PROJECT DESCRIPTION: Construction of Project Facilities, Canalization, and Protection Works that will benefit 65 farmer
beneficiaries
PROGRAM NO: CY 2023-031
NEW AREA:
RESTORE AREA: 20
REHABILITATION AREA:
CALENDAR DAYS: 150
ALLOCATION: 15,000,000.00 CIS/NIS SIP/EXTN OCM PROFIT
IDP 1.50% 1.50% 2.00% 0 0
CS 1.00% 1.00% 2.00% 12 8
OCM % 12.00 0 0
PROFIT % 8.00 0 0
VAT % 5.00
SUPERVISON 3.00
HAULING DISTANCE
MATERIALS BASE COST UNIT BY BOAT SOURCE
MECH(km) MAN(km)
CEMENT 270.00 /bag 18.00 0.10 from jct. luna to end of access road
RSB 67.00 /kg. 18.00 0.10 from jct. luna to end of access road
CWN 87.00 /kg. 18.00 0.10 from jct. luna to end of access road
TIE WIRES 101.00 /kg. 18.00 0.10 from jct. luna to end of access road
PLYWOOD 719.00 /pc. 18.00 0.10 from jct. luna to end of access road
LUMBER 57.00 /bd.ft. 5.00 0.10 from jct. luna to end of access road
GI SHEET 720.00 /pc. 18.00 0.10 from jct. luna to end of access road
SAND 1406.00 /cu.m. 30.00 0.10 from jct. luna to end of access road
GRAVEL 1320.00 /cu.m. 30.00 0.10 from jct. luna to end of access road
BOULDERS 600.00 /cu.m. 30.00 0.10 from jct. luna to end of access road
CONCRETE ADMIXTURE 150.00 /liter 18.00 0.10 from jct. luna to end of access road
GEOTEXTILE FABRIC /sq.m. 18.00 0.10 from jct. luna to end of access road
18.00 0.10
18.00 0.10
18.00 0.10
18.00 0.10
18.00 0.10
40.00 0.10
40.00 0.10
40.00 0.10
40.00 0.10
40.00 0.10
Prepared: Prepared:
KINGSLEY JOHN C. GOROSPE KRISTEL D. ANDRES
Engineering Assistant A Head, Planning Unit
Checked: Checked:
JOSEPHINE C. ALVARADO ROMAR V. TUBON
Chief, Engineering Section Head, Design Unit
Submitted:
SAMUEL C. BAHIWAG
Acting Division Manager
Approved:
BENITO T. ESPIQUE JR.
Regional Manager A
Annex "B"
X. TAXES
Noted:
XI. CONTINGENCIES
A. DIRECT COST
I. CIVIL WORKS
1.a. Contract Works
a. Project Facilities 94,842.18 94,842.18
b. Construction Safety and Health Program 106,005.44 106,005.44
c. Canalization 10,738,572.66 10,738,572.66
d. Protection Works 3,623,686.52 3,623,686.52
1.b. Force Account Works
1.c. Contract Supervision 256,893.20 100,000.00 50,000.00 10,000.00 20,000.00 436,893.20
II. INSTITUTIONAL DEVELOPMENT PROGRAM
III. CONSTRUCTION SURVEY
IV. PARCELLARY MAPPING
V. ROW ACQUISITION, PLANT/PROPERTY DAMAGES
a. Plant/Property Damages
b. Land Acquisition
c. Others
VI. LAND ACQUISITION & RESETTLEMENT PLAN
VII. HEALTH & SAFETY
VIII. PROCUREMENT EQUIPMENT & VEHICLE
IX. CONSULTING SERVICES
X. TAXES
XI. CONTINGENCIES
TOTAL DIRECT COST 256,893.20 100,000.00 - - - - 50,000.00 10,000.00 20,000.00 - 14,563,106.80 - - - - - - 15,000,000.00
2 A. Contract Works
100
100.00
a. Project Facilities C 94,842.18 0.63% PROJECTED 100.00 100.00 100.00 100.00 100.00
ACTUAL
b. Construction Safety and Health Program C 106,005.44 0.71% PROJECTED 20.00 40.00 60.00 80.00 100.00
80.00
ACTUAL 75
c. Canalization C 10,738,572.66 71.59% PROJECTED 8.87 33.71 78.98 100.00 100.00
ACTUAL
d. Protection Works C 3,623,686.52 24.16% PROJECTED 60.00 - - 5.48 55.96 100.00
ACTUAL 50
3 B. Force Account Works F PROJECTED
ACTUAL 40.00
4 C. Contract Supervision F 436,893.20 2.91% PROJECTED 20.00 40.00 60.00 80.00 100.00 25
ACTUAL
5 INSTITUTIONAL DEVELOPMENT PROGRAM F PROJECTED 20.00
ACTUAL
6 CONSTRUCTION SURVEY F PROJECTED
ACTUAL 0
-
15,000,000.00 100.00% 1 2 3 4 5 6
TOTAL DIRECT COST
2 A. Contract Works
100
100.00
a. Project Facilities C 94,842.18 0.63% PROJECTED - 100.00 100.00 100.00 100.00 100.00
ACTUAL
b. Construction Safety and Health Program C 106,005.44 0.71% PROJECTED - 20.00 40.00 60.00 80.00 100.00
80.00
ACTUAL 75
c. Canalization C 10,738,572.66 71.59% PROJECTED - 15.00 33.71 78.98 100.00 100.00
ACTUAL
d. Protection Works C 3,623,686.52 24.16% PROJECTED 60.00 15.00 30.00 45.00 55.96 100.00
ACTUAL 50
3 B. Force Account Works F - PROJECTED
ACTUAL 40.00
4 C. Contract Supervision F 436,893.20 2.91% PROJECTED - 20.00 40.00 60.00 80.00 100.00
ACTUAL 25
5 INSTITUTIONAL DEVELOPMENT PROGRAM F PROJECTED -
20.00
- - - - -
ACTUAL
6 CONSTRUCTION SURVEY F PROJECTED - - - - - -
ACTUAL 0
-
15,000,000.00 100.00% 1 2 3 4 5 6
TOTAL DIRECT COST
c. Canalization
0 c.2 - #NAME? 120 20 40 60 80 100 100 100 100 100
0 0
0 c.2.2 Cut, Bend and Install 557,945.86 #NAME? 120 20 40 60 75 85 100 100 100 100 100 100 100
c.4 Borrow Haul 2,538,316.81 #NAME? 120 20 40 60 75 85 100 100 100 100 100 100 100
### ### #NAME? #NAME? 120 20 40 60 80 100 100 100 100 100 100
### ### #NAME? #NAME? 120 50 100 100 100 100 100 100
### ### #NAME? #NAME? 120 50 100 100 100 100 100 100 100 100 100 100 100 100
### ### #NAME? #NAME? 120 50 100 100 100 100
### ### #NAME? #NAME? 120 50 100 100 100 100 100 100 100 100 100 100 100 100 100 100
### ### #NAME? #NAME? 120 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100
### ### #NAME? #NAME? 120 50 100 100 100 100
### ### #NAME? #NAME? 120 100 100 100 100 100
### ### #NAME? #NAME? 120 50 100 100
### ###
### ### #NAME? #NAME? 120 10 20 30 40 50 60 70 80 90 95 100 100
### ###
### ### #NAME? #NAME? 120 10 15 30 45 60 75 85 100 100 100 100 100 100 100
### ### #NAME? #NAME? 120 10 15 30 45 60 75 85 100 100 100 100 100 100 100
### ### #NAME? #NAME? 120 20 40 60 80 100 100 100 100 100 100 100 100 100 100 100 100
### ### #NAME? #NAME? 120 50 100
TOTAL AMOUNT OF ABC #NAME? #NAME?
Projected (%) #NAME? #NAME? #NAME? #NAME?
Physical Accomplishment
Actual
Projected (%) #NAME? #NAME? #NAME? #NAME?
Financial Accomplishment (Php in Million)
Actual
IRRIGATION FACILITIES
a. Main Canal
Earth Canal km.
Concrete Canal km. 0.658
Structures units
b. Lateral Canal
Earth Canal km.
Concrete Canal km.
Structures units
PROTECTION WORKS
Slope Protection km. 0.180
Prepared:
Checked: Submitted:
Construction
Project Safety & 211 Common Gravel
Name of Structure/Canal/Location Length Billboard & kg/sq.cm. RSB Excavation Borrow Haul
Health Blanket
Bunkhouse Concrete (Equipment)
Program
c. Canalization
c.1 211 kg/sq.cm. Concrete 5,008,033.48 34.39% 15.00 30.00 45.00 60.00 75.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00
c.2 RSB
c.2.1. Furnishing and Stockpile 2,323,048.98 15.95% 15.00 30.00 45.00 60.00 75.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
c.2.2 Cut, Bend and Install 557,945.86 3.83% 15.00 30.00 45.00 60.00 75.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
c.3 Common Excavation (Equipment) 196,700.79 1.35% 15.00 30.00 45.00 60.00 75.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
c.4 Borrow Haul 2,538,316.81 17.43% 15.00 30.00 45.00 60.00 75.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
c.5 Gravel Blanket 114,526.74 0.79% 15.00 30.00 45.00 60.00 75.00 90.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00 100.00
d. Protection Works
d.1 211 kg/sq.cm. Concrete 2,300,352.17 15.80% 15.00 30.00 45.00 60.00 75.00 90.00 100.00
###
d.2 RSB
d.2.1. Furnishing and Stockpile 1,067,051.73 7.33% 15.00 30.00 45.00 60.00 75.00 90.00 100.00 100.00 100.00
###
d.2.2 Cut, Bend and Install 256,282.62 1.76% 15.00 30.00 45.00 60.00 75.00 90.00 100.00 100.00 100.00
###
TOTAL AMOUNT OF ABC 14,563,106.80 100.00%
Projected (%) 7.34 25.80 60.69 88.90 100.00 ###
Physical Accomplishment
Actual
Projected 2.18 3.76 8.84 12.95 14.56 ###
Financial Accomplishment (Php in Million)
Actual
1 PROJECT FACILITIES
a Project Billboard = 1.00 lot
b Bunkhouse = 1.00 lot
3 CANALIZATION
Canal Lining STA. 0+312.00 - 0+970.00 Main Canal Length = 658.00 Meters
Class A Concrete, 211 kg/sq.cm.
