Status as on 31.08.

2022

ORIGINAL WORKS - NHIDCL

Total Completed Works Total Civil works in progress


Sl. No STATE
Length Cost Length Cost
Nos. (in Km ) (Rs in Cr) Nos. (in Km ) (Rs in Cr)

Andaman & Nicobar


1 6 142.78 675.407 5 178.172 1407.43
Island
2 Arunachal Pradesh 14 327.415 3336.28 21 423.151 6744.96

3 Assam 6 84.18 791.7 29 587.828 18806.71

4 Jammu & Kashmir 2 37.20 24.5 17 262.999 15140

5 Ladakh 0 0 0 8 230.01 2286.97

6 Manipur 3 65.072 1117.61 37 732.116 12259.46

7 Meghalaya 0 0 0 12 281.069 3819.51

8 Mizoram 0 0 0 27 736.36 14944.929

9 Nagaland 5 107.56 1327.36 29 558.628 9647.83

10 Sikkim 4 38.36 649.79 14 168.08 3942.15

11 West Bengal 1 1.50 158.65 5 77.15 1598.28

12 Tripura 5 211.576 2097.71 18 279.912 4075.06

13 Uttarakhand 7 5.51 348.92 4 99.459 2478.69

Grand Total 53 1021 10528 226 4615 97152


Status as on 31.08.2022
Target date
Date of Right of way Remarks/ Issues
NHDP NH No. Sanctioned Awarded Cumulative Cumulative of
SL. Mo Length Date of Start/ (ROW) Likely Date of (Land Aquisition Issues/
Phase/ Name of Project (Old/ Cost/TPC Cost Physical Financial completion Name of the Contractor
No. de (Km) Award Appointed Available completion Forest Issues/ Utility
Scheme New) Rs. in crore Rs. in crore progress % progress % as per
Date % Shifting/ Contractor Issue)
contract
Andaman & Nicobar
Rehabilitation and Upgradation of Jarwa
Item area of NH-223 (New NH-4) from Km 59.40
1 NH(O) NH-4 64.3 59.56 53.73 05/03/2018 4/9/2018 100.00% 100.00% 97.38% 3/31/2021 Completed M/s Jandu Construction Company
Rate to Km 107.00 and Km 138.30 to Km 155.00
on Item Rate basis
Construction of Major Bridge over
2 EPC NH(O) Humphrey Strait Creek between NH-223 /NH-4 1.45 277.17 202.909 15/02/2017 4/26/2017 100.00% 100.00% 95.00% 4/25/2020 Completed MBZ -RDS (JV)
Km.129.420 to Km. 130.600 of NH-223
2-Lane with hard shoulder, Rehabilitation
and up-gradation of Beodnabad-
3 EPC NH(O) Ferrargunj section of NH-223 from Km NH-223 /NH-4 25.93 175.127 124.74 01/03/2017 11/1/2017 100.00% 100.00% 100.00% 4/2/2019 Completed M/s DRA Infracon Pvt. Ltd.
12.0 to 45.0 (excluding Km 21.0 to 28.0)
(Package-I)
Rehabilitation of Km 0.00 to Km 12.00
section in Andaman Trunk Road of NH-4
4 EPC NH(O) NH-4 12 32.54 22.6 14/02/2019 4/2/2019 100.00% 100.00% 99.19% 3/30/2020 Completed M/s Mohan Mutha Exports Pvt Ltd
to Intermediate lane with hard shoulder
(Package-V)
Rehabilitation of section from Km 45.00
5 EPC NH(O) to Km 59.20 of NH-4 to Intermediate lane NH-4 14.1 59.08 37.67 14/02/2019 4/2/2019 100.00% 99.68% 98.80% 3/30/2020 Completed M/s Mohan Mutha Exports Pvt Ltd
with hard shoulder (Package-VI)
Rehabilitation of Km 181.00 to Km 206.00
section in Andaman Trunk Road of NH-4 M/s Garg & Sons Estate Promoters
6 EPC NH(O) NH-4 25 71.93 53.96 28/11/2018 1/1/2019 100.00% 100.00% 99.06% 12/31/2019 Completed
to Intermediate lane with hard shoulder Pvt Ltd
(Package-VII)
Construction of Major Bridge over Middle
Strait Creek between Km. 106.590 to Km. M/s Mantena Constructions Pvt. Ltd.-
7 EPC NH(O) 107.762 of NH-223 (New NH-4) connecting NH-223 /NH-4 1.9 262.97 170.4 18/12/2017 1/3/2019 100.00% 38.78% 38.41% 1/2/2022 3/31/2024 Vasishta Constructions Pvt. Ltd.
South Andaman and Baratang Islands in Bridge (JV)
UT of A&N.
2-Lane with hard shoulder, Rehabilitation
and up-gradation of section from Km M/s Vasishta Constructions Pvt. Ltd. -
8 EPC NH(O) 233/ NH-4 55.45 409.85 190.7 31/03/2017 12/5/2017 100.00% 83.99% 83.45% 12/5/2019 12/8/2022 Forest Issues
242.0 to 298.0 of NH-223 (New NH-4). Mantena Infra LLP NH (JV)
(Package-II)

