Labour New Rate-2023

Unskilled 345.00
Semi skilled 385.00
Skilled 435.00
Highly skilled 495.00
Overhead charges 7.50 %
Contractor's profit 7.50 %
Contractor's profit & overhead charges 15.00 %
Labour CESS 1.00 %
1 Providing and fixing to wall or ceiling and floor rigid PVC pipes conforming to ASTM-D-1785/89[Sch-80] and
pipe fittings of the following nominal bore with clamps including making good the wall , ceiling and floor all
complete as per specification.
PH analysis 2013 WATER SUPPLY item no 3.1.4 / P - 100
Data for 10.00 mtr
i 15mm. Diameter
SUPREME 257.00 / 3.0 M
85.66 /M
Deduct 18% GST 15.41
70.25 /M
A.cost of material
15mm dia PVC Sch-80 pipes 10.00 m Rmt 70.25 = Rs 702.50
Pipe Fittings & wastage 15.00 % = Rs 105.37
Wooden plug , clamps cement etc 3.00 % 21.07
807.87
B.Labour
Plumber Fitter 0.67 nos each 435.00 = Rs 291.45
Male worker 0.67 nos each 345.00 = Rs 231.15
522.60
A+B 1330.47
C.Add Contractor's profit &overhead 15.00 % Rs 199.57
charges Total [a+b+c] Rs 1530.04 /10Rmt

Rate per 1Rmt. Rs 153.00 /Rmt


Labour CESS 1.00 % Rs 1.53
Rs 154.53 /Rmt

Or Say. Rs 154.50 /Rmt


ii 20mm. Diameter.
A.cost of material
SUPREME 350.00 / 3.0 M
116.66 / M
Deduct 18% GST 20.99
95.67 / M
20mm dia PVC Sch-80 pipes 10.00 m Rmt 95.67 = Rs 956.70
Pipe Fittings & wastage 15.00 % = Rs 143.50
Wooden plug , clamps cement etc 3.00 % 28.70
1128.90
B. labour
Plumber (Fitter ) 0.75 nos each 435.00 = Rs 326.25
Male worker 0.67 nos each 345.00 = Rs 231.15
557.40
A+B 1686.30
C.Add Contractor's profit &overhead 15.00 % Rs 252.94
charges Rs 1939.24 /10Rmt

Rate per 1Rmt. Rs 193.92 /Rmt


Labour CESS 1.00 % Rs 1.93
Rs 195.85 /Rmt

Or Say. Rs 195.90 /Rmt


iii 25mm. Diameter
SUPREME 512.00 / 3.0 M
170.66 / M
Deduct 18% GST 30.71
139.95 / M
A. Material
25mm dia PVC Sch-80 pipes 10.00 m Rmt 139.95 = Rs 1399.50
Pipe Fittings & wastage 15.00 % = Rs 209.92
Wooden plug , clamps cement etc 3.00 % 41.98
1651.40
B. Labour for laying
Plumber Fitter 0.83 nos each 435.00 = Rs 361.05
Male worker 0.67 nos each 345.00 = Rs 231.15
592.20
A+B 2243.60
C.Add Contractor's profit &overhead 15.00 % Rs 336.54
charges Rs 2580.14 /10Rmt
Rate per 1Rmt. Rs 258.01 /Rmt
Labour CESS 1.00 % Rs 2.58
Rs 260.59 /Rmt

Or Say. Rs 260.60 /Rmt


iv 32mm. dia meter
SUPREME 712.00 / 3.0 M
237.33 / M
Deduct 18% GST 42.71
194.62 / M
A. Materials
32mm dia PVC Sch-80 pipes 10.00 m Rmt 194.62 = Rs 1946.20
Pipe Fittings & wastage 15.00 % = Rs 291.93
Wooden plug , clamps cement etc 3.00 % 58.38
2296.51
B.Labour
Plumber ,Fitter 0.83 nos each 15.00 = Rs 12.45
Male worker 1.00 nos each 345 = Rs 345.00
357.45
A+B 2653.96
C.Add Contractor's profit &overhead 15.00 % Rs 398.09
charges Rs 3052.05 /10Rmt

Rate per 1Rmt. Rs 305.20 /Rmt


Labour CESS 1.00 % Rs 3.05
Rs 308.25 /Rmt

Or Say. Rs 308.30 /Rmt


v 40mm. Diameter.
SUPREME 873.00 / 3.0 M
291 / M
Deduct 18% GST 52.38
238.62 / M
A. Materials
40mm dia PVC Sch-80 pipes 10.00 m Rmt 238.62 = Rs 2386.20
Pipe Fittings & wastage 15.00 % = Rs 357.93
Wooden plug , clamps cement etc 3.00 % 71.58
2815.71
B.Labour
Plumber (Fitter ) 1.00 nos each 435.00 = Rs 435.00
Male worker 1.33 nos each 345.00 = Rs 458.85
893.85
A+B 3709.56
C.Add Contractor's profit &overhead 15.00 % Rs 556.43
charges Rs 4265.99 /10Rmt

Rate per 1Rmt. Rs 426.59 /Rmt


Labour CESS 1.00 % Rs 4.26
Rs 430.85 /Rmt

Or Say. Rs 430.90 /Rmt


vi 50mm. Diameter
SUPREME 1188.00 / 3.0 M
396 / M
Deduct 18% GST 71.28
324.72 / M
A. Materials
50mm dia PVC Sch-80 pipes 10.00 m Rmt 324.72 = Rs 3247.20
Pipe Fittings & wastage 15.00 % = Rs 487.08
Wooden plug , clamps cement etc 3.00 % 97.41
3831.69
B.Labour
Plumber (Fitter ) 1.17 nos each 435 = Rs 508.95
Male mulia 1.67 nos each 345 = Rs 576.15
1085.10
A+B 4916.79
C.Add Contractor's profit &overhead 15.00 % Rs 737.51
charges Rs 5654.30 /10Rmt

Rate per 1Rmt. Rs 565.43 /Rmt


Labour CESS 1.00 % Rs 5.65
Rs 571.08 /Rmt

Or Say. Rs 571.10 /Rmt


3 Providing and fixing Clorinated Polyvinyl Chloride [CPVC]pipes conforming to IS:15778, having thermal
stablity for hot & cold water supply , including all CPVC plain & brass threaded fittingincluding fixing the pipe
with clamps at 1.00m spacing . This includes jointing of pipes and fittings with one stp CPVC solvent cement and
testing of joints complete as per specification and direction of Enfineer-in-charge.