Floor Slab = 0.15 x 1.70 x 658.00 = 167.79
Side Wall = 0.15 x 1.20 x 658.00 x 2.00 = 236.88
Planks = 0.10 x 0.30 x 1.20 x 219.00 = 7.88
Fillet = 0.10 x 0.10 x 658.00 x 2.00 = 6.58
2.00
TOTAL = 419.13 cu.m.
Common Excavation (Equipment) = (Please see attached Earth Volume Computation) = 1,045.28 cu.m.
Borrow Haul = (Please see attached Earth Volume Computation) = 4,197.23 cu.m.
4 PROTECTION WORKS STA. 0+030.00 - 0+040.00 Main Canal Length = 10.00 Meters
Class A Concrete, 211 kg/sq.cm.
Cut of Wall = 0.15 x 0.60 x 10.00 = 0.90
Floor Slab = 0.15 x 0.50 x 10.00 = 0.75
Inclined Wall = 0.15 x 4.53 x 10.00 = 6.80
Cut of Wall = 0.15 x 1.50 x 10.00 = 2.25
TOTAL = 10.70 cu.m.
I. CANALIZATION
Main Canal Sta. 0+312.00 0+970.00
Station Length Area Cut Area Fill Volume Cut Volume Fill
0+312.00 5.03 4.65
0+320.00 8.00 3.05 5.56 32.29 40.87
0+340.00 20.00 4.47 8.29 75.21 138.53
0+360.00 20.00 2.37 8.30 68.44 165.88
0+380.00 20.00 2.34 6.48 47.05 147.75
0+400.00 20.00 3.12 6.40 54.58 128.70
0+420.00 20.00 2.01 9.09 51.32 154.86
0+440.00 20.00 1.85 6.42 38.57 155.13
0+460.00 20.00 2.40 4.23 42.46 106.48
0+480.00 20.00 2.93 11.00 53.30 152.30
0+500.00 20.00 2.87 5.10 58.01 160.99
0+520.00 20.00 2.47 3.58 53.41 86.77
0+530.00 10.00 3.00 4.68 27.38 41.28
0+540.00 10.00 1.05 11.35 20.25 80.10
0+560.00 20.00 2.71 6.06 37.51 174.08
0+580.00 20.00 0.84 10.24 35.49 163.03
0+600.00 20.00 1.03 7.11 18.71 173.51
0+620.00 20.00 3.18 3.34 42.06 104.47
0+640.00 20.00 2.81 7.35 59.91 106.81
0+660.00 20.00 1.31 14.02 41.21 213.61
0+680.00 20.00 3.90 5.42 52.12 194.40
0+700.00 20.00 4.85 5.18 87.52 106.08
0+720.00 20.00 5.02 48.48 102.05
0+740.00 20.00 8.22 - 132.45
0+760.00 20.00 3.54 - 117.61
0+780.00 20.00 8.14 - 116.74
0+800.00 20.00 6.35 - 144.90
0+820.00 20.00 7.19 - 135.42
0+840.00 20.00 3.13 - 103.17
0+860.00 20.00 3.51 - 66.35
0+880.00 20.00 6.88 - 103.84
0+900.00 20.00 4.05 - 109.31
0+920.00 20.00 4.07 - 81.17
0+940.00 20.00 3.98 - 80.46
0+960.00 20.00 3.31 - 72.93
0+970.00 10.00 3.73 - 35.20
TOTAL 658.00 59.58 224.95 1,045.28 4,197.23
Prepared:
Checked: Submitted:
Page 22 of 66
DETAILED COST ESTIMATE
MARAG CIS
Luna, Apayao
Attachment "I" 1 of 8
I. DERIVATION OF UNIT COST OF CONSTRUCTION MATERIALS`:
(BY LOCAL COMPETITIVE BIDDING)
Position Prevailing rate per day
Foreman 550.00
Carpenter 450.00
Mason 450.00
Steelman 450.00
L.E. Operator 550.00
HEO/Driver 550.00
Driver 550.00
Skilled 450.00
Laborer 400.00
EQUIPMENT COST:
Rental : 1,012.00 /hr. x 1.91 hrs./trip = 12.89 /bag
150.00 bags/trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 1.00 bags/trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 2.00 mins./trip
3.00 km./hr.
or Total Cycle Time = 6.00 mins./trip
EQUIPMENT COST:
Rental : 1,012.00 /hr. x 2.77 hrs./trip = 0.47 /kg.
6,000.00 kgs./trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 40.00 kgs./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 2.00 mins./trip
3.00 km./hr.
or Total Cycle Time = 6.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 0.13 /kg.
Base Cost = 67.00 /kg.
Labor Cost = 0.08 /kg.
Rental = 0.47 /kg.
Cost of RSB at worksite = 67.68 /kg.
Summary : TOTAL
Manual Hauling Cost = 0.13 /kg.
Base Cost = 87.00 /kg.
Labor Cost = 0.08 /kg.
Rental = 0.47 /kg.
Cost of C.W. Nails at worksite = 87.68 /kg.
Summary : TOTAL
Manual Hauling Cost = 0.13 /kg.
Base Cost = 101.00 /kg.
Labor Cost = 0.08 /kg.
Rental = 0.47 /kg.
Cost of Tie Wires at worksite = 101.68 /kg.
EQUIPMENT COST:
Rental : 1,012.00 /hr. x 2.25 hrs./trip = 0.57 /bd.ft.
4,000.00 bd.ft./trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 13.00 bd.ft./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 2.00 mins./trip
3.00 km./hr.
or Total Cycle Time = 6.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 0.38 /bd.ft.
Base Cost = 57.00 /bd.ft.
Labor Cost = 0.13 /bd.ft.
Rental = 0.57 /bd.ft.
Cost of Form Lumbers at worksite = 58.08 /bd.ft.
EQUIPMENT COST:
Rental : 1,012.00 /hr. x 2.91 hrs./trip = 11.78 /pc.
250.00 pcs./trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 5.00 pcs./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 2.00 mins./trip
3.00 km./hr.
or Total Cycle Time = 6.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 1.00 /pc.
Base Cost = 720.00 /pc.
Labor Cost = 2.00 /pc.
Rental = 11.78 /pc.
Cost of Form Lumbers at worksite = 734.78 /pc.
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 0.02 cu.m./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 2.00 mins./trip
3.00 km./hr.
or Total Cycle Time = 6.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 250.00 /cu.m.
Base Cost = 650.00 /cu.m.
Labor = 8.47 /cu.m.
Rental = 213.64 /cu.m.
Local Tax = 50.00 /cu.m.
Cost of SAND at worksite = 1172.11 /cu.m.
Summary : TOTAL
Manual Hauling Cost = 250.00 /cu.m.
Base Cost = 750.00 /cu.m.
Labor = 8.47 /cu.m.
Rental = 213.64 /cu.m.
Local Tax = 50.00 /cu.m.
Cost of GRAVEL at worksite = 1272.11 /cu.m.
7 BOULDERS
a. Hauling Cost:
Average hauling distance = 30.00 kms. from source Jct. Libertad, Abulug to end of accessible road
Type of road - all weather road
Utilized : 8-10 Tons Dump Truck
Average speed of W/Load: 35.00 km./hr.
Dump Truck W/o Load: 45.00 km./hr.
Base cost of Boulders = 600.00 /cu.m.
Capacity of Dump truck = 9.00 cu.m./trip
Local Tax = 50.00 /cu.m.
Equipment Rental = 1,265.00 /hr. (ACEL Rate, 2019)
Quarrying ( Gather & Pile)
Capability: 1-lab. @ 2.00 cu.m./day
Labor Cost: 350/ 2.00 = 175.00 /cu.m.
CYCLE TIME:
With Load : 30.00 kms./trip x 60.00 min./hr. = 51.43 mins./trip
35.00 km./hr.
W/o Load : 30.00 kms./trip x 60.00 min./hr. = 40.00 mins./trip
45.00 km./hr.
Manual Loading Capability of Five (5) Laborers:
Loading and Unloading = 3.00 & 4.00 cu.m./hr.
Loading 9.00 cu.m./trip x 60.00 mins./hr. = 180.00 mins./trip
3.00 cu.m./hr.
Unloading 9.00 cu.m./trip x 60.00 mins./hr. = 135.00 mins./trip
4.00 cu.m./hr.
Total = 406.43 mins./trip
or 6.77 hrs./trip
LABOR COST :
Laborers = 5.00 x 400.00 /day x 5.25 hrs./trip = 145.83 /cu.m.
8.00 hrs./day x 9.00 cu.m./trip
EQUIPMENT COST:
Rental : 1,265.00 /hr. x 6.77 hrs./trip = 951.56 /cu.m.
