CRONOGRAMA DE ADQUISICIÓN DE MATERIALES / INSUMOS

: CREACIÓN DE PISTAS Y VEREDAS DE LA AV. 8 DE MAYO DEL CENTRO POBLADO MENOR DE COCHAPAMPA, DISTRITO DE SAN FRANCISCO DE ASIS DE YARUSYACAN, PROVINCIA Y REGIÓN
PROYECTO PASCO
UBICACIÓN : DISTRITO : S.F.A. DE YARUSYACAN
: PROVINCIA : PASCO FECHA : AGOSTO 2012
: DEPARTAMENTO : PASCO LUGAR: COCHAPAMPA

PERIODO PERIODO PERIODO PERIODO


Item Nº Descripcion / Insumos UND CANTIDAD PRECIO S/. MONTO S/. 1º MES 2º MES 3º MES 4º MES
1° DESEMBOLSO 1° DESEMBOLSO 1° DESEMBOLSO 1° DESEMBOLSO

MATERIALES / INSUMOS
1.00 ALAMBRE NEGRO RECOCIDO # 8 kg 738.32 4.50 3,322.44 830.61 830.61 830.61 830.61
2.00 CLAVOS PARA MADERA C/C 2 1/2" kg 161.97 4.50 728.87 182.22 182.22 182.22 182.22
3.00 CLAVOS PARA MADERA C/C 3" kg 762.93 5.30 4,043.53 1,010.88 1,010.88 1,010.88 1,010.88
4.00 CLAVOS Fo No C/C 3/4" kg 0.80 5.30 4.24 1.06 1.06 1.06 1.06
5.00 ALAMBRE NEGRO N°16 kg 41.23 4.50 185.54 46.38 46.38 46.38 46.38
6.00 ALAMBRE NEGRO N°8 kg 64.79 4.50 291.56 72.89 72.89 72.89 72.89
7.00 ACERO CORRUGADO 5/8" kg 193.54 3.40 658.04 164.51 164.51 164.51 164.51
8.00 ACERO CORRUGADO 1/2" kg 1,973.42 3.20 6,314.94 1,578.74 1,578.74 1,578.74 1,578.74
9.00 ACERO CORRUGADO PROMEDIO kg 735.30 3.80 2,794.14 698.54 698.54 698.54 698.54
10.00 ACERO DE CONSTRUCCION LISO 1/2" kg 2,522.42 3.20 8,071.74 2,017.94 2,017.94 2,017.94 2,017.94
11.00 ARENA FINA m3 127.95 102.58 13,125.11 3,281.28 3,281.28 3,281.28 3,281.28
12.00 PIEDRA CHANCADA DE 1/2" m3 1,239.55 102.58 127,153.04 31,788.26 31,788.26 31,788.26 31,788.26
13.00 PIEDRA SELECCIONADA m3 10.72 60.00 643.20 160.80 160.80 160.80 160.80
14.00 ARENA GRUESA m3 1,195.02 75.85 90,642.27 27,192.68 18,128.45 27,192.68 18,128.45
15.00 MATERIAL CLASIFICADO PARA BASE m3 3.97 60.00 238.20 59.55 59.55 59.55 59.55
16.00 MATERIAL DE RELLENO m3 465.59 15.00 6,983.85 1,745.96 1,745.96 1,745.96 1,745.96
17.00 PIEDRA GRANDE m3 359.68 80.00 28,774.40 7,193.60 7,193.60 7,193.60 7,193.60
18.00 ADOQUINES DE CONCRETO HEXAGONALES m2 2,456.82 26.00 63,877.32 15,969.33 15,969.33 15,969.33 15,969.33
19.00 MATERIAL AFIRMADO m3 3,659.21 25.00 91,480.25 22,870.06 22,870.06 22,870.06 22,870.06
20.00 ALCANTARILLA METALICA 0=24" C=16 m 32.50 412.50 13,406.25 3,351.56 3,351.56 3,351.56 3,351.56
21.00 PLACA RECORDATORIO und 1.00 560.00 560.00 140.00 140.00 140.00 140.00
22.00 CEMENTO PORTLAND TIPO I (42.5KG) BOL 22,804.97 18.20 415,050.45 83,010.09 124,515.14 103,762.61 103,762.61
23.00 GUIA m 1,615.61 2.50 4,039.03 1,009.76 1,009.76 1,009.76 1,009.76
24.00 FULMINANTE und 2,154.14 5.00 10,770.70 2,692.68 2,692.68 2,692.68 2,692.68
25.00 DINAMITA kg 430.83 6.50 2,800.40 700.10 700.10 700.10 700.10
26.00 CINTA DE SEGURIDAD DE OBRA m 1,535.10 1.50 2,302.65 575.66 575.66 575.66 575.66
27.00 TACHO DE BASURA + PARANTES INC LOGO und 18.00 150.00 2,700.00 675.00 675.00 675.00 675.00
28.00 BARRENO 5' X 1/8" und 8.62 175.00 1,508.50 377.13 377.13 377.13 377.13
29.00 SEÑALIZACION PREVENTIVA gln 10.00 320.00 3,200.00 800.00 800.00 800.00 800.00
30.00 MANTENIMIENTO DE RED DE AGUAS NEGRAS GLB 1.00 7,500.00 7,500.00 1,875.00 1,875.00 1,875.00 1,875.00
31.00 MANTENIMIENTO DE RED DE AGUA POTABLE GLB 1.00 8,500.00 8,500.00 2,125.00 2,125.00 2,125.00 2,125.00
32.00 MANTENIMIENTO DE RED DE AGUAS PLUVIALES GLB 1.00 10,500.00 10,500.00 2,625.00 2,625.00 2,625.00 2,625.00
33.00 FLETE TERRESTRE GLB 1.00 13,500.00 13,500.00 3,375.00 3,375.00 3,375.00 3,375.00
CRONOGRAMA DE ADQUISICIÓN DE MATERIALES / INSUMOS