PH analysis 2013 WATER SUPPLY item no 3.1.5 / P - 102


Data for 10.00 mtr
i 15mm. Outer Diameter
A.cost of material
15mm dia CPVC pipes 10.00 m Rmt 65.48 = Rs 654.80
Pipe Fittings & wastage 30.00 % = Rs 196.44
Cement sand & grit etc. LS 4.07
855.31
B.Labour
Plumber Fitter 0.33 nos each 435 = Rs 143.55
Helper to plumber 0.82 nos each 385 = Rs 315.70
Male worker 0.66 nos each 345 = Rs 227.70
686.95
A+B 1542.26
C.Add Contractor's profit &overhead 15.00 % Rs 231.33
charges Total [a+b+c] Rs 1773.59 /10Rmt

Rate per 1Rmt. Rs 177.35 /Rmt


Labour CESS 1.00 % Rs 1.77
Rs 179.12 /Rmt

Or Say. Rs 179.10 /Rmt


ii 20mm. Diameter.
A.cost of material
20mm dia CPVC pipes 10.00 m Rmt 96.12 = Rs 961.20
Pipe Fittings & wastage 30.00 % = Rs 288.36
Cement sand & grit etc. LS 4.07
1253.63
B. labour
Plumber (Fitter ) 0.33 nos each 435 = Rs 143.55
Helper to plumber 0.98 nos each 385 = Rs 377.30
Male worker 0.66 nos each 345 = Rs 227.70
748.55
A+B 2002.18
C.Add Contractor's profit &overhead 15.00 % Rs 300.32
charges Rs 2302.50 /10Rmt

Rate per 1Rmt. Rs 230.25 /Rmt


Labour CESS 1.00 % Rs 2.3
Rs 232.55 /Rmt

Or Say. Rs 232.60 /Rmt


iii 25mm. Diameter
A. Material
25mm dia CPVC pipes 10.00 m Rmt 147.73 = Rs 1477.30
Pipe Fittings & wastage 30.00 % = Rs 443.19
Cement sand & grit etc. LS 6.20
1926.69
B. Labour for laying
Plumber Fitter 0.33 nos each 435 = Rs 143.55
Helper to plumber 0.98 nos each 385 = Rs 377.30
Male worker 0.98 nos each 345 = Rs 338.10
858.95
A+B 2785.64
C.Add Contractor's profit &overhead 15.00 % Rs 417.84
charges Rs 3203.48 /10Rmt
Rate per 1Rmt. Rs 320.34 /Rmt
Labour CESS 1.00 % Rs 3.2
Rs 323.54 /Rmt

Or Say. Rs 323.50 /Rmt


iv 32mm. dia meter
A. Materials
32mm dia CPVC pipes 10.00 m Rmt 229.04 = Rs 2290.40
Pipe Fittings & wastage 30.00 % = Rs 687.12
Cement sand & grit etc. LS 6.20
2983.72
B.Labour
Plumber ,Fitter 0.33 nos each 435.00 = Rs 143.55
Helper to plumber 0.98 nos each 385.00 = Rs 377.30
Male worker 0.98 nos each 345.00 = Rs 338.10
858.95
A+B 3842.67
C.Add Contractor's profit &overhead 15.00 % Rs 576.40
charges Rs 4419.07 /10Rmt

Rate per 1Rmt. Rs 441.90 /Rmt


Labour CESS 1.00 % Rs 4.41
Rs 446.31 /Rmt

Or Say. Rs 446.30 /Rmt


5 Providing and fixing of Rational moulded polyethylene cylendrical vertical water storate tanks confirming to
IS:12701-1996 including cutting holes through the tank and fixing mild steel tubes and fittings and proviidng
extra sockets and jam nuts , fixing ball volve ete. including hoisting up to a hite of 5.00metes above ground level
and placing the tank to the required position etc. all complete as per specification and direction of the engineer-
in-charge.
PH analysis 2013 WATER SUPPLY item no 3.1.8/ P - 108
i 2000 liter capacity double layer cylendrical vertical water storage tanks
Details of cost for one tank on the roof ground floor
A. Materials:
SUPREME - 2 Layer ISI Marked
2000 liter capacity double layer
2000.00 liter liter 9.80 = Rs 19600.00
cylendrical vertical water storage tanks
lead paint and yarn LS = Rs 6.60
19606.60
B.Labour
Plumber fitter [S] 0.50 nos each 435 = Rs 217.50
Helper 0.75 nos each 385 = Rs 288.75
Male worker 5.00 nos each 345 = Rs 1725.00
2231.25
A+B 21837.85
Add Contractor's profit &overhead 15.00 % Rs 3275.67
charges Rs 25113.52 /each
Labour CESS 1.00 % Rs 251.13
Rs 25364.65 /each
Or Say. Rs 25364.70 /each
i 1000 liter capacity double layer cylendrical vertical water storage tanks
Details of cost for one tank on the roof ground floor
A. Materials:
1000 liter capacity double layer
1000.00 liter liter 9.00 = Rs 9000.00
cylendrical vertical water storage tanks
lead paint and yarn LS = Rs 6.60
9006.60
B.Labour
Plumber fitter [S] 0.50 nos each 435 = Rs 217.50
Helper 0.75 nos each 385 = Rs 288.75
Male worker 4.00 nos each 345 = Rs 1380.00
1886.25
A+B 10892.85
Add Contractor's profit &overhead 15.00 % Rs 1633.92
charges Rs 12526.77 /each
Labour CESS 1.00 % Rs 125.26
Rs 12652.03 /each

Or Say. Rs 12652.00 /each


6 Extra over item no.3.1.8 for hoisting Rational moulded polyethylene cylendrical vertical water storate tanks of
following sizes for every additional height of 5.00m. Or part thereof complete as per specification and direction of
the engineer-in-charge.
PH analysis 2013 WATER SUPPLY item no 3.1.9/ P - 108
i 2000 liter capacity double layer cylendrical vertical water storage tanks
Details of cost for hoisting one tank
A.Labour
Helper 0.25 nos each 385 = Rs 96.25
Male worker 2.00 nos each 345 = Rs 690.00
786.25
Add Contractor's profit &overhead 15.00 % Rs 117.93
charges Rs 904.18 /each
Labour CESS 345.00 % Rs 9.04
Rs 913.22 /each

Or Say. Rs 913.20 /each


ii 1000 liter capacity double layer cylendrical vertical water storage tanks
Details of cost for hoisting one tank
A.Labour
Helper 0.25 nos each 385 = Rs 96.25
Male worker 2.00 nos each 345 = Rs 690.00
786.25
Add Contractor's profit &overhead 15.00 % Rs 117.93
charges Rs 904.18 /each
Labour CESS 1.00 % Rs 9.04
Rs 913.22 /each

Or Say. Rs 913.20 /each

III HOUSE SERVICE PIPES 3.2


1 Supplying all materials, labour and T&P and laying in trenches, PVC pipes conforming to ASTM-D-1785/89
[Sch-80],the following nominal bore and pipe fittings including testing as per specification all complete.
[excluding earth work in trenches ]
PH analysis 2013 HOUSE SERVICE PIPES item no 3.2.7 / P - 121
Data for 10.00 mtr
i 15mm. Diameter
A.cost of material
15mm. dia ASTM sch-80 pipe
10.00 m Rmt 31.3 = Rs 313.00
[considering 6m length]
Pipe Fittings & wastage 2.00 % = Rs 6.26
319.26
B.Labour
Plumber (Fitter ) 0.08 nos each 435 = Rs 34.80
Male worker 0.16 nos each 345 = Rs 55.20
90.00
A+B 409.26
C.Add Contractor's profit &overhead 15.00 % Rs 61.38
charges Total [a+b+c] Rs 470.64 /10Rmt
Rate per 1Rmt. Rs 47.06 /Rmt
Labour CESS 1.00 % Rs 0.47
Rs 47.53 /Rmt

Or Say. Rs 47.50 /Rmt


ii 20mm. Diameter.
A.cost of material
20mm. dia ASTM sch-80 pipe
10.00 m Rmt 42.3 = Rs 423.00
[considering 6m length]
Fittings & wastages of ( med) 2.00 % = Rs 8.46
431.46
B. labour
Plumber (Fitter ) 0.08 nos each 435 = Rs 34.80
Male worker 0.16 nos each 345 = Rs 55.20
90.00
A+B 521.46
C.Add Contractor's profit &overhead 15.00 % Rs 78.21
charges Rs 599.67 /10Rmt

