Professional Documents
Culture Documents
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,411.37
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 30,142.11
Total Cost for 300.00 cu.m = Resource Cost + Overhead Cost 2,73,690.34
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 29,009.86
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,610.89
Total Cost for 300.00 cu.m = Resource Cost + Overhead Cost 2,63,699.64
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,14,548.51
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 10,309.37
Total Cost for 360.00 cu.m = Resource Cost + Overhead Cost 10,41,245.97
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,08,180.32
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 9,736.23
Total Cost for 360.00 cu.m = Resource Cost + Overhead Cost 9,83,359.13
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,17,534.55
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 10,578.11
Total Cost for 360.00 cu.m = Resource Cost + Overhead Cost 10,68,389.09
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,11,166.36
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 10,004.97
Total Cost for 360.00 cu.m = Resource Cost + Overhead Cost 10,10,502.25
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 1,10,381.05
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 9,934.29
Total Cost for 360.00 cu.m = Resource Cost + Overhead Cost 10,03,363.72
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 62,322.14
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 5,758.57
Total Cost for 75.00 cu.m = Resource Cost + Overhead Cost 5,81,615.13
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 70,246.14
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 6,434.55
Total Cost for 75.00 cu.m = Resource Cost + Overhead Cost 6,49,889.18
Notes: When curing compound is used 4-days water curing will be done
Material Group
1 PM0016 Aggregate (Single size) : 20 mm nominal size 7.94 3,133.67 cu.m 24,881.32
2 PM0049 Cement 3.80 8,481.46 tonne 32,229.56
3 PM0123 Sand (Coarse) 5.70 1,302.44 cu.m 7,417.39
4 PM0144 Water 6.00 135.00 Killo Litre 810.00
Total Resource Amount 84,786.22
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 873.30
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 10,598.28
Total Cost for 112.50 sq.m = Resource Cost + Overhead Cost 98,801.38
Notes: i.In case curing compound is used in places where there is scarcity of water, the water curing will be used for 4-days and rate analysis will
be amended accordingly
ii.Carriage of C.C. block to site of is payable seperately as per Chapter of carriage of material from manufacturing site to the site of work.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 24,314.92
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,188.34
Total Cost for 225.00 sq.m = Resource Cost + Overhead Cost 2,21,022.63
10974 6-7-2 Providing and Laying of Interlocking Concrete Blcok Pavements having thickness 963.40 sq.m
7 60 mm and compressive strength not less than 30 MPa as per drawing and Technical
Specification Clause 1504
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.90 337.56 day 303.81
2 PL15 Beldar/mazdoor (unskilled) 15.00 306.88 day 4,603.13
3 PL41 Mason (average) 7.00 540.10 day 3,780.70
Machine Group
1 PMC035 Water tanker 6 kl capacity (Truck Mounted) 2.00 276.00 hours 552.00
Material Group
1 PM0090 Interlocking Blocks with 80 mm thickness 225.00 774.54 sq.m 1,74,270.50
2 PM0123 Sand (Coarse) 5.42 1,302.44 cu.m 7,059.22
3 PM0144 Water 3.00 135.00 Killo Litre 405.00
Total Resource Amount 1,90,974.35
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,909.74
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 23,871.79
Total Cost for 225.00 sq.m = Resource Cost + Overhead Cost 2,16,755.88
Notes: i.Carriage of interlocking blocks is payable seperately as per Chapter of carriage of material from manufacturing site to the site of work.
ii.Edge blocks may be cast-in-situ. Brick masonry toe wall or CC block 300 mm x 300 mm x 150 mm or any other shape can also be used and
their cost shall be analysed/included accordingly
iii.The rates for sub-grade, sub-base and base course can be taken from Chapters 3 and 4
6-1 Granular Sub- base with Wll Graded Material (Table 400.1)
6-1-A Construction of granular sub- base by providing well graded material, spreading in
uniform layers with motor grader on prepared surface, mixing by mix in place
method with rotavator at OMC and compacting with smooth wheel roller to achieve
the desired density, complete as per technical Specification Clauses 40.1
11254 6-1-A-(i) For Grading I Material 1,798.50 cu.m
0
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.48 337.56 day 162.03
2 PL15 Beldar/mazdoor (unskilled) 10.00 306.88 day 3,068.75
3 PL17 Mazdoor/Beldar (Skilled) 2.00 441.90 day 883.80
Machine Group
1 PMC027 Three wheel 80-100 kN Static Roller 30.00 648.60 hours 19,458.00
2 PMC032 Tractor with Rotavator 12.00 496.80 hours 5,961.60
3 PMC035 Water tanker 6 kl capacity (Truck Mounted) 5.00 276.00 hours 1,380.00
4 PMC145 Tractor Mounted Grader 12.00 531.30 hours 6,375.60
Material Group
1 PM0144 Water 30.00 135.00 Killo Litre 4,050.00
2 PM2250 Well graded granular sub-base material of 360.00 1,204.23 cu.m 4,33,523.58
Grading - I as per table 400.1 of
Specifications.
Total Resource Amount 4,74,863.36
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 59,357.92
11. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 5,342.21
Total Cost for 300.00 cu.m = Resource Cost + Overhead Cost 5,39,563.49
Machine Group
1 PMC027 Three wheel 80-100 kN Static Roller 30.00 648.60 hours 19,458.00
2 PMC032 Tractor with Rotavator 12.00 496.80 hours 5,961.60
3 PMC035 Water tanker 6 kl capacity (Truck Mounted) 5.00 276.00 hours 1,380.00
4 PMC145 Tractor Mounted Grader 12.00 531.30 hours 6,375.60
Material Group
1 PM0144 Water 30.00 135.00 Killo Litre 4,050.00
2 PM2251 Well graded granular sub-base material of 360.00 1,252.23 cu.m 4,50,803.58
Grading - II as per table 400.1 of
Specifications.
