THUMB RULE

Co-efficients
SL No Activity adopted in
terms of SBA UOM
1 Shuttering 3 Sft
2 Reinforcement 4 Kg
3 Concrete (RMC) 0.04 Cum
4 Blockwork 1.5 Sft
5 Plastering 5 Sft
a) Internal Plastering 4 Sft
b) External Plastering 1 Sft
6 Tile Dadoo 0.5 Sft
7 Vitrified Tiling 0.3 Sft
8 Ceramic Tiling 0.2 Sft
9 Common Area Tiling 0.08 Sft
10 Granite 0.3 Sft
11 External Painting 0.8 Sft
12 Internal Painting 3.4 Sft

NMR THUMB RULE FOR 100,000 Sft OF SBA FOR GENERAL WORKS
(MARKING, COVER BLOCK, CURING & HOUSE KEEPING)

No.of persons
Description of works/ Phase I 6 Phase II 6 Phase III
Sl.no Category of workers months months 6 months Remarks
Basement Marking Mason
+ Helpers(1:1) 4( 1 month) 0 0
Masons for cover block +
Helpers(1:1) 2 (6 months) 2 (6 months) 0
Masons for Basement +
A Structure+ Helpers(1:1) 2.5 (6 months) 2.5 (5 months) 0
Masons for finishes +
Helpers(1:1) 2 (2 months) 2 (6 months) 2 (6 months)
Avg. of 5.83 Avg. of 6.08 Avg. of 2
Sub Total for Masons & masons/day masons/day masons/day
Helpers (say 6/day) (say 6/day)
Curing of structure 6 6 6 3 per one tower
Curing of Block work & 4 (4th month
B Plastering onwards) 8 (BF&Finish) 8
2 MC 4 MC 4 MC
House keeping, External
2 FC 2 FC 2 FC
C
House keeping, Internal 4 MC 8 8 12 Flats per person
Debris 2 MC 2 MC 2 MC Filling in Bags
Barricading - Carpenter 1 2 0
D
Helper 2 4 0
E Loading & Unloading 5 8 8
Total 40 56 42