Rate per 1Rmt. Rs 59.96 /Rmt


Labour CESS 1.00 % Rs 0.59
Rs 60.55 /Rmt

Or Say. Rs 60.60 /Rmt


iii 25mm. Diameter
A. Material
25mm. dia ASTM sch-80 pipe
10.00 m Rmt 62.1 = Rs 621.00
[considering 6m length]
Fittings & wastages 2.00 % = Rs 12.42
633.42
B. Labour for laying
Plumber Fitter [S] 0.12 nos each 435 = Rs 52.20
Male worker 0.25 nos each 345 = Rs 86.25
138.45
A+B 771.87
C.Add Contractor's profit &overhead 15.00 % Rs 115.78
charges Rs 887.65 /10Rmt
Rate per 1Rmt. Rs 88.76 /Rmt
Labour CESS 1.00 % Rs 0.88
Rs 89.64 /Rmt

Or Say. Rs 89.60 /Rmt


iv 32mm. dia meter
A. Materials
32mm. dia ASTM sch-80 pipe
10.00 m Rmt 85.9 = Rs 859.00
[considering 6m length]
Pipe Fittings & wastages 2.00 % = Rs 17.18
876.18
B.Labour
Plumber ,Fitter [S] 0.12 nos each 435 = Rs 52.20
Male worker 0.25 nos each 345 = Rs 86.25
138.45
A+B 1014.63
C.Add Contractor's profit &overhead 15.00 % Rs 152.19
charges Rs 1166.82 /10Rmt

Rate per 1Rmt. Rs 116.68 /Rmt


Labour CESS 1.00 % Rs 1.16
Rs 117.84 /Rmt

Or Say. Rs 117.80 /Rmt


v 40mm. Diameter.
A. Materials
40mm. dia ASTM sch-80 pipe
10.00 m Rmt = Rs 0.00
[considering 6m length]
Pipe Fittings & wastages 2.00 % = Rs 0.00
0.00
B.Labour
Plumber (Fitter ) 0.16 nos each 435 = Rs 69.60
Male worker 0.33 nos each 345 = Rs 113.85
183.45
A+B 183.45
C.Add Contractor's profit &overhead 15.00 % Rs 27.51
charges Rs 210.96 /10Rmt

Rate per 1Rmt. Rs 21.09 /Rmt


Labour CESS 1.00 % Rs 0.21
Rs 21.30 /Rmt

Or Say. Rs 21.30 /Rmt


vi 50mm. Diameter
A. Materials
50mm. dia ASTM sch-80 pipe
10.00 m Rmt 144.40 = Rs 1444.00
[considering 6m length]
Fittings & wastages of ( med) 2.00 % = Rs 28.88
1472.88
B.Labour
Plumber (Fitter ) 0.16 nos each 435 = Rs 69.60
Male mulia 0.33 nos each 345 = Rs 113.85
183.45
A+B 1656.33
C.Add Contractor's profit &overhead 15.00 % Rs 248.44
charges Rs 1904.77 /10Rmt

Rate per 1Rmt. Rs 190.47 /Rmt


Labour CESS 1.00 % Rs 1.9
Rs 192.37 /Rmt

Or Say. Rs 192.40 /Rmt


4 Supplying all labour and T&P for fixing CP short body Bib cock [taps] polished bright confirming to IS:781-1995
of the following nominal sizes as per specification all complete .
PH analysis 2013 HOUSE SERVICE PIPES item no 3.2.14 / P - 133
Data for 10 nos
i 15mm. dia. Bib cock
CERA - RIPPLE F1017151
Bib Cock with wall flange & aerator 1825.00 / Each
Deduct 18% GST 328.50
1496.50 / Each
A. Materials:
15mm dia CP short body bib cock 10 nos each 1496.50 = Rs 14965.00
b. Labour
Plumber Fitter(S) 0.33 nos each 435 = Rs 143.55
helper to plumber / fitter 0.33 nos each 385 = Rs 127.05

Jointing materials on labour 2.00 % Rs 5.41


15241.01
Add Contractor's profit &overhead 15.00 % Rs 2286.15
charges 17527.16 /10nos
Rate per each 1752.71
CESS 1.00 % 17.52
1770.23 /each

or 1770.20 /each

5 Supplying all labour and T&P for fixing long body bib cock of the following size as per specification all
complete (including cost of cock )
PH analysis 2013 HOUSE SERVICE PIPES item no 3.2.15 / P - 134
Data for 10 nos
i 15mm. Diameter
CERA - RIPPLE F1017152
Bib Cock long nose with wall flange & aerator 2075.00 / Each
Deduct 18% GST 373.50
1701.50 / Each
A. Materials:
15mm dia long body Bib cock 10 nos each 1701.50 = Rs 17015.00
b. Labour
Plumber Fitter(S) 0.33 nos each 435 = Rs 143.55
helper to plumber / fitter 0.33 nos each 385 = Rs 127.05
Jointing materials on labour 2.00 % Rs 5.41
17291.01
Add Contractor's profit &overhead 15.00 % Rs 2593.65
charges 19884.66 /10nos
Rate per each 1988.46
CESS 1.00 % 19.88
2008.34 /each

or 2008.30 /each
5 Supplying all labour and T&P for fixing 2 in 1 bib cock of the following size as per specification all complete
(including cost of cock )
PH analysis 2013 HOUSE SERVICE PIPES item no 3.2.15 / P - 134
Data for 10 nos
i 15mm. Diameter
CERA - RIPPLE F1017211
2 way angle cock with wall flange 1885.00 / Each
Deduct 18% GST 339.30
1545.70 / Each
A. Materials:
15mm dia 2 in 1 Bib cock 10 nos each 1545.70 = Rs 15457.00
b. Labour
Plumber Fitter(S) 0.33 nos each 435 = Rs 143.55
helper to plumber / fitter 0.33 nos each 385 = Rs 127.05

Jointing materials on labour 2.00 % Rs 5.41


15733.01
Add Contractor's profit &overhead 15.00 % Rs 2359.95
charges 18092.96 /10nos
Rate per each 1809.29
CESS 1.00 % 18.09
1827.38 /each

or 1827.40 /each
6 Supplying all labour and T&P for fixing CP Angular stop cocks polished bright confirming to IS:781-1995 of the
following nominal sizes as per specification all complete .
PH analysis 2013 HOUSE SERVICE PIPES item no 3.2.16 / P - 134
Data for 10 nos
i 15mm. Diameter
A. Materials:
CERA - RIPPLE F1017201
Angle cock with wall flange 1545.00 / Each
Deduct 18% GST 278.10
1266.90 / Each
15mm dia CP angular stop cock 10 nos each 1266.90 = Rs 12669.00
b. Labour
Plumber Fitter(S) 0.50 nos each 435 = Rs 217.50
helper to plumber / fitter 0.50 nos each 385 = Rs 192.50

Jointing materials on labour 2.00 % Rs 8.20


13087.20
Add Contractor's profit &overhead 15.00 % Rs 1963.08
charges 15050.28 /10nos
Rate per each 1505.02
CESS 1.00 % 15.05
1520.07 /each

or 1520.10 /each
ii 20mm. Diameter
A. Materials:
20mm dia CP angular stop cock 10 nos each 592.40 = Rs 5924.00
b. Labour
Plumber Fitter(S) 0.75 nos each 435 = Rs 326.25
helper to plumber / fitter 0.75 nos each 385 = Rs 288.75

