You are on page 1of 1

Painting- 2

Coat of
Raw Supply Site
Sr. Freight to Fab. Fab. Epoxy Desgin Freight Site Erection Erection
Description Unit qty Material Rate Supply Price Touch Erection Price
No. Factory /Conversion Wast. Enemel+Sh cost to Site Expenses cost Rate (INR)
Basic (INR) Up
ot Blasting
+ Painting

1 Primary member Size kg 145000 65.00 1.20 25.00 1.40 3.20 1.00 1.20 98.00 ₹ 1,42,10,000.00 ₹ 0.50 ₹ 1.00 ₹ 6.00 ₹ 7.50 ₹ 10,87,500.00

2 Secondary member size kg 18000 76.00 1.20 10.00 0.50 0.00 1.00 1.20 89.90 ₹ 16,18,200.00 ₹ - ₹ 1.50 ₹ 6.00 ₹ 7.50 ₹ 1,35,000.00

Roofing sheets
(Machine profiling and
3 kg 15000 98.00 1.20 50.00 0.20 0.00 2.00 1.20 152.60 ₹ 22,89,000.00 ₹ - ₹ 1.50 ₹ 27.00 ₹ 28.50 ₹ 4,27,500.00
AL Clips considered in
conversion cost)

4 Cladding sheets kg 10000 98.00 1.20 5.00 0.20 0.00 2.00 1.20 107.60 ₹ 10,76,000.00 ₹ - ₹ 1.50 ₹ 21.00 ₹ 22.50 ₹ 2,25,000.00

5 Decking sheets kg 14000 98.00 1.20 5.00 0.40 0.00 2.00 1.20 107.80 ₹ 15,09,200.00 ₹ 1.50 ₹ 18.50 ₹ 20.00 ₹ 2,80,000.00

HSB 8.8 Connections


Kg 4800 300.00 1.20 0.00 0.00 0.00 2.00 1.20 304.40 ₹ 14,61,120.00 ₹ - ₹ 1.50 ₹ 6.00 ₹ 7.50 ₹ 36,000.00
harware

Turbovent (With
Nos. 18 14000.00 1.20 0.00 0.00 0.00 0.00 1.20 14002.40 ₹ 2,52,043.20 ₹ 45.00 ₹ 1,100.00 ₹ 1,145.00 ₹ 20,610.00
specilized base for SSR
system)
Sqm
Lighting strips (With fall
6 220 8000.00 0.00 0.00 0.00 0.00 0.00 0.00 8000.00 ₹ 17,60,000.00 ₹ 45.00 ₹ 490.00 ₹ 535.00 ₹ 1,17,700.00
protection)
Sqm
7 Roof Insulation 3276 534.00 ₹ 17,49,384.00 ₹ 45.00 ₹ 1,47,420.00

₹ 2,59,24,947.20 ₹ 24,76,730.00

₹ 2,84,01,677.20