Improvement of Dhangidisole-Deuli-Baghra-Morada Road (DDBM) from Km 0.000 to Km 16.

744 for the year 2022-23 in


the district of Mayurbhanj under State Plan
GENERAL ABSTRACT
SL. NO DESCRIPTION OF ITEM AMOUNT
1 Road Proper 16.744 Km (Design Length) Rs 24,83,73,592.30
2 T/Y Junction Rs 21,33,604.83
3 Dismentaling of existing structure Rs 5,21,344.54
4 Road safety & Furnitures Rs 50,93,428.03

5 Hume Pipe Culvert -28 Nos


i Reconstruction of HP Culvert (1x1200 mm) 19Nos Rs 58,95,857.14
ii Reconstruction of HP Culvert (2x1200 mm) 6Nos Rs 28,50,680.95
iii Widening of HP Culvert (2x1000 mm) 2Nos Rs 5,68,138.07
iv Widening of HP Culvert (5x1000 mm) 1Nos Rs 8,85,843.25

6 Box Culvert - 3 Nos


i Reconstruction of Box Culvert (1x3x2.0) 3Nos Rs 82,54,950.94

7 Drain cum Footpath in Built Up Area 1800Mtr Rs 1,24,60,966.79


8 Toe Wall 2mtr Height 425Mtr Rs 42,33,067.83
9 Retaining Wall 2.7 mtr Height 150Mtr Rs 49,48,400.61
Sub Total Rs 29,62,19,875.28
Add 9% SGST Rs 2,66,59,788.77

Add 9% CGST Rs 2,66,59,788.77

Add QUALITY CONTROL 1.00% Rs 29,62,198.75

Add CONTIGENCY 1.00% Rs 29,62,198.75

Add Cost for Utility Shifting and Relocation of Public Utilities Tree Cutting & Avenue
Rs 30,00,000.00
Plantation (L.S)

Total Project Cost Rs 35,84,63,850.33


SAY Rs 35,84,64,000.00
SAY Rs. 35.85
CRORES

Assistant Engineer Executive Engineer Executive Engineer


Baripada (R&B) Section-I Baripada(R&B) Sub Division-I Mayurbhanj(R&B) Division

Chief Construction Engineer


Eastern (R&B) Circle
Balasore