Jointing materials on labour 2.00 % Rs 12.30


6551.30
Add Contractor's profit &overhead 15.00 % Rs 982.69
charges 7533.99 /10nos
Rate per each 753.39
CESS 1.00 % 7.53
760.92 /each

or 760.90 /each
7 Supplying all labour and T&P for fixing CP Concealed stop cocks polished bright confirming to IS:781-1995 of
the following nominal sizes as per specification all complete .
PH analysis 2013 HOUSE SERVICE PIPES item no 3.2.16 / P - 134
Data for 10 nos
i 15mm. Diameter
CERA - RIPPLE F1017351//F4050102
Stop Cock 1660.00 / Each
Deduct 18% GST 298.80
1361.20 / Each
A. Materials:
15mm dia CP concealed stop cock 10 nos each 1361.20 = Rs 13612.00
b. Labour
Plumber Fitter(S) 0.50 nos each 435 = Rs 217.50
helper to plumber / fitter 0.50 nos each 385 = Rs 192.50

Jointing materials on labour 2.00 % Rs 8.20


14030.20
Add Contractor's profit &overhead 15.00 % Rs 2104.53
charges 16134.73 /10nos
Rate per each 1613.47
CESS 1.00 % 16.13
1629.60 /each

or 1629.60 /each
ii 20mm. Diameter
A. Materials:
20mm dia CP concealed stop cock 10 nos each 704.90 = Rs 7049.00
b. Labour
Plumber Fitter(S) 0.75 nos each 435 = Rs 326.25
helper to plumber / fitter 0.75 nos each 385 = Rs 288.75

Jointing materials on labour 2.00 % Rs 12.30


7676.30
Add Contractor's profit &overhead 15.00 % Rs 1151.44
charges 8827.74 /10nos
Rate per each 882.77
CESS 1.00 % 8.82
891.59 /each

or 891.60 /each
7 Supplying all labour and T&P for fixing Brass /Gunmetal full way volve confirming to IS:781-1995 of the
following nominal sizes as per specification all complete.
PH analysis 2013 HOUSE SERVICE PIPES item no 3.2.17/ P - 135
Data for 10 nos
i 25mm. Diameter 20mm/25mm
A. Materials:
15mm dia brass /Gun metal fullway
10 nos each 872.40 = Rs 8724.00
volve
b. Labour
Plumber Fitter(S) 0.50 nos each 435 = Rs 217.50
helper to plumber / fitter 0.50 nos each 385 = Rs 192.50

Jointing materials on labour 2.00 % Rs 8.20


9142.20
Add Contractor's profit &overhead 15.00 % Rs 1371.33
charges 10513.53 /10nos
Rate per each 1051.35
CESS 1.00 % 10.51
1061.86 /each
or 1061.90 /each
ii 32mm. Diameter 40mm/50mm
A. Materials:
32mm dia brass brass /Gun metal fullway
10 nos each 1275.50 = Rs 12755.00
volve
b. Labour
Plumber Fitter(S) 0.75 nos each 435 = Rs 326.25
helper to plumber / fitter 0.75 nos each 385 = Rs 288.75

Jointing materials on labour 2.00 % Rs 12.30


13382.30
Add Contractor's profit &overhead 15.00 % Rs 2007.34
charges 15389.64 /10nos
Rate per each 1538.96
CESS 1.00 % 15.38
1554.34 /each

IV PLUMBING SOIL WASTE,VENTILATING PIPES &FITTINGS 3.3

PVC Vent Cowl


i 110 mm diameter
SUPREME
39.00 / Each
Deduct 18% GST 7.02
31.98 / Each
Details of cost for 1 tee
A.Materials
110mm dia bend 1.00 nos each 31.98 = Rs 31.98
rubber seal ring 1.00 nos Each 20.00 = Rs 20.00
Adhesive etc LS 4.07
Carriage of materils & fixing charges
LS 16.08
etc.
72.13
Add Contractor's profit &overhead 15.00 % Rs 10.81
charges Rs 82.94 /each
rate per one meter 82.94 /each
Labour CESS 1.00 % Rs 0.82
Rs 83.76
Or Say. Rs 83.80 /each
V SANITARY INSTALLATION 3.4

1 Supplying all materials,labour and T&P for fixing water closet ,squatting pan(Indian type.W.C.pan or Orissa pan)
confirming to IS 2556 : Part-3-2004 duly embedded in cement concrete (1:4:8) using 40mm.nominal size h.b.g.
chips [including foot rest for I.W.C. and trap] all complete as per specificationand directon of theEngineer - in -
charge.
PH analysis 2013 Sanitary installation item no 3-4-1 / P-147
CERA ORISSA PAN
CALINA // S3010102 2495.00 / Each
Deduct 18% GST 449.10
2045.90 / Each
I.W.C
A. Materials
Cost of IWC 580mm 1.00 nos each 2045.90 2045.90
Cost of Trap Nahani without Jali each 166.00 166.00
Cement for .12cum cc 0.206 qntl qntl 580.80 = Rs 119.64
sand 0.058 cum cum 48.57 2.81
metal 0.115 cum cum 709.52 81.59

B.Labour
Plumber /Mason 0.50 nos each 435.00 = Rs 217.50
Male mulia 0.50 nos each 345.00 = Rs 172.50
A+B[ labour+material] 2805.94
C.
Add Contractor's profit &overhead 15.00 % Rs 420.89
charges
D.Carriage of materials:
Cement for .12cum cc 0.206 qntl qntl 16.17 3.33
sand 0.058 cum cum 237.67 13.78
metal 0.115 cum cum 607.87 69.90
E.Royality of materials:
sand 0.058 cum cum 35.00 2.03
metal 0.115 cum cum 130.00 14.95

A+B+C 3330.82
Labour CESS 1.00 % Rs 33.3
Rs 3364.12 /each

Or Say. Rs 3364.10 /each


2 Supplying all materials,labour and Supplying all materials,labour and T&P for fixing in cement mortar (1:3) a
pair of white vitereous china (250x130x30mm.) foot rest for squatting water closet. etc. all complete as per
specificationand direction of the Engineer-in-charge.

PH analysis 2013 Sanitary installation item no 3.4.2 / P-147


I.W.C. foot rest:-
A.Material
Cost of IWC Foot rest one pair 1.00 nos each 436.60 436.60
Cement & sand including carriage of
LS = Rs 12.01
materials
448.61
B.labour
Plumber (fitter) 0.06 nos each 435.00 = Rs 26.10

A+B 474.71
contractors profit &Over head charges o 15.00 % Rs 71.20
Rs 545.91 /Pair
Labour CESS 1.00 % Rs 5.45
Rs 551.36 /Pair

Or Say. Rs 551.40 /each


3 Supplying all materials,labour and T&P for fixing of 100mm size'P' or 'S' trap [ with horn or without horn]for
water closet sqatting pan including jointing the trap with pan in cement mortar 1:1 etc. all complete as per
specification and direction of the Engineer-in-charge.