2-Lane with hard shoulder, Rehabilitation


and up-gradation of sect. from Km
M/s Mantena Constructions Pvt. Ltd.-
107.760- 129.445,(Middle strait to
9 EPC NH(O) 233/ NH-4 54.71 391.01 248.277 12/03/2018 9/4/2018 100.00% 51.02% 44.80% 9/2/2020 3/31/2023 Vasishta Constructions Pvt. Ltd. Strait
Humphrey),Km 130.600 -138 (After
(JV)
Humphrey-Kadamtala) & Km155.00 -181.0
(End of Jarwa-Rangat) (Package-III)

2-Lane with hard shoulder, Rehabilitation


and up-gradation of section from Km
10 EPC NH(O) 206.00 to Km 242.00 (Nimbutala to Austin 233/ NH-4 33.45 234.27 148.6 27/03/2018 9/4/2018 100.00% 70.32% 66.82% 2/Sep/20 3/31/2023 M/s Vasishta Construction Pvt.Ltd
Creek) of NH-223 (New NH-4) (Package-
IV).
Rehabilitation of section from Km 298.00
to Km 330.662 (Karala to Kalipur) of NH-
11 EPC NH(O) NH-4 32.36 109.33 74.611 4/13/2021 7/1/2021 100.00% 9.81% 7.27% 7/2/2023 12/31/2023 Kaba Infratech Pvt. Ltd.
04 to Intermediate lane with hard
shoulder (Package-VIII)
Total 320.65 2082.84 1328.20
Status as on 31.08.2022
Right of Target date Remarks/ Issues
Awarded Cumulative
NHDP NH No. Sanctioned Date of way Cumulative of Likely Date (Land Aquisition
SL. Length Cost Date of Financial
Mode Phase/ Name of Project (Old/ Cost/TPC Start/Appoi (ROW) Physical completion of Name of the Contractor Issues/ Forest Issues/
No. (Km) Rs. in Award progress
Scheme New) Rs. in crore nted Date Available progress % as per completion Utility Shifting/
crore %
% contract Contractor Issue)
Arunachal Pradesh
2 laning from Mahadevpur to Buri Dihing M/s Dineshchandra R. Agarwal
1 EPC SARDP 52B/ 215 25.135 136.6 107.16 31/03/2015 5/30/2015 100.00% 100.00% 100.00% 5/30/2018 Completed -
section of NH-52B Infracon Pvt. Ltd.- Puna Hinda (JV)
2 laning from Bordumsa-Namchik (Buri
Dihing-Jairampur) road on NH52-B (New
2 EPC SARDP NH-215) from Km 0.15 km (starting 52B 22.23 189.91 143.21 23/07/2015 10/23/2015 100.00% 100.00% 100.00% 10/22/2018 Completed BIPL-BVEPL (JV) -
Chainage near Buridihing Bridge) to km
22.380
2 laning from Pasighat to Pangin section M/s Dineshchandra R. Agarwal
3 EPC SARDP 229/13 26.58 299.66 235.08 31/03/2015 5/27/2015 100.00% 100.00% 100.00% 5/25/2018 Completed -
of NH-229 from km 0 to Km 28 Infracon Pvt. Ltd.
2 laning from Pasighat to Pangin section
T K Engineering & Consortium
4 EPC SARDP of NH-229 from km 41.3 to 58.420 (Existing 229/13 17.12 247.44 194.11 05/12/2015 5/27/2015 100.00% 100.00% 99.95% 5/25/2018 Completed -
Pvt. Ltd.(TKECPL)
Km 42 to km 59)
Construction of 2-lane road from existing
5 EPC SARDP km. 37.500 of Hunli-Anini road (Near Ithun New NH-313 16 259.52 198 06/05/2016 07-10-2016 100.00% 100.00% 100.00% 10/6/2019 Completed M/s Madhucon Projects Ltd. -
Bridge) to Km. 53.50 - Pkg.II

6 EPC SARDP 2 laning of Singer river to Sijon nala 513 23.38 238.46 179.82 09/11/2015 1/15/2016 100.00% 100.00% 100.00% 1/19/2019 Completed M/s ABL-BIPL (JV) -

2 laning from Changlang Dist Boundary – 14-6-2019/ M/s MGCPL-HGIEPL (JV)


7 EPC SARDP 52B/215 42.844 438.32 334.22 01/03/2016 6/15/2016 100.00% 100.00% 100.00% Completed -
Khonsa (42.844 km) section of NH-52B 04-03-2019
2 laning of Changlang/Tirap District T K Engineering & Consortium
8 EPC SARDP 52B/215 18.266 172.75 130.1 31/03/2015 6/1/2015 100.00% 100.00% 97.31% 5/31/2018 Completed -
boundary to Changlang of NH-52B Pvt. Ltd.(TKECPL)
2 laning from Longding to Kanubari of NH-
9 EPC SARDP 52B/ 215 47.21 522.87 394 31/03/2015 6/2/2015 100.00% 100.00% 96.94% 11/26/2018 Completed M/s Monte Carlo Ltd. -
52B from Km0.00 to Km47.213
2 laning with paved shoulders from
Pasighat to Bomjur section from km
10 EPC SARDP 52 22.15 244.82 163.61 02/03/2016 24-02-2017 100.00% 100.00% 97.81% 2/23/2020 Completed M/s BIPL-ABL (JV ) -
583.450 to 605.600 including Realignment
from km591.900 to 602.600
Construction of 2-lane road from km. 12.00
11 EPC SARDP to Km. 33.00 of Akajan-Likabali- Bame State Road 21 210.5 148 11/02/2015 1/20/2016 100.00% 99.84% 99.34% 1/18/2019 Completed M/s JKM-KCL JV -
road (Pkg-I)
Rehabilitation/ Restoration (One Time
Strengtheni
12 NH(O) Improvement) of Hunli Anini Road from km New NH-313 21.5 23.56 22.12 22/02/2019 10/10/2019 100.00% 100.00% 93.64% 10/9/2020 Completed M/s N.M. Enterprises -
ng
0.00 to km 21.500
2-Laning of Joram – Koloriang Road (NH-
T K Engineering & Consortium
713) from design Km. 20+000 to Km. 20-04-2022/ 28-02-
13 EPC SARDP NH-713 12.05 175.65 102.63 24/03/2017 4/22/2019 100.00% 100.00% 98.80% Completed Pvt. Ltd.-Brand Eagles -
32+050 (Existing Km 20.000 to Km 35.150) 2022
(TKECPL - BE)
(Pkg-I)
2-Laning of Joram – Koloriang Road (NH-
T K Engineering & Consortium
713) from design Km. 32+050 to Km. 20-04-2022/ 09-04-
14 EPC SARDP NH-713 11.95 176.22 103.48 24/03/2017 4/22/2019 100.00% 100.00% 98.46% Completed Pvt. Ltd.-Brand Eagles -
44+000 [Existing Km 35.150 to Km 50.050] 2022
(TKECPL - BE)
(Pkg-II)
2 langing of Khupa - Hayuliang – Hawai
Road on EPC basis from design Km. 0.000
15 EPC SARDP (Khupa) to Km. 17.000 [Existing Km 95.800 NH-313 13.4 252.05 138.13 23/03/2017 10-11-2017 100.00% 98.57% 97.61% 11/9/2020 9/30/2022 M/s Sushee Infra & Mining Limited
of (Khupa – Hayuliang Road) to Km 8.970
(Hayuliang – Hawai Road)] - I
2 langing of Hayuliang – Hawai Road on
EPC basis from design Km. 17.000 (Khupa)
16 EPC SARDP NH-313 17 252.79 168.3 23/03/2017 10-11-2017 100.00% 89.11% 84.73% 11/9/2020 12/31/2022 M/s Sushee Infra & Mining Limited
to Km. 34.000 [Existing Km 16.950 to Km
34.310 (Hayuliang – Hawai Road)] - II
2 langing of Hayuliang – Hawai Road on
EPC basis from Design Km. 34.000 to Km.
17 EPC SARDP NH-313 17.83 263.31 177.3 23/03/2017 10-11-2017 100.00% 83.89% 81.74% 11/9/2020 12/31/2022 M/s Sushee Infra & Mining Limited
51.825 [Existing Km 26.625 to Km 45.050
(Hayuliang – Hawai Road)]- III
2 laning of Balance work of Hayuliang–
Hawai bypass Road on EPC basis from
Poddar Infratech Pvt. Ltd. - GRRB
18 EPC SARDP design Km. 51.825 to Km. 63.131 Existing NH-313 11.3 256.66 131.91 31/03/2021 5/3/2021 100.00% 37.64% 35.00% 5/2/2023 5/2/2023
Associates (JV)
Km 45.050 of Hayuliang – Hawai road to
Hawai Town - IV

Construction of 2-lane road from km. 0.00


(Existing km. 16.00 of Roing -Hunli Road)
M/s DRAIPL - Iron Triangle (ITL)
19 EPC SARDP to Km. 74.00 (Ithun Bridge near existing NH-313 74.86 1718.59 1058.24 24/03/2017 3/5/2018 96.19% 53.99% 52.64% 3/4/2022 1/23/2023
(JV)
km. 21.50 of Anini Road)-Green Field
alignment

Construction of 2 Major bridges at Existing


Ch. 23+650 (Design Ch. 23+550) and Ch.
20 EPC SARDP 28+200 (Design Ch. 28+200) of bridge span Bridge 0.32 45.43 60 28/09/2021 12/17/2021 100.00% 0.00% 0.00% 6/19/2023 6/19/2023 Poddar Infratech Pvt. Ltd.
160 m along the Existing Hunli-Anini Road
(Pkg.1) from Km 21.500 to Km 37.500
Construction of 2-lane road from existing
21 EPC SARDP km. 21.50 of Hunli-Anini road (Near Ithun NH-313 16 322.15 210.44 06/05/2016 21-12-2016 100.00% 97.50% 95.22% 12/20/2019 9/30/2022 M/s Madhucon Projects Ltd.
Bridge) to Km. 37.500 - (Pkg.-I)
Construction of 2-lane Hunli-Anini road
22 EPC SARDP NH-313 39 568.92 434.06 12/09/2016 16-12-2016 100.00% 91.10% 90.04% 12/15/2019 3/31/2023 M/s PCL-Eagle (JV)
from km. 53.500 to km. 92.500 - III
Construction of 2-lane of Hunli-Anini road
23 EPC SARDP NH-313 13.7 188.78 145.8 14/12/2016 19-01-2017 100.00% 98.43% 97.56% 1/18/2020 9/30/2022 M/s Sushee Infra & Mining Limited
from km 92.50 to Km 106.20 - IV
Construction of 2-lane of Hunli-Anini road
24 EPC SARDP NH-313 13.8 200.44 154.8 14/12/2016 19-01-2017 100.00% 89.89% 87.81% 1/18/2020 12/31/2022 M/s Sushee Infra & Mining Limited
from km. 106.20 to Km. 120.00 - V
Construction of 2-lane of Hunli-Anini road
25 EPC SARDP NH-313 10.3 145.17 105 31/03/2018 6/15/2018 100.00% 98.71% 94.70% 6/14/2021 8/30/2022 M/s TTC Infra
from km. 120.0 to Km. 130.30 - VI
Construction of Balance work of 2 - Laning
of existing Akajan-Likabali-Bame Road on
EPC basis from design Km 33.00 to Km
26 EPC SARDP State Road 32.81 118 93 30/06/2021 9/1/2021 100.00% 37.47% 31.78% 3/3/2023 3/3/2023 MVV Satyanaryana
65.810 (Existing km 36.00 to km 71.00) in
the state of Arunachal Pradesh under
SARDP-NE (Pkg-2)
Construction of 2-lane road from Km.
65.810 to Km. 99.00 (Design
27 EPC SARDP State Road 26.118 323.49 220.17 31/03/2017 3/21/2018 100.00% 94.66% 85.57% 3/19/2021 12/31/2022 M/s SCIW-Shivam (JV)
Length=26.118 km) of Akajan-Likabali-
Bame road (Pkg-3)
Construction of Balance work of 2-Lane
with P S of Joram – Koloriang Road (NH-
28 EPC SARDP NH-713 16.558 228.71 100.21 10/08/2020 10/1/2020 100.00% 67.26% 63.56% 4/2/2022 12/31/2022 Valecha Engg. Ltd.
713) from existing Km 50.050 to Km 70.00
[Design Km. 44+989 to Km. 61.547 (Pkg-III)
Construction of Balance work of 2-Lane
with P S of Joram – Koloriang Road (NH- Bhimji Velji Sorathia Construction
29 EPC SARDP NH-713 17.177 294.04 147.13 11/08/2020 10/1/2020 100.00% 74.49% 73.34% 4/2/2022 12/31/2022
713) from existing Km 70.00 to Km 88.700 Pvt. Ltd.
[Design Km61.547 to Km78.724] (Pkg-IV)

Construction of Balance work of 2-Lane


with P S of Joram – Koloriang Road from Bhimji Velji Sorathia Construction
30 EPC SARDP NH-713 15 229.7 121.58 14/08/2020 10/1/2020 100.00% 70.55% 69.04% 4/2/2022 12/31/2022
existing Km88.700 to Km 104.850 [Design Pvt. Ltd.
km 78.724 to Km 93.724] (Pkg-V)
Construction of Balance work of 2-Lane
with P S of Joram – Koloriang Road (NH-
31 EPC SARDP 713) from existing Km104.850 to km NH-713 15 199.03 102.86 17/08/2020 10/1/2020 100.00% 67.34% 66.81% 4/2/2022 12/31/2022 Jainco Enterprises Pvt. Ltd.
122.600 [Design km92.724 to km108.724]
((Pkg-VI)
Construction of Balance work of 2-Lane
with P S of Joram – Koloriang Road from
32 EPC SARDP existing Km122.600 to km138.00 [Design NH-713 15 184.88 101.95 07/08/2020 10/1/2020 100.00% 56.68% 53.31% 4/2/2022 12/31/2022 Jainco Enterprises Pvt. Ltd.
Km108.724 to Km123.714] (Design length=
14.99km) (Pkg-VII)
Construction of Balance Work of 2 lane
with Paved shoulder of Joram-Koloriang
Road (NH-713) on EPC basis from existing
33 EPC SARDP Km 138.000 to Km 158.00 [Design Km NH-713 16.036 244.1 94.966 07/03/2022 5/7/2022 100.00% 2.19% 0.00% 11/6/2023 11/6/2023 Puna Hinda
122+353 to Km 138+389] (Package 8)
[design length - 16.035 km] under SARDP-
NE
Construction of 2-Laning with hard
shoulders of Arrowa-Khupa-Hayuliang
34 EPC NH(O)-NE 113 23.083 301.06 156.7 31/08/2020 10/25/2020 100.00% 13.89% 11.44% 4/27/2022 5/28/2024 M.P. Agarwalla Land Acquisition
section of NH-113 from Ch.68.550 to
Ch.91.633 under SARDP-NE NH(O)-NE
Construction of 2-Laning with hard
shoulders of Demwe-Brahmakund section
35 EPC NH(O)-NE 13 18.464 353.9 205.56 29/09/2020 11/5/2020 27.61% 19.20% 12.77% 5/8/2022 1/24/2023 Valecha Engg. Ltd. Land Aquisition
of NH-13 from Ch.0.00 km to 18.464km on
EPC under SARDP-NE NH(O)-NE

Total 750.17 10027.48 6583.65


Status as on 31.08.2022
Cumulati Remarks/ Issues
Right of Cumulati
Awarded ve (Land Aquisition
NHDP NH No. Sanctioned Date of way ve Target date of
SL. Length Cost Date of Financial Likely date of Name of the Issue/ Forest
Mode Phase/ Name of Project (Old/ Cost/TPC Start/Appointe (ROW) Physical completion as
No. (Km) Rs. in Award completion Contractor Issue/ Utility
Scheme New) Rs. in crore d Date Available progress per contract
crore progress Shifting/
% %
% Contractor Issue)
Assam
Improvement and Strenghtening of Road Section from Chand Khera
Strength
1 NH(O) to Kurti Bridge on Assam-Tripura Border in the state of Assam on 208A 17.95 66.94 60.21 04/10/2016 28-11-2016 100.00% 100.00% 99.50% 1/24/2018 Completed M/s Ganesh Ram Dokania
ening
EPC basis

Strength One time improvement of Moran Town section of NH-37 from km


2 NH(O) NH-37 3.5 14.52 13.5 31/05/2019 8/19/2019 100.00% 100.00% 100.00% 8/17/2020 Completed M/s BB Enterprises
ening 555.000 to km 558.500

Strength One time improvement of Digboi to Ledo Town section (via Powal
3 NH(O) NH-38 33 30.84 26.92 29/07/2019 9/25/2019 100.00% 100.00% 100.00% 9/23/2020 Completed M/s Ganpati Builders
ening and Margherita ) of NH-38 from km 20.000 to km 53.000

Construction of Dibrugarh By Pass / realignment of NH-37 from M/s ABCI-JKM Pvt. Ltd (JV).
4 EPC SARDP 37 15.5 379.32 96.84 20/02/2015 11/2/2015 100.00% 100.00% 99.19% 10/31/2018 Completed
Bogibeel Junction at km. 581.700 to km. 597.147

M/s ECI Engg.Construction Co.


4-Laning from Gohpur to Holongi section from km 264.10 of NH 52 to
5 EPC SARDP 52 10.08 223.3 168.39 30/03/2015 12/11/2015 100.00% 97.55% 93.78% 12/10/2018 Completed- Ltd.
km 20.37 of NH 52A

2-laning with paved shoulders from km 6.25 to 10.40 of Silchar M/s Shree Gautam Construction
6 EPC SARDP 53/37 4.15 76.78 53.21 23/03/2015 10/1/2015 100.00% 100.00% 99.69% 12/11/2017 Completed-
Badarpur section Company Ltd.

4-Laning of NH-37 from Nagaon By-pass to Teliagaon (km 278.600 to


PRL Projects & Infra Structure
7 EPC SARDP km 288.600) in the state of Assam under SARDP-NE Phase-A on EPC 37 10 225.02 87.11 23/03/2020 7/1/2020 100.00% 92.41% 90.69% 12/23/2021 15/08/2022 Land Acquisition
Ltd.
mode-Package-1
4-Laning of NH-37 from Teliagaon to Rangagara (km 288.600 to km
8 EPC SARDP 297.000) in the state of Assam under SARDP-NE Phase-A on EPC 37 8.4 66.25 20/03/2020 7/1/2020 100.00% 77.87% 75.54% 12/23/2021 12/31/2022 Ganga Sagar Singh Land Acquisition
mode – Package - 2

4-Laning from Rangagara to Kaliabhor Tiniali from km 297.00 to km


9 EPC SARDP 37 18.315 289.99 196.24 16/01/2017 23-10-2017 100.00% 65.14% 61.24% 4/21/2020 12/31/2022 M/s Simplex Infrastructure Land Acquisition
315.315 of NH-37 on EPC basis.

4-Laning from Kaliabor Tinali to Dolabari section from Km 0.0 to Km M/s Gammon India- S P
10 EPC SARDP 37A 14.01 811.28 588.95 31/10/2014 11/29/2014 100.00% 94.91% 94.52% 11/28/2018 9/30/2022
17.3 of NH 37-A including construction of new Brahmaputra bridge Singla[SPSCPL] (JV)

4-Lane highway connecting km 17.3 of NH 37A and km 182 of NH 52


11 EPC SARDP 37A &52 16.862 1049.51 124.584 05/11/2021 2/7/2022 100.00% 11.18% 10.34% 8/11/2023 8/11/2023 Sri Babul Nath
between Dolabari and Jamuguri on EPC basis

Construction of Jia Bharali Bridge (1.2Km) along with its approaches


37A/ MKC Infrastructure Ltd. - RSM
12 EPC SARDP and River Training Work from km 25.552 to km 27.500 of NH-37A 1.948 448.03 21/12/2020 2/17/2021 100.00% 42.71% 41.58% 8/5/2023 8/5/2023 Land Acquisition
715 Infra Projects (JV)
(New NH-715) (Re-awarded : CoS work)

4-Laning from Jamuguri to Biswanath Chariali from km 182 to km 208 M/s T K Engineering Consortium
13 EPC SARDP 52 26 520.01 303.49 13/10/2016 12/19/2016 100.00% 74.10% 70.70% 6/19/2019 31-11-2022
of NH-52 Pvt. Ltd.(TKECPL)

4-Laning from Biswanath Chariali by-pass Km 208.00 to Gohpur Km


Dhatarwal Construction
14 EPC SARDP 265.50 (Total length 57.50) in the state of Assam on EPC basis Under 52 57.5 1099.35 393.482 18/10/2021 12/11/2021 100.00% 22.30% 17.97% 6/14/2023 6/14/2023
Company Pvt. Ltd.
SARDP-NE
4-Laning of Numaligarh to Jorhat section from Km. 402.500 to Km.
M/s Hindustan Construction
15 EPC SARDP 453.000 (Design Km 403.200 to Km 454.240) except Dergaon bypass 37 39.72 814.56 454.89 31/10/2014 5/23/2015 99.47% 87.97% 86.15% 5/23/2020 10/31/2022 Land Acquisition
Company (HCC)
(with Toll Plaza)

Vijeta Projects - Sweety


16 EPC SARDP 4-Laning of Jorhat to Jhanji section from Km. 453.00 to Km. 491.08 37 37.8 738.15 220.4 05/11/2021 2/9/2022 98.38% 8.00% 7.11% 8/11/2023 8/11/2023 Land Acquisition
Infrastructure (JV)

4-Laning of Jhanjhi Jn to Demow section from Km. 491.050 to Km. M/s-Kamac Engg - M/s Shiva
17 EPC SARDP 37 44.075 1369.02 234.199 25/07/2022 - 97.35% 0.00% 0.00% - - Land Acquisition
535.250(Design Km 490.800 to Km 534.800) (with Toll Plaza) Harlalka

4-Laning of NH-37 Section between Demow to End of Moran Bypass


18 EPC SARDP 37 26.9 385.57 - - - 98.84% 0.00% 0.00% - - Terminated yet to award Land Acquisition
(From Km. 534.800 to Km. 561.700) on EPC Mode.

4-Laning of NH-37 Section between End of Moran Bypass to Bogibeel


19 EPC SARDP 37 19.17 330.3 223.5 31/01/2019 6/7/2019 100.00% 64.37% 63.15% 12/2/2021 10/26/2022 M/S Manaranjan Brahma[MB]
junction near Lapetketa ((Km. 561.700-Km. 580.778) on EPC Mode.

4-Laning of Balachera-Harangjao section of NH-54 (ext.) from km


M/s Sushee Infra- M/s JSC
20 EPC NHDP II 275.00 to km 244.00 in the state of Assam under east west corridor 54 Ext. 25.25 887.68 519.3 31/10/2017 12/26/2017 100.00% 51.93% 50.51% 6/24/2020 4/30/2023
PTPS (JV)
project.
Construction and up gradation to 4-Lane of existing two lane with
paved shoulder from Hapachara to Tulungia road of NH-117 of
21 EPC NH(O)-NE 102B/ 117 14.66 220.19 138.25 26/03/2020 6/26/2020 99.50% 40.25% 37.61% 12/26/2022 12/26/2022 B.K.Sons Infra Pvt. Ltd.
existing Km 0.00 to km 14.050 and (Design Km 0.000 to km 14.660),
(Design length- 14.660 km) under BMP

Widening/Improvement to 4 -Lane with Paved Shoulder from Ch.


52.470km to Ch.71.500 km (DesignCh.48.655km to Ch.67.556km)of Rajendra Singh Bhamboo Infra
22 EPC NH(O)-NE 17 18.9 636.42 418.49 22/03/2021 7/9/2021 80.42% 26.77% 23.52% 12/31/2022 1/10/2023
Tulungia Jogighopa Bridge Approach Section (Package-5) of Pvt. Ltd.
Bilasipura- Guwahati road (NH 17)

Construction of New 2-Lane Bridge with its approaches from km Satpal (S. P.) Singla
23 EPC NH(O)-NE 17 4.385 746.76 402.75 10/08/2021 11/12/2021 90.43% 6.98% 2.42% 11/11/2024 11/11/2024
0+000 to Km 4+385 across River Brahmaputra on NH-17 at Jogighopa construction Pvt. Ltd.

Widening/Improvement to 4-Lane with paved shoulder from


Ch.75.330Km to Ch.88.00km (Design Ch.71.800 to 84.100 km) of
24 EPC NH(O)-NE Jogighopa Bridge Approach (Near Pancharatna)- Agia (near Nichinta) NH-17 12.3 208.84 114.3 25/08/2020 10/26/2020 94.16% 26.27% 24.43% 4/19/2022 4/15/2023 Mayasheel Construction
section (Pkg. 6) of Bilasipura-Guwahati road (NH-17) on EPC under
BMP

Widening/Improvement to 4 -Lane with Paved Shoulder from Ch.