Total Resource Amount 4,92,143.36
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 61,517.92
11. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 5,536.61
Total Cost for 300.00 cu.m = Resource Cost + Overhead Cost 5,59,197.89
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 66,557.92
11. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 5,990.21
Total Cost for 300.00 cu.m = Resource Cost + Overhead Cost 6,05,011.49
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 46,006.21
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 4,140.56
Total Cost for 225.00 cu.m = Resource Cost + Overhead Cost 4,18,196.47
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 46,083.78
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 4,147.54
Total Cost for 225.00 cu.m = Resource Cost + Overhead Cost 4,18,901.56
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 46,083.78
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 4,147.54
Total Cost for 225.00 cu.m = Resource Cost + Overhead Cost 4,18,901.56
Specification:
Notes: Rate as appropriate for the type of soil/rock are to be taken in (i)
1 11-5-2 Brick masonry in 1:4 cement mortar 1.00 8,340.80 cu.m 8,340.80
10975 7-1-5 Providing P.C.C M20 architectural coping on top of wall 403.50 metre
2
S.No. Item Code Item Description Quantity Rate Unit Amount
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 65.00
1 14-1 Providing and laying boulder apron for 1.00 1,338.10 cu.m 1,338.10
bed protection with stone boulders
Total Child Item Amount 1,338.10
10975 7-6-2 Providing and Laying of Boulder Apron Laid in Wire Crates as per Drawing and 2,162.60 cu.m
8 Technnical Specification Clause 1301
1 14-2 Providing and laying of boulder apron 1.00 2,162.60 cu.m 2,162.60
laid in wire crates with 4 mm dia GI
wire
Total Child Item Amount 2,162.60
10975 7-6-3 Providing and Laying of Apron with Cement Concrete Blocks as per Drawing and 6,375.90 cu.m
9 Technical Specification Clause 1301
1 14-3 Providing and laying of apron with 1.00 6,375.90 cu.m 6,375.90
cement concrete blocks
Total Child Item Amount 6,375.90
10976 7-7 Construction of R.C.C. guide posts of 250 mm dia, M25 grade as per drawing and 64,462.00 cu.m
0 technical specification Clause 1401.6
1 8-8-(i) Earth work in excavation for structures 1.00 294.10 cu.m 294.10
4 8-8-(iv) Painting two coats including prime 1.00 121.50 sq.m 121.50
coat on new concrete surface
Total Child Item Amount 64,462.00
10976 7-8-2 Type B (first class) Bedding Clause 1402.5 1,884.30 cu.m
2
S.No. Item Code Item Description Quantity Rate Unit Amount
10976 7-9 Laying Reinforced Cement Concrete Pipe NP3 as per drawing and technical 8,960.60 metre
3 specification Clause 1402.6
10976 7-10 Laying Reinforced Cement Concrete Pipe NP4 as per technical specification Clause 10,324.10 metre
4 1402.6
Specification:
Over Heads
24. White Washing, Lettering and Painting, etc. 5% on ( Resource Cost + Over Head Cost + Child Item Amount) 373.69
Total Cost for 1.00 km = Sub Items Cost + Overhead Cost 7,847.53
10976 8-2-(2) Construction of back piller as per Fig. 1600.1( c) as per drawing and Technical 30,663.20 km
7 Specification Clause 1602.3
Over Heads
24. White Washing, Lettering and Painting, etc. 5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,460.15
Total Cost for 1.00 km = Sub Items Cost + Overhead Cost 30,663.17
10976 8-2-(3) Construction of Job pillers as per Fig. 1600.1 (d) and Technical Specification Clause 765.90 km
8 1602.4
Over Heads
24. White Washing, Lettering and Painting, etc. 5% on ( Resource Cost + Over Head Cost + Child Item Amount) 36.47
Total Cost for 1.00 km = Sub Items Cost + Overhead Cost 765.90
Notes: (i)The dimensions of reference pillars, back pillars and job pillars are as per figure/site conditions. The above items are covered under
different Chapters of MORD Specifications for payment.
(ii)The marking of centre line, setting out, curves, recording of levels, etc. by the surveyor will be incidental to work and no extra payment shall
be made for the same.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 2,402.83
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 216.25
Total Cost for 120.00 cu.m = Resource Cost + Overhead Cost 21,841.74
10977 8-3-1-B Extra for Every Additional Lift of 1.5 m or Part thereof Excavation in Soil 19.20 cu.m
0
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL15 Beldar/mazdoor (unskilled) 0.55 306.88 day 168.78
Total Resource Amount 168.78
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 21.10
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1.90
Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 191.78
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 3,233.19
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 290.99
Total Cost for 260.00 cu.m = Resource Cost + Overhead Cost 29,389.73
10977 8-3-2-B Extra for Every Additional Lift of 1.5 m or Part thereof Excavation in Soil 19.20 cu.m
2
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL15 Beldar/mazdoor (unskilled) 0.55 306.88 day 168.78
Total Resource Amount 168.78
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 21.10
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1.90
Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 191.78
Notes: (i)In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision
of front end loader and tipper shall be deleted as excavated earth shall be disposed off on the valley side.
(ii)For disposal of excavated surplus earth beyond 20 m, the relevant items of carriage be followed
(iii)In case, alternative machine like hydraulic excavator 0.9 cum bucket capacity is necessited because of site conditions, the same can be used.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 5,286.23
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 475.76
Total Cost for 120.00 cu.m = Resource Cost + Overhead Cost 48,051.82
10977 8-3-3-B Extra for Every Additional Lift of 1.5 m or Part thereof For Ordinary Rock 30.00 cu.m
4
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL15 Beldar/mazdoor (unskilled) 0.86 306.88 day 263.91
Total Resource Amount 263.91
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 32.99
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 2.97
Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 299.87
10977 8-3-4 Excavation in Hilly Areas in Ordinary Rock by mechanical means not requiring 170.40 cu.m
5 blasting
Excavation in hilly area in ordinary rock not requiring blasting by mechanical means
including cutting and trimming of slopes and disposal of cut material with a lift upto
1.5 m and lead upto 20 m as per Clause 1603.2.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.68 337.56 day 229.54
2 PL15 Beldar/mazdoor (unskilled) 26.00 306.88 day 7,978.75
Machine Group
1 PMC009 Dozer D 50 6.00 2,001.00 hours 12,006.00
2 PMC014 Hydraulic Excavator 0.9/1.0 cum 4.25 1,242.00 hours 5,278.50
Total Resource Amount 25,492.79
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 3,186.60
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 286.79
Total Cost for 170.00 cu.m = Resource Cost + Overhead Cost 28,966.19
Notes: (i)In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision
of front end loader and tipper shall be deleted as excavated earth shall be disposed off on the valley side.
(ii)In case, alternative machine like hydraulic excavator 0.9 cum bucket capacity is necessited because of site conditions, the same can be used.
Labour Group
1 PL04 Blaster 10.00 540.10 day 5,401.00
2 PL09 Rock Hole Driller 2.00 337.56 day 675.13
3 PL14 Mate 1.36 337.56 day 459.09
4 PL15 Beldar/mazdoor (unskilled) 22.00 306.88 day 6,751.25
Machine Group
1 PMC001 Air Compressor 210 cfm 28.00 414.00 hours 11,592.00
2 PMC009 Dozer D 50 3.00 2,001.00 hours 6,003.00
3 PMC014 Hydraulic Excavator 0.9/1.0 cum 5.00 1,242.00 hours 6,210.00
Material Group
1 PM0072 Electric Detonator 235.00 11.00 Nos. 2,585.00
2 PM0081 Gelatine 80 per cent 67.00 110.00 kilogram 7,370.00
Total Resource Amount 47,046.46
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 5,880.81
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 529.27
Total Cost for 170.00 cu.m = Resource Cost + Overhead Cost 53,456.54
10977 8-3-5-B Extra for Every Additional Lift of 1.5 m or Part thereof For Hard Rock 37.70 cu.m
7
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL15 Beldar/mazdoor (unskilled) 1.08 306.88 day 331.43
Total Resource Amount 331.43
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 41.43
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 3.73
Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 376.58
Notes: (1)In case the land on the valley side is barren and there is no objection for disposing of excavated earth on the valley side, the provision
of front end loader and tipper shall be deleted as excavated earth shall be disposed off on the valley side.
(2)In case of hill roads, the altitude effect comes into play. The output of men and machines decreases progressively after 2100 m elevation
MORDto- increase
leading 2016-2017 - 01/05/2016
in cost. - 8 effect has been explained Page
High altitude 28 ofapproach.
in the basic 106 14/05/16 8:14
(2)In case of hill roads, the altitude effect comes into play. The output of men and machines decreases progressively after 2100 m elevation
leading to increase in cost. High altitude effect has been explained in the basic approach.