PH analysis 2013 Sanitary installation item no 3.4.3 / P-147


P' trap
SUPREME
333.00 / Each
Deduct 18% GST 59.94
273.06 / Each
A.Material
Rate same as per item no.3.3.4 [ ii ]
excluding sundries and OH charges #REF!
B.110mm dia PVC SWR 'P' trap 1.00 nos each 273.06 273.06

A+B #REF!
contractors profit &Over head charges o 15.00 % Rs #REF!
Rs #REF! /each
Labour CESS 1.00 % Rs #REF!
Rs #REF! /each

Or Say. Rs #REF! /each

4 Supplying all materials,labour and T&P for Supplying all materials,labour and T&P for fixing wash down water
closet (European type W.C.) with integral "S" or "P" trap tothe floor with wooden plug and chromium plated
screw including jointing the trap with soil pipe in cement mortar (1:1) etc. all complete as per specification.
PH analysis 2013 Sanitary installation item no 3.4.4/ P-148
White vtreous China wash down water closet [E.W.C.]
CERA CEMELIA-Concealed // Snow White
4040.00 / Each
Deduct 18% GST 727.20
3312.80 / Each
A.Materials
White vtreous
Jointing China
trap with soil EWC with
pipe as 'P' trap
percement
item 1.00 nos each 3312.80 3312.80
C.P. screw,washers,plugs,white
no.3.3.4 [ ii ] excluding sundries and OH LS = Rs 19.95
etc
charges #REF!
Carriage of materials LS = Rs 20.14
#REF!
B.Labour
Plumber (fitter) 0.50 nos each 435.00 = Rs 217.50
Male mulia 0.50 nos each 345.00 = Rs 172.50
390.00
A+B #REF!
Over head charges on A+B 15.00 % Rs #REF!
Rs #REF! /each
Labour CESS 1.00 % Rs #REF!
Rs #REF! /each

Or Say. Rs #REF! /each

5 Supplying all materials,labour and T&P for fixing plastic seat and cover for wash down water closet with
chromium plated brass hinges and rubber buffers all complete as per specification.
PH analysis 2013 Sanitary installation item no 3.4.5/ P-148
Plastic Seat & Cover
CERA CARINA PLUS // Snow White
900.00 / Each
Deduct 18% GST 162.00
738.00 / Each
A.Materials
White Plastic seat and cover 1.00 nos each 738.00 738.00

B.Labour
Fixing charges including sundries ,T&P and carriage of T&P LS = Rs 19.95

A+B 757.95
Over head charges on A+B 15.00 % Rs 113.69
Rs 871.64 /each
Labour CESS 1.00 % Rs 8.71
Rs 880.35 /each

Or Say. Rs 880.40 /each

6 Supplying all materials,labour and T&P for fixing of PVC10.00 ltr capacity low level flushing cistern with
manually controlled device[handle cover] confirming to IS 7231 with fittings and fixtures etc. all complete as per
specification.

PH analysis 2013 Sanitary installation item no 3.4.6/ P-148


10 ltrs capacity low level cistern:-
CERA CONVENTIONAL // SNOW WHITE
Cat No. S1060105 2445.00 / Each
Deduct 18% GST 440.10
2004.90 / Each
A.Materials
Cost of 10lt. Low level cistern fittings
1.00 nos each 2004.90 2004.90
and accessories
Carriage of materials LS = Rs 7.75
B.Labour[ considering one fitter & one belder can fix 8 cisterns per day]
Plumber (fitter)/Mason. 0.125 nos each 435.00 = Rs 54.37
Man mulia 0.125 nos each 345.00 = Rs 43.12
A+B 2110.14
Over head charges & C.Profiton A+B 15.00 % Rs 316.52
Rs 2426.66 /each
Labour CESS 1.00 % Rs 24.26
Rs 2450.92 /each

Or Say. Rs 2450.90 /each

7 Supplying all materials,labour and T&P for fixing Bowl pattern urinal conforming to IS :2556: part 6-1996
including connecting the urinal of 430x260x350 mm or 340x410x265mm sizes respectively with waste pipe by
means of white lead mixed with choppedhempetc. all complete as per specification.

PH analysis 2013 Sanitary installation item no 3.4.8/ P-150


i.Vitreous china -Flat Back urinal of 375x390x590 mm size
CERA CAPRIANA // Snow White
Cat No. S4020112 5555.00 / Each
Deduct 18% GST 999.90
4555.10 / Each
CERA Urinal Spreader
F8070201 810.00 / Each
Deduct 18% GST 145.80
664.20 / Each
A.Materials
Cost of Flat back urinal 375x390x590mm 1.00 nos each 4555.10 4555.10
Urinal Spreader 1.00 nos each 664.20 664.20
Domed Waste coupling 5.0 % 305.4 305.40
Waste pipe 50x800mm 5.0 % 94.92 94.92
Carriage materials LS = Rs 14.14
B.Labour
Plumber (fitter)/Mason. 0.38 nos each 435.00 = Rs 165.30
Male mulia 0.38 nos each 345.00 = Rs 131.10
A+B 5930.16
Over head charges on A+B 15.00 % Rs 889.52
Rs 6819.68 /each

Labour CESS 1.00 % Rs 68.19


Rs 6887.87 /each

Or Say. Rs 6887.90 /each

8 Supplying all materials,labour and T&P for fixing glazed earthen-ware squatting plate of size (600 mmx350mm.)
confirming to IS : 2556-part-6-1995 with integral longitudinal flushing pipe including embedding the plate in
25mm. cement mortar (1:8) laid over 150mm. cement concrete (1:4:8) using 40mm. size h.b.g. chips all complete
as per specification.
PH analysis 2013 Sanitary installation item no 3.4.9/ P-150
One - seated Urinal 600 x 355 mm size
A Materials
A.Vitreous china squatting plate urinal 1.00 nos each 1397.40 1397.40
Cement ,sand grit etc. 16.08
Carriage of materials 19.95

B.Labour
Plumber (fitter) 0.50 nos each 435.00 = Rs 217.50
Mason. 0.50 nos each 435.00 = Rs 217.50
Male mulia 1.00 nos each 345.00 = Rs 345.00

A+B 2213.43
D. oh charges etc.
Over head charges contractors profit 15.00 % Rs 332.01

Rs 2545.44 /each

Labour CESS 1.00 % Rs 25.45


Rs 2570.89 /each

Or Say. Rs 2570.90 /each

9 Supplying all materials,labour and T&P for fixing wash hand basin with hole for pillar taps confirming to IS
2556:part4-2004 with cast iron /M.S. brackets painted white including cutting holes in walls and making good to
the damages etc. all complete as per specification.
PH analysis 2013 Sanitary installation item no 3.4.11/ P-151
Vitreoous china flat back Wash hand basin 460x350x180mm
CERA CHIME // Snow White
Cat No. S2040139 1830.00 / Each
Deduct 18% GST 329.40
1500.60 / Each
A. Materials
Cost of wash hand basin 460x350x180 1.00 nos each 1500.60 1500.60
CI bracket for wash basin and sinks 53.00 % 132 185.00
Waste pipe 32x1150mm 80.00 % 59.32 139.32
Cement, sand and wooden plugs etc. LS = Rs 24.02
1848.94
B.Labour
Plumber (fitter) 0.33 nos each 435.00 = Rs 143.55
Mason. 0.33 nos each 435.00 = Rs 143.55
Man mulia 0.67 nos each 345.00 = Rs 231.15
518.25
A+B 2367.19
Over head charges contractors profit 15.00 % Rs 355.07
Rs 2722.26 /each
Labour CESS 1.00 % Rs 27.22
Rs 2749.48 /each

