You are on page 1of 16

ROUGH COST ESTIMATE FOR SPECIAL REPAIR TO TRAINING HALL OF AGRICULTURE

DEPARTMENT TAUNSA SHARIF.


ABSTRACT OF COST

1 Main Buildings Rs: 1037700 /-

2 Electric Rs: 315782 /-

3 Sanitary Rs: 81000 /-

4 Submersible Pump Rs: 555800 /-

5 Water Tank500 gln 500 x 90.1 Rs: 45050 /-

6 External Development Rs: 531000 /-

Total Rs: 2566332 /-


add 3% Contigency Rs: 76990 /-
add 16% PRA Rs: 410613 /-
Total Rs: 3053935 /-
G.Total Rs: 3054000 /-
Say Rs: 3.054 (M)

Sub Divisional Officer Executive Engineer


Sub Engineer Buildings Sub Division Buildings Division
Taunsa Taunsa
ROUGH COST ESTIMATE FOR SPECIAL REPAIR TO TRAINING HALL OF
AGRICULTURE DEPARTMENT TAUNSA SHARIF.
S.No Description N L B H D Contents Amount
1 Removing door
5 = 5 Nos
Total = 5 N os
@ 346.50 Each 1733
2 Removing windows and sky lights
with chowkat.
Window 3 = 3 Nos
CW 4 = 4 Nos
Total = 7 Nos
@ 294.35 Each 2060
3 Removing cement or lime plaster
10 x 8 x 3 = 240 Sft
20 x 4 x 1.5 = 120 Sft
16 x 3 x 2.5 = 120 Sft
Total = 480 Sft
@ 352.00 %Sft 1690
4 Distempering:- b) old surface:- ii)One coats
1 x 33.16 x 22 = 730 Sft
1 x 13.25 x 7.75 = 103 Sft
1 x 9 x 12 = 108 Sft
1 x 2 x( 33.16 + 22 )x 12.5 = 1379 Sft
1 x 2 x( 13.25 + 7.75 )x 10 = 420 Sft
1 x 2 x( 9 + 12 )x 10 = 420 Sft
Total = 3160 Sft
@ 505.05 %Sft 15960
5 Providing and applying weather shield paint of approved quality on
external surface of building including preparation of surface, application
of primer complete in all respect: 02 caot (Colour Change)

2 x 35.5 x 15 = 1065 Sft


2 x 36.375 x 15 = 1091 Sft
Total = 2156 Sft
@ 1750.20 %Sft 37734
6 Providing and laying superb quality Porcelain glazed tiles flooring of
MASTER brand of specified size inapproved design, Color and Shade
with adhesive / bond over 3/4" thick (1:3) cement plaster i/c the cost of
sealer for finishing the joints i/c cutting grinding complete in allrespect as
approved and directed by the Engineer Incharge. Full body Glazed tiles
400 mm x 400 mm

1 x 32.16 x 22 = 708 Sft


1 x 13.25 x 7.75 = 103 Sft
1 x 9 x 11.375 = 102 Sft
1 x 5 x 1.125 = 6 Sft
1 x 3 x 1.125 = 3 Sft
1 x 3.5 x 0.75 = 3 Sft
Total = 925 Sft
@ 263.10 P-Sft 243368
7 Providing and laying superb quality Porcelain glazed tiles dao /
skirting of MASTER brand of specified size inapproved design,
Color and Shade with adhesive / bond over 3/4" thick (1:3) cement
plaster i/c the cost of sealer for finishing the joints i/c cutting
grinding complete in allrespect as approved and directed by the
Engineer Incharge. Full body Glazed tiles 400 mm x 400 mm

