Professional Documents
Culture Documents
Sn Items
1 Sub grades Description Units Quantity Rate Amount
Preparation of Sub-grade for rehabilitation filling
or cutting depth of (10-20cm) unskilled m.d. 0.15 350 52.5
Common soil miscellane. % 3% 1.575
per Sub-Total 54.075
1 Sq.m Contractor overhead 15% 8.11125
Sub-Total 62.18625
Vat 13% 8.084213
Grand total with Vat Sq.m. 70.27046
per Sq.ft 6.530712
6 Tact coat over premix carpetting Description Units Quantity Rate Amount
Providing mixing and laying fine slurry mix seal Skilled m.d. 0.2 450 90
per 100 sq.m Unskilled m.d. 3 350 1050
Emulsion Lt 122 35042700
Cement Kg 8.3 11.192.13
Aggregate Cu.m 0.49 1500 735
Water Ls 10
Diesel Lit 8.4 75.00 630
Mixer Hr 0.07 2245.00 157.15
Pneumatic tyred roller Hr 0.55 3824.50 2103.475
3% of labour cost for T&P 34.2
Sub-Total 47601.96
Contractor overhead 15% 7140.293
Sub-Total 54742.25
Vat 13% 7116.492
100 Sq.m Grand total with Vat 100 Sq.m 61858.74
per Sq.m 618.5874
per Sqft 57.48954
Sub-Total 6931.4
Contractor overhead 15% 1039.71
Sub-Total 7971.11
Vat 13% 1036.244
100 Cu.m Grand total with Vat cu.m 9007.354
per Cu.ft 255.2179
8 Form work Description Units Quantity Rate Amount
Providing , Preparing and Installing form work &
removing afte r completion for Precast elements.
(class F3 Finish) Skilled m.d. 1.5 450 675
i)Square/Rectangular Section Unskilled m.d. 2 350 700
a) Using Timber Plywood 9mm thick Sq.m 11 430.4 4734.4
Timber Cu.m 0.2 5500 1100
Nails Kg 2 65.00 130
Sub-Total 7339.4
Contractor overhead 15% 1100.91
Sub-Total 8440.31
Vat 13% 1097.24
10 Sq.m Grand total with Vat 10 Sq.m 9537.55
per Sq.m 886.3894