Or Say. Rs 2749.50 /each

9 Supplying all materials,labour and T&P for fixing corner wash hand basin with hole for pillar taps confirming to
IS 2556:part4-2004 with cast iron /M.S. brackets painted white including cutting holes in walls and making good
to the damages etc. all complete as per specification.
PH analysis 2013 Sanitary installation item no 3.4.11/ P-151
Vitreoous china corner Wash hand basin 16" x 16"
A. Materials
Cost of wash hand basin 550x400 1.00 nos each 960.70 960.70
CI bracket for wash basin and sinks 53.00 % 132 185.00
Waste pipe 32x1150mm 80.00 % 59.32 139.32
Cement, sand and wooden plugs etc. LS = Rs 24.02
1309.04
B.Labour
Plumber (fitter) 0.33 nos each 435.00 = Rs 143.55
Mason. 0.33 nos each 435.00 = Rs 143.55
Man mulia 0.67 nos each 345.00 = Rs 231.15
518.25
A+B 1827.29
Over head charges contractors profit 15.00 % Rs 274.09
Rs 2101.38 /each
Labour CESS 1.00 % Rs 21.01
Rs 2122.39 /each

Or Say. Rs 2122.40 /each


10 Supplying all materials,labour and T&P for fixing Pedestal for wash hand basin complete recessed at the back for
the receiptionof pipe and fittings etc. all complete as per specification including cost of pedestal for wash basin

PH analysis 2013 Sanitary installation item no 3.4.12/ P-151


Pedestal
CERA CLIO HALF PEDESTAL // Snow White
Cat No. S2090103 1730.00 / Each
Deduct 18% GST 311.40
1418.60 / Each
A.Materials
Cost of Pedestal 1.00 nos each 1418.60 1418.60
Cement, sand and wooden plugs etc. LS = Rs 60.05
Carriage of materials and fixing charges LS = Rs 60.24
1538.89
Over head charges on A+B 15.00 % Rs 230.83
Rs 1769.72 /each
Labour CESS 1.00 % Rs 17.69
Rs 1787.41 /each

Or Say. Rs 1787.40 /each

11 Supplying all materials,labour and T&P for fixing stainless steel AISI 304 [18/8] Kitchen sink as per IS 13983
with cast iron bracet and stainless steel plug including painting of fittings and brackets ,cutting and making good
to the walls etc. all as per specification including cost of sink with all accessories.
PH analysis 2013 Sanitary installation item no 3.4.14/ P-152
sink 24"x18"10" (Parryware)
CERA SILA
Cat No. B4721501 6535.00 / Each
Deduct 18% GST 1176.30
5358.70 / Each
A.Materials
Cost of Sink 1.00 nos each 5358.70 5358.70
castiron brackets[one pair] 2.00 264.00 528.00
Cement, sand and wooden plugs etc. LS = Rs 40.29
Painting of bracketsetc. LS 40.10
Carriage of materials LS 20.14
5987.23
B.Materials
Plumber (fitter) 0.220 nos each 435.00 = Rs 95.70
Mason. 0.600 435.00 261.00
Man mulia 0.820 nos each 345.00 = Rs 282.90
639.60
A+B 6626.83
Over head charges on A+B 15.00 % Rs 994.02
Rs 7620.85 /each
Labour CESS 1.00 % Rs 76.20
Rs 7697.05 /each

Or Say. Rs 7697.10 /each

B.Materials 36"x18"10" (Parryware)


Cost of Sink with drain board 1.00 nos each 5470.70 5470.70
castiron brackets[one pair] 1.00 264.00 264.00
Cement, sand and grit etc. LS = Rs 20.14
Painting of brackets etc. LS 40.10
Carriage of materials LS 20.14
5815.08
B.Materials
Plumber (fitter) 0.220 nos each 435.00 = Rs 95.70
Mason. 0.330 435.00 143.55
Man mulia 0.560 nos each 345.00 = Rs 193.20
432.45
A+B 6247.53
Over head charges on A+B 15.00 % Rs 937.12
Rs 7184.65 /each
Labour CESS 1.00 % Rs 71.84
Rs 7256.49 /each

Or Say. Rs 7256.50 /each


12 Supplying all materials,labour and T&P for fixing CP Gratings of the following nominal diameter of outlet, of self
cleaning design with sand cast iron screwed down or hinged grating with or without vent arm including cutting
and making good to the walls and floors etc. all complete as per specification.
PH analysis 2013 Sanitary installation item no 3.4.17/ P-154
C.P Gratings IS :1729 :-
A.Materials

Cost of CP Gratings 1.00 nos each 36.70 36.70


Cement, sand and grit etc. LS = Rs 20.14
Carriage of materials LS 4.07
60.91
B.Labour
Mason. 0.50 nos each 435.00 = Rs 217.50
Man mulia 0.50 nos each 345.00 = Rs 172.50
390.00
A+B 450.91
Over head charges on A+B 15.00 % Rs 67.63
Rs 518.54 /each
Labour CESS 1.00 % Rs 5.18
Rs 523.72 /each

Or Say. Rs 523.70 /each

II.A.Floor trap Centrifugally cast [spun]iron SS as per IS :3989 :-


A.Materials
Cost of trapCS (spun) iron SS
1.00 nos each 0.00 0.00
(100mm.inlet &75mm. Out let.)
Cement, sand and grit etc. LS = Rs 20.14
Carriage of materials LS 4.07
24.21
B.Labour
Mason. 0.50 nos each 435.00 = Rs 217.50
Man mulia 0.50 nos each 345.00 = Rs 172.50
390.00
A+B 414.21
Over head charges on A+B 15.00 % Rs 62.13
Rs 476.34 /each
Labour CESS 1.00 % Rs 4.76
Rs 481.10 /each

Or Say. Rs 481.10 /each


II.B.Floor trap Centrifugally cast [spun]iron SS as per IS :1729 :-
A.Materials
Cost of trapCS (spun) iron SS
1.00 nos each 0.00 0.00
(100mm.inlet &75mm. Out let.)
Cement, sand and grit etc. LS = Rs 20.14
Carriage of materials LS 4.07
24.21
B.Labour
Mason. 0.50 nos each 435.00 = Rs 217.50
Man mulia 0.50 nos each 345.00 = Rs 172.50
390.00
A+B 414.21
Over head charges on A+B 15.00 % Rs 62.13
Rs 476.34 /each
Labour CESS 1.00 % Rs 4.76
Rs 481.10 /each

Or Say. Rs 481.10 /each

13 Supplyingfitting fixing of PVC waste pipe of following nominal diameter of wash basin or sink inclusing brass
check nut complete as per specification.
PH analysis 2013 Sanitary installation item no 3.4.20/ P-155
A.Materials
Semirigid PVC waste pipe for sink and
wash basin 32mm dia with length not
less than 700mm with PVC waste fittings 1.00 nos each 42.37 42.37
Carriage of materials LS 30.22
72.59
Over head charges on A+B 15.00 % Rs 10.88
Rs 83.47 /each
Labour CESS 1.00 % Rs 0.83
Rs 84.30 /each

Or Say. Rs 84.30 /each


14 Supplying fitting fixing of C.P Pillar Taps highpressure lettered Hot and cold with long screws shanks and back
nuts of the following nominal bore as per specification.
PH analysis 2013 Sanitary installation item no 3.4.21/ P-156
A.Materials
CERA RIPPLE
F1017101 1825.00 / Each
Deduct 18% GST 328.50
1496.50 / Each
15mm dia
15mm dia CP Piller cock 1.00 nos each 1496.50 1496.50
Carriage of materialsand fixing charges LS 14.14
1510.64
Over head charges on 15.00 % Rs 226.59
Rs 1737.23 /each
Labour CESS 1.00 % Rs 17.37
Rs 1754.60 /each

