GENERAL ABSTRACT

S.No Description Area in Sq.ft Amount Rate/Sq.ft (Rs)


A Substructure
Strip Raft, Full Raft & Pile 1690
1 foundation & Basement 1271 Rs. 2,148,513

B SuperStructure
1 Stilt Floor (including Parking) 1271 Rs. 1,340,640 1055

2 First Floor 1499 Rs. 2,104,037 1404

3 Second Floor 1499 Rs. 2,104,037 1404

4 Third Floor 1499 Rs. 2,104,037 1404

5 Terrace 1499 Rs. 188,770 126

6 Head & Machine Room 378 Rs. 302,792 801

Total amount (A+B) Rs. 10,292,826


C/o to Next page
( Rupees One Crore two lac ninety two thousand eight hundred and twenty six only)

General Abstract 1 Elango Nagar


B/F Rs. 10,292,826

C. Services

7 Internal water Supply and plumbing and Sanitary lines


installation for (3 floor +1 Ground floor ) @6% on ( A+B ) Rs. 617,570

8 Internal Electrification Teakwood boxes + kundan


or Anchor or Vinay Switches @7.5% on ( A+B) Five three
phase supply Rs. 771,962

9 Interior Decoration (POP Cornice + Cuboard +shutter to all


Cuboards + semi modular kitchen to all floors @6% on (A+B) Rs. 617,570

10 External Service Connection (Electrical, sanitary & pannel board)


@5% on (A+B) Rs. 514,641

11 Provision for Lift (6 person Capacity) Lumpsum Rs. 900,000


( Tenative)

Provision for Anti Termite Chemical Treatment


12 (( 1494x4)+228) = 6204) Rs:7.50/sqft Rs. 46,530

13 Provision for swerage connection Rs. 50,000

14 Provision for 5inches deep bore well appx. 180feet


depth including the cost of 5inches pvc threaded
pipes (CS), 1.5HP submersible motor etc, complete
(Bill will be charged for the actual executed quantity
only)
Lumpsum Rs. 85,000

Provision for Elevation Work as per Architect's


15 Detailing Lumpsum Rs. 250,000

16 Over Head Tank (RCC)


with motor Lumpsum Rs. 125,000

17 Structural design & detailing Fees Lumpsum Rs. 45,000

18 Soil testing fees Lumpsum Rs. 20,000

Total Amount ( C ) Rs. 4,043,272

(Rupees Fourty Lac fourty three thousand two hundred seventy two only)

Total amount = A+B+C Rs. 14,336,098


Rs. 336,098
Rs. 14,000,000
(Rupees One Crore fourty lac only)

Notes:
The following items are not included :
1.) Compound wall with gate
2.) Water Supply & Electricity, Municipal charges etc., during construction period

General Abstract 2 Elango Nagar


is under client scope
3.) Cost of Demolition of Existing Building

General Abstract 3 Elango Nagar


A1

PILE, PILE CAP & BASEMENT

S.No Description Nos L B D Qty Rate unit Amount


(in Feet) (in Feet) (in Feet)
1 Pile :
Driving bored cast in situ piles of
450mm dia to a depth of 7.50M from the
virgin G.L. (Labour Only)
Pile 1 x 33 24.6 811.80
Sundries 0.20
812.00 229 rft 185,948
2 Earthwork:
Earthwork in excavation including disposal
of earth; disposed earth to be levelled and
neatly dressed.
Strip Raft 1 1 x 1 28 6 6 1008.00
Strip Raft 2 1 x 2 28 8 6 2688.00
Strip Raft 3 1 x 1 19 6 6 684.00
Full Raft RF1 1 x 1 22 15 6 1980.00
Grade beam 1 x 1 257 1.41 1.83 663.14
Sump 1 x 1 10.2 10.2 6 624.24
Sundries 0.04
7647.00 9 cft 68,823
3 Demolishing of pile

Breaking the Loose concrete portion of piles 1 x 33 1.76 1 5 290.40 75 cft 21,780
4 P.C.C:
P.C.C work: Providing and laying plain
cement concrete of 1:5:10 (1cement:
5 coarse sand: 10 graded stone aggregate)
including the cost of centering
and shuttering.
Strip Raft 1 1 x 1 28 6 0.33 55.44
Strip Raft 2 1 x 2 28 8 0.33 147.84
Strip Raft 3 1 x 1 19 6 0.33 37.62
Full Raft RF1 1 x 1 22 15 0.33 108.90
Below Grade beam 1 x 1 217 1.41 0.33 100.97
Hall 1 x 1 15.1 10 0.33 49.83
Kitchen 1 x 1 9 11 0.33 32.67
Passage 1 x 1 2.62 10 0.33 8.65
Bath & toilet 1 x 1 4 10 0.33 13.20
Bedroom 1 x 1 13.1 11 0.33 47.55
Satircase 1 x 1 96.45 0.33 31.83
Parking area 1 x 1 61.87 0.33 20.42
Sump 1 x 1 10.2 10.2 0.33 34.33
Sundries 0.53
690.00 135 cft 93,150

Substructure 3 Elango Nagar


A1

S.No Description Nos L B D Qty Rate unit Amount


5 P.C.C 1:5:10 brick jelly
P.C.C work: Providing and laying plain
cement concrete of 1:5:10 (1cement:
5 coarse sand: 10 graded Brick aggregate)
including the cost of centering
and shuttering.
Bath & toilet 1 x 1 4 10 1 40.00
40.00 135 cft 5,400
6 Sand Filling:
Supplying and filling with river sand
including watering, ramming, consolidating
and dressing.
Qty as per Item No 3 690.00 51 cft 35,190