1 x 2 x( 32.16 + 22 )x 0.5 = 54 Sft


1 x 2 x( 13.25 + 7.75 )x 0.5 = 21 Sft
1 x 2 x( 9 + 11.375 )x 0.5 = 20 Sft
1 x 5 x 5.5 = 28 Sft
Total = 124 Sft
@ 263.10 P-Sft 32502
8 Providing and fixing 2 mm thick Double glazed aluminium windows
of anodized bronze colour partly fixed and party sliding using
deluxe section of 100mm x 40mm x2 mm using frame (70501) at
bottom, (70502) at Top & Side made of Pakistan Cables/Alcop
having Leaf Frame size 31mm x 60mm x2 mm (70506) at Top &
Bottom, 35mm x 60mm x2 mm (70505) at center and 35mm x
60mm x2 mm(70503) at sides , fixing 5 mm thick imported tinted
double glass and air tight using double tape, chemical strips,
Silicon using approved latches, wheels for channel, stopper, brush
channel angle joint and hardware etc.( excluding the cost of Fly
Proofing). Complete in all respect as approved and directed by the
Engineer Incharge.

3 x 4 x 6 = 72 Sft
4 x 2 x 1.5 = 12 Sft
Total = 84 Sft
@ 1,347.65 P-Sft 113203
9 Providing and fixing M.S. flat ½"x1/8" (13mm x 3mm) grill
including ¾" x 1/8" (20 mmx3 mm) M.S. flat frame, in
windows of approved design, including painting three coats,
complete in all respects.

3 x 4 x 6 = 72 Sft
4 x 2 x 1.5 = 12 Sft
Total = 84 Sft
@ 415.45 P-Sft 34898
10 Providing and fixing all types of partly fixed and partly openable
glazed anodised bronze colour aluminium doors, using delux
section of M/s Al-Cop or Pakistan Cables, having chowkat frame of
size 40 x 100 mm (1½" x 4") and leaf frame of 60x40mm (2½"x1½")
wide sections including the cost of ¼" (5 mm) thick imported tinted
glass with aluminium triangular gola and rubber gasket to support
the glass and leaf edging, using approved standard fittings, locks,
3" (75 mm) wide long handles etc., and hardware any required as
approved by the engineer in-charge.

1 x 5 x 8.5 = 43 Sft
Total = 43 Sft
@ 592.20 P-Sft 25465
11 Providing and fixing collapsible gate made of 2"x2"x"¼"
(50x50x6 mm) tee iron at top and bottom, channel iron
verticals ¾"x¼"x¼"x1/8" (20x6x6x3 mm) at 3" (75 mm) to 5"
(125 mm) centre to centre (approximate) and flat iron crosses
3"x3/16" (75x5 mm), and best quality rollers at bottom of 3"
(75 mm) diameter including holdfasts, handles 12" (300 mm)
long of ¾"x¼"x¼"x1/8" (20x6x6x3 mm) channel iron, locking
arrangement inside and outside, painting 3 coats of black
Japan enameled, complete in working order.

1 x 5 x 9 = 45 Sft
Total = 45 Sft
@ 1,356.65 P-Sft 61049
12 Providing and laying superb quality Ceramic tile floors of
Master brand of specified size, Glossy / Matt / Texture of
approved Colorand Shade as per approved design with
adhesive bond, over 3/4" thick (1;2) cement sand plaster i/c
the cost of sealer for finishing the joints i/c cutting grinding
complete in all respect sand as approved and directed by the
Engineer Incharge. 12"x18"/12"x24"/10"x24" /8"x24"/12"x36"

1 x 9 x 6.25 = 56 Sft
2 x 5 x 4.75 = 48 Sft
2 x 2.5 x 0.375 = 2 Sft
Total = 106 Sft
@ 204.70 P-Sft 21698
13 Providing and laying superb quality Ceramic tile dado / skirting of
Master brand of specified size, Glossy / Matt / Texture of approved
Colorand Shade as per approved design with adhesive bond, over
3/4" thick (1;2) cement sand plaster i/c the cost of sealer for
finishing the joints i/c cutting grinding complete in all respect sand
as approved and directed by the Engineer Incharge.
12"x18"/12"x24"/10"x24" /8"x24"/12"x36"

1 x 2 x( 9 + 6.25 )x 5 = 153 Sft


2 x 2 x( 5 + 4.75 )x 5 = 195 Sft
2 x 2 x( 2.5 + 0.375 )x 5 = 58 Sft
Total = 405 Sft
@ 211.95 P-Sft 85840
14 Providing and fixing 1½" (40 mm) thick deodar wood panelled or
panelled and glazed, doors and windows, with mild steel chowkat
(frame), etc. complete in all respects excluding sliding bolt or lock)
with:- i) M.S. angle iron 1½"x1½"x¼", welded