Construction of retaining walls/breast walls in cement mortar 1:5 as per drawing and
technical specifications Clause 1604
10977 8-4-1 Earthwork in excavation for structures 291.20 cu.m
8
S.No. Item Code Item Description Quantity Rate Unit Amount
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 3,873.80
1 12-2 Pointing with cement mortar (1:3) on 1.00 78.20 sq.m 78.20
brickwork as per drawing
Total Child Item Amount 78.20
10978 8-4-5 Providing P.C.C. M 20 architectural coping on top of retaining wall/breast wall 4,051.10 metre
2
S.No. Item Code Item Description Quantity Rate Unit Amount
1 12-11 Providing and laying filter media with 1.00 4,051.10 cu.m 4,051.10
granular crushed aggregates as per
specification
Total Child Item Amount 4,051.10
10978 8-4-6 Filter material behind retaining wall / breast wall as per Specification 1204.3.8 in a 199.30 cu.m
3 width of 600 m
10978 8-4-7 Back filling behind retaining wall/breast wall 699.80 cu.m
4
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 291.20
1 11-4-1-2 Nominal mix 1:3.6 (Hand mixing) 1.00 6,414.90 cu.m 6,414.90
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 6,414.90
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 3,873.80
1 11-4-2-2 Nominal mix 1:2.5:5 (Hand mixing) 1.00 6,291.20 cu.m 6,291.20
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 6,291.20
10978 8-5-5 Cement plaster 15 mm thick 1:4 on stone masonry 205.50 sq.m
9
S.No. Item Code Item Description Quantity Rate Unit Amount
1 12-3 Plastering with cement mortar (1:4), 15 1.00 205.50 sq.m 205.50
mm thick on brickwork in substructure
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 sq.m = Sub Items Cost + Overhead Cost 205.50
10979 8-5-6 Providing P.C.C. M20 architectural coping on top of wall 4,051.10 metre
0
S.No. Item Code Item Description Quantity Rate Unit Amount
1 12-11 Providing and laying filter media with 1.00 4,051.10 cu.m 4,051.10
granular crushed aggregates as per
specification
Total Child Item Amount 4,051.10
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 metre = Sub Items Cost + Overhead Cost 4,051.10
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 291.20
1 11-4-1-2 Nominal mix 1:3.6 (Hand mixing) 1.00 6,414.90 cu.m 6,414.90
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 6,414.90
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 3,873.80
1 11-4-2-2 Nominal mix 1:2.5:5 (Hand mixing) 1.00 6,291.20 cu.m 6,291.20
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 6,291.20
10979 8-6-5 Cement plaster 15 mm thick 1:4 on stone masonry 205.50 sq.m
5
S.No. Item Code Item Description Quantity Rate Unit Amount
1 12-3 Plastering with cement mortar (1:4), 15 1.00 205.50 sq.m 205.50
mm thick on brickwork in substructure
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 sq.m = Sub Items Cost + Overhead Cost 205.50
10979 8-6-6 Providing P.C.C. M 20 architectural coping on top of wall 4,051.10 metre
6
S.No. Item Code Item Description Quantity Rate Unit Amount
1 12-11 Providing and laying filter media with 1.00 4,051.10 cu.m 4,051.10
granular crushed aggregates as per
specification
Total Child Item Amount 4,051.10
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 metre = Sub Items Cost + Overhead Cost 4,051.10
Construction of scupper with dry stone masonry as per drawing and technical
specifications as per Clause 1606.5.
MORD - 2016-2017 - 01/05/2016 - 8 Page 35 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016
10979 8-7-1 Earthwork in excavation for structures as per drawing and technical specifications 5,581.30 metre
7
S.No. Item Code Item Description Quantity Rate Unit Amount
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 6.00 metre = Sub Items Cost + Overhead Cost 33,488.00
Notes: Quantity for 6 m formation width of hill side rock cutting and foundation as per plate No. 7.27 of Rural Road Manual
Over Heads
2. Water Charges 10% on ( Resource Cost + Over Head Cost + Child Item Amount) 6,728.36
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 9,251.50
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 832.63
Total Cost for 6.00 metre = Resource Cost + Overhead Cost 84,096.12
10979 8-7-3 Random course rubble dry stone masonry in corbelling 5,869.10 metre
9
Quantity for 6 m formation width = 10 cum
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 6.00 558.51 day 3,351.08
2 PL14 Mate 0.72 337.56 day 243.05
3 PL15 Beldar/mazdoor (unskilled) 12.00 306.88 day 3,682.50
Material Group
1 PM0055 Corbelling Stones (300 mm x 150 mm x 150 1,335.00 15.65 Nos. 20,898.09
mm)
Total Resource Amount 28,174.71
Over Heads
2. Water Charges 10% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,817.47
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 3,874.02
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 348.66
Total Cost for 6.00 metre = Resource Cost + Overhead Cost 35,214.87
10980 8-7-4 Stone filling in foundation trenches as per drawing and technical specification 682.00 metre
0
Quantity for 6 m formation width = 10 cum
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.12 337.56 day 40.51
2 PL15 Beldar/mazdoor (unskilled) 3.00 306.88 day 920.63
Material Group
1 PM0099 Loose stone 12.00 220.00 cu.m 2,640.00
Total Resource Amount 3,601.13
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 450.14
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 40.51
Total Cost for 6.00 metre = Resource Cost + Overhead Cost 4,091.79
8-8 Construction of RCC guide posts of 250 mm dia M15 grade cast-in-situ with 20 mm
nominal size aggregate, true to line and grade, tolerance of vertical RCC posts not to
exceed 1 in 500 as per drawing and Technical Specification Clause 1608.2
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 2.91
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 294.11
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 62.51
Total Cost for 1.00 cu.m = Sub Items Cost + Overhead Cost 6,313.41
1 12-6 Supplying, fitting and placing HYSD 1.00 57,161.40 tons 57,161.40
bar reinforcement (Fe 415) in
substructrue
Total Child Item Amount 57,161.40
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 571.61
Total Cost for 1.00 tonne = Sub Items Cost + Overhead Cost 57,733.01
10980 8-8-(iv) Painting two coats including prime coat on new concrete surface 121.50 sq.m
5
S.No. Item Code Item Description Quantity Rate Unit Amount
1 10-5 Painting Two Coats on New Concrete 1.00 121.50 sq.m 121.50
Surfaces
Total Child Item Amount 121.50
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 0.00
Total Cost for 1.00 sq.m = Sub Items Cost + Overhead Cost 121.50
10980 8-9 Providing edge stones on valley side of formation as per drawing and Technical 253.90 metre
6 Specification Clause 1608.2.6
Taking Output = 45 m (100 no of edge stones of size 450 mm x 300 mm x 100 mm)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL13 Mason (brick layer) 2nd class 1.50 540.10 day 810.15
2 PL14 Mate 0.18 337.56 day 60.76
3 PL15 Beldar/mazdoor (unskilled) 3.00 306.88 day 920.63
Material Group
1 PM0069 Hammer Dressed Edge Stone (450 mm x 350 100.00 58.35 Nos. 5,835.20
mm x 100 mm)
1 10-5 Painting Two Coats on New Concrete 22.50 121.50 sq.m 2,733.75
Surfaces
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 953.34
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 113.14
Total Cost for 45.00 metre = Sub Items Cost + Resource Cost + Overhead 11,426.97
Cost
Item Rate Per metre 253.93
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 59.56
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 744.44
Total Cost for 100.00 sq.m = Resource Cost + Overhead Cost 6,759.50
Over Heads
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 303.08
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 3,788.46
Total Cost for 240.00 sq.m = Resource Cost + Overhead Cost 34,399.19
Specification:
9-1 Earthwork in excavation for foundation of structures upto 3 m depth as per drawing
and technical specification Clause 1104 including setting out, construction of
shoring and bracing, removal of stumps and other deleterious matter, dressing of
sides and bottom and backfilling with approved material
11255 9-1-1 Excavation in Ordinary Soil 291.20 cu.m
4
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.32 337.56 day 108.02
2 PL15 Beldar/mazdoor (unskilled) 8.00 306.88 day 2,455.00
Total Resource Amount 2,563.02
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 320.38
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 28.83
Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 2,912.23
11255 9-1-2 Excavation in Ordinary Rock (not requiring blasting) 364.00 cu.m
5
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.40 337.56 day 135.03
2 PL15 Beldar/mazdoor (unskilled) 10.00 306.88 day 3,068.75
Total Resource Amount 3,203.78
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 400.47
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 36.04
Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 3,640.29
3
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.60 337.56 day 202.54
2 PL15 Beldar/mazdoor (unskilled) 15.00 306.88 day 4,603.13
Total Resource Amount 4,805.66
Over Heads
82. Contractor's Profit Including Over Head 12.5% on (All Resource) 600.71