7 Quarry dust filling:


Supplying and Filling the Quarry Dust
and proper compaction with watering.
Hall 1 x 1 15.1 10 3 453.00
Kitchen 1 x 1 9 11 3 297.00
Bedroom 1 x 1 13.1 11 3 432.30
Bath & toilet (incl Passage) 1 x 1 7 10 3 210.00
Satircase 1 x 1 96.45 2 192.90
Parking area 1 x 1 641.87 2 1283.74
Sundries 0.75
2870.00 29 cft 83,230
8 Flooring in parking area:
Cement Concrete Flooring PCC 1:2:4 40
to 50mm thick with neat cement finish
Parking area 1 x 1 641.87
Sundries 0.13
642.00 48 Sqft 30,816
9 Reinforced Concrete Work:
R.C.C 1:1.5:3 mix using 20 mm stone
jelly for roof slab,lintel,roof slab, lintel
and sunshade excluding fabrication of
RCC items and including cost and
conveyance of all materials labour etc.,
Pile (450mm) 1 x 33 1.76 24.6 1428.77
Strip Raft 1 1 x 1 26.75 5 1.25 167.19
Strip Raft 1 Beam 1 x 1 26.75 1.5 1 40.13
Strip Raft2 1 x 2 26.75 6.5 1.25 434.69
Strip Raft 2 Beam 1 x 2 26.75 1.5 1 80.25
Strip Raft3 1 x 1 17.50 5 1.25 109.38
Strip Raft 3 Beam 1 x 1 17.50 1.25 1 21.88
Full Raft RF1 1 x 1 20.50 13 1.5 399.75
Full Raft RF1 Beam 1 x 2 20.50 1.5 1 61.50
Column 1 x 15 0.75 1.5 5 84.38
Column (lift) 1 x 4 0.75 0.75 5 11.25
Grade beam 1 x 1 216.75 0.75 1.25 203.20
Plinth beam 1 x 1 268 0.75 0.75 150.75
Sump Base 1 x 1 10.2 10.2 0.5 52.02
Sump Wall Peri 1 x 1 34.8 0.5 6 104.40
Sump Top slab 1 x 1 9.0 9.0 0.5 40.50
Sundries 0.63
3391.00 200 cft 678,200
10 Reinforcement:
Reinforcement for R.C.C work including
straightening, cutting, bending, placing Assume 120Kg/m3
in position & binding all TMT bars Qty as per item no 6 11.52 T
Sundries 0.48

Substructure 4 Elango Nagar


A1

S.No Description Nos L B D Qty Rate unit Amount


12.00 61,000 T 732,000

Substructure 5 Elango Nagar


A1

S.No Description Nos L B D Qty Rate unit Amount


11 Centering and Shuttering work:
Centering and shuttering including of
strutting, propping etc. and removal o
formwork for Cut lintel & roof
Using MS Sheets
Strip Raft 1 1 x 2 26.75 1 1.25 66.88
Strip Raft 1 Beam 1 x 2 26.75 1 1 53.50
Strip Raft2 1 x 4 26.75 1 1.25 133.75
Strip Raft 2 Beam 1 x 4 26.75 1 1 107.00
Strip Raft3 1 x 2 17.50 1 1.25 43.75
Strip Raft 3 Beam 1 x 2 17.50 1 1 35.00
Full Raft RF1 1 x 2 20.50 1 1.5 61.50
Full Raft RF1 Beam 1 x 4 20.50 1 1 82.00
RCC wall (lift) 2 x 4 5 1 0.00
Column 1 x 15 4.5 5 337.50
Column (lift) 1 x 4 3 5 60.00
Grade beam 1 x 2 216.75 1.5 650.25
Plinth beam 1 x 2 268 0.75 402.00
Sump Base 1 x 4 10.2 0.5 20.40
Sump wall Peri 1 x 2 34.8 6 417.60
Sump Top slab 1 x 1 9 9 81.00
Sundries 0.25
2552.00 28 Sq.ft 71,456
12 Brick Work - 230mm:
Brick Work in cement mortar
1:4 for Substructure all around upto
all around 1 x 1 94 0.75 3 211.50
Intermediate wall b/w Hall & Kitchen 1 x 1 9.37 0.75 3 21.08
Intermediate wall b/w BD & Kitchen 1 x 1 11 0.75 3 24.75
Intermediate wall b/w Hall & Bedroom 1 x 1 9 0.75 3 20.25
Intermediate wall b/w Hall & Passage(bath) 1 x 1 10 0.75 3 22.50
Stair wall all around 1 x 1 32.5 0.75 3 73.13
Carparking all around to Support Fillling 1 x 1 81 0.75 2.5 151.88
Sundries 0.39
525.00 146 cft 76,650

13 Plastering:- Sump:
Plastering with cement mortar 1:3
(1 cement : 3 fine sand) of 12mm thickness.
Sump wall Peri 1 x 2 34.8 1 6 417.60
Sump Top slab 1 x 2 9 1 9 162.00
Sundries 0.40
580.00 30 sq.ft 17,400

14 Flooring
Flooring with CC 1:1.5:3 of 50mm Thick
including haunching the Corners and punning
with cement slurry 1 x 1 9 9 1 81.00
1 x 1 36 1 1 36.00
117.00 50 sq.ft 5,850

15 Wall Tiles:
Providing and laying ceramic wall tiles of
20mm thick cement mortar 1:4 (1 Cement
:4 coarse sand) including grouting the
joints with white cement and matching the
pigments etc.
Sump wall Peri 1 x 1 34.8 1 6 208.80
Sump Top slab 1 x 1 9 1 9 81.00
Sundries 0.20
290.00 78 sq.ft 22,620

Substructure 6 Elango Nagar


A1

S.No Description Nos L B D Qty Rate unit Amount

16 Supplying and fixing of pump, 1HP Capacity


with related plumbing works Lumpsum 20,000

Rupees Twenty one Lac fourty eight thousand five Hundred and thirteen only Rs. 2,148,513

Substructure 7 Elango Nagar


B1

STILT (Parking and Rear side a single BHK unit)

S.No Description Nos L B D Qty Rate unit Amount


(in Feet) (in Feet) (in Feet)
1 Reinforced Concrete Work:
R.C.C 1:1.5:3 mix using 20 mm stone
jelly for roof slab,lintel,roof slab, lintel
and sunshade excluding fabrication of
RCC items and including cost and
conveyance of all materials labour etc.,
Column 1 x 13 0.75 1.5 10 146.25
Column 1 x 2 1 1.5 10 30.00
Column (lift) 1 x 4 0.75 0.75 10 22.50
Cut Lintel over Window W1 1 x 2 6 0.75 0.5 4.50
Cut Lintel over Window-W2 1 x 1 5 0.75 0.5 1.88
Cut Lintel over Window -kW 1 x 1 5 0.75 0.5 1.88
Cut Lintel over French Window -FW1 1 x 1 3.5 0.75 0.5 1.31
Cut Lintel over door-MD 1 x 1 5 0.75 0.5 1.88
Cut Lintel over door-D 1 x 2 4 0.75 0.5 3.00
Cut Lintel over door-D1 1 x 3 3.5 0.75 0.5 3.94
Floor Beam 1 x 1 361.25 0.75 1 270.94
Waist slab 1 x 3 7.75 3 0.41 28.60
Slab 1 x 1 1345 0.416 559.52
Sunshade 1 x 4 5 2 0.33 13.20
Sundries 0.60
1090.00 200 cft 218,000
2 Reinforcement:
Reinforcement for R.C.C work including
straightening, cutting, bending, placing Assume 100Kg/m3
in position & binding all TMT bars Qty as per item no 1 3.09 T
Sundries 0.01
3.10 61,000 T 189,100
3 Centering and Shuttering work:
Centering and shuttering including of
strutting, propping etc. and removal of
formwork for Cut lintel & roof
Using MS Sheets
Column 1 x 13 4.5 10 585.00