9.00 cu.m./trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 0.02 cu.m./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 2.00 mins./trip
3.00 km./hr.
or Total Cycle Time = 6.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 250.00 /cu.m.
Base Cost = 600.00 /cu.m.
Labor Cost = 145.83 /cu.m.
Rental = 951.56 /cu.m.
Local Tax = 50.00 /cu.m.
Quarrying = 0.00 /cu.m.
Cost of Boulders at worksite = 1997.39 /cu.m.
CYCLE TIME:
With Load : 30.00 kms./trip x 60.00 min./hr. = 51.43 mins./trip
35.00 km./hr.
W/o Load : 30.00 kms./trip x 60.00 min./hr. = 40.00 mins./trip
45.00 km./hr.
Manual Loading Capability of Five (5) Laborers:
Loading and Unloading = 6000.00 & 6000.00 lit./hr.
Loading 6,000.00 lit./trip x 60.00 mins./hr. = 60.00 mins./trip
6,000.00 lit./hr.
Unloading 6,000.00 lit./trip x 60.00 mins./hr. = 60.00 mins./trip
6,000.00 lit./hr.
Total = 211.43 mins./trip
or 3.52 hrs./trip
LABOR COST :
Laborers = 5.00 x 400.00 /day x 2.00 hrs./trip = 0.08 /liter
8.00 hrs./day x 6,000.00 lit./trip
EQUIPMENT COST:
Rental : 1,012.00 /hr. x 3.52 hrs./trip = 0.59 /liter
6,000.00 lit./trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 16.00 lit./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 2.00 mins./trip
3.00 km./hr.
or Total Cycle Time = 6.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 1.56 /liter
Base Cost = 150.00 /liter
Labor Cost = 0.08 /liter
Rental = 0.59 /liter
Cost of Boulders at worksite = 152.23 /liter
c. Equipment Cost
Capacity = 80.00 cu.m./day
One Bagger Mixer = 172.00 /hr.
Rental = 8.00 hrs./day x 172.00 /hr.
80.00 cu.m./day
Rental = 17.20 /cu.m.
SUB - TOTAL:
Materials = 7265.85 /cu.m.
Labor = 2200.00 /cu.m.
Equipment = 17.20 /cu.m.
ESTIMATED DIRECT COST = 9483.05 /cu.m.
OCM (12% of DC) = 1137.97 /cu.m.
PROFIT (8% of DC) = 758.64 /cu.m.
VAT (5% of DC, OCM, PROFIT) = 568.98 /cu.m.
TOTAL UNIT COST = 11948.64 /cu.m.
2 REINFORCED STEEL BAR
a. Furnishing and Stockpile
Hauling Cost From Source to Jobsite
Materials Unit Base Cost Total Cost
Labor Rental Local Tax
RSB kg. 67.00 0.21 0.47 67.68
SUB - TOTAL:
Materials = 67.00 /kg.
Labor = 0.21 /kg.
Equipment = 0.47 /kg.
ESTIMATED DIRECT COST = 67.68 /kg.
OCM (12% of DC) = 8.12 /kg.
PROFIT (8% of DC) = 5.41 /kg.
VAT (5% of DC, OCM, PROFIT) = 4.06 /kg.
TOTAL UNIT COST = 85.27 /kg.
b. Cut, Bend and Install
b.1. Direct Labor Cost
b.1.1. RSB Cutting, Bending, & Placing:
Crew: 1 - Steelman 1 - Bar Cutter 1 - Laborer
Capability: 80.00 kgs./day
L A B O R
Cutting, Bending, and
POSITION Rate Per Day Placing
No. Cost
Steelman 450.00 1.00 450.00
Bar cutter 450.00 1.00 450.00
Laborer 400.00 1.00 400.00
TOTAL COST 1,300.00
UNIT COST 16.25
SUB - TOTAL:
Labor = 16.25 /kg.
ESTIMATED DIRECT COST = 16.25 /kg.
OCM (12% of DC) = 1.95 /kg.
PROFIT (8% of DC) = 1.30 /kg.
VAT (5% of DC, OCM, PROFIT) = 0.98 /kg.
TOTAL UNIT COST = 20.48 /kg.
3 COMMON EXCAVATION(EQUIPMENT)
Utilized Backhoe PC200LC-5 = 200 hp
Capability of One(1) Laborer = 20.00 cu.m./hr
Rental Rate ACEL 2019 = 2,987.00 /hr
Rental Cost = 149.35 /cu.m.
ESTIMATED DIRECT COST = 149.35 /cu.m.
OCM (12% of DC) = 17.92 /cu.m.
PROFIT (8% of DC) = 11.95 /cu.m.
VAT (5% of DC, OCM, PROFIT) = 8.96 /cu.m.
TOTAL UNIT COST = 188.18 /cu.m.
4 GRAVEL BLANKET
Material Cost
Base Hauling Cost From Sourse to Jobsite Total
Materials Unit
Cost Labor Tax Rental Cost
Gravel cu.m. 750.00 258.47 50.00 213.64 1,272.11
Sand cu.m. 650.00 258.47 50.00 213.64 1,172.11
Total 1,400.00 516.94 100.00 427.28 2,444.22
Material Requirement
Base Hauling Cost From Sourse to Jobsite Total
Materials Per cu.m.
Cost Labor Tax Rental Cost
Gravel 0.8 600 206.78 40 170.91 1,017.69
Sand 0.45 292.5 116.31 22.5 96.14 527.45
Total 892.50 323.09 62.50 267.05 1,545.14
Labor Cost
a. Direct Labor Cost
a.1.1 Spreading / Compaction of Aggregates:
Crew: 1 Laborer
Capability = 5.00 cu.m./day
Rate Labor Cost
POSITION per day Spreading / Compaction
No. Cost
Laborer 400.00 1.00 400.00
Total Cost 400.00
Unit Cost 80.00
Sub-Toal
Materials 892.50 = 892.50
Laborer 323.09 + 80.00 = 403.09
Local Tax 62.50 = 62.50
Rental 267.05 = 267.05
ESTIMATED DIRECT COST = 1625.14 /cu.m
OCM (12% of DC) = 195.02 /cu.m
PROFIT (8% of DC) = 130.01 /cu.m
VAT (5% of DC, OCM, PROFIT) = 97.51 /cu.m
TOTAL UNIT COST = 2047.68 /cu.m
I. TEMPORARY WORKS
1. Project Billboard = 1.00 lot
2. Bunkhouse = 1.00 lot
3. Rubble Masonry
Core Filler = 2.05 x 5.00 x 5.90 = 60.48 cu.m.
4. Demolition of Concrete
Beam = 0.40 x 0.30 x 1.70 x 2.00 = 0.41 cu.m.
Slab = 0.15 x 1.70 x 2.05 x 2.00 = 1.05 cu.m.
TOTAL = 1.46 cu.m.
IV. CANALIZATION
CONCRETE COVER STA. 0+392.00 - 0+977.00 MC L = 585.00 m
1. 211 kg/sq.cm. Concrete = 0.10 x 0.80 x ( 585.00 - 58.50 ) = 42.12 cu.m.
= 0.05 x 0.60 x ( 585.00 - 58.50 ) = 15.80 cu.m.
TOTAL = 57.92 cu.m.
3. Common Excavation (Manual) = (Please see attached Earth Volume Computation) = 154.58 cu.m.
4. Backfill w/ Manual Compaction = (Please see attached Earth Volume Computation) = 112.33 cu.m.
I. CANALIZATION
CANAL LINING Sta. 1+180.40 1+800.00 Main Canal L = 619.60
Station Length Area Cut Area Fill Volume Cut Volume Fill
1+180.40 0.29 0.18 - -
1+200.00 19.60 0.29 0.18 5.68 3.53
1+220.00 20.00 0.29 0.18 5.80 3.60
1+240.00 20.00 0.29 0.17 5.80 3.50
1+260.00 20.00 0.29 0.18 5.80 3.50
1+280.00 20.00 0.32 0.20 6.10 3.80
1+300.00 20.00 0.29 0.18 6.10 3.80
1+320.00 20.00 0.31 0.19 6.00 3.70
1+340.00 20.00 0.29 0.17 6.00 3.60
1+360.00 20.00 0.18 0.19 4.70 3.60
1+380.00 20.00 0.18 0.18 3.60 3.70
1+400.00 20.00 0.18 0.18 3.60 3.60
1+420.00 20.00 0.19 0.18 3.70 3.60
1+440.00 20.00 0.20 0.18 3.90 3.60
1+460.00 20.00 0.20 0.18 4.00 3.60
1+480.00 20.00 0.29 0.18 4.90 3.60
1+500.00 20.00 0.29 0.18 5.80 3.60
1+520.00 20.00 0.29 0.18 5.80 3.60
1+540.00 20.00 0.29 0.17 5.80 3.50
1+560.00 20.00 0.29 0.18 5.80 3.50
1+580.00 20.00 0.32 0.20 6.10 3.80
1+600.00 20.00 0.29 0.18 6.10 3.80
1+620.00 20.00 0.31 0.19 6.00 3.70
1+640.00 20.00 0.29 0.17 6.00 3.60
1+660.00 20.00 0.18 0.19 4.70 3.60
1+680.00 20.00 0.18 0.18 3.60 3.70
1+700.00 20.00 0.18 0.18 3.60 3.60
1+720.00 20.00 0.19 0.18 3.70 3.60
1+740.00 20.00 0.20 0.18 3.90 3.60
1+760.00 20.00 0.20 0.18 4.00 3.60
1+780.00 20.00 0.20 0.18 4.00 3.60
1+800.00 20.00 0.20 0.18 4.00 3.60
TOTAL 619.60 7.98 5.80 154.58 112.33
Prepared:
Checked: Submitted:
Attachment "I" 1 of 8
I. DERIVATION OF UNIT COST OF CONSTRUCTION MATERIALS`:
(BY LOCAL COMPETITIVE BIDDING)
Position Prevailing rate per day
Foreman 550.00
Carpenter 450.00
Mason 450.00
Steelman 450.00
L.E. Operator 550.00
HEO/Driver 550.00
Driver 550.00
Skilled 450.00
Laborer 400.00
EQUIPMENT COST:
Rental : 936.00 /hr. x 1.91 hrs./trip = 11.92 /bag
150.00 bags/trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 1.00 bags/trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 3.00 mins./trip
2.00 km./hr.
or Total Cycle Time = 7.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 5.80 /bag
Base Cost = 270.00 /bag
Labor Cost = 1.67 /bag
Rental = 11.92 /bag
Cost of cement at worksite = 289.39 /bag
EQUIPMENT COST:
Rental : 936.00 /hr. x 2.77 hrs./trip = 0.43 /kg.
