You are on page 1of 6

Summary of Cost

Name of Work: Construction of New Septic tank and Drainage line at RHC Main
Building Tando Qaiser District Hyderabad

Part A Civil work


Cost of schedule item Rs. 26826
Add 20 % Above Rs. 5365
cost of Non-schedule Item Rs.
cost of Carraige Rs.

Total Rs. 32,191

Diff: in cost of Cement per Bag @ Rs. 205 24.89 Rs. 5103
Diff: in cost of Bricks per 0% @ Rs. 3800 4950.72 Rs. 18813
Diff: in cost of steel 0.11 ton x 32000 3600
Total Rs. 27,516

Part B W/S, S/F


Cost of Schedule Item Rs.
Add 20.0% above Rs. 0
Cost of non-Schedule item Rs. 3140
3140
Part B
Cost of Schedule Item Rs.
Add 20.0% above Rs. 0
Rs. 0
Total Amount Rs. 62,847
Say Rs. 63,000
Construction of New Septic tank and Drainage line at RHC Main Building Tando Qaiser District Hyderabad

PART -A

1 Excavation in foundation of building bridges, footpath etc complete

Septic Tank 1x 17x 9x 6 918

Total 918
918 @RS 1306.8 %Cft Rs 1200

2 Cement concerate brick or stone blast in 1:5:10

Septic Tank Walls 2x 17 x 1.5 x 0.5 25.5


2x 9 x 2 x 0.5 18

Total 43.5
43.5 @Rs 3213.95 %Cft Rs 1398

3 Pacca Brick work in foundation and plinth in 1:6 etc complete

Septic Tank Walls 2x 16 x 1.13 x 1.5 54.24


Septic Tank Walls 4x 8 x 1.13 x 1.5 54.24
Septic Tank Walls 2x 16 x 0.75 x 5 120
Septic Tank Walls 2x 8 x 0.75 x 5 60
Mid Walls 2x 7.5 x 0.37 5 27.75

Total 316.23
316.23 @Rs 3865.15 %Cft Rs 12222.76

4 R.C.C work in roof slab beam column etc complete

Septic Tank Slab 1 x 17 x 9 x 0.33 50.49


Total 50.49
50.49 @Rs 114 Cft Rs 5756

5 Fabrication of mild steel reinforcement bar i/c cutting bending laying etc complete

50.49x 5Lbs 252.45 /112 2.25

Total 2.25
2.25 @Rs 2772.55 Cwt Rs 6249

Grand Total RS 26826

Page 2
Construction of New Septic tank for Drainage of Building at RHC Tando Qaiser District Hyderabad

PART - B

1 Providing and laying UPVC soil ben pipe of 4" dia i/c cutting etc complete

20Rft @ Rs 157P-Rft Rs 3140

Grand Total RS 3140

Page 3
Material Statement RHC TANDO QAISER
Cement
S.NO: Name of ITEM Qty:
Bags

1 C.C Stone 1:5:10 43.5 3.39

2 DPC 2" thick 1:2:4 Ratio 0.00 0.00

3 Pacca brick work Other then Building 366.7 12.62

4 Rough cost stucco 3/4" inches 0.0 0.00

5 Cement pointing 0.0 0.00

6 Cement plaster 1:6 1/2" Inches 0.0 0.00

7 Cement plaster 1:4 3/8" inches 0.0 0.00

8 Cement plaster 1:4 3/4" Inches 0.0 0.00

9 RCC Work 50.5 8.89

11 Galzed /maiser Tiles bed 1:2 3/4"thick 0.0 0.00

12 Galzed /maiser Tiles skirting 1:2 3/4"thick 0.0 0.00

Total 24.89

Lead in mile 19
Carrage Rate in Rs. 17.73
Total Amount 441
Grand Total
HC TANDO QAISER

Hill send cft Bajri Cft Stone Cft Bricks Nos

21.32 0 42.63 0

0.00 0

94.25 0 0 4950.72

0.00 0.00 0 0

0.00 0 0 0.00

0.00 0.00 0 0

0.00 0.00 0 0

0.00

22.22 44.43 0 0

0.00 0 0 0

0.00

137.78 44.43 42.63 4950.72

30 25 44 10
1505.4 1352.6 2707.61 721.71
2074 601 1154 3573
7844
Construction of New Septic tank and Drainage line at RHC Main Building
Tando Qaiser District Hyderabad

ESTIMATE COST : - 63000

ESTIMATE PREPARED BY: ASAD ALI MEMON


REGIONAL ENGINEER
RSU PPHI HYDERABAD

VERYFIED BY INAM-UR-RAHIM ABRO


DISTRICT SUPPORT MANAGER
DSU PPHI HYDERABAD