Stilt floor 6 Elango Nagar


B1

S.No Description Nos L B D Qty Rate unit Amount


Column 1 x 2 5 10 100.00
Column (lift) 1 x 4 3 10 120.00
Cut Lintel over Window W1 (bottom) 1 x 2 5 0.75 7.50
Cut Lintel over Window W1 (Side) 2 x 2 6 0.5 12.00
Cut Lintel over Window-W2(bottom) 1 x 1 4 0.75 3.00
Cut Lintel over Window-W2(Side) 2 x 1 5 0.5 5.00
Cut Lintel over Window -kW (bottom) 1 x 1 4 0.75 3.00
Cut Lintel over Window -kW (side) 2 x 1 5 0.5 5.00
Cut Lintel over French Window -FW1 (side) 1 x 1 2.5 0.5 1.25
Cut Lintel over French Window -FW1 (Bottom) 1 x 2 2.5 0.75 3.75
Cut Lintel over door-MD(bottom) 1 x 1 4 0.75 3.00
Cut Lintel over door-MD(Side) 2 x 1 5 0.5 5.00
Cut Lintel over door-D(Bottom) 1 x 2 3 0.75 4.50
Cut Lintel over door-D(Side) 2 x 2 4 0.5 8.00
Cut Lintel over door-D1(bottom) 1 x 3 2.5 0.75 5.63
Cut Lintel over door-D1(Side) 2 x 3 3.5 0.5 10.50
Slab ( Bottom) 1 x 1 1345 1345.00
Slab (outer) 1 x 1 172 0.41 70.52
Floor Beam 1 x 2 361.25 1 722.50
Waist slab(Bottom) 1 x 3 7.5 3 67.50
Waist slab(Side) 2 x 3 7.5 0.5 22.50
Sunshade 1 x 4 5 2 40.00
Sundries 0.85
3151.00 28 Sq.ft 88,228
4 Brick Work - 230mm:
Brick Work in cement mortar
1:6 for Superstructure of first floor
all around 1 x 1 91.5 0.75 10 686.25
Intermediate wall b/w Hall & Kitchen 1 x 1 9 0.75 10 67.50
Intermediate wall b/w BD & Bath 1 x 1 11 0.75 10 82.50
Stair wall all around 1 x 1 29.25 0.75 10 219.38
Staircase 3 x 7 3 0.83 0.5 26.15
Lift all around 1 x 1 15.25 0.75 10 114.38
Deduction
Main Door-MD 1 x -1 4 0.75 7 -21.00
Door-D1 1 x -2 3 0.75 7 -31.50
Window-W1 1 x -2 5 0.75 4.5 -33.75
Window-W2 1 x -2 4 0.75 4.5 -27.00
Kitchen Window-KW 1 x -1 4 0.75 3 -9.00
French Window-FW 1 x -1 2.5 0.75 6 -11.25
Ventilator -V1 1 x -2 2 0.75 2 -6.00
Lift Opening 1 x -1 3.5 0.75 7 -18.38
Sundries 0.72
1039.00 146 cft 151,694
5 Brick Work - 115mm:
Brick Work in cement mortar 1:4
for Superstructure of first floor

Stilt floor 7 Elango Nagar


B1

S.No Description Nos L B D Qty Rate unit Amount


Intermediate wall b/w BD & Kitchen 1 x 1 11 10 110.00
Intermediate wall b/w Hall & Passage 1 x 1 7.5 10 75.00
Intermediate wall b/w Bath & W.C 1 x 1 4 10 40.00
Intermediate wall b/w Passage & Toilet 1 x 1 4.58 10 45.80
Sundries 0.20
271.00 70 Sq.ft 18,970

6 Wood work: -Door


Providing and fixing in position of doors
including paneling and fixtures like
hold-fast, hinges, tower-bold ,locks etc.,
complete- country wood.
Main Door -MD-teak wood Lumpsum 45,000
Door-D 1 x 2 3 7 42.00
Door-D1 1 x 1 2.5 7 17.50
Sundries 0.50
60.00 716 Sq.ft 42,960

7 UPVC Windows
Supply and fixing of sliding windows at all
levels made out from Unplasticised Poly
vinyl chloride frame (UPVC) with outer frame
of size 40x56x40mm
Window-W1 1 x 2 5 4.5 45.00
Window-W2 1 x 1 4 4.5 18.00
French Window -FW1 1 x 1 2.5 6 15.00
Sundries 0.00
78.00 725 Sq.ft 56,550

8 PVC sheet doors for bathrooms:


Providing and fixing in position of doors
including paneling and fixtures like
hold-fast, hinges, tower-bold,locks etc.,
complete - PVC sheet. 1 x 2 2.5 7 35.00 175 Sq.ft 6,125

9 Grill work (in kg):


Supplying and fixing of steel grill work
including cost of welding charges, fixing
in position in frames of
windows (finished items) Qty as per item no 7
Assume 2kg/sq.ft = 78x2 156.00 120 kg 18,720
10 Plastering:-Outer wall
Plastering with cement mortar 1:5
(1cement : 5 fine sand) of 12mm thickness.
all around 1 x 1 94 10 940.00
Stair all around 1 x 1 32.5 10 325.00
Lift all around 1 x 1 19.5 10 195.00
Sundries 0.00
1460.00 31 Sq.ft 45,260

