UJAHID DAM
WITH HDPE PIPE
ESTIMATED LENTH LENGTH
HDPE PIPE
DIFFRENCE TOTAL WORK TO BE
PER RFT
LENGTH DONE DONE
Executive Engineer
Small Dams Division
Islamabad
CONSTRUCTION OF MUJAHID DAM
Unit 100 ft
S.# Description No. Length Bredth Hight Qty Unit
2 RCC 1:2:4
a R.C.C 1:2:4
M.S pipe 30" dia 1 100 4.5 4.50 2025 Cft
Total 2025 Cft
Deduction of pipe
M.S pipe 30" dia 1 100 3.142(2.5) 2 /4 491 Cft
Net 1534 Cft
b R.C.C 1:2:4
M.S pipe 24" dia 1 100 4 4 1600 Cft
Total 1600 Cft
Deduction of pipe
M.S pipe 24" dia 1 100 3.142(2.0) 2 /4 314 Cft
Net 1286 Cft
3 Steel
a Steel for 30" dia
24.42kg/Rft detail attached Total 2442 Kg
c Steel for 24" dia
21.92 kg/Rft detail attached Total 2192 Kg
Total
30" dia M.S Pipe 671243 21.27 below 528470
24" dia M.S Pipe 386481 21.27below 304276.3
Composite Rate M.S pipe M.S pipe Rcc Conduit
30" dia M.S Pipe 8052 5284.70
24" dia M.S Pipe 5716.35 3042.76
Rate Amount
21.27%
Below
147.1464 225731.7
21.27%
Below
147.1464 189200.8
9000 219780
9000 197280
5284.70
3042.76
13336.70
8759.11
CONSTRUCTION OF MUJAHID DAM
ANALYSIS OF RATES 30" DIA HDPE PIPE
Providing laying, jointing and testing HDPE PIPE (PN 8)
MRS 2nd bi-annual 2020
G.Total 17079.61
Say Rs. 17080
inch
inch
inch
Remarks
707.2
5994.5
162.5
200.00
7064.20
#VALUE!
xecutive Engineer
mall Dams Division
CONSTRUCTION OF MUJAHID DAM
ANALYSIS OF RATES 30" DIA HDPE PIPE
Making arrangments, assembling, conducting water pressure test and disassembling pressure
devices and finshing pipe ends etc complete in all respect
(Two tests per Day)
MRS 2nd bi-annual 2020
Sr. Description QTY Unit Rate Amount
1 Cost of 2 No. End caps = 2x102000 =
204000. This caps can be used for 8 tests
For two tests = 2x(204000/8)= 51000 51000
2 Cost lof 4 No. joints as per analysis attached
4 No. 19653.4 78613.6
3 Bailing out water by pump for testing 687 %0Cft 504.70 346.73
4 Hire charges of compressor 8 hours a day
INPUT RATE EQ-20 8 Hrs 767.00 6136.00
5 Hire charges of wheel Tractor with water
tank. INPUT RATE EQ-19 8 Hrs 634.00 5072.00
Skilled Labour
INPUT RATE LB-024 2 P.day 786.00 1572.00
Un-Skilled Labour
INPUT RATE LB-015 6 P.day 689.00 4134.00
S.Total 146874.33
Add 10% Sundries
14687.43
Add 20% Contractor profit
29374.87
Cost of two tests Total 190936.63
Cost of one test 95468.31
(Frequency of Testing one Length in every
7th length) Rate per Linear ft 340.96
Certified that the rates provided in the analysis are compatible with
market rates.
Remarks
162.5 687.3125
24.00 9.61625
845.70 1538.6
1153.95
#VALUE!
Executive Engineer
Small Dams Division
CONSTRUCTION OF MUJAHID DAM
ANALYSIS OF RATES 30" DIA HDPE PIPE
Jointing HDPE pipe to correct alignment and grade
Daily Progress 160 ft
MRS 2nd bi-annual 2020
S.Total 60472.00
Add 10% Sundries
6047.20
Add 20% Contractor profit
12094.40
G.Total 78613.60
Certified that the rates provided in the analysis are compatible with
market rates.
Remarks
162.5 392.75
821.70 #VALUE!
#VALUE!
#VALUE!
Executive Engineer
Small Dams Division
CONSTRUCTION OF MUJAHID DAM
ANALYSIS OF RATES 24" DIA HDPE PIPE
Providing laying, jointing and testing HDPE PIPE (PN 8)
MRS 2nd bi-annual 2020
G.Total 9756.21
Say Rs. 9756
inch
inch
inch
Remarks
659.2
5377
162.5
24.00
6222.70
#VALUE!
xecutive Engineer
mall Dams Division
CONSTRUCTION OF MUJAHID DAM
ANALYSIS OF RATES 24" DIA HDPE PIPE
Making arrangments, assembling, conducting water pressure test and disassembling pressure
devices and finshing pipe ends etc complete in all respect
(Two tests per Day)
MRS 2nd bi-annual 2020
Sr. Description QTY Unit Rate Amount
1 Cost of 2 No. End caps= 2x50000= 100000.
This caps can be used for 8 tests
For two tests = 2x(100000/8)= 25000 25000
2 Cost lof 4 No. joints as per analysis attached
4 No. 18694.65 74778.6
3 Bailing out water by pump for testing 440 %0Cft 504.70 222.07
4 Hire charges of compressor 8 hours a day
INPUT RATE EQ-20 8 Hrs 767.00 6136.00
5 Hire charges of wheel Tractor with water
tank. INPUT RATE EQ-19 8 Hrs 634.00 5072.00
6 Skilled Labour
INPUT RATE LB-024 2 P.day 786.00 1572.00
7 Un-Skilled Labour
INPUT RATE LB-015 6 P.day 689.00 4134.00
S.Total 116914.67
Add 10% Sundries
11691.47
Add 20% Contractor profit
23382.93
Cost of two tests Total 151989.07
Cost of one test 75994.53
(Frequency of Testing one Length in every
7th length) Rate per Linear ft 271.41
Certified that the rates provided in the analysis are compatible with
market rates.
Remarks
25000
162.5 439.88
24.00 9.61625
845.70 1538.6
1153.95
#VALUE!
Executive Engineer
Small Dams Division
CONSTRUCTION OF MUJAHID DAM
ANALYSIS OF RATES 24" DIA HDPE PIPE
Jointing HDPE pipe to correct alignment and grade
Daily Progress 160 ft
MRS 2nd bi-annual 2020
S.Total 57522.00
Add 10% Sundries
5752.20
Add 20% Contractor profit
11504.40
G.Total 74778.60
Certified that the rates provided in the analysis are compatible with
market rates.
Remarks
162.5 392.75
821.70 #VALUE!
#VALUE!
#VALUE!
Executive Engineer
Small Dams Division