6,000.00 kgs./trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 40.00 kgs./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 3.00 mins./trip
2.00 km./hr.
or Total Cycle Time = 7.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 0.14 /kg.
Base Cost = 67.00 /kg.
Labor Cost = 0.08 /kg.
Rental = 0.43 /kg.
Cost of RSB at worksite = 67.65 /kg.
Summary : TOTAL
Manual Hauling Cost = 0.14 /kg.
Base Cost = 87.00 /kg.
Labor Cost = 0.08 /kg.
Rental = 0.43 /kg.
Cost of C.W. Nails at worksite = 87.65 /kg.
Summary : TOTAL
Manual Hauling Cost = 0.14 /kg.
Base Cost = 101.00 /kg.
Labor Cost = 0.08 /kg.
Rental = 0.43 /kg.
Cost of Tie Wires at worksite = 101.65 /kg.
EQUIPMENT COST:
Rental : 936.00 /hr. x 2.91 hrs./trip = 10.90 /pc.
250.00 pcs./trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 1.00 pcs./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 3.00 mins./trip
2.00 km./hr.
or Total Cycle Time = 7.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 5.80 /pc.
Base Cost = 719.00 /pc.
Labor Cost = 2.00 /pc.
Rental = 10.90 /pc.
Cost of Plywood at worksite = 737.70 /pc.
4 FORM LUMBERS
a. Hauling Cost:
Average hauling distance = 5.00 kms. from source Jct. Libertad, Abulug to end of accessible road
Type of road - all weather road
Utilized : 6-8 tons Cargo truck with (1) Laborer
Average speed of W/Load: 35.00 km./hr.
Cargo truck W/o Load: 45.00 km./hr.
Base cost of form lumbers = 57.00 /bd.ft.
Capacity of cargo truck = 4,000.00 bd.ft./trip
Equipment Rental = 936.00 /hr. (ACEL Rate, 2014)
CYCLE TIME:
With Load : 5.00 kms./trip x 60.00 min./hr. = 8.57 mins./trip
35.00 km./hr.
W/o Load : 5.00 kms./trip x 60.00 min./hr. = 6.67 mins./trip
45.00 km./hr.
Manual Loading Capability of Five (5) Laborers:
Loading and Unloading = 4000.00 & 4000.00 bd.ft./hr.
Loading 4,000.00 bd.ft./trip x 60.00 mins./hr. = 60.00 mins./trip
4,000.00 bd.ft./hr.
Unloading 4,000.00 bd.ft./trip x 60.00 mins./hr. = 60.00 mins./trip
4,000.00 bd.ft./hr.
Total = 135.24 mins./trip
or 2.25 hrs./trip
LABOR COST :
Laborers = 5.00 x 400.00 /day x 2.00 hrs./trip = 0.13 /bd.ft.
8.00 hrs./day x 4,000.00 bd.ft./trip
EQUIPMENT COST:
Rental : 936.00 /hr. x 2.25 hrs./trip = 0.53 /bd.ft.
4,000.00 bd.ft./trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 13.00 bd.ft./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 3.00 mins./trip
2.00 km./hr.
or Total Cycle Time = 7.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 0.45 /bd.ft.
Base Cost = 57.00 /bd.ft.
Labor Cost = 0.13 /bd.ft.
Rental = 0.53 /bd.ft.
Cost of Form Lumbers at worksite = 58.11 /bd.ft.
EQUIPMENT COST:
Rental : 936.00 /hr. x 2.91 hrs./trip = 10.90 /pc.
250.00 pcs./trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 5.00 pcs./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 3.00 mins./trip
2.00 km./hr.
or Total Cycle Time = 7.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 1.16 /pc.
Base Cost = 720.00 /pc.
Labor Cost = 2.00 /pc.
Rental = 10.90 /pc.
Cost of Form Lumbers at worksite = 734.06 /pc.
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 0.02 cu.m./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 3.00 mins./trip
2.00 km./hr.
or Total Cycle Time = 7.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 289.86 /cu.m.
Base Cost = 1406.00 /cu.m.
Rental = 257.64 /cu.m.
Local Tax = 50.00 /cu.m.
Cost of SAND at worksite = 2003.50 /cu.m.
Summary : TOTAL
Manual Hauling Cost = 289.86 /cu.m.
Base Cost = 1320.00 /cu.m.
Rental = 257.64 /cu.m.
Local Tax = 50.00 /cu.m.
Cost of GRAVEL at worksite = 1917.50 /cu.m.
7 BOULDERS
a. Hauling Cost:
Average hauling distance = 30.00 kms. from source Jct. Libertad, Abulug to end of accessible road
Type of road - all weather road
Utilized : 8-10 Tons Dump Truck
Average speed of W/Load: 35.00 km./hr.
Dump Truck W/o Load: 45.00 km./hr.
Base cost of Boulders = 600.00 /cu.m.
Capacity of Dump truck = 6.00 cu.m./trip
Local Tax = 50.00 /cu.m.
Equipment Rental = 1,017.00 /hr. (ACEL Rate, 2014)
Quarrying ( Gather & Pile)
Capability: 1-lab. @ 2.00 cu.m./day
Labor Cost: 350/ 2.00 = 175.00 /cu.m.
CYCLE TIME:
With Load : 30.00 kms./trip x 60.00 min./hr. = 51.43 mins./trip
35.00 km./hr.
W/o Load : 30.00 kms./trip x 60.00 min./hr. = 40.00 mins./trip
45.00 km./hr.
Manual Loading Capability of Five (5) Laborers:
Loading and Unloading = 3.00 & 4.00 cu.m./hr.
Loading 6.00 cu.m./trip x 60.00 mins./hr. = 120.00 mins./trip
3.00 cu.m./hr.
Unloading 6.00 cu.m./trip x 60.00 mins./hr. = 90.00 mins./trip
4.00 cu.m./hr.
Total = 301.43 mins./trip
or 5.02 hrs./trip
LABOR COST :
Laborers = 5.00 x 400.00 /day x 3.50 hrs./trip = 145.83 /cu.m.
8.00 hrs./day x 6.00 cu.m./trip
EQUIPMENT COST:
Rental : 1,017.00 /hr. x 5.02 hrs./trip = 850.89 /cu.m.
6.00 cu.m./trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 0.02 cu.m./trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 3.00 mins./trip
2.00 km./hr.
or Total Cycle Time = 7.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 289.86 /cu.m.
Base Cost = 600.00 /cu.m.
Labor Cost = 145.83 /cu.m.
Rental = 850.89 /cu.m.
Local Tax = 50.00 /cu.m.
Quarrying = 0.00 /cu.m.
Cost of Boulders at worksite = 1936.58 /cu.m.
EQUIPMENT COST:
Rental : 936.00 /hr. x 2.91 hrs./trip = 0.45 /liter
6,000.00 liters/trip
Note: The travel time on with and without load were only considered and the loading and unloading time
were excluded in fuel consumption.
b. Manual Hauling Cost: ( From Proj. Bodega to job site; average distance ) = 0.10 kms.
Prevailing Rate per laborer = 400.00 /day
Capability of one (1) Laborer = 16.00 liters/trip
CYCLE TIME:
With load : 0.10 km./trip x 60.00 mins./hr. = 4.00 mins./trip
1.50 km./hr.
W/O load : 0.10 km./trip x 60.00 mins./hr. = 3.00 mins./trip
2.00 km./hr.
or Total Cycle Time = 7.00 mins./trip
Summary : TOTAL
Manual Hauling Cost = 0.36 /liter
Base Cost = 150.00 /liter
Labor Cost = 0.08 /liter
Rental = 0.45 /liter
Cost of Concrete Admixture at worksite = 150.89 /liter
b. Labor Cost
b.1. Direct Labor Cost
b.1.1. Fabrication, Placing and Dismantling Cost:
Crew: 2 - Carpenters 4 - Laborers
Capability: 3.50 cu.m./day
1.a.2. Curing & concreting w/ One- Bagger Conc. Mixer Cost:
Crew: 1 - Foreman 2 - Masons 1 - L.E. Operator 8 - Laborers
Capability: 3.50 cu.m./day
L A B O R
c. Equipment Cost
Capacity = 80.00 cu.m./day
One Bagger Mixer = 172.00 /hr.
Rental = 8.00 hrs./day x 172.00 /hr.