Stilt floor 8 Elango Nagar


B1

S.No Description Nos L B D Qty Rate unit Amount


11 Plastering:- Inner wall:
Plastering with cement mortar 1:5
(1 cement : 5 fine sand) of 12mm thickness.
Hall 1 x 1 50.16 10 501.60
Kitchen 1 x 1 39.58 10 395.80
Bedroom 1 x 1 48.16 10 481.60
Passage 1 x 1 25.16 10 251.60
Bath 1 x 1 32 10 320.00
Toilet 1 x 1 19.08 10 190.80
Lift 1 x 1 19 10 190.00
Stair 1 x 1 32.5 10 325.00
Staircase 3 x 7 3 0.5 31.50
Deduction
Door -MD 1 x -1 4 7 -28.00
Door 1 x -2 3 7 -42.00
Door-D1 1 x -3 2.5 7 -52.50
Window-W1 1 x -2 5 4.5 -45.00
Window-W2 1 x -1 4 4.5 -18.00
opening 1 x -1 3 7 -21.00
Kitchen Window-KW 1 x -1 4 3 -12.00
French Window-FW 1 x -1 2.5 6 -15.00
Ventilator-V1 1 x -2 2 2 -8.00
Sundries 0.60
2447.00 32 Sq.ft 78,304
12 Plastering:-Ceiling:
Plastering with cement mortar 1:3
(1 cement : fine sand) of 6mm thickness.
Hall 1 x 1 13.12 10 131.20
Kitchen 1 x 1 9 11 99.00
Bedroom 1 x 1 13.12 11 144.32
Bath, Toilet and Passage 1 x 1 7 9.75 68.25
Car Parking 1 x 1 658 658.00
Sunshade 2 x 4 5.25 2.25 94.50
Sundries 0.73
1196.00 30 Sq.ft 35,880
13 Flooring:-Marbonite
Providing & laying marbonite tiles of size
600x600mm (thickness to be specified by
the manufacturer) with water absorptions
less than 0.08% & conforming Johnson
in all colors and shades laid on 20mm thick
cement mortar 1:4 (1 Cement: 4 coarse s
and) including grouting the joints with
white cement and matching the
cpigments etc., omplete.
Hall 1 x 1 13.12 10 131.20
Kitchen 1 x 1 9 11 99.00
Bedroom 1 x 1 13.12 11 144.32
Sundries 0.48
375.00 110 Sq.ft 41,250

Stilt floor 9 Elango Nagar


B1

S.No Description Nos L B D Qty Rate unit Amount


14 Skirting:
Skirting the junctions of flooring to wall
with the same tile. 1 x 1 125.00 33 Rft 4,125

15 Wall Tiles:
Providing and laying ceramic wall tiles of
20mm thick cement mortar 1:4 (1 Cement
:4 coarse sand) including grouting the
joints with white cement and matching the
pigments etc.
Kitchen 1 x 1 17.5 4 70.00 78 Sq.ft 5,460

16 Bathroom & Toilet Tiles


Wall tile (Bath) 1 x 1 16.5 7 115.50
Wall tile (Toilet) 1 x 1 13.75 4 55.00
Rectified Floor Tile (Bath) 1 x 1 4 5.5 22.00
Rectified Floor Tile (W.C) 1 x 1 4 4.12 16.48
Sundries 0.02
209.00 78 Sq.ft 16,302
17 Wall Putty
(As per item no. 10, 11, 12 & 18 inner wall
and deduct \wall tiling area) Providing and
applying ready mixed wall putty (JK/Birla)
of 2mm thickness over plastred surface to
prepare the surface even and smooth - two
coats including a priming coat. 1 x 1 5033.00 15.5 Sq.ft 78,012

18 Painting :Inner wall


Wall painting with distemper of approved
brand and manufacture to give an even
shade - two coats Qty as per item no 11 2447.00 18 Sq.ft 44,046

19 Painting: Outer wall


Wall painting with exterior emulsion Paint
ACE (Asian brand) to give an even shade
two coats Qty as per item no 10 1460.00 18 Sq.ft 26,280

20 Painting: Ceiling
White washing with whiting using Ramcem
3 coats mixed with Robinblue. Qty as per item no 12 1196.00 10 Sq.ft 11,960

21 Painting:Grill
Finishing with epoxy paint (two coats) at all
locations prepared and applied as per
manufacturer specifications including
appropriate priming coat, preparation
of surface, etc., complete. Qty as per item no 9 156.00 24 Kg 3,744

23 Painting:Door
Painting of door Qty as per item no 6 60.00 22 sq.ft 1,320

Stilt floor 10 Elango Nagar


B1

S.No Description Nos L B D Qty Rate unit Amount

24 Kitchen Slab
Providing and fixing 18mm thick kitchen
platform (premoulded and prepolished) of
including curing moulding & edge polishing
etc, Complete- Granite work. approved
shade & colour laid over 20mm thick
C.M 1:4 with joints treated with white
cement, mixed with matching pigment . 1 x 1 15.5 2 31.00 350 Sq.ft 10,850

25 Precast Slab Cupboards:


Providing cuddapha slab of maximum
in each room - double side polished
and edge rounded.
Bedroom 1 x 2 10 7 140.00
Sundries 0.00
140.00 250 Sq.ft 35,000
26 Bathroom Fittings & Sanitary ware
Bathroom Fitting Taps (Gurumake), I.W.C
& E.W.C, Wash basin, Half turn valve 2 Nos,
Waste hose, Flexible hose, Bolt, tank, seat cover
Health faceat, two in one, Mixer tap, One
Long body, shower , Shower arm,Pillar cork 1 x 2 (toilets) Lumpsum 37,500

27 Providing Loft 1 x 2 (Nos) Lumpsum 30,000

Rupees Thirteen lac fourty thousands six hundred and fourty only Rs. 1,340,640

Stilt floor 11 Elango Nagar


B2, B3 and B4

TYPICAL FLOOR -FF, SF & TF

S.No Description Nos L B D Qty Rate unit Amount


(in Feet) (in Feet) (in Feet)
1 Reinforced Concrete Work:
R.C.C 1:1.5:3 mix using 20 mm stone
jelly for roof slab,lintel,roof slab, lintel
and sunshade excluding fabrication of
RCC items and including cost and
conveyance of all materials labour etc.,
Column 1 x 13 0.75 1.5 10 146.25
Column 1 x 2 1 1.5 10 30.00
Column (lift) 1 x 4 0.75 0.75 10 22.50
Cut Lintel over Window W1 1 x 2 6 0.75 0.5 4.50
Cut Lintel over Window-W2 1 x 1 5 0.75 0.5 1.88
Cut Lintel over Window-W3 1 x 4 3.25 0.75 0.5 4.88
Cut Lintel over Window-W4 1 x 2 2.5 0.75 0.5 1.88
Cut Lintel over French Window -FW 1 x 2 6 0.75 0.5 4.50
Cut Lintel over door-MD 1 x 1 5 0.75 0.5 1.88
Cut Lintel over door-D 1 x 3 4 0.75 0.5 4.50
Cut Lintel over door-D1 1 x 6 3.5 0.75 0.5 7.88
Floor Beam 1 x 1 361.25 0.75 1 270.94
Waist slab 1 x 3 12 3 0.41 44.28
Slab 1 x 1 1345 0.416 559.52
Sunshade 1 x 4 5 2 0.33 13.20
Sundries 0.41
1119.00 200 cft 223,800
2 Reinforcement:
Reinforcement for R.C.C work including
straightening, cutting, bending, placing Assume 100Kg/m3
in position & binding all TMT bars Qty as per item no 1 3.17 T
Sundries 0.03
3.20 61,000 T 195,200
3 Centering and Shuttering work:
Centering and shuttering including of
strutting, propping etc. and removal of
formwork for Cut lintel & roof

