You are on page 1of 9

Basic Rates

Sr. No. Item Unit Basic GST Total


1 Cement Bags 210 210
2 Aggregate Cft 26 26
3 Crushed Sand Cft 32 32
4 River Sand Cft 85 85
5 Chiken Mesh Sft 4 4
6 Waterproofing Compound Kg 150 150
7 AAC Blocks Cum 3000 3000
8 Block Fix Chemical Bags 425 425
9 Reinforcement Steel Kg 38 38
10 Labor for 100mm thick Masonry Sft 12 12
11 Labor for 125mm thick Masonry Sft 12 12
12 Labor for 150mm thick Masonry Sft 12 12
13 Labor for 200mm thick Masonry Sft 16 16
14 Labor for 250mm thick Masonry Sft 16 16
15 Labor for 300mm thick Masonry Sft 18 18
16 Labor for Patli Rft 0 0
17 Labor for Back Coat Plaster Sft 14 14
18 Labor for Single Coat Plaster Sft 18 18
19 Labor for Double Coat Plaster Sft 24 24
20 Gypsum to Walls Sft 23 23
21 Gypsum to Ceiling Sft 12 12
Project :
Item No.: 1a Unit : Cum
Description PCC 1:2:4 Analysis for : 1.00
Concrete Mix Manual Placing Manual
Sr. No. Description Unit Qty. Rate Amount
A MATERIAL :
1
2 Cement BAG 6.40 210.00 1,344.00
3 20 mm Aggregate CFT 29.99 26.00 779.69
5 Crushed Sand CFT 19.40 32.00 620.93
Wastage -
Wastage 5% 137.23
Total Material Cost Per : Cum 2,881.85
B LABOUR :

1 Production cost - PCC, RCC Cum 1.00 200.00 200.00


2
3

Add for Extra Lift


Lead per Floor 0 6.00% -
> Total Labor Cost Per : Cum 200.00

Material & Labor Cost 3,081.85

C Water & Electriciry -


Plant & Machinery -
Tools & Tackles -
Total Cost including Overheads 3,081.85
D Overheads -
Profit -
Total Rate 3,081.85

Rate in Rs/ Cum 3,082.00

Project :
Item No.: Unit : Sqm
Description 100mm thick AAC Block Masonry Analysis for : 1.00
Sr. No. Description Unit Qty. Rate Amount
A MATERIAL :
1 100mm AAC blocks Cum 0.10 3,000.00 300.00
2 Jointing Compound Bag 0.07 425.00 30.36
3 Steel Flat & Fasteners Kg 75.00 -
4 Concrete Band Cum 0.01 3,082.00 38.53
Wastage -
Wastage 3% 11.07
Total Material Cost Per : Sqm 379.95
B LABOUR :

1 AAC Block Masonry 100mm Sft 10.76 12.00 129.17


2 Concrete Band Rft 4.10 - -
Add for Extra Lift
Lead per Floor 3.00% -
> Total Labor Cost Per : Sqm 129.17

Material & Labor Cost 509.12

C Water & Electriciry -


Plant & Machinery -
Tools & Tackles -
Total Cost including Overheads 509.12

D Overheads -
Profit -
Total Rate 509.12

Rate in Rs/ Sqm 509.00

Project :
Item No.: Unit : Sqm
Description 125mm thick AAC Block Masonry Analysis for : 1.00
Sr. No. Description Unit Qty. Rate Amount
A MATERIAL :
1 100mm AAC blocks Cum 0.13 3,000.00 375.00
2 Jointing Compound Bag 0.08 425.00 32.69
3 Steel Flat & Fasteners Kg 75.00 -
4 Concrete Band Cum 0.02 3,082.00 48.16
Wastage -
Wastage 3% 13.68
Total Material Cost Per : Sqm 469.52
B LABOUR :

