SCHEME NO -00

OFFICE OF THE DISTRICT MUNICIPAL CORPORATION


MALIR KARACHI

Name of Work:

PROVIDING AND LAYING SEWERAGE LINE AT FUTURE COLONY B


AREA IN STREET NO 9, UC07 QUAID ABAD DMC MALIR KARACHI

FACE SHEET

Part Amount

Cost of Sewerage Works 995,000

Total Amount 995,000

Sub Engineer
District Municipal Corportion Malir
(B&R)

Assistant Executive Engineer Executive Engineer


District Municipal Corportion Malir District Municipal Corporation Malir
(B&R) (B&R)

Superientending Engineer
District Municipal Corportion Malir
SCHEME NO -00
COST ESTIMATE
Name of Work:
PROVIDING AND LAYING SEWERAGE LINE AT FUTURE COLONY B AREA IN STREET NO 9, UC07 QUAID
ABAD DMC MALIR KARACHI
S.No Items No. Length Breadth Depth Quantity Amount

Excavation for pipe lines in trenches


and pits in all kind of soil ic trìmming
and dressing sides to true alignment
and shape leveling off beds of trenches
to correct level and grade, cutting joint
holes and disposal of surplus earth
1 within a one chain as directed by
Engineer Incharge. Providing fence
guards, lights, flags and temporary
crossings for non-vehicular traffic
where ever required lift upto 5 ft.
(1.52m) and lead up to one chain
(30.5m).P.H.S.I.NO/P.4715
12" dia pipe
Street No 9 7 100 3 5.5 = 11550
1 60 3 5.5 = 990
Quantity 12540
12540 @ RATE. 4650 per % 0 Cft Rs 58,311.00

Providing /Laying R.C.C Pipe Line of


A.S.T.M C-76-62 T/C-76- 70 of class
I wall B and fixing in trench ilc cutting
fitting and jointing with rubber ring i/c
testing with water to specified
2 pressure. (P.H.S. Item No.B-1(b) P-
Page No.17).
12" dia pipe
Street No 9 7 100 = 700
1 60 = 60
Quantity 760
760 @ RATE. 412 per P.Rft Rs 313,120.00

Refilling of the excavated stuff in


trenches 6" thick layers i/c watering
3
ramming to full compacting etc
complete (P.H.S.I. No.24, P177).
Quantity same as item no 01 12540 90% = 11286
Quantity 11286
11286 @ RATE. 2760 per % 0 Cft Rs 31,149.36
Providing Manhole 4' feet internal dia
without RCC cover with C.I Frame 15
Kg and 5 feet clear depth 1:2:4 cast in
situ with in 9" thick wall, 1:4:8 C.C in
6ft dia and 6" inch thick in foundation,
1:2:4 C.C in benching, 1/2" thick
cement plaster with 1:3 cement mortar
4 on all inside wall surfaces of channel
and benching i/c making required nos
of main and branch channels, 3/4" dia
M.S Footrest @12" c/c i/e cost of
excavation in all kinds of soil,
backfilling and disposal of excavated
stuff etc complete as per design and
instruction of Engineer Incharge.
26 = 26
Quantity 26
26 @ RATE. 14529.29 per Each Rs 377,761.54

Add or deduct extra depth of manhole


5
etc.
10 = 10
Quantity 10
10 @ RATE. 2538.62 per P.Ft Rs 25,386.20
Manufacturing and supplying R.C.C
Ring slab of 21" dia inside 36" dia out
side 7.5" width and 6" thick i/c 3/8"
dia tor steel bars two concentric rings
with 3/8" dia 8 nos cross link bars
welded and two sunk type hooks cast
6 in a 1:1-1/2:3 concrete with embedded
15 Kg C.I frame. It will be transported
in perfect position i/c transportation
charges for an average lead of 20 Km
per trip from casting yard to town
office ( Minimum of 25 slabs of per
trip)
28 1 = 28
Quantity 28
28 @ RATE. 1906.6 per Each Rs 53,384.80
Manufacturing and supplying R.C.C
Manhole covers cast in 1:2:4 concrete
ratio 3"inch deep at center, reinforced
with 1/2" dia tor steel bars @ 4" c/c
7 etc, welded to 3/16" thick 2" wide
M.S. plate, two hooks of 3/8" dia tor
bar i/c compacting, curing and
transportation within ten miles. 21"
dia.
28 1 = 28
Quantity 28
28 @ RATE. 913.63 per Each Rs 25,581.64
TOTAL AMOUNT Rs. 884,694.54
Add 20% above on item no 2
62,624.00
Rs 313,120.00
TOTAL AMOUNT Rs. 947,318.54
Add SRB 5% 47,365.93
TOTAL AMOUNT Rs. 994,684.47
SAY AMOUNT Rs. 995,000.00

Sub Engineer
District Municipal Corporation Malir
(B&R)

Executive Engineer Assistant Executive Engineer


District Municipal Corporation Malir District Municipal Corporation Malir
(B&R) (B&R)