Typical floor 12 Elango Nagar


B2, B3 and B4

S.No Description Nos L B D Qty Rate unit Amount


Using MS Sheets.
Column 1 x 13 4.5 10 585.00
Column 1 x 2 5 10 100.00
Column (lift) 1 x 4 3 10 120.00
Cut Lintel over Window W1 (bottom) 1 x 2 5 0.75 7.50
Cut Lintel over Window W1 (Side) 2 x 2 6 0.5 12.00
Cut Lintel over Window-W2(bottom) 1 x 1 4 0.75 3.00
Cut Lintel over Window-W2(Side) 2 x 1 5 0.5 5.00
Cut Lintel over Window-W3(bottom) 1 x 4 2.25 0.75 6.75
Cut Lintel over Window-W3(Side) 2 x 4 3.25 0.5 13.00
Cut Lintel over Window-W4(bottom) 1 x 2 1.5 0.75 2.25
Cut Lintel over Window-W4(Side) 2 x 2 2.5 0.5 5.00
Cut Lintel over French Window-FW (bottom) 1 x 2 6 0.75 9.00
Cut Lintel over French Window-FW (Side) 2 x 2 5 0.5 10.00
Cut Lintel over door-MD(bottom) 1 x 1 4 0.75 3.00
Cut Lintel over door-MD(Side) 2 x 1 5 0.5 5.00
Cut Lintel over door-D(Bottom) 1 x 3 3 0.75 6.75
Cut Lintel over door-D(Side) 2 x 3 4 0.5 12.00
Cut Lintel over door-D1(bottom) 1 x 6 2.5 0.75 11.25
Cut Lintel over door-D1(Side) 2 x 6 3.5 0.5 21.00
Floor Beam 1 x 2 361.25 1 722.50
Slab ( Bottom) 1 x 1 1345 1345.00
Slab (outer) 1 x 1 172 0.41 70.52
Waist slab(Bottom) 1 x 3 7.5 3 67.50
Waist slab(Side) 2 x 3 7.5 0.5 22.50
Sunshade 1 x 4 5 2 40.00
Sundries 0.20
3206.00 28 Sq.ft 89,768
4 Brick Work - 230mm:
Brick Work in cement mortar
1:6 for Superstructure of first floor
all around 1 x 1 168 0.75 10 1260.00
Intermediate wall b/w Hall & stair 1 x 1 12 0.75 10 90.00
Intermediate wall b/w BD & Stair 1 x 1 12.87 0.75 10 96.53
Intermediate wall b/w Dinningl & Pooja 1 x 1 7.87 0.75 10 59.03
Intermediate wall b/w BD & Bath 1 x 1 7 0.75 10 52.50
Intermediate wall b/w Dinning & Kitchen 1 x 1 8.91 0.75 10 66.83
Intermediate wall b/w BD(Near Kitchen)
& Bath 1 x 1 14.25 0.75 10 106.88
Intermediate wall b/w BD & Kitchen 1 x 1 11 0.75 10 82.50
Staircase 3 x 7 3 0.83 0.5 26.15
Stair wall all around 1 x 1 29.25 0.75 10 219.38
Lift all around 1 x 1 15.25 0.75 10 114.38
Deduction
Main Door-MD 1 x -1 4 0.75 7 -21.00
Door-D 1 x -3 3 0.75 7 -47.25
Door-D1 1 x -6 3 0.75 7 -94.50
Window-W1 1 x -2 5 0.75 4.5 -33.75
Window-W2 1 x -1 4 0.75 4.5 -13.50
Window-W3 1 x -4 2.25 0.75 4.5 -30.38

Typical floor 13 Elango Nagar


B2, B3 and B4

S.No Description Nos L B D Qty Rate unit Amount


Window-W4 1 x -2 1.5 0.75 4.5 -10.13
French Window-FW 1 x -2 5 0.75 6 -45.00
Ventilator -V1 1 x -2 2 0.75 2 -6.00
Opening in study room 1 x -1 5 0.75 2 -7.50
Lift Opening 1 x -1 3.5 0.75 7 -18.38
Sundries 0.21
1847.00 146 cft 269,662
5 Brick Work - 115mm:
Brick Work in cement mortar 1:4
for Superstructure of first floor
Intermediate wall b/w Pooja & Passage 1 x 1 11 10 110.00
Intermediate wall b/w BD & Passage 1 x 1 11.25 10 112.50
Intermediate wall b/w Bath & Dinning 1 x 1 10.25 10 102.50
Intermediate wall b/w Bath & Bath 1 x 1 7 10 70.00
Intermediate wall b/w BD & Bath 1 x 1 7 10 70.00
Parapet wall in balcony(near Hall) 1 x 1 29 3 87.00
Parapet wall in balcony(near Dinning) 1 x 1 10 3 30.00
Parapet wall in balcony(near Kitchen) 1 x 1 19.5 3 58.50
Sundries 0.50
641.00 70 Sq.ft 44,870

6 Wood work: -Door


Providing and fixing in position of doors
including paneling and fixtures like
hold-fast, hinges, tower-bold ,locks etc.,
complete- country wood.
Main Door -MD-teak wood Lumpsum 45,000
Door-D 1 x 3 3 7 63.00
Door-D1 1 x 3 2.5 7 52.50
Sundries 0.50
116.00 716 Sq.ft 83,056