1 AAC Block Masonry 125mm Sft 10.76 12.00 129.17


2 Concrete Band Rft 4.10 - -
Add for Extra Lift
Lead per Floor 3.00% -
> Total Labor Cost Per : Sqm 129.17

Material & Labor Cost 598.69

C Water & Electriciry -


Plant & Machinery -
Tools & Tackles -
Total Cost including Overheads 598.69

D Overheads -
Profit -
Total Rate 598.69

Rate in Rs/ Sqm 599.00

Project :
Item No.: Unit : Sqm
Description 150mm thick AAC Block Masonry Analysis for : 1.00
Sr. No. Description Unit Qty. Rate Amount
A MATERIAL :
1 125mm AAC blocks Cum 0.15 3,000.00 450.00
2 Jointing Compound Bag 0.10 425.00 42.50
3 Steel Flat & Fasteners Kg 75.00 -
4 Concrete Band Cum 0.02 3,082.00 57.79
Wastage -
Wastage 3% 16.51
Total Material Cost Per : Sqm 566.80
B LABOUR :

1 AAC Block Masonry 150mm Sft 10.76 12.00 129.17


2 Concrete Band Rft 4.10 - -
Add for Extra Lift
Lead per Floor 3.00% -
> Total Labor Cost Per : Sqm 129.17

Material & Labor Cost 695.96

C Water & Electriciry -


Plant & Machinery -
Tools & Tackles -
Total Cost including Overheads 695.96

D Overheads -
Profit -
Total Rate 695.96
Rate in Rs/ Sqm 696.00

Project :
Item No.: Unit : Sqm
Description 200mm thick AAC Block Masonry Analysis for : 1.00
Sr. No. Description Unit Qty. Rate Amount
A MATERIAL :
1 200mm AAC blocks Cum 0.20 3,000.00 600.00
2 Jointing Compound Bag 0.14 425.00 60.71
3 Steel Flat & Fasteners Kg 75.00 -
4 Concrete Band Cum 0.03 3,082.00 77.05
Wastage -
Wastage 3% 22.13
Total Material Cost Per : Sqm 759.90
B LABOUR :

1 AAC Block Masonry 200mm Sft 10.76 16.00 172.22


2 Concrete Band Rft 4.10 - -
Add for Extra Lift
Lead per Floor 3.00% -
> Total Labor Cost Per : Sqm 172.22

Material & Labor Cost 932.12

C Water & Electriciry -


Plant & Machinery -
Tools & Tackles -
Total Cost including Overheads 932.12

D Overheads -
Profit -
Total Rate 932.12

Rate in Rs/ Sqm 932.00

Project :
Item No.: Unit : Sqm
Description 250mm thick AAC Block Masonry Analysis for : 1.00
Sr. No. Description Unit Qty. Rate Amount
A MATERIAL :
1 150mm AAC blocks Cum 0.25 3,000.00 750.00
2 Jointing Compound Bag 0.17 425.00 70.83
3 Steel Flat & Fasteners Kg 75.00 -
4 Concrete Band Cum 0.03 3,082.00 96.31
Wastage -
Wastage 3% 27.51
Total Material Cost Per : Sqm 944.66
B LABOUR :

1 AAC Block Masonry 200mm Sft 10.76 16.00 172.22


2 Concrete Band Rft 4.10 -
Add for Extra Lift
Lead per Floor 3.00% -
> Total Labor Cost Per : Sqm 172.22

Material & Labor Cost 1,116.88

C Water & Electriciry -


Plant & Machinery -
Tools & Tackles -
Total Cost including Overheads 1,116.88

D Overheads -
Profit -
Total Rate 1,116.88

Rate in Rs/ Sqm 1,117.00

Project :
Item No.: Unit : Sqm
Description 300mm thick AAC Block Masonry Analysis for : 1.00
Sr. No. Description Unit Qty. Rate Amount
A MATERIAL :
1 300mm AAC blocks Cum 0.30 3,000.00 900.00
2 Jointing Compound Bag 0.20 425.00 85.00
3 Steel Flat & Fasteners Kg 75.00 -
4 Concrete Band Cum 0.04 3,082.00 115.58
Wastage -
Wastage 3% 33.02
Total Material Cost Per : Sqm 1,133.59
B LABOUR :