Or Say. Rs 1754.60 /each


14 Supplying fitting fixing of C.P health facuit highpressure lettered Hot and cold with long screws shanks and back
nuts of the following nominal bore as per specification.
PH analysis 2013 Sanitary installation item no 3.4.21/ P-156
A.Materials
CERA
F8030104AB 750.00 / Each
Deduct 18% GST 135.00
615.00 / Each
15mm dia
15mm dia CP health facuit with 1.0M
PVC tube 1.00 nos each 615.00 615.00
Carriage of materialsand fixing charges LS 14.14
629.14
Over head charges on #REF! % Rs #REF!
Rs #REF! /each
Labour CESS 1.00 % Rs #REF!
Rs #REF! /each

Or Say. Rs #REF! /each


15 Supplying fitting fixing of 15mm dia PVC inlet connection pipe and making connectiion with piller cock and
supply mains for wash basin complete as per specification.
PH analysis 2013 Sanitary installation item no 3.4.22/ P-156
A.Materials
CERA 12 mm dia Geyser Connection Pipe
F8070403 345.00 / Each
Deduct 18% GST 62.10
282.90 / Each
15mm dia 15mm x 300mm
UPVC connecting pipe 1.00 nos each 282.90 282.90
Carriage of materialsand fixing charges LS 18.21
301.11
Over head charges on 15.00 % Rs 45.16
Rs 346.27 /each
Labour CESS 1.00 % Rs 3.46
Rs 349.73 /each

Or Say. Rs 349.70 /each


16 Supplying fitting fixing of CP waste of the following noninal diameter for wash hand basin and sink as per
specification.
PH analysis 2013 Sanitary installation item no 3.4.23/ P-157
A.Materials
CERA Waste Coupling (Half Threaded)
F8050102 545.00 / Each
Deduct 18% GST 98.10
446.90 / Each
32mm dia
32mm CP waste 1.00 nos each 446.90 446.90
Carriage of materialsand fixing charges LS 2.71
449.61
Over head charges on 15.00 % Rs 67.44
Rs 517.05 /each
Labour CESS 1.00 % Rs 5.17
Rs 522.22 /each

Or Say. Rs 522.20 /each


17 Supplying fitting fixing of cromium plated CP over head shower rose with arm including polishing and complete
as per specification.
PH analysis 2013 Sanitary installation item no 3.4.24/ P-157
A.Materials
CERA 100x100mm size
F7020306CH 725.00 / Each
Deduct 18% GST 130.50
594.50 / Each

Over head shower 1.00 nos each 594.50 594.50


CP arm of over head shower CERA //
[F7040102] 1.00 nos each 430.00 430.00
CP extension piece 3" 1.00 nos each 85.20 85.20
1109.70
B.Labour
Plumber (fitter) 0.07 nos each 435.00 = Rs 30.45
Helper to plumber 0.07 nos each 385.00 = Rs 26.95
57.40
1167.10
Over head charges on 15.00 % Rs 175.06
Rs 1342.16 /each
Labour CESS 1.00 % Rs 13.42
Rs 1355.58 /each

Or Say. Rs 1355.60 /each


18 Supplying all materials,labour and T&P for fixing of 600x450 bevelled edge mirror of superior glass mounted on
6mm thick ac sheet or ply wood sheet and fixed to wooden plugs with chromium plated brass screws and washers
etc. All complete as per specification .
PH analysis 2013 Sanitary installation item no 3.4.26/ P-158
I.Bevelled edge mirror (450x300mm.) :-
A.Materials
CERA 450x300
Cat No. B3510116 1025.00 / Each
Deduct 18% GST 184.50
840.50 / Each
600mmx450mmbevelled edge mirrer 1.00 nos each 840.50 840.50
Hard board 6mm 0.27 sqm sqm 170.00 45.90
25mm cp screw 4.00 nos each 1.12 4.48
wooden cleats 4.000 nos each 17.40 69.60
cement , sand,chips, &carriageof materials LS 8.33
968.81
B.Labour
Carpenter 0.33 nos each 435.00 = Rs 143.55
Man mulia 0.33 nos each 345.00 = Rs 113.85
257.40
A+B 1226.21
Over head charges on A+B 15.00 % Rs 183.93
Rs 1410.14 /each
Labour CESS 1.00 % Rs 14.10
Rs 1424.24 /each

Or Say. Rs 1424.20 /each

II. Circular shape 450mm dia:-


A.Materials
Circular shape 450mm dia 1.00 nos each 305.40 305.40
Hard board 6mm 0.22 sqm sqm 170.00 37.40
25mm CP screws 2.00 nos each 1.12 2.24
Rawlplug50mm [designation 10ns] 2.000 nos each 10.00 20.00
cement , sand,chips, &carriageof materials LS 8.33
373.37
B.Labour
Carpenter 0.33 nos each 435.00 = Rs 143.55
Man mulia 0.33 nos each 345.00 = Rs 113.85
257.40
A+B 630.77
Over head charges on A+B 15.00 % Rs 94.61
Rs 725.38 /each
Labour CESS 1.00 % Rs 7.25
Rs 732.63 /each

Or Say. Rs 732.60 /each


III. Regtangular shape 453mmx357mm:-
A.Materials
Regtangular shape 453mmx357mm 1.00 nos each 260.00 260.00
Hard board 6mm 0.18 sqm sqm 170.00 30.60
25mm CP screws 4.00 nos each 1.12 4.48
Rawlplug50mm [designation 10ns] 4.000 nos each 10.00 40.00
cement , sand,chips, &carriageof materials LS 8.33
343.41
B.Labour
Carpenter 0.33 nos each 435.00 = Rs 143.55
Man mulia 0.33 nos each 345.00 = Rs 113.85
257.40
A+B 600.81
Over head charges on A+B 15.00 % Rs 90.12
Rs 690.93 /each
Labour CESS 1.00 % Rs 6.90
Rs 697.83 /each

Or Say. Rs 697.80 /each

19 Supplying all materials,labour and T&P for fixing standard size glass self with chromium plated brass brackets
and guard rails fixed to wooden plugs with chromium plated brass screws and washers etc. all complete as per
specification.
PH analysis 2013 Sanitary installation item no 3.4.27/ P-159
Glass self :- (per each)
A.Materials
CERA
F5005301 4035.00 / Each
Deduct 18% GST 726.30
Cost of Glass shelf 600x120mm with 3308.70 / Each
anodised aluminum angle frame CP brass 1.00 nos each 3308.70 = Rs 3308.70
bracket and50mm
Rawl plug guard rail of standrad size 2.00 nos each 10.00 = Rs 20.00
25mm cp screw 4.00 nos each 1.12 = Rs 4.48
Cement, sand and chips and carriage of
LS = Rs 6.20
materials
3339.38
B.Materials
Carpenter 0.25 nos each 435.00 = Rs 108.75
Man mulia 0.25 nos each 345.00 = Rs 86.25
195.00
A+B 3534.38
Over head charges on A+B 15.00 % Rs 530.15
Rs 4064.53 /each
Labour CESS 1.00 % Rs 40.64
Rs 4105.17 /each

Or Say. Rs 4105.20 /each


20 Supplying all materials,labour and T&P for fixing standard size C. P. towel rail fixed with chromium plated brass
brackets fixed to wooden plugs with cromium plated brass screws complete as per specification.