7 UPVC Windows
Supply and fixing of sliding windows at all
levels made out from Unplasticised Poly
vinyl chloride frame (UPVC) with outer frame
of size 40x56x40mm
Window-W1 1 x 2 5 4.5 45.00
Window-W2 1 x 1 4 4.5 18.00
Window-W3 1 x 4 2.25 4.5 40.50
Window-W4 1 x 2 1.5 4.5 13.50
French Window -FW 1 x 2 5 6 60.00
Sundries 0.00
177.00 725 Sq.ft 128,325

8 PVC sheet doors for bathrooms:


Providing and fixing in position of doors
including paneling and fixtures like
hold-fast, hinges, tower-bold,locks etc.,
complete - PVC sheet. 1 x 3 2.5 7 52.50 175 Sq.ft 9,188

Typical floor 14 Elango Nagar


B2, B3 and B4

S.No Description Nos L B D Qty Rate unit Amount

9 Grill work (in kg):


Supplying and fixing of steel grill work
including cost of welding charges, fixing
in position in frames of
windows (finished items) Qty as per item no 7
Assume 2kg/sq.ft = 78x2 354.00 120 kg 42,480
Doors
Front Doors 1 x 2 5 7.5 75.00
Rearer Door 1 x 1 4 7.5 30.00
South East Balcony 1 x 1 10 5 50.00
Kitchen Balcony 1 x 1 19.5 5 97.50
252.50
Assume 2kg/sq.ft 505.00 120 Kg 60,600

10 Stainless Steel Handrail:


Supplying and fixing of steel grill work
including cost of welding charges, fixing
in position in frames of
Staircase Handrail 1 x 1 70 70.00 550 rft 38,500

11 Plastering:-Outer wall
Plastering with cement mortar 1:5
(1cement : 5 fine sand) of 12mm thickness.
all around 1 x 1 168 10 1680.00
Lift all around 1 x 1 19 10 190.00
Sundries 0.00
1870.00 32 Sq.ft 59,840
12 Plastering:- Inner wall:
Plastering with cement mortar 1:5
(1 cement : 5 fine sand) of 12mm thickness.
Hall 1 x 1 49.25 10 492.50
Stair 1 x 1 19 10 190.00
Pooja 1 x 1 43.75 10 437.50
Bedroom 1 x 1 48.16 10 481.60
Passage 1 x 1 32.25 10 322.50
Dinning 1 x 1 50.25 10 502.50
Bath 1 x 1 34 10 340.00
Kitchen 1 x 1 40 10 400.00
Bedroom 1 x 1 49.75 10 497.50
Lift 1 x 1 19 10 190.00
Toilet 1 x 1 23 10 230.00
Stair 1 x 1 32.5 10 325.00
Staircase 3 x 7 3 0.5 31.50
Deduction
Door -MD 1 x -1 4 7 -28.00
Door 1 x -3 3 7 -63.00
Door-D1 1 x -6 2.5 7 -105.00
Window-W1 1 x -2 5 4.5 -45.00
Window-W2 1 x -1 4 4.5 -18.00
Window-W3 1 x -4 2.25 4.5 -40.50

Typical floor 15 Elango Nagar


B2, B3 and B4

S.No Description Nos L B D Qty Rate unit Amount


Window-W4 1 x -2 1.5 4.5 -13.50
opening 1 x -1 5 7 -35.00

Typical floor 16 Elango Nagar


B2, B3 and B4

S.No Description Nos L B D Qty Rate unit Amount


French Window-FW 1 x -1 5 6 -30.00
Ventilator-V1 1 x -2 2 2 -8.00
Sundries 0.40
4055.00 32 Sq.ft 129,760
13 Plastering:-Ceiling:
Plastering with cement mortar 1:3
(1 cement : fine sand) of 6mm thickness.
Hall 1 x 1 12.25 12.37 151.53
Pooja 1 x 1 10.87 11 119.57
Bedroom(stair) 1 x 1 12.25 11.25 137.81
Passage 1 x 1 4 12.12 48.48
Dinning 1 x 1 15.12 10 151.20
Bath 1 x 1 7 10 70.00
Kitchen 1 x 1 9 11 99.00
Bedroom(kitchen) 1 x 1 13.87 11 152.57
Toilet 1 x 1 4.5 7 31.50
Balcony(near Hall) 1 x 1 81 81.00
Balcony(near Dinning) 1 x 1 3 10 30.00
Balcony(near Kitchen) 1 x 1 3 13.5 40.50
Sunshade 2 x 3 5.25 2.25 70.88
Sundries 0.96
1185.00 30 Sq.ft 35,550
13 Flooring:-Marbonite
Providing & laying marbonite tiles of size
600x600mm (thickness to be specified by
the manufacturer) with water absorptions
less than 0.08% & conforming Johnson
in all colors and shades laid on 20mm thick
cement mortar 1:4 (1 Cement: 4 coarse s
and) including grouting the joints with
white cement and matching the
cpigments etc., omplete.
Hall 1 x 1 12.25 12.37 151.53
Pooja 1 x 1 10.87 11 119.57
Bedroom(stair) 1 x 1 12.25 11.25 137.81
Passage 1 x 1 4 12.12 48.48
Dinning 1 x 1 15.12 10 151.20
Bath 1 x 1 7 10 70.00
Kitchen 1 x 1 9 11 99.00
Bedroom(kitchen) 1 x 1 13.87 11 152.57
Sundries 0.83
931.00 110 Sq.ft 102,410
14 Skirting:
Skirting the junctions of flooring to wall
with the same tile. 1 x 1 375 435.00 33 Rft 14,355

15 Wall Tiles:
Providing and laying ceramic wall tiles of
20mm thick cement mortar 1:4 (1 Cement
:4 coarse sand) including grouting the
joints with white cement and matching the

Typical floor 17 Elango Nagar


B2, B3 and B4

S.No Description Nos L B D Qty Rate unit Amount


pigments etc.
Kitchen 1 x 1 23.5 4 94.00 78 Sq.ft 7,332

Typical floor 18 Elango Nagar


B2, B3 and B4

S.No Description Nos L B D Qty Rate unit Amount

16 Bathroom & Toilet Tiles


Wall tile (Bath) 1 x 1 23 7 161.00
Wall tile (Bath) 1 x 1 24.25 7 169.75
Wall tile (Toilet) 1 x 1 23 4 92.00
Rectified Floor Tile (Bath) 1 x 1 7 5.125 35.88
Rectified Floor Tile (Bath) 1 x 1 4.5 7 31.50
Rectified Floor Tile (Toilet) 1 x 1 4 7 28.00
Sundries 0.87
519.00 78 Sq.ft 40,482
17 Wall Putty
(As per item no. 10, 11, 12 & 18 inner wall
and deduct \wall tiling area) Providing and
applying ready mixed wall putty (JK/Birla)
of 2mm thickness over plastred surface to
prepare the surface even and smooth - two
coats including a priming coat. 1 x 1 7110.00 15.5 Sq.ft 110,205