1 AAC Block Masonry 300mm Sft 10.76 16.00 172.22


2 Concrete Band Rft 4.10 -
Add for Extra Lift
Lead per Floor 3.00% -
> Total Labor Cost Per : Sqm 172.22

Material & Labor Cost 1,305.82

C Water & Electriciry -


Plant & Machinery -
Tools & Tackles -
Total Cost including Overheads 1,305.82

D Overheads -
Profit -
Total Rate 1,305.82

Rate in Rs/ Sqm 1,306.00

Project :
Item No.: Unit : Sqm
Description 350mm thick AAC Block Masonry Analysis for : 1.00
Sr. No. Description Unit Qty. Rate Amount
A MATERIAL :
1 350mm AAC blocks Cum 0.35 3,000.00 1,050.00
2 Jointing Compound Bag 0.25 425.00 106.25
3 Steel Flat & Fasteners Kg 75.00 -
4 Concrete Band Cum 0.04 3,082.00 115.58
Wastage -
Wastage 3% 38.15
Total Material Cost Per : Sqm 1,309.98
B LABOUR :

1 AAC Block Masonry 200mm Sft 10.76 16.00 172.22


2 Concrete Band Rft 4.10 -
Add for Extra Lift
Lead per Floor 3.00% -
> Total Labor Cost Per : Sqm 172.22

Material & Labor Cost 1,482.20

C Water & Electriciry -


Plant & Machinery -
Tools & Tackles -
Total Cost including Overheads 1,482.20

D Overheads -
Profit -
Total Rate 1,482.20

Rate in Rs/ Sqm 1,482.00

Project :
Item No.: PLW003 Unit : Sqm
Description 12mm thick Backcoat plaster to Internal Faces Analysis for : 1.00
Sr. No. Description Unit Qty. Rate Amount
A MATERIAL :
1 Cement BAG 0.15 210.00 31.50
2 River Sand CFT 1.23 85.00 104.96
Chiken Mesh Sqm 0.10 43.06 4.31
GI wire Nails & Washers LS 5.00
5 -
Wastage -
Wastage 5% 7.29
Total Material Cost Per : Sqm 153.05
B LABOUR :

1 Plaster - Internal rough Sqft 10.76 14.00 150.70


2 Scaffolding 10.00
Add for Extra Lift
Lead per Floor 6.00% -
> Total Labor Cost Per : Sqm 160.70
Material & Labor Cost 313.75

C Water & Electriciry -


Plant & Machinery -
Tools & Tackles -
Total Cost including Overheads 313.75

D Overheads -
Profit -
Total Rate 313.75

Rate in Rs/ Sqm 314.00

Project :
Item No.: 3 Unit : Sqm
Description 20mm thick External Face plaster (Single Coat) Analysis for : 1.00
Sr. No. Description Unit Qty. Rate Amount
A MATERIAL :
1 Cement BAG 0.22 210.00 46.20
2 River Sand CFT 1.94 85.00 164.93
Chiken Mesh Sqm 0.10 43.06 4.31
GI wire Nails & Washers LS 5.00
Waterproofing Compound Kg 0.22 150.00 33.00
5 -
Wastage -
Wastage 5% 12.67
Total Material Cost Per : Sqm 266.11
B LABOUR :

1 Plaster - External Single Coat Sft 10.76 18.00 193.75


2 Scaffolding 15.00
Add for Extra Lift
Lead per Floor 6.00% -
> Total Labor Cost Per : Sqm 208.75

Material & Labor Cost 474.86

C Water & Electriciry -


Plant & Machinery -
Tools & Tackles -
Total Cost including Overheads 474.86

D Overheads -
Profit -
Total Rate 474.86

Rate in Rs/ Sqm 475.00

Project :
Item No.: 2 Unit : Sqm
Description 20mm thick External Face plaster (Double Coat) Analysis for : 1.00
Sr. No. Description Unit Qty. Rate Amount
A MATERIAL :
1 Cement BAG 0.27 210.00 56.70
2 River Sand CFT 1.94 85.00 164.93
Chiken Mesh Sqm 0.10 43.06 4.31
GI wire Nails & Washers LS 5.00
Waterproofing Compound Kg 0.27 150.00 40.50
Wastage -
Wastage 3% 8.14
Total Material Cost Per : Sqm 279.58
B LABOUR :

1 Plaster - External Double Coat Sft 10.76 24.00 258.34


2 Scaffolding 30.00
Add for Extra Lift
Lead per Floor 6.00% -
> Total Labor Cost Per : Sqm 288.34

Material & Labor Cost 567.92

C Water & Electriciry -


Plant & Machinery -
Tools & Tackles -
Total Cost including Overheads 567.92

D Overheads -
Profit -
Total Rate 567.92

Rate in Rs/ Sqm 568.00

You might also like