1 x 5 x 9 = 45 Sft
Total = 45 Sft
@ 1,545.95 P-Sft 69568
15 Painting :- c) Painting doors and windows, any type: (Three
coat) new surface
Take Doubel Qty of item no. 14 45 2 x = 90 Sft
Total = 90 Sft
1149.35 + 576.95 + 576.95 @ 2303.25 %Sft 2073
16 Cement plaster 1:4 upto 20' (6.00 m) height:- ½" (13 mm)
thick
10 x 8 x 3 = 240 Sft
20 x 4 x 1.5 = 120 Sft
16 x 3 x 2.5 = 120 Sft
Total = 480 Sft
@ 2657.50 %Sft 12756
17 Excavation in foundation of building, bridges and other
structures, including dagbelling, dressing, refilling around
structure with excavated earth, watering and ramming lead
upto one chain (30 m) and lift upto 5 ft. (1.5 m).in ordinary
soil.

1x 162 x 1.5 x 1.5 = 365 Cft


Total = 365 Cft
@ 8949.60 %0Cft 3267
18 Dry rammed brick or stone ballast, 1½" to 2"( 40 mm to 50
mm) gauge.
1x 162 x 1.5 x 0.5 = 122 Cft
Total = 122 Cft
@ 4554.00 %Cft 5556
19 Pacca brick work in foundation and plinth in:- Cement, sand
mortar:- Ration 1:6
1x 162 x 1.125 x 0.25 = 46 Cft
1x 162 x 0.75 x 4 = 486 Cft
Total = 532 Cft
@ 23134.00 %Cft 123073
20 Filling, watering and ramming earth under floors:-with
surplus earth from foundation, etc.
Take 2/3 item noo. 17 365 x 2 / 3 = 243 Cft
Total = 243 Cft
@ 4303.20 %0Cft 1047
ii with new earth excavated from outside, lead upto one mile
1x 150 x 3.25 x 2.59 = 1263 Cft
Total = 1263 Cft
@ 13591.40 %0Cft 17166
21 Supplying and filling sand under floor; or plugging in wells.
1x 150 x 3.25 x 0.33 = 161 Cft
Total = 161 Cft
@ 2752.00 %Cft 4431
22 Providing, laying, watering and ramming brick ballast 1½" to
2"(40 mm to 50 mm) gauge mixed with 25% sand, for floor
foundation, complete in all respects.

Same qty of Above item = 1263 Cft


Total = 1263 Cft
@ 5245.80 %Cft 66254
23 Providing and laying conglomerate flooring (two coat work)
with top layer of ½"(13mm) thick wearing surface, consisting
of one part of cement and 2 parts of stone chips passing
3/16"(6 mm) sieve, over bottom layer of cement concrete
1:3:6, including surface finishing and dividing in panels:- (a)
1½"(40 mm) thick

1x 150 x 4 = 600 Sft


Total = 600 Sft
@ 6193.60 %Sft 37162
24 Providing and fixing marble strip of any shade for dividing
the mosaic flooring into panels a) s Size 1½" x 3/8" (40 x 10
mm)
Take 60 % of Above qty 600 x 60 / 100 = 360 Rft
Total = 360 Rft
@ 15.85 P-Rft 5706
25 Applying floating coat of cement 1/32" (0.8 mm) thick.
1 x 35.5 x 36.5 = 1296 Sft
Total = 1296 Sft
@ 1517.75 %Sft 19670

Total 1044928
Deduct Cost of Old material
1 OId broken door = 5
@ 800 P-No 4000

OId broken widow = 4


2
@ 800 P-No 3200

Total 7200

1044928 - 7200 Net Total 1037728

Say Rs: 1037700

Sub Divisional Officer


Sub Engineer Buildings Sub Division
Taunsa
. Page 7 of 16

Electric Installation
1 Supply and Erection of PVC pipe for wiring on
resessed i/c inspection boxes pull boxes hook
bends reducer and prepairing surface etc
complete. 3/4" dia
= 200 Rft
Total. = 200 Rft
Total 200.0 Rft @ 71.40/Rft Rs.14280/-
ii-1" dia. = 100 Rft
Total 100.0 Rft @ 82.65/Rft Rs.8265/-