80.00 cu.m./day
Rental = 17.20 /cu.m.
SUB - TOTAL:
Materials = 8447.20 /cu.m.
Labor = 2200.00 /cu.m.
Equipment = 17.20 /cu.m.
ESTIMATED DIRECT COST = 10664.40 /cu.m.
OCM (12% of DC) = 1279.73 /cu.m.
PROFIT (8% of DC) = 853.15 /cu.m.
VAT (5% of DC, OCM, PROFIT) = 639.86 /cu.m.
TOTAL UNIT COST = 13437.14 /cu.m.
b. Labor Cost
b.1. Direct Labor Cost
b.1.1. Fabrication, Placing and Dismantling Cost:
Crew: 2 - Carpenters 4 - Laborers
Capability: 5.00 cu.m./day
1.a.2. Curing & concreting w/ One- Bagger Conc. Mixer Cost:
Crew: 1 - Foreman 2 - Masons 1 - L.E. Operator 8 - Laborers
Capability: 5.00 cu.m./day
L A B O R
c. Equipment Cost
Capacity = 80.00 cu.m./day
One Bagger Mixer = 172.00 /hr.
Rental = 8.00 hrs./day x 172.00 /hr.
80.00 cu.m./day
Rental = 17.20 /cu.m.
SUB - TOTAL:
Materials = 5710.12 /cu.m.
Labor = 1540.00 /cu.m.
Equipment = 17.20 /cu.m.
ESTIMATED DIRECT COST = 7267.32 /cu.m.
OCM (12% of DC) = 872.08 /cu.m.
PROFIT (8% of DC) = 581.39 /cu.m.
VAT (5% of DC, OCM, PROFIT) = 436.04 /cu.m.
TOTAL UNIT COST = 9156.83 /cu.m.
SUB - TOTAL:
Labor = 16.25 /kg.
ESTIMATED DIRECT COST = 16.25 /kg.
OCM (12% of DC) = 1.95 /kg.
PROFIT (8% of DC) = 1.30 /kg.
VAT (5% of DC, OCM, PROFIT) = 0.98 /kg.
TOTAL UNIT COST = 20.48 /kg.
4 RUBBLE MASONRY
a. Material Cost
Hauling Cost From Source to Jobsite
Materials Unit Base Cost Total Cost
Labor Rental Local Tax
Cement bag 270.00 7.47 11.92 289.39
Sand cu.m. 1,406.00 289.86 257.64 50.00 2003.50
Gravel cu.m. 1,320.00 289.86 257.64 50.00 1917.50
Boulders cu.m. 600.00 435.69 850.89 50.00 1936.58
Form Lumber bd.ft. 57.00 0.58 0.53 58.11
Plywood pc. 719.00 7.80 10.90 737.70
C.W. Nails kg. 87.00 0.22 0.43 87.65
Admixture liter 150.00 0.44 0.45 150.89
Material Requirement
Hauling Cost From Source to Jobsite
Materials Per cu.m. Base Cost Total Cost
Labor Rental Local Tax
Cement 4.50 1,215.00 33.62 53.64 - 1302.26
Sand 0.23 316.35 65.22 57.97 11.25 450.79
Gravel 0.45 594.00 130.44 115.94 22.50 862.88
Boulders 0.95 570.00 413.91 808.35 47.50 1839.76
Form Lumber 5.00 285.00 2.90 2.65 - 290.55
Plywood 0.25 179.75 1.95 2.73 - 184.43
C.W. Nails 0.25 21.75 0.06 0.11 - 21.92
Admixture 3.00 450.00 1.32 1.35 - 452.67
TOTAL 3,631.85 649.42 1,042.74 81.25 5405.26
b. Labor Cost
b.1. Direct Labor Cost
b.1.1. Laying of Boulders:
Crew: 1 - Laborer
Capability: 1.50 cu.m./day
1.a.2. Curing & concreting w/ One- Bagger Conc. Mixer Cost:
Crew: 1 - Foreman 2 - Masons 1 - L.E. Operator 8 - Laborers
Capability: 5.00 cu.m./day
L A B O R
c. Equipment Cost
Capacity = 80.00 cu.m./day
One Bagger Mixer = 172.00 /hr.
Rental = 8.00 hrs./day x 172.00 /hr.
80.00 cu.m./day
Rental = 17.20 /cu.m.
SUB - TOTAL:
Materials = 5405.26 /cu.m.
Labor = 1306.67 /cu.m.
Equipment = 17.20 /cu.m.
ESTIMATED DIRECT COST = 6729.13 /cu.m.
OCM (12% of DC) = 807.50 /cu.m.
PROFIT (8% of DC) = 538.33 /cu.m.
VAT (5% of DC, OCM, PROFIT) = 403.75 /cu.m.
TOTAL UNIT COST = 8478.71 /cu.m.
5 GROUTED RIPRAP
a. Material Cost
Hauling Cost From Source to Jobsite
Materials Unit Base Cost Total Cost
Labor Rental Local Tax
Cement bag 270.00 7.47 11.92 289.39
Sand cu.m. 1,406.00 289.86 257.64 50.00 2003.50
Gravel cu.m. 1,320.00 289.86 257.64 50.00 1917.50
Boulders cu.m. 600.00 435.69 850.89 50.00 1936.58
Form Lumber bd.ft. 57.00 0.58 0.53 58.11
Plywood pc. 719.00 7.80 10.90 737.70
C.W. Nails kg. 87.00 0.22 0.43 87.65
Admixture liter 150.00 0.44 0.45 150.89
Material Requirement
Hauling Cost From Source to Jobsite
Materials Per cu.m. Base Cost Total Cost
Labor Rental Local Tax
Cement 4.50 1,215.00 33.62 53.64 - 1302.26
Sand 0.23 316.35 65.22 57.97 11.25 450.79
Gravel 0.45 594.00 130.44 115.94 22.50 862.88
Boulders 0.95 570.00 413.91 808.35 47.50 1839.76
Form Lumber 5.00 285.00 2.90 2.65 - 290.55
Plywood 0.25 179.75 1.95 2.73 - 184.43
C.W. Nails 0.25 21.75 0.06 0.11 - 21.92
Admixture 3.00 450.00 1.32 1.35 - 452.67
TOTAL 3,631.85 649.42 1,042.74 81.25 5405.26
b. Labor Cost
b.1. Direct Labor Cost
b.1.1. Laying of Boulders:
Crew: 1 - Laborer
Capability: 1.50 cu.m./day
1.a.2. Curing & concreting w/ One- Bagger Conc. Mixer Cost:
Crew: 1 - Foreman 2 - Masons 1 - L.E. Operator 8 - Laborers
Capability: 5.00 cu.m./day
L A B O R
c. Equipment Cost
Capacity = 80.00 cu.m./day
One Bagger Mixer = 172.00 /hr.
Rental = 8.00 hrs./day x 172.00 /hr.
80.00 cu.m./day
Rental = 17.20 /cu.m.
SUB - TOTAL:
Materials = 5405.26 /cu.m.
Labor = 1306.67 /cu.m.
Equipment = 17.20 /cu.m.
ESTIMATED DIRECT COST = 6729.13 /cu.m.
OCM (12% of DC) = 807.50 /cu.m.
PROFIT (8% of DC) = 538.33 /cu.m.
VAT (5% of DC, OCM, PROFIT) = 403.75 /cu.m.
TOTAL UNIT COST = 8478.71 /cu.m.
b. Labor Cost
b.1. Direct Labor Cost
b.1.1. Laying of CHB:
Crew: 1 - Mason 2 - Laborer
Capability: 10.00 sq,m,/day
L A B O R
Laying of CHB
POSITION Rate Per Day
No. Cost
Mason 450.00 1.00 450.00
Laborer 400.00 2.00 800.00
TOTAL COST 1,250.00
UNIT COST 125.00
SUB - TOTAL:
Materials = 1914.51 /sq.m.
Labor = 125.00 /sq.m.
ESTIMATED DIRECT COST = 2039.51 /sq.m.
OCM (12% of DC) = 244.74 /sq.m.
PROFIT (8% of DC) = 163.16 /sq.m.
VAT (5% of DC, OCM, PROFIT) = 122.37 /sq.m.
TOTAL UNIT COST = 2569.78 /sq.m.
b. Labor Cost
b.1. Direct Labor Cost
b.1.1. Laying of CHB:
Crew: 1 - Mason 2 - Laborer
Capability: 8.00 sq,m,/day
L A B O R
Laying of CHB
POSITION Rate Per Day
No. Cost
Mason 450.00 1.00 450.00
Laborer 400.00 2.00 800.00
TOTAL COST 1,250.00
UNIT COST 156.25
SUB - TOTAL:
Materials = 2151.23 /sq.m.
Labor = 156.25 /sq.m.
ESTIMATED DIRECT COST = 2307.48 /sq.m.
OCM (12% of DC) = 276.90 /sq.m.
PROFIT (8% of DC) = 184.60 /sq.m.
VAT (5% of DC, OCM, PROFIT) = 138.45 /sq.m.
TOTAL UNIT COST = 2907.43 /sq.m.
