour Group
1 PL14 Mate 0.01 337.56 day 4.73
2 PL15 Beldar/mazdoor (unskilled) 0.35 306.88 day 107.41
3 PL19 Plumber 0.01 540.10 day 5.40
Machine Group
1 PMC031 Tractor with trolley. 0.25 276.00 hours 69.00
Material Group
1 PM0083 GI Pipe 50 mm dia 30.00 297.05 metre 8,911.45
Total Resource Amount 9,097.98

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 1.30 291.20 cu.m 377.40


& brest walls
Excavation for foundation (6 Nos.) 6 x
0.6 x 0.6 x 0.6
2 11-4-2-2 Nominal mix 1:2.5:5 (Hand mixing) 0.65 6,291.20 cu.m 4,076.70

Foundation concrete M15 grade PCC 6


x 0.6 x 0.6 x 0.3
3 12-5-3 R.C.C grade M 20 0.33 8,900.70 cu.m 2,937.23

RCC M20 for precast posts (6 nos.) of


1.8 m each
4 10-6 Painting on Steel Surfaces 4.71 111.90 sq.m 527.05

Painting of pipe
5
12-6 Supplying, fitting and placing HYSD 0.03 57,161.40 tons 1,829.16
bar reinforcement (Fe 415) in
substructrue
MORD - 2016-2017 - 01/05/2016 - 10 Page 103 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit
5 12-6 0.03 57,161.40 tons 1,829.16

substructrue
Total Child Item Amount 9,747.54

Over Heads

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,137.25

102. Labour Cess 1% on (All Resource) 90.98

Total OH Amount 1,228.23

Total Cost for 10.00 metre = Sub Items Cost + Resource Cost + Overhead 20,073.75
Cost
Item Rate Per metre 2,007.37

10988 10-16 Providing and Fixing 'Logo' of PMGSY Project 14,067.80 each
6 Providing and fixing of typical PMGSY informatory sign board with Logo as per
MORD specifications and drawing. Three MS Plates of 1.6 mm thick, top and
middle plate duly welded with MS flat iron 25mm x 5m size on back on edges. The
lower plate will be welded with MS angle iron frame of 25mm x 25mm x 5mm. The
angle iron frame of the lower most plate and flat iron frame of middle plate will be
welded to 2 nos. 75mm x 75 mm of 12 SWG sheet tubes posts duly embedded in
cement concrete M-15 grade blocks of 450mm x 450mm x 600mm, 600mm below
ground level. The top most diamond plate will be welded to middle plate by 47mm
x 47mm of 12 SWG steel plate tube. All M.S. will be stove enameled on both sides.
Lettering and printing arrows, border etc. will be painted with ready mixed synthetic
enamel paint of superior quality in required shade and colour. All sections of
framed posts and steel tube will be painted with primer and two coats of epoxy paint
as per drawing Clause 1701 and Annexure 1700.1
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.03 337.56 day 10.13
2 PL15 Beldar/mazdoor (unskilled) 0.75 306.88 day 230.16
Machine Group
1 PMC031 Tractor with trolley. 0.24 276.00 hours 66.24
Material Group
1 PM0101 MS Flat / Structural Steel 2.12 41,781.46 M.T. 88.58
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 67.62 61.38 kilogram 4,150.61
Sheet)
3 PM0104 MS Sheet 2 mm thick 1.44 866.17 sq.m 1,247.28
Total Resource Amount 5,793.00

S.No. Item Code Item Description Quantity Rate Unit Amount

1 11-1-1-1 Excavation in foundation for retaining 0.25 291.20 cu.m 73.38


& brest walls
MORD - 2016-2017 - 01/05/2016 - 10 Page 104 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

2 11-4-2-2 Nominal mix 1:2.5:5 (Hand mixing) 0.25 6,291.20 cu.m 1,585.38

3 10-1-1 Hindi (Matras commas and the like not 4,532.50 1.20 cm 5,439.00
to be measured and paid for.
Printing new letters and figures of any
shade with synthetic enamel paint
black or any other approved colour to
give an even shade.
Logo Border 60x4x5 = 1200 per cm
height per letter
Figure 60x10 = 600 per cm height per
letter
Middle plate words 28x5 = 140 per cm
height per letter
Bottom plate border 150x2x5 = 1500
per cm height per letter
Bottom plate border 60x2x5 = 600 per
cm height per letter
Words 101x2.5 = 252.5
Words 80x3 = 240.00
Total 4532.5 per cm height per letter
4 10-7 Painting on Concrete/Steel Surfaces 1.80 111.50 sq.m 200.70
with Epoxy

Painting on MS Steel tubes with primer


and two coats of epoxy paint
2x2.05x.30 = 1.23
1x1.10x188 = 0.21
As per item no. 10.7 of Chapter 10
Total Child Item Amount 7,298.46

Over Heads

25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 164.59

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 744.70

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 67.02

Total OH Amount 976.32

Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 14,067.78
Cost
Item Rate Per each 14,067.78

10988 10-17 Traffic Cone 207.70 each


7 Provision of red fluorescent with white reflective sleeve traffic cone made of Low
Density Polyethylene (LDPE) material with a square base of 390 x 390 x 35 mm and
a height of 770 mm, 4 kg in weight, placed at 1.5 m interval, all as per BS:873

MORD - 2016-2017 - 01/05/2016 - 10 Page 105 of 106 14/05/16 8:14


Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016

Amount And Rate In (Rs)


Item Description Rate Unit

10988 10-18 Rumble Strips 0.00 sq.m


8 Provision of 15 nos. rumble strips covered with premix bituminous carpet, 15-20
mm high at centre, 250 mm wide placed at 1 m centre-to-centre at approved
locations to control speed, marked with white strips of road marking paint.

10988 10-19 Safety Devices and Signs in Construction Zones 0.00 each
9 Provision and fixing of traffic signs for limited period at suitable locations in
construction zone comprising of warning zone, approach transition zone, working
zone and terminal transition zone with a minimum distance of 2-3 m from the edge
of the carriageway. The bottom edge of the lowest sign plate to be not less than 2 m
above the road level, fixed on 600 mm x 600 mm x 6 mm angle iron post, founded
and installed as per approved design and drawings, removed and disposed of after
completion of construction work, all as per IRC:SP:55-2001.

10989 10-20 Road Markers/Road Stud with Lens Reflector 88.50 each
0 Providing and fixing of road stud 100 x 100 mm die cast in aluminium, resistant to
corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or
asphaltic surface by drilling holes 30 mm upto a depth of 600 mm and bedded in a
suitable bituminous grout or epoxy mortar, all as per BS:873 (Part 4) 1973.

S.No Resource Code Resource Quantity Rate Unit Amount


.
Labour Group
1 PL14 Mate 0.04 337.56 day 13.50
2 PL15 Beldar/mazdoor (unskilled) 1.00 306.88 day 306.88
Material Group
1 PM0027 Aluminium Studs 100 mm x 100 mm fitted 50.00 65.00 Nos. 3,250.00
with lense reflectors
Total Resource Amount 3,570.38

Over Heads

26. Fixing and Installation 10% on (Material Group) 325.00

82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 486.92

102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 43.82

Total OH Amount 855.75

Total Cost for 50.00 each = Resource Cost + Overhead Cost 4,426.12

Item Rate Per each 88.52

Specification:

MORD - 2016-2017 - 01/05/2016 - 10 Page 106 of 106 14/05/16 8:14

You might also like