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 54.06
Total Cost for 10.00 cu.m = Resource Cost + Overhead Cost 5,460.43
9-3 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per design in Single
Row
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets Clause 1106.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 7,393.23
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 665.39
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 67,204.43
Notes: The labour rate for 600 mm dia Hume pipe may be derived from the rates for 750 dia by decreasing 20 per cent
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 5,885.09
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 529.66
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 53,495.45
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 3,517.99
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 316.62
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 31,978.56
9-4 Providing and Laying Reinforced Cement Concrete Pipe NP4 as per design in Single
Row
Providing and laying reinforced cement concrete pipe NP4 for culverts on first class
bedding of granular material in single row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets Clause 1106.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 8,518.23
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 766.64
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 77,430.68
Labour Group
1 PL12 Mason (brick layer) 1st class 0.25 558.51 day 139.63
2 PL14 Mate 0.09 337.56 day 30.38
3 PL15 Beldar/mazdoor (unskilled) 2.00 306.88 day 613.75
Material Group
1 PM0049 Cement 0.03 8,481.46 tonne 254.44
2 PM0117 RCC Pipe NP4 (1000 mm dia) 7.50 7,132.35 metre 53,492.60
3 PM0124 Sand (Fine) 0.04 1,247.44 cu.m 49.90
Total Resource Amount 54,580.70
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 6,822.59
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 614.03
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 62,017.32
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 4,174.24
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 375.68
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 37,943.87
Notes: The labour rate for 600 mm dia Hume pipe may be derived from the rates for 750 dia by decreasing 20 per cent
9-5 Providing and Laying Reinforced Cement Concrete Pipe NP3 as per Design in
Double Row
Providing and laying reinforced cement concrete pipe NP3 for culverts on first class
bedding of granular material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets as per Clause 1106.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 14,850.54
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,336.55
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 1,34,991.40
Material Group
1 PM0049 Cement 0.06 8,481.46 tonne 508.89
2 PM0112 RCC Pipe NP3 (1000 mm dia) 15.00 6,132.35 metre 91,985.21
3 PM0124 Sand (Fine) 0.08 1,247.44 cu.m 99.80
Total Resource Amount 94,476.26
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 11,809.53
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,062.86
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 1,07,348.65
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 7,035.16
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 633.16
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 63,949.62
Notes: The labour rate for 600 mm dia Hume pipe should be decreased by 20 per cent
9-6 Providing and Laying Reinforced Cement Concrete Pipe NP4 as per Design in
Double Row
Providing and laying reinforced cement concrete pipe NP4 for culverts on first class
MORD - 2016-2017 - 01/05/2016 - 9 Page 49 of 106 14/05/16 8:14
bedding of granular material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets as per Clause 1106.
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016
Providing and laying reinforced cement concrete pipe NP4 for culverts on first class
bedding of granular material in double row including fixing collar with cement
mortar 1:2 but excluding excavation, protection works, backfilling, concrete and
masonry works in head walls and parapets as per Clause 1106.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 17,100.54
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,539.05
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 1,55,443.90
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 13,684.53
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,231.61
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 1,24,392.40
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 7,035.16
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 633.16
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 63,949.62
Notes: The labour rate for 600 mm dia Hume pipe should be decreased by 20 per cent
10982 9-7 Laying Cement Concrete Pipe NP3 (burried conduits) on first class bedding of 2,998.50 metre
4 granular material including fixing collar with cement sand mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonary work in head wall
and parapets
(3 pipes of 2.5 m length each)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.11 558.51 day 61.44
2 PL14 Mate 0.04 337.56 day 13.50
3 PL15 Beldar/mazdoor (unskilled) 0.90 306.88 day 276.19
Material Group
1 PM0049 Cement 0.01 8,481.46 tonne 84.81
2 PM0115 RCC Pipe NP3 (500 mm dia) 7.50 2,577.45 metre 19,330.87
3 PM0124 Sand (Fine) 0.02 1,247.44 cu.m 24.95
Total Resource Amount 19,791.76
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,473.97
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 222.66
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 22,488.38
Notes: The labour rate for 300 mm dia shall be decreased by 20 per cent
10982 9-8 Laying Cement Concrete Pipe NP4 (burried conduits) on first class bedding of 2,998.50 metre
5 granular material including fixing collar with cement sand mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and masonary work in head wall
and parapets
(3 pipes of 2.5 m length each)
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL12 Mason (brick layer) 1st class 0.11 558.51 day 61.44
2 PL14 Mate 0.04 337.56 day 13.50
3 PL15 Beldar/mazdoor (unskilled) 0.90 306.88 day 276.19
Material Group
1 PM0049 Cement 0.01 8,481.46 tonne 84.81
2 PM0120 RCC Pipe NP4 (500 mm dia) 7.50 2,577.45 metre 19,330.87
3 PM0124 Sand (Fine) 0.02 1,247.44 cu.m 24.95
Total Resource Amount 19,791.76
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 2,473.97
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 222.66
Total Cost for 7.50 metre = Resource Cost + Overhead Cost 22,488.38
Notes: The labour rate for 300 mm dia shall be decreased by 20 per cent
10982 9-9 Plain Cement Concrete M10 (1:3:6 nominal mix) in levelling course below open 6,389.40 cu.m
6 foundation of Head walls as per drawings & Technical Specification Clause 1109
9-10 Brick Masonry Work in cement mortar in foundation of Head walls complete
exculding pointing and plastering as per drawing and technical specification Clause
1109
10982 9-10-A Brick Masonry in 1:4 cement mortar 8,340.80 cu.m
7
S.No. Item Code Item Description Quantity Rate Unit Amount
1 11-5-2 Brick masonry in 1:4 cement mortar 1.00 8,340.80 cu.m 8,340.80
9-11 Stone Masonry Work in cement mortar in foundation of Head walls complete as per
drawing and technical specification Clasue 1109
10982 9-11-A In 1:4 cement mortar 4,989.60 cu.m
9
S.No. Item Code Item Description Quantity Rate Unit Amount
10983 9-12 Pointing with Cement Mortar (1:3) on brickwork as per technical specification 78.20 sq.m
1 Clause 613.3
1 12-2 Pointing with cement mortar (1:3) on 1.00 78.20 sq.m 78.20
brickwork as per drawing
Total Child Item Amount 78.20
10983 9-13 Plastering with Cement Mortar (1:4), 15 mm thick on brickwork in substructure as 2,055.00 sq.m
2 per technical specification
1 12-3 Plastering with cement mortar (1:4), 15 10.00 205.50 sq.m 2,055.00
mm thick on brickwork in substructure
10983 9-14 Backfilling in Foundation Trenches as per drawing and technical specification 187.10 cu.m
3 Clause 1108
1 11-2-2 Earth filling (For marshy soil) 1.00 187.10 cu.m 187.10
10983 9-15 Providing PCC M20 Architectural Coping on the top of wing wall, return wall etc. 403.50 metre
4 complete as per drawing and technical specification Clause 615
Specification:
Printing new letter and figures of any shade with synthetic enamel paint black or any
other approved colour to give an even shade as per drawings and Technical
Specification Clause 1701
10983 10-1-1 Hindi (Matras commas and the like not to be measured and paid for. Half letters 1.20 cm
5 shall be counted as half only)
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 202.77
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 18.25
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 123.90
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 11.15
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0101) 25.07
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 297.52
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 26.78
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,704.48
Cost
Item Rate Per each 2,704.48
specifications
Total Child Item Amount 785.46
