Dismantling Data SSR 2020-21

Repairs and Renovation of Sayanam Hostel, TSIRD Rajendranagar.


Amount
Sl. No. Description Quantity Rate (Rs.) Per Unit Unit
(Rs.)
1 Dismantling, clearing away and carefully stacking useful materials for re-use
and disposal of unserviceable materials with 100m lead as directed by Executive
Engineer duly taking actual premeasurements before dismantling including all
labour charges , overheads & contractor profit etc., complete

Brick masonry
(BLD-CSTN-14-9/299)
Mazdoor(unskilled) 0.409 465.00 1 Each 190.19
Add for MA @ 40% 0.40 190.19 76.07
Rate per 1 cum 266.26
Overheads&Contractors Profit @
13.615% 0.13615 266.26 36.25
Rate per 1 cum 302.51
say 303

Unreinforced cement concrete up to 15cm thickness


(BLD-CSTN-14-8/296)
Mazdoor(unskilled) 2.44 465.00 1 Each 1134.60
Add for MA @ 40% 0.40 1134.60 453.84
Rate per 1 cum 1588.44
Overheads&Contractors Profit @
13.615% 0.13615 1588.44 216.27
Rate per 1 cum 1804.71
say 1805

Unreinforced cement concrete more than 15cm thickness


(BLD-CSTN-14-8/297)
Mazdoor(unskilled) 4.88 465.00 1 Each 2269.20
Add for MA @ 40% 0.40 2269.20 907.68
Rate per 1 cum 3176.88
Overheads&Contractors Profit @
13.615% 0.13615 3176.88 432.53
Rate per 1 cum 3609.41
say 3609

Reinforced cement concrete


(BLD-CSTN-14-8/298)
Mazdoor(unskilled) 4.32 465.00 1 Each 2008.80
Add for MA @ 40% 0.40 2008.80 803.52
for cutting steel bars (BLD-CSTN-14-
10/300)
Blacksmith 2nd class 0.50 490.00 1 Each 245.00
Mazdoor(Male) 0.50 465.00 1 Each 232.50
Add for MA @ 40% 0.40 477.50 191.00
Rate per 1 cum 3480.82
Overheads&Contractors Profit @
13.615% 0.13615 3480.82 473.91
Rate per 1 cum 3954.73
say 3955

Kadapa slabs or shahabad stone slabs on sand bed


Rate as per SSR 10.00 8.00 1 sqm 80.00
Add for MA @ 40% 0.40 80.00 32.00
Rate per 10 sqm 112.00
Rate per 1 sqm 11.20
Overheads&Contractors Profit @
11.20
13.615% 0.13615 1.52
Rate per 1 sqm 12.72
say 13

Stone masonry in cement mortar


Rate as per SSR 1.00 485.00 1 cum 485.00
Add for MA @ 40% 0.40 485.00 194.00
Rate per 1 cum 679.00
Overheads&Contractors Profit @
679.00
13.615% 0.13615 92.45
Rate per 1 cum 771.45
say 771

Pan tiled or Mangalore tiled roof with out roof timbers :


Rate as per SSR 10.00 16.00 1 sqm 160.00
Add for MA @ 40% 0.40 160.00 64.00
Rate per 10 sqm 224.00
Rate per 1 sqm 22.40
Overheads &Contractors Profit @
0.13615 22.40
13.615% 3.05
Rate per 1 sqm 25.45
say 25.45