Crushed stone base

Material Cost Labor Cost


Indexed
Qty per Cost per Labor Hourly
Labor type Rate No. UF Hourly
unit Unit type Cost
cost

Crushed Aggregate 1.05 500 525 Foreman 1 1 75 75


Fuel 0.6 18.71 11.226 Drivers 6 1 28 168
operators 4 1 30 120
Helpers 10 1 13 130
DL 5 1 13 65

Sub Total 536.226 Sub Total 558

Labor Cost 6.377143


Daily Out Put 700 m3/d Material Cost 536.226
Hourly Out Put 87.5 m3/h Equipment Cost 69.71429

Total Direct Cost 612.3174


30% Profit + overhead 183.6952

Unit rate 796.0127

MC-30 Cut back Butemen


Material Cost Labor Cost
Indexed
Qty per Rate Cost per Labor Hourly
Labor type No. UF Hourly
unit Unit type Cost
cost
Bitumen 60/70 0.13 23713 3082.664 Foreman 1 0.25 75 18.75
Drivers 1 1 28 28
operators 3 1 30 90
Helpers 4 1 13 52
DL 5 1 13 65

Sub Total 3082.664 Sub Total 253.75

Labor Cost 0.112778


Daily Out Put 18000 m2/d Material Cost 3082.664
Hourly Out Put 2250 m2/h Equipment Cost 2.226667

Total Direct Cost 3085.003


40% Profit + overhead 1234.001
Unit rate 4319

0.05
116.5 kg
0.1165
Equipment Cost lit fuel
Hourly
Hourly
Type No UF Rental
Cost
Rate

Grader 1 1 1200 1200 200


DT 5 1 550 2750 30
Loader 1 1 700 700 100
Roller 2 1 500 1000 50
Water Truck 1 1 450 450 25
405 for 700m3/d output
Sub Total 6100
0.578571

1.968504

Equipment Cost
Hourly
Hourly
Type No UF Rental
Cost
Rate
Asphalt Dist 1 1 2500 2500
broom 1 1 50 50
roller 2 1 1000 2000
Water Truck 1 1 450 450
hand tools 5 1 2 10

Sub Total 5010

130 2.6 t m3
0.056521739 0.13
0.05 3192