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0101) 25.07
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 253.74
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 22.84
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,306.54
Cost
Item Rate Per each 2,306.54
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0101) 25.07
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 282.40
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 25.42
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,567.05
Cost
Item Rate Per each 2,567.05
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0026) 26.00
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 326.97
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 29.43
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,972.20
Cost
Item Rate Per each 2,972.20
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0026) 14.62
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 278.16
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 25.03
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,528.51
Cost
Item Rate Per each 2,528.51
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0026) 19.50
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 299.08
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 26.92
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,718.66
Cost
Item Rate Per each 2,718.66
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0101) 25.07
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 370.19
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 33.32
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 3,364.99
Cost
Item Rate Per each 3,364.99
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 292.87
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 26.36
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,662.15
Cost
Item Rate Per each 2,662.15
5
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.16 1,805.28 sq.m 281.62
2 PM0083 GI Pipe 50 mm dia 3.00 297.05 metre 891.14
Total Resource Amount 1,274.94
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 247.77
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 22.30
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,252.27
Cost
Item Rate Per each 2,252.27
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 277.29
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 24.96
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,520.60
Cost
Item Rate Per each 2,520.60
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 323.08
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 29.08
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,936.82
Cost
Item Rate Per each 2,936.82
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 274.27
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 24.68
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,493.13
Cost
Item Rate Per each 2,493.13
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 295.19
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 26.57
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,683.28
Cost
Item Rate Per each 2,683.28
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 367.71
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 33.09
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 3,342.47
Cost
Item Rate Per each 3,342.47
3 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
4 11-1-1-1 Excavation in foundation for retaining 0.13 291.20 cu.m 36.69
& brest walls
Excavation for foundation
5 10-7 Painting on Concrete/Steel Surfaces 0.90 111.50 sq.m 100.35
with Epoxy
Total Child Item Amount 1,555.31
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 91.75
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 8.26
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,389.34
Cost
Item Rate Per each 2,389.34
1 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 47.97
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 4.32
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 1,991.40
Cost
Item Rate Per each 1,991.40
1 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 76.63
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 6.90
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,251.91
Cost
Item Rate Per each 2,251.91
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 121.09
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 10.90
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,656.01
Cost
Item Rate Per each 2,656.01
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 93.02
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 8.37
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,400.86
Cost
Item Rate Per each 2,400.86
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 113.33
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 10.20
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,585.47
Cost
Item Rate Per each 2,585.47
1 12-6 Supplying, fitting and placing HYSD 0.01 57,161.40 tons 440.14
bar reinforcement (Fe 415) in
substructrue
2 11-4-2-1 Nominal mix (1:2.5:5) 0.13 6,250.90 cu.m 787.61
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 183.74
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 16.54
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 3,225.47
Cost
Item Rate Per each 3,225.47
Notes: 1 Any one area of aluminium sheeting given at (i) to (vii) may be adopted as per site requirement and in accordance with IRC:67.
2 The rate for excavation, cement concrete M-15, RCC M-15 in Sub-structure, steel re-inforcement and painting may be taken from
respective Chapters.
3 The depth of foundation and quantity of cement concrete in the foundation are indicative. These may be increased for areas having
higher wind velocities like in coastal areas. This is applicable to all road signs and directions boards.
Providing and fixing of semi reflective cautionary, mandatory and informatory sign
board as per IRC:67 made of 1.5 mm thick MS Sheet duly stove white colour in
front and gray colour on back with red reflective border of 65 mm width and
required letters and figures with reflective tape engineering grade as per Clause
1701.3.9 of MORD for Rural Roads of required shade and colour supported and
welded on 47mm x 47 mm x 12 SWG sheet tube firmly fixed to the ground by mean
of properly designed foundations with M-15 grade cement concrete 450x450x600
mm, 600 mm below ground level as per approved drawing Clause 1701.2.2
10985 10-2-B-(i) 900 mm equilateral & triangle 2,391.00 each
8
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0101 MS Flat / Structural Steel 1.06 41,781.46 M.T. 44.29
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 12.40 61.38 kilogram 761.13
Sheet)
3 PM0103 MS Sheet 1.5 mm thick 0.35 686.17 sq.m 240.16
Total Resource Amount 1,302.31
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 31.37
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 166.71
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 15.00
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,390.99
Cost
Item Rate Per each 2,390.99
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 27.46
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 149.92
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 13.49
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,238.41
Cost
Item Rate Per each 2,238.41
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 29.99
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 160.79
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 14.47
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,337.18
Cost
Item Rate Per each 2,337.18
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 34.04
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 178.19
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 16.04
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,495.38
Cost
Item Rate Per each 2,495.38
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 29.72
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 159.64
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 14.37
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,326.74
Cost
Item Rate Per each 2,326.74
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 31.57
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 167.59
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 15.08
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,399.02
Cost
Item Rate Per each 2,399.02
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 37.95
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 194.98
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 17.55
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 2,647.96
Cost
Item Rate Per each 2,647.96
Notes: 1 Any one area of M.S. Sheet given at (i) to (viii) may be adopted as per site requirement and in accordance with IRC-67.
2 The rate for excavation, cement concrete M-15, and painting may be taken from respective Chapters.
3 The depth of foundation and quantity of cement in the foundation are indicative. These may be increased for areas having higher wind
velocities like in coastal area. This is applicable to all road signs and direction boards.