2 Supply and erection of single core PVC insulated


copper conductor cables, in prelaid PVC
pipe/M.S. conduit/G.I pipe/wooden strip
batten/wooden casing and capping/G.I.wire
/trenches (rate for cables only):- a) 250/440 volts,
PVC insulated:

i- 3/0.029"
= 2000 Rft
Total = 2000 Rft @ 21.35/Rft Rs.42700/-
ii- 7/0.029"
= 1500 Rft
Total 1500 Rft @ 33.40/Rft Rs.50100/-
iii- 7/0.036" = 200 Rft
Total 200 Rft @ 43.95/Rft Rs.8790/-
iv- 7/0.064" = 300 Rft
Total 300 Rft @ 141.65/Rft Rs.42495/-
3 Supply & Erection of switch piano type 5 Amp.
= 40 No @ 62.05/Each Rs.2482/-
4 Supply and erection of 3 pin. 5 Amp wall socket.

= 4 No @ 77.45/Each Rs.310/-
5 Supply and erection of Energy Sewer etc 24 watt

= 20 No @ 240.00/Each Rs.4800/-
6 Supply and erection of ceiling rose, bakelite.
= 20 No @ 57.25/Each Rs.1145/-
7 Supply and Erection of button holder backlite
large size.
= 20 No @ 46.15/Each Rs.923/-
10 Providing and fixing M.S. iron box for housing
main switches,made of 1.5 mm (1/16") thick M.S.
sheet, with locking arrangement, including
painting:-i) 60x35x15 cm (24"x14"x6")

= 1 No @ 6275.60/Each Rs.6276/-
11 Cost of ceiling fans 56" sweep of approved firm
like,GFC,Pak,Royal,Younis,fan with regulator i/c
carriage from local market to site of work etc.

= 13 No @ 6500.0/Each Rs.84500/-
12 Erection of ceiling fan alongwith regulator (all
sizes), including carriage from local Railway
Station/Store to site of work,electric wire/cable
for suspension rod and board connection,and
cutting, threading on the rod, where necessary.

= 13 No @ 394.75/Each Rs.5132/-
13 Supply and erection of 3 pin switch and plug
combined, recessed type. ii) 10/15 Amp
= 4 No @ 127.85/Each Rs.511/-
14 Supply and erection of M.S. sheet box of 16 SWG,
10 cm (4") deep, with 4.75 mm thick (3/16")
bakelite sheet top, for recessed wiring, including
making holes for regulators, switches, plugs, etc.

i) 17.5 x 10 cm (7"x4")
. Page 8 of 16
= 7 No
Total 7 No @ 319.35/Each Rs.2235/-
22.5 x 10 cm (9"x4")
= 7 No
Total 7 No @ 410.75/Each Rs.2875/-
16 Supply and erection of roof suspension hook of
M.S plate 75x40x12.7mm (3"x1½"x½") with 16 mm
(5/8") hook complete with bolts, nuts and fixing
with cement concrete 1:3:6
= 13 No
= 13 No @ 2624.70/Each Rs.34121/-
Sub Engineer, Executive Engineer
Provincial Buildings Division
17 Supply and erection of iron/aluminum clad, 500
Muzaffargarh.
volts main switches with triple pole and neutral
link and HRC fuses, on angle iron board with 3
mm (1/8") thick M.S. sheet covering, including
bonding to earth with necessary flexible pipe and
thimbles. 30/35Amp

= 1 No @ 2747.15/Each Rs.2747/-

18 Supply and erection of iron/aluminum clad,


Sub Engineer, Executive Engineer
branch distribution board, 250 volt, on angle iron Provincial Buildings Division
Muzaffargarh.
frame of suitable size with 3 mm (1/8") M.S. sheet
covering: ii) 3 way, 15 Amp per way

= 1 No @ 1095.40/Each Rs.1095/-

Sub Engineer, Total. Executive Engineer Rs.315782/-


Provincial Buildings Division
Muzaffargarh.