18 Painting :Inner wall


Wall painting with distemper of approved
brand and manufacture to give an even
shade - two coats Qty as per item no 11 4055.00 18 Sq.ft 72,990

19 Painting: Outer wall


Wall painting with exterior emulsion Paint
ACE (Asian brand) to give an even shade
two coats Qty as per item no 10 1870.00 18 Sq.ft 33,660

20 Painting: Ceiling
White washing with whiting using Ramcem
3 coats mixed with Robinblue. Qty as per item no 12 1185.00 10 Sq.ft 11,850

21 Painting:Grill
Finishing with epoxy paint (two coats) at all
locations prepared and applied as per
manufacturer specifications including
appropriate priming coat, preparation
of surface, etc., complete. Qty as per item no 9 354.00
Doors
Front Doors
Rearer Door
South East Balcony
Kitchen Balcony Qty as per item no 9 505.00
Sundries 0.00
859.00 24 Kg 20,616

23 Painting:Door
Painting of door Qty as per item no 6 144.00 22 sq.ft 3,168

Typical floor 19 Elango Nagar


B2, B3 and B4

S.No Description Nos L B D Qty Rate unit Amount


24 Kitchen Slab
Providing and fixing 18mm thick kitchen
platform (premoulded and prepolished) of
including curing moulding & edge polishing
etc, Complete- Granite work. approved
shade & colour laid over 20mm thick
C.M 1:4 with joints treated with white
cement, mixed with matching pigment . 1 x 1 16 2 32.00 350 Sq.ft 11,200

25 Precast Slab Cupboards:


Providing cuddapha slab of maximum
in each room - double side polished
and edge rounded.
Bedroom,hall,pooja 1 x 3 11 7 231.00
231.00 400 Sq.ft 92,400
26 Bathroom Fittings & sanitary ware
Bathroom Fitting Taps (Gurumake), I.W.C
& E.W.C, Wash basin, Half turn valve 2 Nos,
Waste hose, Flexible hose, Bolt, tank, seat cover
Health faceat, two in one, Mixer tap, One
Long body, shower , Shower arm,Pillar cork 1 x 3 (Toilets) Lumpsum 54,000

27 P.C.C 1:5:10 brick jelly


P.C.C work: Providing and laying plain
cement concrete of 1:5:10 (1cement:
5 coarse sand: 10 graded Brick aggregate)
including the cost of centering
and shuttering.
Bath 1 x 1 7 10 1 70.00
Toilet 1 x 1 4.5 7 1 31.50
Sundries 0.50
102.00 135 cft 13,770

28 Providing Loft 1 x 4 Lumpsum 60,000

Rupees Twenty one lac four thousand thirty seven only Rs. 2,104,037

Typical floor 20 Elango Nagar


B5

TERRACE

S.No Description Nos L B D Qty Rate unit Amount


(in Feet) (in Feet) (in Feet)

1 Terrace:Lime concrete
Lime concrete terracing on roofs
of 100 mm thickness laid to fall
with 25mm nominal size brick
aggregate and 50% lime mortar 1:2
(1 lime putty : 2 surkhi) rammed
and finished with gur and belgiri
treatment complete including
rounding of junctions with parapet
wall complete
Hall 1 x 1 12.25 12.37 0.33 50.01
Pooja 1 x 1 10.87 11 0.33 39.46
Bedroom(stair) 1 x 1 12.25 11.25 0.33 45.48
Passage 1 x 1 4 12.12 0.33 16.00
Dinning 1 x 1 15.12 10 0.33 49.90
Bath 1 x 1 7 10 0.33 23.10
Kitchen 1 x 1 9 11 0.33 32.67
Bedroom(kitchen) 1 x 1 13.87 11 0.33 50.35
Toilet 1 x 1 4.5 7 0.33 10.40
Balcony(near Hall) 1 x 1 1 81 0.33 26.73
Balcony(near Dinning) 1 x 1 3 10 0.33 9.90
Balcony(near Kitchen) 1 x 1 3 13.5 0.33 13.37
Sundries 0.39
368.00 164 cft 60,352

2 Terrace:Pressed Clay Tiles


Providing and laying pressed clay
tiles (as per approved pattern
20mm nominal thickness and of
approved size) on roofs jointed
with cement mortar 1:4 (1 cement :
4 coarse sand) mixed with 2%

Terrace 19 Elango Nagar


B5

S.No Description Nos L B D Qty Rate unit Amount


intergral water proofing compound
laid over a bed of 20mm thick
cement mortar 1:4 (1 cement : 4
coarse sand) and finished neat
complete.
Hall 1 x 1 12.25 12.37 151.53
Pooja 1 x 1 10.87 11 119.57
Bedroom(stair) 1 x 1 12.25 11.25 137.81
Passage 1 x 1 4 12.12 48.48
Dinning 1 x 1 15.12 10 151.20
Bath 1 x 1 7 10 70.00
Kitchen 1 x 1 9 11 99.00
Bedroom(kitchen) 1 x 1 13.87 11 152.57
Toilet 1 x 1 4.5 7 31.50
Balcony(near Hall) 1 x 1 81 81.00
Balcony(near Dinning) 1 x 1 3 10 30.00
Balcony(near Kitchen) 1 x 1 3 13.5 40.50
Sundries 0.96
1114.00 87 Sq.ft 96,918

3 Brick Work - 115mm:


Brick Work in cement mortar 1:4
for Parapet wall
all around 1 x 1 150 3 450.00
Sundries 0.00
450.00 70 Sq.ft 31,500