10-3 Direction and Place Identification signs upto 0.9 sqm size board
10-3-A Retro-reflectorised Traffic Signs
10986 10-3-A-(i) Providing and erecting direction and place identification retro-reflectorised sign as 4,549.30 sq.m
5 per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on a mild steel single angle iron post 75 x 75 x 6 mm firmly fixed to the
ground by means of properly designed foundation with M-15 grade cement concrete
450 x 450 x 600 mm, 600 mm below ground level as per approved drawing and
Technical Specification Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours/per day 176.64
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.90 1,805.28 sq.m 1,624.76
2 PM0101 MS Flat / Structural Steel 20.00 41,781.46 M.T. 835.63
/kilogram
Total Resource Amount 2,717.12
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 73.81
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 348.87
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 31.40
Total Cost for 0.90 sq.m = Sub Items Cost + Resource Cost + Overhead 4,094.40
Cost
Item Rate Per sq.m 4,549.33
10986 10-3-A-(ii) Providing and erecting direction and place identification retro-reflectorised sign as 4,255.00 sq.m
6 per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on 2 inch dia GI Pipe firmly fixed to the ground by means of properly
designed foundation with M-15 grade cement concrete 450 x 450 x 600 mm, 600
mm below ground level as per approved drawing and Tehnical Specification Clause
1701.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.90 1,805.28 sq.m 1,624.76
2 PM0083 GI Pipe 50 mm dia 3.00 297.05 metre 891.14
Total Resource Amount 2,618.07
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0083) 26.73
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 330.60
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 29.75
Total Cost for 0.90 sq.m = Sub Items Cost + Resource Cost + Overhead 3,829.47
Cost
Item Rate Per sq.m 4,254.97
10986 10-3-A-(iii) Providing and erecting direction and place identification retro-reflectorised sign as 3,967.30 sq.m
7 per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminium sheeting, 2 mm thick with area not exceeding 0.9 sqm
supported on RCC Post 100 mm x 100 mm firmly fixed to the ground by means of
properly designed foundation with M-15 grade cement concrete 450 x 450 x 600
mm, 600 mm below ground level as per approved drawing and Technical
Specification Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.01 337.56 day 3.38
2 PL15 Beldar/mazdoor (unskilled) 0.25 306.88 day 76.72
Machine Group
1 PMC031 Tractor with trolley. 0.08 276.00 hours 22.08
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 0.90 1,805.28 sq.m 1,624.76
Total Resource Amount 1,726.93
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 221.70
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 19.95
Total Cost for 0.90 sq.m = Sub Items Cost + Resource Cost + Overhead 3,570.55
Cost
Item Rate Per sq.m 3,967.28
Notes: (1)Lettering and arrow markings on sign board to be provided separately as per actual requirement. Rates for these items have been
analysed separately.
(2)The rate for excavation, cement concret M15, RCC M15 in Sub-structure, steel re-inforcement and painting may be taken from respective
Chapters.
(3)The depth of foundation and quantity of cement concrete in the foundation are indicative. These may be increased for areas having higher
wind velocities like in coastal areas. This is applicable to all road signs and directions boards.
Material Group
1 PM0101 MS Flat / Structural Steel 1.06 41,781.46 M.T. 44.29
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 12.40 61.38 kilogram 761.13
Sheet)
3 PM0104 MS Sheet 2 mm thick 0.90 866.17 sq.m 779.55
Total Resource Amount 1,687.14
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 47.55
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 216.84
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 19.52
Total Cost for 0.90 metre = Sub Items Cost + Resource Cost + Overhead 2,861.13
Cost
Item Rate Per metre 3,179.04
Notes: Rate for excavation, cement concrete M15 and painting may be taken from respective Chapters.
10-4 Direction and Place Identification signs with size more than 0.9 sqm size board
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0101) 50.14
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 577.83
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 52.00
Total Cost for 1.50 sq.m = Sub Items Cost + Resource Cost + Overhead 7,098.87
Cost
Item Rate Per sq.m 4,732.58
10987 10-4-A-2 Providing and erecting direction and place identification retro-reflectorised sign as 4,687.30 sq.m
0 per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported
on 2 inch dia GI Pipe firmly fixed to the ground by means of properly designed
foundation with M-15 grade cement concrete 450 x 450 x 600 mm, 600 mm below
ground level as per approved drawing and Tehnical Specification Clause 1701.
S.No Resource Code Resource Quantity Rate Unit Amount
.
MORD - 2016-2017 - 01/05/2016 - 10 Page 88 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016
Labour Group
1 PL14 Mate 0.02 337.56 day 6.75
2 PL15 Beldar/mazdoor (unskilled) 0.50 306.88 day 153.44
Machine Group
1 PMC031 Tractor with trolley. 0.12 276.00 hours 33.12
Material Group
1 PM0026 Aluminium sheeting (1.5 mm thick) 1.50 1,805.28 sq.m 2,707.93
2 PM0083 GI Pipe 50 mm dia 6.00 297.05 metre 1,782.29
Total Resource Amount 4,683.52
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (PM0083) 53.47
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 592.12
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 53.29
Total Cost for 1.50 sq.m = Sub Items Cost + Resource Cost + Overhead 7,031.02
Cost
Item Rate Per sq.m 4,687.35
10987 10-4-A-3 Providing and erecting direction and place identification retro-reflectorised sign as 4,345.20 sq.m
1 per IRC:67 made of encapsulated lens type reflective sheeting vide Clause 1701.2.3,
fixed over aluminium sheeting, 2 mm thick with area exceeding 0.9 sqm supported
on RCC Post 100 mm x 100 mm firmly fixed to the ground by means of properly
designed foundation with M-15 grade cement concrete 450 x 450 x 600 mm, 600
mm below ground level as per approved drawing and Technical Specification
Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.02 337.56 day 6.75
2 PL15 Beldar/mazdoor (unskilled) 0.50 306.88 day 153.44
Machine Group
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (All Item) 93.45
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 374.34
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 33.69
Total Cost for 1.50 sq.m = Sub Items Cost + Resource Cost + Overhead 6,517.79
Cost
Item Rate Per sq.m 4,345.19
Notes: (1)Lettering and arrow markings on sign boards to be provided separately as per actual requirement. Rates for these items have been
analysed separately.
(2)The rate for excavation, cement concrete M15, RCC M15 in Sub-structure, steel re-inforcement and painting may be taken from respective
Chapters.
(3)The depth of foundation and quantity of cement concrete in the foundation are indicative. These may be increased for areas having higher
wind velocities like in coastal areas. This is applicable to all road signs and directions boards.