PH analysis 2013 Sanitary installation item no 3.4.28/ P-160


Chromium plated towel rail 25mm x 600mm long:-
CERA
F5006104 1910.00 / Each
Deduct 18% GST 343.80
1566.20 / Each
A.Materials
Cost of towel rail 600 x 200mm 1.00 nos each 1566.20 = Rs 1566.20
25mm CP screws 6.00 nos each 1.12 = Rs 6.72
Wooden plugs 2.00 nos each 17.40 = Rs 34.80
Cement, sand and chips etc. LS = Rs 6.20
1613.92
B.Labour
Carpenter. 0.17 nos each 435.00 = Rs 73.95
Man mulia 0.17 nos each 345.00 = Rs 58.65
132.60
A+B 1746.52
Over head charges on A+B 15.00 % Rs 261.97
Rs 2008.49 /each
Labour CESS 1.00 % Rs 20.08
Rs 2028.57 /each
Or Say. Rs 2028.60 /each

21 Supplying all materials,labour and T&P for fixing standard size C. P. towel ring fixed fixed to wooden plugs
with cromium plated brass screws complete as per specification.
PH analysis 2013 Sanitary installation item no 3.4.29/ P-160
Chromium plated towel ring:-
CERA
F5003105 910.00 / Each
Deduct 18% GST 163.80
746.20 / Each
A.Materials
Cost of towel ring 1.00 nos each 746.20 = Rs 746.20
Carriage of materials and fixing charges LS 30.22
776.42
Over head charges on A+B 15.00 % Rs 116.46
Rs 892.88 /each
Labour CESS 1.00 % Rs 8.92
Rs 901.80 /each

Or Say. Rs 901.80 /each

22 Supplying all materials,labour and T&P for fixing of [A] liquid soap container - glass container or plastic
container with chromium plated brass lid and brackets fixed to wooden plugs with chromium plated brass screws
[B] cromium plated brass soap dish complete with chromium plated brass brackets fixed to wooden plugs with
chromium plated brass screws [ C] white glased tooth brush holder fixed to wooden plugs with chromiumplated
brass screws as per specification

PH analysis 2013 Sanitary installation item no 3.4.30/ P-160


II. Soap holder :- // Soap Dish
CERA Soap Dish
F5003106 760.00 / Each
Deduct 18% GST 136.80
623.20 / Each
A.Materials
Cost of CP sope holder/ disc 1.00 nos each 623.20 = Rs 623.20
25mm cp screw 2.00 nos each 1.12 = Rs 2.24
wooden plugs of specified size 2.00 nos each 17.40 = Rs 34.80
Cement, sand and chips etc. LS = Rs 6.20
666.44
B.Materials
Plumber (fitter)/Mason. 0.12 nos each 435.00 = Rs 52.20
Man mulia 0.12 nos each 345.00 = Rs 41.40
93.60
A+B 760.04
Over head charges on A+B 15.00 % Rs 114.00
Rs 874.04 /each
Labour CESS 1.00 % Rs 8.74
Rs 882.78 /each

Or Say. Rs 882.80 /each


II. Soap holder :- // Liquid Soap Dispenser
CERA Liquid Soap Dispenser
F5007111 1580.00 / Each
Deduct 18% GST 284.40
1295.60 / Each
A.Materials
Cost of CP Liquid Soap Dispenser 1.00 nos each 1295.60 = Rs 1295.60
Cost of CP Tumbler Holder 1.00 nos each 910.00 = Rs 910.00
25mm cp screw 2.00 nos each 1.12 = Rs 2.24
wooden plugs of specified size 2.00 nos each 17.40 = Rs 34.80
Cement, sand and chips etc. LS = Rs 6.20
2248.84
B.Materials
Plumber (fitter)/Mason. 0.12 nos each 435.00 = Rs 52.20
Man mulia 0.12 nos each 345.00 = Rs 41.40
93.60
A+B 2342.44
Over head charges on A+B 15.00 % Rs 351.36
Rs 2693.80 /each
Labour CESS 1.00 % Rs 26.93
Rs 2720.73 /each

Or Say. Rs 2720.70 /each

27 Laying (to level or slopes) and jointing with rubber rings pre-cast reinforced socket and spigot concrete pipes
Class NP-2 conforming to IS:458 - 2003 suitable for rubber ring roll on joint of the following internal diameter as
per specification complete.(Earthwork in trenches to be measured and paid for separately)

[ iii ]200mm diameter


Details of cost for 10 joints =10x1.93=19.3 mtrs
a. Materials
200mm Concrete S/S Pipes Class NP-2 19.30 mtr 657.80 12695.54
labour for laying (same as C.I pipe)
wt. of 10 pcs of pipe= 19.30 x 48.92=944.156 kg =9.4416 qntl
9.4416 qntl 71.35 673.66
Jointing with rubber ring
200 mm dia rubber ring for 10 joints 10 each 40.00 400.00
b. Labour charges
Plumber Fitter(S) 1.33 Each 435.00 580.00
Helper to plumber or fitter 1.00 Each 385.00 385.00
Male worker 3.00 Each 345.00 1035.00
(a+b) 3073.66 12695.54
c. Add Contractor's Profit & Overhead charges 15% 461.05 1904.33
Total (a+b+c) 3534.71 14599.87
Rate per metre = 3,534.71 ÷ 19.30 = 183.15 756.47
d. Add 1% labour cess 1.83 7.56
Total 184.98 764.03
say 185.00 764.00
With Material 949.00 /Meter

19 Supplying all materials labour T&P and


fitting and fixing 1000 ltrs. Capacity
FG/PM/Sintex/Vertix tank with locking
type cover including cutting holes for
fittings and fixing GI/PVC pipes with
supply extra
PH analysis 2010-11sockets
Internal&water
jamnuts
supply item no2(a) / P-140
(A)Materials ,Fitting & fixing of
Cost of vertix tank 1000 lt.@6.24/ltTank
including vat 1 nos each 6240 6240.00
Lead, paint,yarnetc. 15.40
6255.40
(B) Labour
Plumber (fitter) 0.25 nos each 190 = Rs 47.50
Helper to plumber 0.25 nos each 170 = Rs 42.50
Male mulia 1.50 nos each 150 = Rs 225.00
315.00
A+B 6570.40
Add overhead charges 7.50 % 492.78
Contractor's profit 7.50 % 492.78
(c) cost of staging
1st class BW (1:4) 1x5.45x.25x.35 0.47
Circular portion∏/4[1.60x1.60-1.35x1.35
0.28
]x.5
0.75 cum cum 4068.75 3051.56
(d) 12mm thick cement plaster 1:4
1x5.45x.95 5.17
∏/4[1.60x1.60-1.35x1.35 ] 0.58
1x∏x1.35x.35 1.48
1x∏x1.60x.35 1.75
8.98 sqm sqm 136.38 1224.69

(e)weather coat 8.98 sqm sqm 57.89 519.85


(f) RCCM-20 including centering and
shuttering beam and base slab
Beam3.06x.25x.30 0.22 cum cum 10393.92 2286.66
slab∏/4[1.60x1.60 ]x0.10 0.20 cum cum 8723.52 1744.70

(h) Reinforcement @ 1.00qntl/cum 0.42 qntl qntl 9781.28 4108.13


20491.55

Labour CESS 1.00 % Rs 204.91


Rs 20696.46 /each

Or Say. Rs 20696.50 /each