Rupees One Lac eighty eight thousand seven hundred and seventy only Rs. 188,770

Terrace 20 Elango Nagar


B6
HEAD ROOM & MACHINE ROOM

S.No Description Nos L B D Qty Rate unit Amount


(in Feet) (in Feet) (in Feet)
1 Reinforced Concrete Work:
R.C.C 1:1.5:3 mix using 20 mm stone
jelly for roof slab,lintel,roof slab, lintel
and sunshade excluding fabrication of
RCC items and including cost and
conveyance of all materials labour etc.,
Column 1 x 4 0.75 1.5 8 36.00
Column (lift) 1 x 4 0.75 0.75 13 29.25
Cut Lintel over door-D 1 x 1 4 0.75 0.5 1.50
Floor Beam in HR & MR 1 x 1 85 0.75 0.83 52.91
Roof Beam in HR & MR 1 x 1 32.5 0.75 0.83 20.23
Waist slab 1 x 3 7.5 3 0.41 27.68
HR & MR Floor Slab 1 x 1 14 13.5 0.41 77.49
Machine Room Roof Slab 1 x 1 6 10.25 0.41 25.22
Sundries 0.00
270.00 200 cft 54,000
2 Reinforcement:
Reinforcement for R.C.C work including
straightening, cutting, bending, placing Assume 100Kg/m3
in position & binding all TMT bars Qty as per item no 1 0.76 T
Sundries 0.04
0.80 61,000 T 48,800
3 Centering and Shuttering work:
Centering and shuttering including of
strutting, propping etc. and removal of
formwork for Cut lintel & roof
Using MS Sheets.
Column 1 x 4 4.5 8 144.00
Column (lift) 1 x 4 3 13 156.00
Cut Lintel over door-D(Bottom) 1 x 1 3 0.75 2.25
Cut Lintel over door-D(Side) 2 x 1 4 0.5 4.00
Floor Beam in HR & MR 1 x 2 85 0.83 141.10
Roof Beam in HR & MR 1 x 2 32.5 0.83 53.95

HR MR 21 Elango Nagar
B6
S.No Description Nos L B D Qty Rate unit Amount
Slab ( Bottom) in Floor of HR & MR 1 x 1 13.5 14 189.00
Slab (outer) in Floor of HR & MR 1 x 1 55 0.41 22.55
Slab ( Bottom) in Roofof HR & MR 1 x 1 10.25 6 61.50
Slab (outer) in Roof of HR & MR 1 x 1 32.5 0.41 13.33
Waist slab(Bottom) 1 x 3 7.5 3 67.50
Waist slab(Side) 2 x 3 7.5 0.5 22.50
Sundries 0.32
878.00 28 Sq.ft 24,584
4 Brick Work - 230mm:
Brick Work in cement mortar
1:6 for Superstructure
all around in Stair 1 x 1 31.25 0.75 6 140.63
all around in Lift 1 x 1 15.25 0.75 10 114.38
Staircase 3 x 7 3 0.83 0.5 26.15
Deduction
Lift Opening 1 x -3 3.5 0.75 7 -55.13
Sundries 0.97
227.00 146 cft 33,142
5 Brick Work - 115mm:
Brick Work in cement mortar 1:4
for Superstructure
Parapet wall in balcony over HR 1 x 1 31.25 1 31.25
Parapet wall in balcony over MR 1 x 1 15.25 1 15.25
Sundries 0.50
47.00 70 Sq.ft 3,290

6 Wood work: -Door


Providing and fixing in position of doors
including paneling and fixtures like
hold-fast, hinges, tower-bold ,locks etc.,
complete- country wood.
Door-D 1 x 1 3 7 21.00
Sundries 0.00
21.00 550 Sq.ft 11,550

7 Plastering:-Outer wall
Plastering with cement mortar 1:5
(1cement : 5 fine sand) of 12mm thickness.
all around 1 x 1 32.5 8 260.00
Lift all around 1 x 1 19 13 247.00
Parapet wall 1 x 1 51.5 1 51.50
Sundries 0.50
559.00 32 Sq.ft 17,888
8 Plastering:- Inner wall:
Plastering with cement mortar 1:5
(1 cement : 5 fine sand) of 12mm thickness.
Stair 1 x 1 32.5 7 227.50
Lift all around 1 x 1 19 10 190.00
Parapet wall 1 x 1 51.5 1 51.50

HR MR 22 Elango Nagar
B6
S.No Description Nos L B D Qty Rate unit Amount
Steps 3 x 7 3 0.5 31.50
Deduction
Door 1 x -3 3 7 -63.00
Sundries 0.50
438.00 32 Sq.ft 14,016
9 Plastering:-Ceiling:
Plastering with cement mortar 1:3
(1 cement : fine sand) of 6mm thickness.
Headroom 1 x 1 12.75 14 178.50
Lift room 1 x 1 5 4.5 22.50
Sundries 0.00
201.00 31 Sq.ft 6,231
10 Wall Putty
(As per item no. 7, 8 & 9 inner wall
and deduct \wall tiling area) Providing and
applying ready mixed wall putty (JK/Birla)
of 2mm thickness over plastred surface to
prepare the surface even and smooth - two
coats including a priming coat. 1 x 1 1198.00 15.5 Sq.ft 18,569

11 Painting :Inner wall


Wall painting with distemper of approved
brand and manufacture to give an even
shade - two coats Qty as per item no 8 438.00 18 Sq.ft 7,884

12 Painting: Outer wall


Wall painting with exterior emulsion Paint
ACE (Asian brand) to give an even shade
two coats Qty as per item no 7 559.00 18 Sq.ft 10,062

13 Painting: Ceiling
White washing with whiting using Ramcem
3 coats mixed with Robinblue. Qty as per item no 10 201.00 10 Sq.ft 2,010

14 Painting:Door
Painting of door Qty as per item no 6 21.00 15 sq.ft 315

15 Terrace:Lime concrete
Lime concrete terracing on roofs
of 100 mm thickness laid to fall
with 25mm nominal size brick
aggregate and 50% lime mortar 1:2
(1 lime putty : 2 surkhi) rammed
and finished with gur and belgiri
treatment complete including
rounding of junctions with parapet
wall complete
Headroom 1 x 1 12.75 14 178.50
Lift room 1 x 1 5 4.5 22.50
Sundries 0.00
201.00 164 cft 32,964

HR MR 23 Elango Nagar
B6
S.No Description Nos L B D Qty Rate unit Amount
16 Terrace:Pressed Clay Tiles
Providing and laying pressed clay
tiles (as per approved pattern
20mm nominal thickness and of
approved size) on roofs jointed
with cement mortar 1:4 (1 cement :
4 coarse sand) mixed with 2%
intergral water proofing compound
laid over a bed of 20mm thick
cement mortar 1:4 (1 cement : 4
coarse sand) and finished neat
complete.
Headroom 1 x 1 12.75 14 178.50
Lift room 1 x 1 5 4.5 22.50
Sundries 0.00
201.00 87 cft 17,487

( Rupees Three Lac two thousand seven hundred and ninety two only) Rs. 302,792