Providing and erecting direction and place identification of semi reflective sign
boards as per IRC-67 made of 2 mm thick M.S. Sheet duly stove enameled paint
white colour in front and grey colour on back with reflective border of 70 mm width
and required message, letters, figures with reflective tape of engineering grade as per
MORD specifications of required shade and colour. Supported and welded on two
nos. 47 mm x 47 mm of 12 SWG square tube of 3050 mm height duly strengthened
by 25 mm x 5 mm MS flat iron on edges on back firmly fixed to the ground by
means of properly designed foundations with M-15 grade cement concrete 450 mm
x 450 mm x 600 mm, 600 mm below ground level as per approved drawing and
Technical Specification Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.02 337.56 day 6.75
2 PL15 Beldar/mazdoor (unskilled) 0.50 306.88 day 153.44
Machine Group
1 PMC031 Tractor with trolley. 0.16 276.00 hours 44.16
Material Group
1 PM0101 MS Flat / Structural Steel 2.12 41,781.46 M.T. 88.58
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 24.80 61.38 kilogram 1,522.26
Sheet)
3 PM0104 MS Sheet 2 mm thick 1.50 866.17 sq.m 1,299.25
Total Resource Amount 3,114.44
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 87.30
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 400.22
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 36.02
Total Cost for 1.50 each = Sub Items Cost + Resource Cost + Overhead 5,389.17
Cost
Item Rate Per each 3,592.78
Notes: Rate for excavation cement concrete M15 and painting may be taken from respective chapter
10987 10-5 Painting Two Coats on New Concrete Surfaces 121.50 sq.m
3
Painting two coats including primer coat after filling the surface with synthetic
enamel paint in all shades on new, plastered / concrete surfaces as per drawing and
Technical Specification Clause 1701
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.20 337.56 day 67.51
2 PL15 Beldar/mazdoor (unskilled) 2.00 306.88 day 613.75
3 PL18 Painter (Ist class) 3.00 540.10 day 1,620.30
Material Group
1 PM0050 Cement Primer 3.00 95.00 litre 285.00
2 PM0106 Paint (Synthetic Enamel) 6.00 278.00 litre 1,668.00
Total Resource Amount 4,254.56
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 534.70
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 48.12
Total Cost for 40.00 sq.m = Resource Cost + Overhead Cost 4,860.40
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 123.15
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 11.08
Total Cost for 10.00 sq.m = Resource Cost + Overhead Cost 1,119.43
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 122.68
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 11.04
Total Cost for 10.00 sq.m = Resource Cost + Overhead Cost 1,115.12
10987 10-8 Painting lines, Dashes, Arrows, etc. on Road in Two Coats on New Work 114.00 sq.m
6
Painting lines, dashes, arrows, etc. on roads in two coats on new work with ready
mixed road marking paint conforming to IS:164 on bituminous/concrete surface,
including cleaning the surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control as per drawing and Technical Specification Clause 1702
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 125.36
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 11.28
Total Cost for 10.00 sq.m = Resource Cost + Overhead Cost 1,139.54
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 490.02
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 44.10
Total Cost for 6.00 each = Sub Items Cost + Resource Cost + Overhead 25,271.17
Cost
Item Rate Per each 4,211.86
1 10-5 Painting Two Coats on New Concrete 11.41 121.50 sq.m 1,386.32
Surfaces
2 12-6 Supplying, fitting and placing HYSD 0.27 57,161.40 tons 15,433.58
bar reinforcement (Fe 415) in
substructrue
@ 5 kg per sqm
3 11-1-1-1 Excavation in foundation for retaining 2.77 291.20 cu.m 806.62
& brest walls
Excavation in soil for foundation
4 10-1-1 Hindi (Matras commas and the like not 1,680.00 1.20 cm 2,016.00
to be measured and paid for.
lettering on km post (average 12 letters
of 10 cm height each)
5 12-5-1-1 Nominal mix (1:2.5:5) 3.77 6,684.60 cu.m 25,200.94
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 558.83
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 50.29
Total Cost for 14.00 each = Sub Items Cost + Resource Cost + Overhead 49,923.24
Cost
Item Rate Per each 3,565.95
1 10-5 Painting Two Coats on New Concrete 6.27 121.50 sq.m 761.81
Surfaces
2 12-6 Supplying, fitting and placing HYSD 0.07 57,161.40 tons 3,772.65
bar reinforcement (Fe 415) in
substructrue
@ 5 kg per sqm
3 11-1-1-1 Excavation in foundation for retaining 1.39 291.20 cu.m 404.77
& brest walls
Excavation in soil for foundation
4 10-1-1 Hindi (Matras commas and the like not 330.00 1.20 cm 396.00
to be measured and paid for.
lettering on km post (average 1 letter of
10 cm height each)
5 12-5-1-1 Nominal mix (1:2.5:5) 1.58 6,684.60 cu.m 10,561.67
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 594.58
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 53.51
Total Cost for 33.00 each = Sub Items Cost + Resource Cost + Overhead 21,301.65
Cost
Item Rate Per each 645.50
Notes: (1)The rate for excavation, cement concrete, steel reinforcement, painting and lettering may be taken from respective Chapters.
(2)In case local stone is to be used in place of precast RCC stones, then rate of cement concrete and steel reinforcement may be deleted.
10988 10-9 Painting lines, Dashes, Arrows, etc. on Roads in Two Coats on Old Work 78.10 sq.m
0
Painting lines, dashes, arrows, etc. on roads in two coats on old work with ready
mixed road marking paint conforming to IS:164 on bituminous/concrete surface,
including cleaning the surface of all dirt, dust and other foreign matter, demarcation
at site and traffic control as per drawing and technical specification Clause 1702
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 85.92
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 7.73
Total Cost for 10.00 sq.m = Resource Cost + Overhead Cost 781.03
1 10-1-1 Hindi (Matras commas and the like not 2,280.00 1.20 cm 2,736.00
to be measured and paid for.
lettering, each 10 cm high
2 11-1-1-1 Excavation in foundation for retaining 10.72 291.20 cu.m 3,121.66
& brest walls
Excavation in soil
3 12-5-1-1 Nominal mix (1:2.5:5) 1.25 6,684.60 cu.m 8,355.75
4 12-6 Supplying, fitting and placing HYSD 0.08 57,161.40 tons 4,561.48
bar reinforcement (Fe 415) in
substructrue
Total Child Item Amount 18,774.89
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 927.30
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 83.46
Total Cost for 57.00 each = Sub Items Cost + Resource Cost + Overhead 27,204.03
Cost
Item Rate Per each 477.26
Notes: (1)In case of soft ground, a proper foundation may be provided as per approved design. In case foundation is required to be provided, the
items of excavation and foundation concrete are required to be measured and paid separately.
(2)In case local stone is to be used in place of precast RCC stones, then rate of cement concrete and steel reinforcement may be deleted.
10988 10-12 G.I Barbed Wire Fencing 1.2 m high 424.60 metre
2
Providing and fixing 1.2 m high GI barbed wire fencing with 1.8 m RCC posts 150
mm x 150 mm placed every 3 m centre-to-centre founded in M15 grade cement
concrete, 0.6 m below ground level, every 15th post, last but one end post and
corner post shall be strutted on both sides and end post on one side only and
provided with 9 horizontal lines and 2 diagonals interwoven with horizontal wires,
fixed with GI staples, turn buckles etc. complete as per Clause 1705.
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL03 Blacksmith 1st class/Electrician 0.25 558.51 day 139.63
2 PL14 Mate 0.09 337.56 day 30.38
3 PL15 Beldar/mazdoor (unskilled) 2.00 306.88 day 613.75
Material Group
1 PM0034 Barbed wire 31.42 90.00 kilogram 2,827.80
Total Resource Amount 3,611.56
2 12-6 Supplying, fitting and placing HYSD 0.07 50,307.02 tons 3,722.72
bar reinforcement (Fe 415) in
substructrue
Supply of HYSD Bars including
cutting, bending, tying & placing in
position.
10 mm dia HYSD bars for posts
Total =74.02
kg
3 10-5 Painting Two Coats on New Concrete 8.14 106.36 sq.m 865.80
Surfaces
Total Child Item Amount 7,401.69
Over Heads
38. Labour Cost for Drilling Holes etc. 2% on (Material Group) 56.56
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,401.31
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 126.12
Total Cost for 30.00 metre = Sub Items Cost + Resource Cost + Overhead 12,737.89
Cost
Item Rate Per metre 424.60
Notes: Cost of excavation for foundation and foundation concrete to be added separately in the cost estimate as per approved design. The rate for
these items may be taken from respective Chapters.
10988 10-13 G.I Barbed Wire Fencing 1.8 m high 585.50 metre
3
Providing and fixing 1.8 m high GI barbed wire fencing with 2.4 m RCC M15 grade
150 mm x 150 mm concrete post placed every 3 m centre-to-centre founded in M15
grade cement concrete, 0.6 m below ground level, every 15th post, last but one end
post and corner post shall be strutted on both sides and end post on one side only
and provided with 12 horizontal lines and 2 diagonals interwoven with horizontal
wires, fixed with GI staples, turn buckles etc. complete as per Clause 1705.