: CREACIÓN DE PISTAS Y VEREDAS DE LA AV. 8 DE MAYO DEL CENTRO POBLADO MENOR DE COCHAPAMPA, DISTRITO DE SAN FRANCISCO DE ASIS DE YARUSYACAN, PROVINCIA Y REGIÓN
PROYECTO PASCO
UBICACIÓN : DISTRITO : S.F.A. DE YARUSYACAN
: PROVINCIA : PASCO FECHA : AGOSTO 2012
: DEPARTAMENTO : PASCO LUGAR: COCHAPAMPA

PERIODO PERIODO PERIODO PERIODO


Item Nº Descripcion / Insumos UND CANTIDAD PRECIO S/. MONTO S/. 1º MES 2º MES 3º MES 4º MES
1° DESEMBOLSO 1° DESEMBOLSO 1° DESEMBOLSO 1° DESEMBOLSO

34.00 MOVILIZACION Y DESMOVILIZACION DE EQUIPO GLB 1.00 10,500.00 10,500.00 2,625.00 2,625.00 2,625.00 2,625.00
35.00 HORMIGON m3 449.79 85.75 38,569.49 9,642.37 9,642.37 9,642.37 9,642.37
36.00 HORMIGON (PUESTO EN OBRA) m3 2.99 70.00 209.30 52.33 52.33 52.33 52.33
37.00 AGUA m3 51.47 5.00 257.35 64.34 64.34 64.34 64.34
38.00 CARTEL DE OBRA S/DISEÑO INST Y TRANS. und 1.00 560.00 560.00 140.00 140.00 140.00 140.00
39.00 PRUEBAS DE CALIDAD DE CONCRETO ROTURA und 12.00 20.00 240.00 60.00 60.00 60.00 60.00
40.00 PRUEBA : PROCTO MODIFICADO Y DENS. CAMPO und 22.00 180.00 3,960.00 990.00 990.00 990.00 990.00
41.00 DISEÑO DE MEZCLA f'c=175 kG/CM2 und 1.00 250.00 250.00 62.50 62.50 62.50 62.50
42.00 MADERA TORNILLO p2 3,296.01 3.20 10,547.23 2,636.81 2,636.81 2,636.81 2,636.81
43.00 TRIPLAY DE 6 MM m2 2.80 48.00 134.40 33.60 33.60 33.60 33.60
44.00 MADERA TORNILLO O SIMILAR p2 10,490.73 3.20 33,570.34 8,392.58 8,392.58 8,392.58 8,392.58
45.00 REJILLA m 36.00 25.00 900.00 225.00 225.00 225.00 225.00
46.00 THINER gln 87.40 22.00 1,922.80 480.70 480.70 480.70 480.70
47.00 BREA kg 1,392.36 1.35 1,879.69 469.92 469.92 469.92 469.92
48.00 PETROLEO gln 24.29 12.10 293.91 73.48 73.48 73.48 73.48
49.00 PINTURA ESMALTE PARA TRAFICO gln 159.82 38.00 6,073.16 1,518.29 1,518.29 1,518.29 1,518.29
50.00 TEKNOPOR DE 1" x 4' x 8' pln 4,649.67 1.10 5,114.64 1,278.66 1,278.66 1,278.66 1,278.66
51.00 TUBO PVC SAL 3/4" X 3M und 2.76 6.50 17.94 4.49 4.49 4.49 4.49

MANO DE OBRA
1.00 TOPOGRAFO hh 675.15 12.50 8,439.38 2,109.84 2,109.84 2,109.84 2,109.84
2.00 OPERARIO hh 10,748.29 11.30 121,455.68 30,363.92 30,363.92 30,363.92 30,363.92
3.00 OFICIAL hh 8,813.67 8.75 77,119.61 19,279.90 19,279.90 19,279.90 19,279.90
4.00 PEON hh 33,229.41 7.50 249,220.58 62,305.14 62,305.14 62,305.14 62,305.14
4.00 CAPACITADORES hh 21.68 200.00 4,336.00 1,084.00 1,084.00 1,084.00 1,084.00

EQUIPOS Y HERRAMIENTAS
1.00 TEODOLITO hm 41.27 9.50 392.07 98.02 98.02 98.02 98.02
2.00 HERRAMIENTAS MANUALES %MO 0.00 0.00 0.00 0.00 0.00
3.00 MIRAS Y JALONES hm 633.88 5.00 3,169.40 792.35 792.35 792.35 792.35
4.00 VOLQUETE DE 15 M3 hm 341.56 150.00 51,234.00 12,808.50 12,808.50 12,808.50 12,808.50
5.00 COMPACTADOR VIBR. TIPO PLANCHA 4 HP hm 624.13 15.00 9,361.95 2,340.49 2,340.49 2,340.49 2,340.49
6.00 CARGADOR S/LLANTAS 80-95 HP 1.5-1.75 YD3 hm 169.52 190.00 32,208.80 8,052.20 8,052.20 8,052.20 8,052.20
CRONOGRAMA DE ADQUISICIÓN DE MATERIALES / INSUMOS

: CREACIÓN DE PISTAS Y VEREDAS DE LA AV. 8 DE MAYO DEL CENTRO POBLADO MENOR DE COCHAPAMPA, DISTRITO DE SAN FRANCISCO DE ASIS DE YARUSYACAN, PROVINCIA Y REGIÓN
PROYECTO PASCO
UBICACIÓN : DISTRITO : S.F.A. DE YARUSYACAN
: PROVINCIA : PASCO FECHA : AGOSTO 2012
: DEPARTAMENTO : PASCO LUGAR: COCHAPAMPA

PERIODO PERIODO PERIODO PERIODO


Item Nº Descripcion / Insumos UND CANTIDAD PRECIO S/. MONTO S/. 1º MES 2º MES 3º MES 4º MES
1° DESEMBOLSO 1° DESEMBOLSO 1° DESEMBOLSO 1° DESEMBOLSO

7.00 TRACTOR DE ORUGAS DE 190-240 HP hm 136.35 260.00 35,451.00 8,862.75 8,862.75 8,862.75 8,862.75
8.00 PIONGER hm 984.66 50.00 49,233.00 12,308.25 12,308.25 12,308.25 12,308.25
9.00 MOTONIVELADORA DE 125 HP hm 60.64 130.00 7,883.20 1,970.80 1,970.80 1,970.80 1,970.80
10.00 MEZCLADORA CONCRETO TAMBOR 18HP 11P3 hm 1.14 15.50 17.67 4.42 4.42 4.42 4.42
11.00 MEZCLADORA CONCRETO TROMPO 8 HP 9 P3 hm 1,047.59 18.00 18,856.62 4,714.16 4,714.16 4,714.16 4,714.16
12.00 RODILLO VIBRATORIO LISO AUTOPROPLUSADO hm 55.41 160.00 8,865.60 2,216.40 2,216.40 2,216.40 2,216.40
13.00 NIVEL DE INGENIERO hm 633.88 3.50 2,218.58 554.65 554.65 554.65 554.65
14.00 TEODOLITO hm 316.94 9.50 3,010.93 752.73 752.73 752.73 752.73

COSTO DIRECTO TOTAL 1,696,816.55 407,983.73 440,424.55 428,736.25 419,672.02