8 PLASTERING
a. Material Cost
Hauling Cost From Source to Jobsite
Materials Unit Base Cost Total Cost
Labor Rental Local Tax
Cement bag 270.00 7.47 11.92 289.39
Sand cu.m. 1,406.00 289.86 257.64 50.00 2003.50
Material Requirement
Hauling Cost From Source to Jobsite
Materials Per sq.m. Base Cost Total Cost
Labor Rental Local Tax
Cement 0.41 110.70 3.06 4.89 - 118.65
Sand 0.03 47.80 9.86 8.76 1.70 68.12
TOTAL 158.50 12.92 13.65 1.70 186.77
b. Labor Cost
b.1. Direct Labor Cost
b.1.1. Plastering:
Crew: 1 - Mason 1 - Laborer
Capability: 12.00 sq,m,/day
L A B O R
Plastering
POSITION Rate Per Day
No. Cost
Mason 450.00 1.00 450.00
Laborer 400.00 2.00 800.00
TOTAL COST 1,250.00
UNIT COST 104.17
SUB - TOTAL:
Materials = 186.77 /sq.m.
Labor = 104.17 /sq.m.
ESTIMATED DIRECT COST = 290.94 /sq.m.
OCM (12% of DC) = 34.91 /sq.m.
PROFIT (8% of DC) = 23.28 /sq.m.
VAT (5% of DC, OCM, PROFIT) = 17.46 /sq.m.
TOTAL UNIT COST = 366.59 /sq.m.
b. Labor Cost
b.1. Direct Labor Cost
b.1.1. Curing & concreting w/ One- Bagger Conc. Mixer Cost:
Crew: 1 - L.E. Operator 2 - Laborers
Capability: 12.00 pcs./day
1.a.2. Laying of Concrete Blocks
Equipment Crew: 1 unit 26 - 30 tons Crane
Capability: 18.00 pcs./day
L A B O R
c. Equipment Cost
Capability = 18.00 pcs./day
26 - 30 tons Crane = 1738.00 /hr.
Rental = 8.00 hrs./day x 1738.00 /hr.
18.00 pcs./day
Rental = 772.44 /pc.
SUB - TOTAL:
Materials = 4987.03 /pc.
Labor = 112.50 /pc.
Equipment = 772.44 /pc.
ESTIMATED DIRECT COST = 5871.97 /pc.
OCM (12% of DC) = 704.64 /pc.
PROFIT (8% of DC) = 469.76 /pc.
VAT (5% of DC, OCM, PROFIT) = 352.32 /pc.
TOTAL UNIT COST = 7398.69 /pc.
b. Labor Cost
b.1. Direct Labor Cost
b.1.1. Curing & concreting w/ One- Bagger Conc. Mixer Cost:
Crew: 1 - L.E. Operator 2 - Laborers
Capability: 10.00 pcs./day
1.a.2. Laying of Concrete Blocks
Equipment Crew: 1 unit 26 - 30 tons Crane
Capability: 16.00 pcs./day
L A B O R
c. Equipment Cost
Capability = 16.00 pcs./day
26 - 30 tons Crane = 1738.00 /hr.
Rental = 8.00 hrs./day x 1738.00 /hr.
16.00 pcs./day
Rental = 869.00 /pc.
SUB - TOTAL:
Materials = 5030.79 /pc.
Labor = 135.00 /pc.
Equipment = 869.00 /pc.
ESTIMATED DIRECT COST = 6034.79 /pc.
OCM (12% of DC) = 724.17 /pc.
PROFIT (8% of DC) = 482.78 /pc.
VAT (5% of DC, OCM, PROFIT) = 362.09 /pc.
TOTAL UNIT COST = 7603.83 /pc.
8 GEOTEXTILE FABRIC
a. Material Cost
Hauling Cost From Source to Jobsite
Materials Unit Base Cost Total Cost
Labor Rental Local Tax
Geotextile Fabric sq.m. - 0.00
b. Labor Cost
b.1. Direct Labor Cost
b.1.1. Plastering:
Crew: 2 - Laborer
Capability: 40.00 sq,m,/day
L A B O R
Plastering
POSITION Rate Per Day
No. Cost
Laborer 400.00 2.00 800.00
TOTAL COST 800.00
UNIT COST 20.00
SUB - TOTAL:
Materials = 0.00 /sq.m.
Labor = 20.00 /sq.m.
ESTIMATED DIRECT COST = 20.00 /sq.m.
OCM (12% of DC) = 2.40 /sq.m.
PROFIT (8% of DC) = 1.60 /sq.m.
VAT (5% of DC, OCM, PROFIT) = 1.20 /sq.m.
TOTAL UNIT COST = 25.20 /sq.m.
11 DEMOLITION OF CONCRETE
Capability of One(1) Laborer = 0.50 cu.m./day
Rate per day = 400.00 /day = 800.00 /cu.m.
ESTIMATED DIRECT COST = 800.00 /cu.m.
OCM (12% of DC) = 96.00 /cu.m.
PROFIT (8% of DC) = 64.00 /cu.m.
VAT (5% of DC, OCM, PROFIT) = 48.00 /cu.m.
TOTAL UNIT COST = 1008.00 /cu.m.
A. QUARRYING/STOCKPILING
Utilized: 200 hp Dozer; Rental = P 3,985.00 /hr
Capability 70.00 cu.m./hr
Labor Cost:
Laborer 1@P 400.00 /day
8 hrs/day * 70 cu.m./hr = 0.71
Labor Cost:
1 Stopper/laborer @ 400.00
8.00 hrs * 75.00 cu.m./hr = P 0.67
Labor Cost = P 0.67
Equipment Cost:
Rentals: 1,681.00 / 75.00 cu.m./hr; = P 22.41
CYCLE TIME
With Load: 15.00 kms/trip * 60.00 min/hr/ 20.00 kms/hr 45.00 min/trip
Without Load: 15.00 kms/trip * 60.00 min/hr/ 25.00 kms/hr 36.00 min/trip
Loading, Spot Maneuver, Unloading & Delay 6.00 min/trip
Equipment Cost:
Rentals: 1,265.00 hr * 1.45 hrs/trip = P 305.71
6.00 cu.m./trip
Equipment Cost = P = P 305.71
D. SPREADING
Utilized: 200 hp Dozer; Rental = 3,985.00 /hr
Capability: 90.00 cu.m./hr
Labor Cost:
1 Stopper/laborer @ 400.00 /day
8.00 hrs * 90.00 cu.m./hr = P 0.56
E. COMPACTION
Utilized: 6.78 tons Vibratory Roller Rental = P 1,784.00 /hr
Capability: 60.00 cu.m./hr
Labor Cost:
1 Stopper/laborer @ 400.00 /day
8.00 hrs * 60.00 cu.m./hr = P 0.83
Prepared : Checked :
Submitted :
SAMUEL C. BAHIWAG
Acting Division Manager
DETAILED COST ESTIMATE
MARAG CIS
Luna, Apayao
Attachment "I" 2 of 8
VOLUME OF COFFERDAMMING WITH DEWATERING
A. DAM REHABILITATION
1 Cofferdamming with Dewatering (Care of the River with Dewatering)
L = 6.00 meters
2.00
2.50
4.00
First Stage
V = ( 2.00 + 4.00 ) x 2.50 x 6.00
2.00
= 45.00 cu.m.
Mixed Aggregates
V = 45.00 x 1.30 x 1.50
= 87.75 cu.m.
b. Dewatering
Utilized: 100-mm dia. Submersible pump; Size of Eqp't. ( 9 HP )
Rental: 3,076.00 /day (ACEL Rate, 2019)
No. of Days: 1.00 days
Equipment Cost:
= 3,076.00 x 1.00 days = 3,076.00 /lot
Labor Cost: 1 - Laborer
= 400.00 x 1.00 = 400.00 /lot
Summary of Cofferdamming:
a. Side Borrow (Mechanical) w/ Spreading & Compaction = 7,488.84 /lot
ESTIMATED DIRECT COST = 7,488.84 /lot
OCM (12% of DC) = 898.66 /lot
PROFIT (8% of DC) = 599.11 /lot
VAT (5% of DC, OCM, PROFIT) = 449.33 /lot
TOTAL UNIT COST = 9,435.94 /lot
Prepared: Checked: Submitted:
EQUIPMENT COST:
Rental = 3,985.00 /hr = 56.93 /cu.m.
70.00 cu.m./hr.
B. LOADING
Utilized: 2.25 cu.m. Loader; Rental (accel rate 2019) = 1,681.00 /hr
Manpower = 1.00 Laborer
Labor Rate = 400.00 /day
Capability = 75.00 cu.m./hr.
LABOR COST:
Labor Cost = 1.00 Laborer x 400.00 /day = 0.67 /cu.m.
8.00 hrs./day x 75.00 cu.m./hr.
EQUIPMENT COST:
Rental = 1,681.00 /hr = 22.41 /cu.m.
75.00 hrs./day
CYCLE TIME:
With Load : 10.00 kms./trip x 60.00 min./hr. = 17.14 mins./trip
35.00 km./hr.
W/o Load : 10.00 kms./trip x 60.00 min./hr. = 13.33 mins./trip
45.00 km./hr.
Total = 30.48 mins./trip
or 0.51 hrs./trip
EQUIPMENT COST:
Rental = 1,265.00 /hr. x 0.51 hrs./trip = 71.39 /cu.m.
9.00 cu.m./trip
SUMMARY: A. B. C.
Labor Cost = 0.71 + 0.67 + 2.78 = 4.16
Rental Cost = 56.93 + 22.41 + 71.39 = 150.73
DIRECT COST = 154.89 /cu.m.
OCM (12% of DC) = 18.59
PROFIT (8% of DC) = 12.39
VAT (5% of DC, OCM, PROFIT) = 9.30
UNIT COST = 195.17 /cu.m.