Labour Group
1 PL03 Blacksmith 1st class/Electrician 0.40 558.51 day 223.41
2 PL14 Mate 0.12 337.56 day 40.51
3 PL15 Beldar/mazdoor (unskilled) 2.50 306.88 day 767.19
Material Group
1 PM0034 Barbed wire 40.15 90.00 kilogram 3,613.50
Total Resource Amount 4,644.60
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,932.23
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 173.90
Total Cost for 30.00 metre = Sub Items Cost + Resource Cost + Overhead 17,564.00
Cost
Item Rate Per metre 585.47
Notes: Cost of excavation for foundation and foundation concrete to be added separately in the cost estimate as per approved design. The rate for
these items may be taken from respective Chapters.
Page 101 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016
10988 10-14 Tubular Steel Railing on Medium Weight Steel Channel (ISMC series) 100 mm x 50 2,056.60 metre
4 mm
Providing, fixing and erecting 50 mm dia steel pipe railing in 3 rows duly painted on
medium weight steel channels (ISMC series) 100 mm x 50 mm, 1.2 m high above
ground, 2 m centre-to-centre, complete as per approved drawings Clause 1706
Painting of pipe
Painting of channel section (6 nos.) 1.8
m each 0.2 x 1.8 x 1.6 = 2.16
Total Child Item Amount 5,222.85
Over Heads
30. Electricity Charges, Welding and Drilling Equipment, Electrodes and Other Consumables 3% on (PM0101) 130.77
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,687.92
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 151.91
Total Cost for 10.00 metre = Sub Items Cost + Resource Cost + Overhead 20,566.01
Cost
Item Rate Per metre 2,056.60
10988 10-15 Tubular Steel Railing on Precast RCC posts, 1.2 m high above Ground Level 2,007.40 metre
5
Providing, fencing and erecting 50 mm dia painted steel pipe railing in 3 rows on
precast M-20 grade RCC vertical posts 175 mm x 175 mm x 1.8 m high (1.2 m
above Gl) with 3 holes 50 mm dia for pipe, fixed 2 m centre-to- centre complete as
per approved drawings Clause 1706
Painting of pipe
5
12-6 Supplying, fitting and placing HYSD 0.03 57,161.40 tons 1,829.16
bar reinforcement (Fe 415) in
substructrue
MORD - 2016-2017 - 01/05/2016 - 10 Page 103 of 106 14/05/16 8:14
Rate Card Block 6 Bhatwari (UTTARKASHI) Effective Date 01/05/2016
substructrue
Total Child Item Amount 9,747.54
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 1,137.25
Total Cost for 10.00 metre = Sub Items Cost + Resource Cost + Overhead 20,073.75
Cost
Item Rate Per metre 2,007.37
10988 10-16 Providing and Fixing 'Logo' of PMGSY Project 14,067.80 each
6 Providing and fixing of typical PMGSY informatory sign board with Logo as per
MORD specifications and drawing. Three MS Plates of 1.6 mm thick, top and
middle plate duly welded with MS flat iron 25mm x 5m size on back on edges. The
lower plate will be welded with MS angle iron frame of 25mm x 25mm x 5mm. The
angle iron frame of the lower most plate and flat iron frame of middle plate will be
welded to 2 nos. 75mm x 75 mm of 12 SWG sheet tubes posts duly embedded in
cement concrete M-15 grade blocks of 450mm x 450mm x 600mm, 600mm below
ground level. The top most diamond plate will be welded to middle plate by 47mm
x 47mm of 12 SWG steel plate tube. All M.S. will be stove enameled on both sides.
Lettering and printing arrows, border etc. will be painted with ready mixed synthetic
enamel paint of superior quality in required shade and colour. All sections of
framed posts and steel tube will be painted with primer and two coats of epoxy paint
as per drawing Clause 1701 and Annexure 1700.1
S.No Resource Code Resource Quantity Rate Unit Amount
.
Labour Group
1 PL14 Mate 0.03 337.56 day 10.13
2 PL15 Beldar/mazdoor (unskilled) 0.75 306.88 day 230.16
Machine Group
1 PMC031 Tractor with trolley. 0.24 276.00 hours 66.24
Material Group
1 PM0101 MS Flat / Structural Steel 2.12 41,781.46 M.T. 88.58
/kilogram
2 PM0102 MS Sheet Tube (47 mm x 47 mm x 12 SWG 67.62 61.38 kilogram 4,150.61
Sheet)
3 PM0104 MS Sheet 2 mm thick 1.44 866.17 sq.m 1,247.28
Total Resource Amount 5,793.00
2 11-4-2-2 Nominal mix 1:2.5:5 (Hand mixing) 0.25 6,291.20 cu.m 1,585.38
3 10-1-1 Hindi (Matras commas and the like not 4,532.50 1.20 cm 5,439.00
to be measured and paid for.
Printing new letters and figures of any
shade with synthetic enamel paint
black or any other approved colour to
give an even shade.
Logo Border 60x4x5 = 1200 per cm
height per letter
Figure 60x10 = 600 per cm height per
letter
Middle plate words 28x5 = 140 per cm
height per letter
Bottom plate border 150x2x5 = 1500
per cm height per letter
Bottom plate border 60x2x5 = 600 per
cm height per letter
Words 101x2.5 = 252.5
Words 80x3 = 240.00
Total 4532.5 per cm height per letter
4 10-7 Painting on Concrete/Steel Surfaces 1.80 111.50 sq.m 200.70
with Epoxy
Over Heads
25. MS tube and Angle Iron Towards the Cost of Fabrications, Drilling Holes, Nuts, Bolts, etc. 3% on (Material Group) 164.59
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 744.70
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 67.02
Total Cost for 1.00 each = Sub Items Cost + Resource Cost + Overhead 14,067.78
Cost
Item Rate Per each 14,067.78
10988 10-19 Safety Devices and Signs in Construction Zones 0.00 each
9 Provision and fixing of traffic signs for limited period at suitable locations in
construction zone comprising of warning zone, approach transition zone, working
zone and terminal transition zone with a minimum distance of 2-3 m from the edge
of the carriageway. The bottom edge of the lowest sign plate to be not less than 2 m
above the road level, fixed on 600 mm x 600 mm x 6 mm angle iron post, founded
and installed as per approved design and drawings, removed and disposed of after
completion of construction work, all as per IRC:SP:55-2001.
10989 10-20 Road Markers/Road Stud with Lens Reflector 88.50 each
0 Providing and fixing of road stud 100 x 100 mm die cast in aluminium, resistant to
corrosive effect of salt and grit, fitted with lense reflectors, installed in concrete or
asphaltic surface by drilling holes 30 mm upto a depth of 600 mm and bedded in a
suitable bituminous grout or epoxy mortar, all as per BS:873 (Part 4) 1973.
Over Heads
82. Contractor's Profit Including Over Head 12.5% on ( Resource Cost + Over Head Cost + Child Item Amount) 486.92
102. Labour Cess 1% on ( Resource Cost + Over Head Cost + Child Item Amount) 43.82
Total Cost for 50.00 each = Resource Cost + Overhead Cost 4,426.12
Specification: