WORKS DEPARTMENT
24.
It has been decided at Government level to exhibit Asset Display Board to boost up public
awareness & for preservation of public property. Accordingly, the estimate has been prepared as per the
instruction of higher authority.
The rates taken in the estimate are based on the current state schedule of rates (SR-2022) and
lowest local market rate. The estimate also includes transportation charges, enhanced labour rate, etc.
Note :
1 Labour rates for un-skilled, Semi-skilled, Skilled and Highly skilled as are to be fixed from time to time by Labour
Department under Minimum Wages Act shall prevail in respect of any category what so ever.
2 The rates for above four categories of labour are inclusive of weekly day of rest.
3 An adult Employee shall work for 8 (Eight) hours per day including half-an-hour of rest.
Sl No. Description Unit Rate in (Rs.)
E. Other Category (Note covered by the Notification of Labour & Employment
Department).
01 Boring Mistry (Special) Per Day 495.00
02 Winch operator Per Day 495.00
03 Well Sinker (Special) Per Day 495.00
04 Helper to Well Sinker Per Day 435.00
05 Computer Programmer / Analyzer Per Month 16493.00
06 Computer Operator Per Month 12690.00
07 Helper to operator of Heavy construction Machineries Per Month 11281.00
08 Mechanic for Heavy construction Per Month 14137.00
09 Helper to mechanic for heavy construction machines. Per Month 11781.00
10 Operator for Heavy construction Per Month 14137.00
11 Junior Research Assistant (Technical Assistant) Per Month 12690.00
V- HIRE CHARGES OF PLANTS AND MACHINERIES
SI. DESCRIPTIONS USAGE RATES IN RS.
No. Machine Activity Output Unit Rate
1 DozerD-50-A15 Spreading 200 Cum/Hour per hour 2834.00
Cutting 100 Cum/Hour per hour
Cleaning 150 Cum/Hour per hour
2 Dozer D-80-A 12 Spreading 300 Cum/Hour per hour 3898.96
Cutting 150 Cum/Hour per hour
Cleaning 250 Cum/Hour per hour
3 Motor Grader 3.35 meter blade Clearing 200 Cum/Hour per hour 2394.39
Spreading 200 Cum/Hour per hour
GSB 50 Cum/Hour per hour
WMM 50 Cum/Hour per hour
4 Tractor with ordinary grader per hour 447.31
5 Hydraulic Excavator of 1cum bucket Soil ordinary 60 Cum/Hour per hour 1300.16
Soil Marshy 60 Cum/Hour per hour
Soil unsuitable 60 Cum/Hour per hour
6 Hydraulic Excavator of 2cum bucket Soil per hour 2891.34
7 Front End loader 1 cum bucket capacity Soil loading 60 Cum/Hour per hour 804.86
Aggregate loading 25 Cum/Hour per hour
8 Tipper-5cum Transportation of soil, 5.5 Cum per km. 37.15
GSB, WMM, Hotmix etc. per tonne.km 3.86
per hour 900.84
9 Vibratory Roller 8-10 tonne Earth/soil 100 Cum/Hour per hour 1538.54
GSB 60 Cum/Hour per hour
WMM 60 Cum/Hour per hour
10 Smooth wheeled Roller 8 -10 tonne Soil compaction 70 Cum/Hour per hour 524.70
BM compaction 25 Cum/Hour per hour
11 Sheep foot Roller Soil compaction per hour 100.60
12 Truck mounted water tanker Water transport 6 KL per hour 900.84
13 Tractor Pulling 50 HP per hour 357.55
14 Rotavator Mixing 25 Cum/Hour per hour 16.00
15 Ripper Scarifying 60 Cum/Hour per hour 21.00
16 Air Compressor General purpose 170/250 cfm per hour 585.00
17 Diesel Compressor 400 cfm per hour 1324.94
18 Diesel Compressor 500 cfm per hour 1039.82
19 Electrical Compressor 500 cfm per hour 769.26
20 Wet Mix Plant 60 TPH Wet Mix 25 Cum/Hour per hour 1400.00
21 Wet Mix Plant 75 TPH Wet Mix 34 Cum/Hour per hour 1700.00
22 Mechanical broom hydraulic Surface cleaning 1250 Sqm/Hour per hour 356.00
23 Bitumen pressure distributor Applying bitumen tack 1750 Sqm/Hour per hour 1071.10
coat
24 Emulsion pressure distributor Applying emulsion tack 1750 Sqm/Hour per hour 798.68
coat
25 Hotmix plant -1 20 TPH DBM/BM/SDC/ Premix 40 Cum/Hour per hour 23372.17
26 Hotmix plant -1 00 TPH DBM/BM/SDC/ Premix 30 Cum/Hour per hour 17284.56
27 Hotmix plant -60 to 90TPH DBM/BM/SDC/ Premix 25 Cum/Hour per hour 13822.09
28 Hotmix plant -40 to 60TPH DBM/BM/SDC/Premi X 17 Cum/Hour per hour 11066.95
29 Hotmix plant -8 to 10TPH Premix Cum/Hour per hour 1586.51
30 Paver Finisher Hydrostatic with sensor control 1 00 Paving of DBM IBM 40 Cum/Hour per hour 1724.97
TPH /SDC/Premix
31 Paver Finisher Mechanical 100 TPH Paving of WMM/PMC 40 Cum/Hour per hour 1143.90
Paving of DLC 30 Cum/Hour per hour
32 Paver Finisher Mechanical Paving of DLC 75 Cum/Hour per hour 1816.61
33 Hydraulic Chips Spreader Surface Dressing 1500 Sqm/Hour per hour 1480.62
34 Tandem Road Roller Rolling of Asphalt 30 Cum/Hour per hour 1142.30
surface
35 Pneumatic Road Roller Rolling of Asphalt 25 Cum/Hour per hour 1026.27
surface
36 Pot hole repair machine Repair of pot holes 4 Cum/Hour per hour 632.92
37 Bitumen boiler oil fired Bitumen spraying 1500 Litre per hour 198.11
38 Tar boiler Bitumen spraying per hour 114.54
39 GSB Plant 50 cum Producing GSB 40 Cum/Hour per hour 1037.04
40 Mastic Cooker Mastic Wearing Coat 1 tonne per hour 2454.85
41 Batching and Mixing plant 15-20cum Concrete Mixing 13 Cum/Hour per hour 1836.26
42 Batching and Mixing plant SOcum Concrete Mixing 20 Cum/Hour per hour 2144.23
43 Batching and Mixing plant 112.5cum Concrete Mixing 75 Cum/Hour per hour 3421.29
44 Batching and Mixing plant 262.5cum Concrete Mixing 175 Cum/Hour per hour 8791.61
72 Concrete Paver Finisher with 40HP Motor Paving of Concrete 175 Cum/Hour per hour 25056.20
Surface
73 Prestressing Jack with Pump & Access Stressing of Steel Wires/Stands per hour 360.00
Aluminium sheeting or ACP fixed with high intensity retro-reflective 13.500 Sqm @ Rs. 5907.17 / Sqm = Rs. 79746.80
sheeting of type-IV
1x4.50x3.00m=13.50Sqm
Add 2 percent of cost of materials for drilling holes, nuts, bolts, = Rs. 1848.71
fabrication cost, etc.
b) Machineries
Tractor - Trolly 5.76 0.020 Hours @ Rs. 357.55 / Hour = Rs. 41.19
(B) Rs. 94943.86
Overhead Charges @ 7.5% on 'B' = Rs. 4272.47
Contractor's Profit @ 7.5% on 'B' = Rs. 4272.47
(C) Rs. 8544.94
Total (A+B+C)= Rs. 108058.83
Add Labour Cess @ 1% = Rs. 1080.59
Rs. 109139.42 / Each
Link Analysis of Rates
01. Earth work in Hard Soil or Gravelly Soil within 50m initial lead and 1.5m initial lift
including rough dressing and breaking clods to maximum 5cm to 7cm and laying
in layers not exceeding 0.3m in depth and as per the direction of Engineer-in-
charge.
Unit = Cum Data for 100 Cum.
A) Upto 1.5 M Depth
a) Labour
Man Mulia 21.50 Nos @ Rs. 345.00 / Each = Rs. 7417.50
Woman Mulia 21.50 Nos @ Rs. 345.00 / Each = Rs. 7417.50
Overhead charges @ 7.5% = Rs. 1112.63
Contractor's Profit @ 7.5% = Rs. 1112.63
Rs. 17060.26 / % Cum
Add 20% extra for excavation of foundation. = Rs. 3412.05
Rs. 20472.31 / % Cum
Rate per 1 Cum = = Rs. 204.72 / Cum
02. CC work of M-15 grade including cost of Centering and shuttering using 20mm
and down grade size black hard granite (Crusher Broken) chips of approved
quality from approved quary including the cost of all materials, cost of all labour,
conveyance, taxes, loading, unloading, T&P, royalty, labour cess, all complete as
Unit = Cum Data per 1.00 Cum
Using Concrete Mixer
a) Materials
20mm size granite chips. 0.54 Cum @ Rs. 1382.29 / Cum = Rs. 746.44
10mm size granite chips. 0.36 Cum @ Rs. 1418.67 / Cum = Rs. 510.72
Sand (Screened & washed) 0.45 Cum @ Rs. 75.86 / Cum = Rs. 34.14
Cement 2.80 Qntl @ Rs. 515.44 / Qntl = Rs. 1443.23
b) Labour
Mate 0.06 Nos @ Rs. 385.00 / Each = Rs. 23.10
Mason 2nd class 0.10 Nos @ Rs. 435.00 / Each = Rs. 43.50
Mazdoor 1.33 Nos @ Rs. 345.00 / Each = Rs. 458.85
c) Machinery
Concrete Mixer 0.40 Hours @ Rs. 229.55 / Hour = Rs. 91.82
Generator 0.40 Hours @ Rs. 700.00 / Hour = Rs. 280.00
Rs. 3631.80 / Cum
Overhead charges @ 7.5% = Rs. 272.39
Contractor's Profit @ 7.5% = Rs. 272.39
e) Carriage
Coarse aggrigate. 0.90 Cum @ Rs. 764.95 / Cum = Rs. 688.46
Sand (Screened & washed) 0.45 Cum @ Rs. 645.76 / Cum = Rs. 290.59
Cement 2.80 Qntl @ Rs. 24.79 / Qntl = Rs. 69.41
Rs. 5225.04 / Cum
03. Providing and Painting two coats of synthetic enamel paint of approved quality,
make and shade on Iron / Wood Works over one coat of primer including the cost
of sand papering, surface polishing, cost of all materials, cost of labour,
conveyance, taxes, loading, unloading, scaffolding, T&P, etc. as per direction of
Engineer-in-charge.
figure/ words) % excess/ less over/ than the estimated cost of Rs.2,69,333/-
Page 1
COMPARATIVE COST OF CEMENT (AS ON 9.5.2023)
Rate quoted by
UltraTech Rate Quoted By Rate Quoted By
SI.No. Description Unit (AdityaBirla) ACC Cement Dalmia Cement. Average Cost
Cement