A. QUARRYING/STOCKPILING
Utilized: 200 hp Dozer; Rental = P 3,985.00 /hr
Capability 70.00 cu.m./hr
Labor Cost:
Laborer 1@P 400.00 /day
8 hrs/day * 70 cu.m./hr = 0.71
Labor Cost:
1 Stopper/laborer @ 400.00
8.00 hrs * 75.00 cu.m./hr = P 0.67
Labor Cost = P 0.67
Equipment Cost:
Rentals: 1,681.00 / 75.00 cu.m./hr; = P 22.41
CYCLE TIME
With Load: 10.00 kms/trip * 60.00 min/hr/ 20.00 kms/hr 30.00 min/trip
Without Load: 10.00 kms/trip * 60.00 min/hr/ 25.00 kms/hr 24.00 min/trip
Loading, Spot Maneuver, Unloading & Delay 6.00 min/trip
Equipment Cost:
Rentals: 1,265.00 hr * 1.00 hrs/trip = P 210.83
6.00 cu.m./trip
Equipment Cost = P = P 210.83
D. SPREADING
Utilized: 200 hp Dozer; Rental = 3,985.00 /hr
Capability: 90.00 cu.m./hr
Labor Cost:
1 Stopper/laborer @ 400.00 /day
8.00 hrs * 90.00 cu.m./hr = P 0.56
E. COMPACTION
Utilized: 6.75 tons Vibratory Roller Rental = P 1,784.00 /hr
Capability: 60.00 cu.m./hr
Labor Cost:
1 Stopper/laborer @ 400.00 /day
8.00 hrs * 60.00 cu.m./hr = P 0.83
Prepared: Checked:
Submitted by:
SAMUEL C. BAHIWAG
Acting Division Manager
Attachment "I" 3 of 8
DETAILED BREAKDOWN OF ESTIMATE
Item Description : Project Billboard
MARAG CIS
Luna, Apayao
Construction Schedule: Pay Quantity: 1.00 lot Construction Method/ Notes:
From: To: Working Quantity: 1.00
Working Days: 1.00 Working Production: 1.00 /Day
LABOR EQUIPMENT MATERIALS TOTAL
PARTICULARS No. Unit
Day Rate Cost Hour Rate Cost Unit Cost Unit DIRECT COST
A. LABOR COST
Foreman 1 man 1.00 550.00 550.00 550.00
Skilled 1 man 1.00 450.00 450.00 450.00
Laborers 1 man 1.00 400.00 400.00 400.00
TOTAL 1,400.00
B. MATERIAL COST
Printed Tarpaulin 64.00 sq.ft. 50.00 /sq.ft. 3,200.00
(50mm x 50mm) Lumber 34.00 bd.ft. 58.08 /bd.ft. 1,974.72
CWN 0.50 kgs 87.68 /kgs 43.84
TOTAL 5,218.56
ESTIMATED DIRECT COST 6,618.56
VAT (5% of EDC) 330.93
TOTAL UNIT COST 6,949.49
Helmet Safety Working Rain Dust Mask Eye Gogles Ear MOP Body Lanyarn Rubber
Shoes Gloves Coats Harness Boots
Service Life, Days 730 365 3 730 1 60 730 730 730 320
Purchase Cost, (Php) 200 1250 25 250 3 50 650 1300 1100 380
Unit Cost per Man-Day 0.27 3.42 8.33 0.34 3.00 0.83 0.89 1.78 1.51 1.19
ITEM NO. WORKERS SAFETY SAFETY DUST WORKING NO. OF MAN- UNIT TOTAL COST
HELMET SHOES MASK GLOVES DAYS DAYS COST
CIVIL WORKS
1. Construction safety Safety Officer 1 1 1 1 13 13 15.02 195.26
and Health Program
Service Life, Days 730.00 365.00 3.00 730.00 1.00 60.00 730.00 730.00 730.00 320.00
Purchase Cost, (Php) 200.00 1,250.00 25.00 250.00 3.00 50.00 650.00 1,300.00 1,100.00 380.00
UNIT COST PER MAN-DAY 0.27 3.42 8.33 0.34 3.00 0.83 0.89 1.78 1.51 1.19
Safety Officer 1.00 1.00 1.00 1.00 1.00 20.00 20.00 15.02 300.40
CIVIL WORKS
Manpower 25.00 25.00 25.00 25.00 25.00 150.00 3,750.00 15.02 56,325.00
TOTAL 26.00 26.00 26.00 26.00 26.00 170.00 3,770.00 30.04 56,625.40
B. STAKE-OUT SURVEY
1. LABOR
Salary No. of Days Earned 13th Mo. &
Personnel Involved Wages Total Wages Total T.E.V. Total Allow. Total
Grade Worked Leaves Cash
1 Engineer A 14.00 3.00 1,261.59 3,784.77 - 472.44 452.37 687.60 5,397.18
1 Geodetic Engineer 14.00 3.00 1,261.59 3,784.77 - 472.44 452.37 687.60 5,397.18
2 Survey Aide A 6.00 3.00 674.86 4,049.16 - 896.46 483.96 788.52 6,218.10
2 Laborer 1.00 3.00 503.09 3,018.54 - 882.30 360.78 616.74 4,878.36
TOTAL 3,784.77 - 2,723.64 1,749.48 2,780.46 21,890.82
No. of days Complete the activity = 3.00 days
TOTAL LABOR COST = 21,890.82
D. EQUIPMENT UTILIZATION
EQUIPMENT USED: Mitsubishi Pick-Up
a. Driver = 715.36 x 5.00 days = 3,576.80
DISTANCE FROM AIMO TO PROJECT SITE (Round Trip): = 42.00 kms
a. Rental Cost = 25.00 /km x 42.00 kms x 5.00 = 5,250.00
b. Fuel Cost = 90.00 x 42.00 kms x 5.00 = 2,700.00
7.00 kms./ltr.
c. Oil Cost = 250.00 x 42.00 kms x 5.00 = 7,500.00
7.00 kms./ltr.
d. Spare Parts = = 8,500.00
TOTAL COST = 27,526.80
SUMMARY:
A. PRE-CONSTRUCTION MEETING = 8,995.30
B. STAKE-OUT SURVEY = 21,890.82
C. PROJECT SUPERVISION & MONITORING = 71,962.40
D. EQUIPMENT UTILIZATION = 27,526.80
E. OFFICE & EQUIPMENT SUPPLIES = 306,517.88
TOTAL COST FOR CONSTRUCTION SURVEY = 436,893.20
Personnel Involved Job Grade No. of Days Wages Total Wages Total T.E.V. Total Allow. Earned 13th Mo. & Total
Worked Leaves Cash
1 IDO A 8.00 10.00 1,227.27 12,272.70 - 1,692.20 1,466.60 2,234.80 17,666.30
TOTAL 12,272.70 - 1,692.20 1,466.60 2,234.80 17,666.30
B. PRE-CONSTRUCTION MEETING
1. LABOR
Personnel Involved Job Grade No. of Days Wages Total Wages Total T.E.V. Total Allow. Earned 13th Mo. & Total
Worked Leaves Cash
1 IDO A 8.00 10.00 1,227.27 12,272.70 - 1,692.20 1,466.60 2,234.80 17,666.30
TOTAL 12,272.70 - 1,692.20 1,466.60 2,234.80 17,666.30
Personnel Involved Job Grade No. of Days Wages Total Wages Total T.E.V. Total Allow. Earned 13th Mo. & Total
Worked Leaves Cash
1 IDO A 8.00 15.00 1,227.27 18,409.05 - 2,538.30 2,199.90 3,352.20 26,499.45
TOTAL 18,409.05 - 2,538.30 2,199.90 3,352.20 26,499.45
E. EQUIPMENT UTILIZATION
EQUIPMENT USED: Mitsubishi Pick-Up
a. Driver = 817.05 x 15.00 days = 12,255.75
DISTANCE FROM AIMO TO PROJECT SITE (Round Trip): = 96.00 kms
a. Rental Cost = 21.00 /km x 96.00 kms x 15.00 = 30,240.00
b. Fuel Cost = 80.00 x 96.00 kms x 15.00 = 16,457.14
7.00 kms./ltr.
c. Oil Cost = 100.00 x 96.00 kms x 15.00 x 0.10 = 2,057.14
7.00 kms./ltr.