Sub Divisional Officer


Sub Engineer Buildings Sub Division
Taunsa

Executive Engineer
Provincial Buildings Division
Muzaffargarh.
SANITARY INSTALLATION
1 Providing and fitting glazed earthen ware water
closet, squatter type (Orisa pattern), combined
with foot rest. i) white
= 2 Nos
Total = 2 Nos

@ 1954.50 Each 3909


2 Providing and fitting "P" trap:- 10 cm (4") glazed.

= 2 Nos
Total = 2 Nos

@ 223.85 Each 448


3 Providing and fitting glazed earthen ware wash
hand basin 56x40 cm (22"x16") including bracket
set, waste pipe and waste coupling, etc.

= 2 Nos
Total = 2 Nos

@ 4611.00 Each 9222


4 Providing and fixing chromium plated stop cock,
heavy:- 1.5 cm (½")
= 4 Nos
Total = 4 Nos

@ 648.40 Each 2594


5 Providing and fixing, chromium plated mixing
valve, for wash hand basin, sink or shower.

= 2 Nos
Total = 2 Nos

@ 1980.50 Each 3961


6 Providing and fixing chromium plated bib cock:-
1.5 cm (½")

= 4 Nos
Total = 4 Nos

@ 468.40 Each 1874


7 Providing and fitting plastic made low down
flushing cistern 1363 litre (3 gallons) capacity,
including bracket set, copper connection, etc.
complete. i) white

= 2 Nos
Total = 2 Nos

@ 2401.10 Each 4802

8 Providing and fixing, floor trap of cast iron,


including concrete chamber all round, and C.I.
grating:- i) 10x5 cm (4"x2")

= 4 Nos
Total = 4 Nos

@ 544.80 Each 2179

9 Providing, laying, cutting, jointing, testing and


disinfecting G.I. pipeline in trenches, with socket
joints, using G.I. pipes of B.S.S. 1387-1967
complete in all respects, with specials and valves.
Medium Quality

ii ¾" i/d (20 mm) 2.65mm thick 1x 50 = 50 Rft


Total = 50 Rft

@ 188.90 P-Rft 9445


ii 1" i/d (32 mm) 3.25mm thick 1x 60 = 60 Rft
Total = 60 Rft

@ 282.05 P-Rft 16923


10 Providing, laying, cutting, jointing, testing and
disinfecting pipe line in trenches with P.V.C. pipes
of B.S.S. with `D' Class working pressure complete
in all respects:-

i 3" i/d (75 mm) 1x 15 = 15 Rft


Total = 15 Rft

@ 391.15 P-Rft 5867


ii 4" i/d (100 mm) 2x 15 = 30 Rft
Total = 30 Rft

@ 657.75 P-Rft 19733

Total Rs. 80956

SAY Rs. 81000

Sub Divisional Officer


Sub Engineeer Buildings Sub Division
Taunsa
DETAILED OF SUBMERSIBLE PUMP (Up to 300 feet Depth)
1st Bi Annual 2022
1 Boring for tubewell in all types of soil except shingle and
rock included sinking with drawing of casing pipe
complete in all respect 5” dia

(i) 0' to 100' = 100 Rft


Total = 100 Rft

@ 502.80 P.Rft 50280

(ii) 100.01' to 200' = 100 Rft


Total = 100 Rft

@ 842.40 P.Rft 84240

(iii) 200.01' to 300' = 100 Rft


Total = 100 Rft

@ 1176.00 P.Rft 117600


2 P/I PVC bail/end plug in tube well bore hole BSS
Class "D" 4" dia
= 1 No
Total = 1 No

@ 138.60 Each 139


3 P/I PVC strainer BSS class "D" in tube well bore
hole complete in all respect 4" dia
= 60 Rft
Total = 60 Rft

@ 363.35 P.Rft 21801


4 P/I PVC blind pipe BSS class "D" in tube well bore
hole complete in all respect
(i) 1-1/4" i/d (30 mm) = 240 Rft
Total = 240 Rft