d. Spare Parts = = 5,000.00
TOTAL COST = 66,010.04
SUMMARY:
A. COMMUNITY CONCURENCE = 17,666.30
B. PRE-CONSTRUCTION MEETING = 17,666.30
C. MONITORING/ FOLLOW-UP OF POLICIES & SYSTEM, ETC: = 26,499.45
D. TRAININGS/IA STRENGTHENING/IA REGISTRATION = 30,000.00
E. EQUIPMENT UTILIZATION = 66,010.04
F. OFFICE & EQUIPMENT SUPPLIES = 74,657.91
TOTAL COST FOR INSTITUTIONAL ACTIVITIES = 232,500.00
Personnel Involved Job Grade No. of Days Wages Total Wages Total T.E.V. Total Allow. Earned 13th Mo. & Total
Worked Leaves Cash
1 Geodetic Engineer 10.00 10.00 1,664.50 16,645.00 1,779.60 1,989.10 2,963.60 23,377.30
2 Survey Aide A 5.00 10.00 708.45 14,169.00 3,176.80 1,693.20 2,740.20 21,779.20
5 Laborer 2.00 10.00 590.90 29,545.00 7,824.50 3,530.50 5,871.00 46,771.00
TOTAL 60,359.00 12,780.90 7,212.80 11,574.80 91,927.50
Personnel Involved Job Grade No. of Days Wages Total Wages Total T.E.V. Total Allow. Earned 13th Mo. & Total
Worked Leaves Cash
1 Geodetic Engineer 10.00 10.00 1,664.50 16,645.00 1,779.60 1,989.10 2,963.60 23,377.30
2 Survey Aide A 5.00 10.00 708.45 14,169.00 3,176.80 1,693.20 2,740.20 21,779.20
5 Laborer 2.00 10.00 590.90 29,545.00 7,824.50 3,530.50 5,871.00 46,771.00
TOTAL 60,359.00 12,780.90 7,212.80 11,574.80 91,927.50
Personnel Involved Job Grade No. of Days Wages Total Wages Total T.E.V. Total Allow. Earned 13th Mo. & Total
Worked Leaves Cash
1 Engineer A 9.00 10.00 1,423.63 14,236.30 1,731.40 1,701.20 2,562.10 20,231.00
1 Draftsman 5.00 10.00 708.45 7,084.50 1,588.40 846.60 1,370.10 10,889.60
TOTAL 21,320.80 3,319.80 2,547.80 3,932.20 31,120.60
No. of days Complete the activity = 10.00 days
TOTAL LABOR COST = 31,120.60
D. EQUIPMENT UTILIZATION
EQUIPMENT USED: Mitsubishi Pick-Up
a. Driver = 817.05 x 10.00 days = 8,170.50
DISTANCE FROM AIMO TO PROJECT SITE (Round Trip): = 96.00 kms
a. Rental Cost = 21.00 /km x 96.00 kms x 10.00 = 20,160.00
b. Fuel Cost = 90.00 x 96.00 kms x 10.00 = 12,342.86
7.00 kms./ltr.
c. Oil Cost = 150.00 x 96.00 kms x 10.00 = 20,571.43
7.00 kms./ltr.
d. Spare Parts = = 10,000.00
TOTAL COST = 71,244.79
SUMMARY:
A. ESTABLISHMENT OF HORIZONTAL AND VERTICAL CONTROL POINTS = 91,927.50
B. PROFILE AND CROSS-SECTION = 91,927.50
C. COMPUTATION AND PLOTTING = 31,120.60
D. EQUIPMENT UTILIZATION = 71,244.79
E. OFFICE & EQUIPMENT SUPPLIES = 142,571.65
TOTAL COST FOR INSTITUTIONAL ACTIVITIES = 428,792.04
C I. CIVIL WORKS
1.A. CONTRACT WORKS Public Bidding 08/18/2023 08/19-09/07/23 08/27/23 8/9/2023 10/9/2023 09/11-14/23 09/16/2023 Construction of Project
Facilities, Canalization, and
A. PROJECT FACILITIES CALAMITY - 94,842.18 Protection Works that will
B. CONSTRUCTION SAFETY & HEALTH TD EGAY benefit 65 farmer
PROGRAM 106,005.44 beneficiaries
C. CANALIZATION 10,738,572.66
D. PROTECTION WORKS 3,623,686.52
TOTAL 15,000,000.00
EQUIPMENT COST:
Utilized: 200 HP Dozer; Rental (acel rate 2019) = 3,985.00 /hr
Capability = 130.00 sq.m./hr. (251 & above trees per Hectares)
Equipment Cost = 3,985.00 /hr = 30.65 /sq.m.
130.00 sq.m./hr.
SUMMARY:
Labor Cost = 2.45 = 2.45
Rental Cost = 30.65 = 30.65
DIRECT COST = 33.10 /sq.m.
OCM (12% of DC) = 3.97 /sq.m.
PROFIT (8% of DC) = 2.65 /sq.m.
VAT (5% of DC, OCM, PROFIT) = 1.99 /sq.m.
UNIT COST = 41.71 /sq.m.
EQUIPMENT:
Utilized: 135 HP Grader; Rental (Acel rate 2019) = 3,267.00 /hr
Capability = 80.00 sq.m./hr.
Equipment Cost = 3,267.00 /hr = 40.84 /sq.m.
80.00 cu.m./hr.
B. SPREADING
LABOR COST:
Utilized: 135 HP Grader; Rental (Acel rate 2019) = 3,267.00 /hr
Manpower = 1.00 Laborer
Rate = 400.00 /day
Capability = 80.00 sq.m./hr.
Labor Cost = 1.00 Laborer x 400.00 /day = 0.63 /sq.m.
8.00 hrs./day x 80.00 cu.m./hr.
EQUIPMENT:
Utilized: 135 HP Grader; Rental (Acel rate 2019) = 3,267.00 /hr
Capability = 80.00 sq.m./hr.
Equipment Cost = 3,267.00 /hr = 40.84 /sq.m.
80.00 hrs./day
C. COMPACTION
LABOR COST:
Utilized: 125HP Single Smooth Drum Vibratory; Rental (Acel rate 2019) = 1,846.00 /hr
Manpower = 1.00 Laborer
Rate = 400.00 /day
Capability = 80.00 sq.m./hr.
Labor Cost = 1.00 Laborer x 400.00 /day = 0.63 /sq.m.
8.00 hrs./day x 80.00 cu.m./hr.
EQUIPMENT:
Utilized: 10 Tons; Rental (Acel rate 2019) = 1,846.00 /hr
Capability = 80.00 sq.m./hr.
Equipment Cost = 1,846.00 /hr = 23.08 /sq.m.
80.00 hrs./day
SUMMARY:
Labor Cost = 0.63 + 0.63 + 0.63 = 1.89 /sq.m.
Equipment Cost = 40.84 + 40.84 + 23.08 = 104.76 /sq.m.
ESTIMATED DIRECT COST = 106.65 /sq.m.
OCM (12% of DC) = 12.80 /sq.m.
PROFIT (8% of DC) = 8.53 /sq.m.
VAT (5% of DC, OCM, PROFIT) = 6.40 /sq.m.
TOTAL UNIT COST = 134.38 /sq.m.
A. QUARRYING/STOCKPILE
Utilized: 200 HP Dozer; Rental (acel rate 2019) = 3,985.00 /hr
Manpower = 1.00 Laborer
Labor Rate = 400.00 /day
Capability = 70.00 cu.m./hr.
LABOR COST:
Labor Cost = 1.00 Laborer x 400.00 /day = 0.71 /cu.m.
8.00 hrs./day x 70.00 cu.m./hr.
B. LOADING
Utilized: Loader; Rental (acel rate 2019) = 1,681.00 /hr
Manpower = 1.00 Laborer
Labor Rate = 400.00 /day
Capability = 75.00 cu.m./hr.
LABOR COST:
Labor Cost = 1.00 Laborer x 400.00 /day = 0.67 /cu.m.
8.00 hrs./day x 75.00 cu.m./hr.
EQUIPMENT COST:
Rental = 1,681.00 /hr = 22.41 /cu.m.
75.00 hrs./day
CYCLE TIME:
With Load : 30.00 kms./trip x 60.00 min./hr. = 51.43 mins./trip
35.00 km./hr.
W/o Load : 30.00 kms./trip x 60.00 min./hr. = 40.00 mins./trip
45.00 km./hr.
Total = 91.43 mins./trip
or 1.52 hrs./trip
Page 15 of 66
5.00 trip/day x 6.00 cu.m./trip
EQUIPMENT COST:
Rental = 1,265.00 /hr. x 1.52 hrs./trip = 321.27 /cu.m.
6.00 cu.m./trip
Page 16 of 66
D. COMPACTION
LABOR COST:
Utilized: 10 Tons; Rental (Acel rate 2019) = 1,846.00 /hr
Manpower = 1.00 Laborer
Rate = 400.00 /day
Capability = 60.00 cu.m./hr.
Labor Cost = 1.00 Laborer x 400.00 /day = 0.83 /cu.m.
8.00 hrs./day x 60.00 cu.m./hr.
EQUIPMENT:
Utilized: 10 Tons; Rental (Acel rate 2019) = 1,846.00 /hr
Capability = 60.00 cu.m./hr.
Equipment Cos = 1,846.00 /hr = 30.77 /cu.m.
60.00 hrs./day
SUMMARY:
Base Cost = 650.00 = 650.00
Local Tax = 50.00 = 50.00
Labor Cost = 15.54 = 15.54
Rental Cost = 374.45 = 374.45
ESTIMATED DIRECT COST = 1,089.99 /cu.m.
OCM (12% of DC) = 130.80 /cu.m.
PROFIT (8% of DC) = 87.20 /cu.m.
VAT (5% of DC, OCM, PROFIT) = 65.40 /cu.m.
TOTAL UNIT COST = 1,373.39 /cu.m.
Page 17 of 66
VOLUME COMPUTATION
SALVACION MACLIT CIS
LUNA, APAYAO
I. TEMPORARY WORKS
a. Project Billboard = 1.00 lot
b. Bunkhouse = 1.00 lot
ManHole
Floor Slab = 0.15 x 1.30 x 1.30 x 2.00 = 0.51
Side Wall = 0.15 x 1.30 x 3.47 x 2.00 x 2.00 = 2.71
= 0.15 x 1.30 x 2.10 x 2.00 x 2.00 = 1.64
= 0.15 x 1.30 x 0.42 x 2.00 x 2.00 = 0.33
Fillet = 1.30 x 0.15 x 0.15 x 4.00 = 0.06
2.00
ManHole Cover = 0.15 x 1.30 x 1.30 x 2.00 = 0.51
Groove = 0.05 x 0.05 x 1.30 x 2.00 x 2.00 = 0.01
24.04 cu.m.