@ 112.15 P.Rft 26916

(ii) 4" i/d (100 mm) = 290 Rft


Total = 290 Rft

@ 689.15 P.Rft 199854


6 P/F 3-BHP (Mastera) A.C electric motor single
phase 2" dia (Delivery) i/c submersible pump
(height 4'x9") i/c carriage of the following items:
(i) P/F PVC ploy pipe 2" dia.
(ii) P/F steel rope.
(iii) P/F cable 3 core 7/0.036".
(iv) Automatic panel board with capacitor.

= 1 Job
Total = 1 Job
@ 55000.00 P.Job 55000

Total Rs. 555829

SAY Rs. 555800

Sub Divisional Officer


Sub Engineer Buildings Sub Division
Taunsa
EXTERNAL DEVELOPMENT

ABSTRACT OF COST

1 Sewerage Line Rs: 246000

2 Tuff Pavers Rs: 285000

Total 531000

Say Rs 531000

Sub Divisional Officer


Sub Engineer Buildings Sub Division
Taunsa
EXTERNAL DEVELOPMENT (Sewerage System)
S.No Description No Length Breadth Depth Contents Amount
1 Earthwork excavation in open cutting for
sewers and manholes as shown in
drawings including shuttering and
timbering, dressing to correct section and
dimensions according to templates and
levels, and removing surface water, in all
types of soil except shingle, gravel and
rock:-
i) 0 ft. to 7.0 ft. (0 to 2.10 m) depth
9'' dia 1x 200 x 3 x( 2.5 + 3.5 )= 1800 Cft
2
Total: = 1800 Cft
@ 7,446.05 %oCft 13403
2 Providing and laying R.C.C. pipe sewers,
moulded with cement concrete 1:1½:3
conforming to ASTM Specification C-76-79,
Class II. Wall B, including carriage of pipe
from factory to site of work, lowering in
trenches to
correct alignment and grade, jointing with
rubber ring, cutting pipes where necessary,
testing, etc., complete.
i) 9'' dia RCC pipe = 200 Rft
@ 439.1 P.Rft 87820
3 Man Hole Small - - - - = 6 Nos
@ 23500 Each 141000
4 Rehandling of earthwork:Lead upto a single
throw of Kassi, phaorah or shovel
Same as per item No. 1 - - - - = 1800 Cft
@ 2,112.00 %oCft 3802

Total: 246025

Say Rs: 246000

Sub Engineer Sub Divisional Officer


Buildings Sub Division
Taunsa
EXTERNAL DEVELOPMENT (Man holes Size 4 ft. * 2-1/2 ft.)
S.No Description No Length Breadth Depth Contents Amount

1
Earthwork excavation in open cutting for sewers and
manholes as shown in drawings including shuttering and
timbering, dressing to correct section and dimensions
according to templates and levels, and removing surface
water, in all types of soil except shingle, gravel and rock:- i) 0
ft. to 7.0 ft. (0 to 2.10 m) depth

1x 5.5 x 4x 3= 66 Cft
@ 7,446.05 %0Cft 491
2 Cement concrete brick or stone ballast 1½ " to 2" (40 mm to
50 mm) gauge, in foundation and plinth:-1:6:12.

1x 5.5 x 4x 0.5 = 11 Cft


@ 14230.8 %Cft 1565
3 Pacca brick work other than building upto 10ft.
i) cement, sand mortar:-Ratio 1:4

2x 5.5 x 0.75 x 3.25 = 27 Sft


2x 2.5 x 0.75 x 3.25 = 12 Sft
Total: = 39 Sft
@ 25225.2 %Cft 9838
4 Cement plaster 1:4 upto 20' (6.00 m) height:-
½" (13 mm) thick
2 x( 4+ 2.5 )x 3.5 = 46 Sft
@ 2657.5 %Sft 1222
5 Cement concrete plain including placing, compacting,
finishing and curing complete (including screening and
washing of stone aggregate):1:2:4
1x 4x 2.5 x 0.25 = 3 Cft
@ 29158.8 %Cft 875
6 Fabrication of mild steel reinforcement for cement concrete,
including cutting, bending, laying in position, making
jointsand fastenings, including cost of binding wire and
labour charges for binding of steel reinforcement (also
includes removal of rust from bars):-
Deformed bars (Grade-40)
1/2'' Q.B 7x 4x 0.667 x 0.4535 = 8 Kg
8x 5.5 x 0.667 x 0.4535 = 13 Kg
Total: = 21 Kg
@ 26003.05 %Kg 5461
7 Reinforced cement concrete in roof slab, beams, columns
lintels, girders and other structural members laid in situ or
precast laid in position, or prestressed members cast in situ,
complete in all respects:-(1:2:4).
1x 5.5 x 4x 0.375 = 8 Cft
@ 477.8 P.Cft 3822
8 Extra for making and finishing benching floor work in
manhole chamber, with 1/8" (3 mm) thick cement finish.

1x 4x 2.5 x - = 10 Sft
@ 2367.8 %Sft 237

Total: 23511

Say Rs: 23500

Sub Divisional Officer


Sub Engineer Buildings Sub Division
Taunsa
EXTERNAL DEVELOPMENT (TUFF TILE)
S.No Description No Length Breadth Depth Contents Amount
1 Excavation in foundation of building,
bridges and other structures,
including dagbelling, dressing,
refilling around structure with
excavated earth, watering and
ramming lead upto one chain (30 m)
and lift upto 5 ft. (1.5 m)in ordinary
soil

1x 100 x 2x 1.5 = 300 Cft


Total: = 300 Cft
@ 8,949.60 %oCft 2685
2 P/L Dry rammed brick or stone ballast
1/1/2” to 2” gauge
1x 100 x 2x 0.5 = 100 Cft
Total: = 100 Cft
@ 4,554.00 %Cft 4554
2 Providing and laying sub-base course
of stone product of approved quality
and grade, ncluding placing, mixing,
spreading and compaction of sub-base
material to required depth, camber,
grade to achieve 100% maximum
modified AASHO dry density,
including carriage of all material to
site of work except gravel and
aggregate. i) Pit run or bed run
gravel. lead upto 35 Km

1x 35 x 30 x 0.5 = 525 Cft


Total: = 525 Cft
4327.50 + 1546.7 @ 5,874.20 %Cft 30840
3 Pacca brick work in foundation and
plinth 1:6 cement sand mortar.

1x 100 x 1.5 x 0.5 = 75 Cft


1x 100 x 1.125 x 2.5 = 281 Cft
Total: = 356 Cft
@ 24,302.80 %Cft 86518
4 Cement concrete plain including
placing, compacting, finishing and
curing complete (including screening
and washing of stone aggregate): Ratio
1: 2: 4
1x 100 x 1.125 x 0.25 = 28 Cft
Total: = 28 Cft
@ 29,158.80 %Cft 8164
5 Filling, watering and ramming earth
under floors:- i) with surplus earth
from foundation, etc.

2x 3/ 300 = 200 Cft


Total: = 200 Cft
@ 4,303.20 %0Cft 861
6 Filling, watering and ramming earth
under floors:- i) with surplus earth
from foundation, etc. ii) with new
earth excavated from outside, lead
upto one mile
1x 35 x 30 x 1.5 = 1575 Cft
Total: = 1575 Cft
D/d Surplus Earth = 200 Cft
Net Total = 1375 Cft
@ 13,591.40 %0Cft 18688

7 Providing and laying Tuff pavers ,


having 7000 PSI ,crushing strength of
approved manufacturer
over2"to3"sand cushion i/c grouting
with sand in joints i/c finishing to
require slope. Complete in all respect.
(50% Grey / 50% Coloured) 60-mm
thick

1x 35 x 30 = 1050 Sft
Total: = 1050 Sft
@ 126.80 P-Sft 133140

Total: 285450

Say Rs: 285000

Sub Divisional Officer


Sub Engineer Buildings Sub Division
Taunsa