88.000km to Ch.99.930 km (Design Ch.84.100km to Ch.96.000 km) of
25 EPC NH(O)-NE NH-17 11.63 286.72 131.865 31/03/2021 7/9/2021 0.00% 0.00% 0.00% - - Ram Chandra Paul
Sagunbashi forest (near Nichinta) to starting of Krishnai Bypass
Section (Package-7) of Bilasipura Guwahati road (NH 17)

Widening/lmprovement to 4-Lane with paved shoulders from Km.


P. D. Agrawal Infrastructure Ltd.
26 EPC NH(O)-NE 51+246 to Km. 66+000 (Design Chainage 50+710 Km to 65+923 Km) of 29 15.21 335.88 138.329 26/03/2021 7/12/2021 92.20% 52.03% 50.37% 1/3/2023 1/3/2023 Land Acquisition
-Apex Structure Pvt Ltd. (JV)
Parokhuwa-Dokmoka section (Package-2)

Widening/Improvement to 4-Lane with Paved shoulder from km 66.00


27 EPC NH(O)-TSP to km 81.00 (Design Chainage 65.923 to 80.930) of Dokmoka - 29 15.007 278.46 129.14 10/08/2020 9/30/2020 100.00% 94.08% 93.34% 3/24/2022 11/30/2022 Skylark Infra Engg. Pvt. Ltd. Land Acquisition
LoringThepi section- (Package-3)

Widening/Improvement to 4-Lane with Paved Shoulder from km


28 EPC NH(O)-TSP 81+000 to km 95+400 (Design Chainage 80+930 to 96+400) of Loring 29 15.47 260.07 141.35 03/02/2021 6/25/2021 94.18% 78.48% 77.33% 12/17/2022 12/17/2022 S.S Builders Land Acquisition
Thepi - Ganapath Gaur Gaon Section - (Package-4)

Widening/lmprovement to 4-Lane of Daboka Dimapur Stretch from


29 EPC NH(O)-NE Km 95+400 to Km 113+830 (Design Chainage 96+400 Km to 113+830 29 17.43 288.85 141.464 31/03/2021 7/12/2021 40.00% 6.48% 6.16% 1/12/2023 1/12/2023 B.K.Sons Infra Pvt. Ltd. Land Acquisition
Km) of Ganpath Gaur Gaon- Kwaram Taro Vitlage- (Package-5)

Widening/Improvement to 4-Lane with Paved Shoulder from KM


30 EPC NH(O)-NE 113+300 to Km 146+230 (Design Chainage 113+830 to 145+712) of 29 31.88 625.64 282.11 10/09/2021 to be given - 0.00% 0.00% 7/13/2024 7/13/2024 Ashoka Buildcon Ltd. Land Acquisition
Kwaram Taro Village - Dillai Section (Package-6)

Widening/lmprovement to 4-Lane with Paved Shoulder from Dillai at


31 EPC NH(O)-NE Km 146+230 to Lahorijan at Km 157+46O (Design Chainage 145+712 29 10.79 204.1 81.27 02/09/2022 to be given - 0.00% 0.00% - - M/s Shankar Agarwal Land Acquisition
to 156+502) of Dillai - Lahorijan (Package - 7)

4-Lane Bridge including approaches over River Brahmaputra Larsen & Toubro Ltd. Heavy
(65%)
32 EPC EAP (JICA) between Dhubri (on North Bank,Assam) and Phulbari (on south 127B 19.282 4997.04 3165.99 24/11/2020 12/15/2020 100.00% 12.21% 11.51% 9/12/2028 Civil Infrastructure IC Larsen &
15-03-2025
Bank,Meghalaya) on NH-127B Toubro Ltd.(L&T)
Widening / Improvement to 4-Lane with Paved Shoulder configuration
of existing single lane road from Srirampur (near Bhairiguri Village)
to Kachukhana Harichara Paglagaunj (Package-I) of Srirampur -
33 EPC EAP (JICA) 127B 27.65 613.89 - - - - 0.00% 0.00% - - Under Bidding
Dhubri Section of NH-127B from existing Km 0.000 to Km 28.050
(Design Km 0.000 to Km 27.650), (Design Length=27.650 Km) under
JICA ODA Loan assistance (Phase-V) [Srirampur - Dhubri Pkg-1]

Widening / Improvement to 4-Lane with Paved Shoulder


configuration of existing single lane road from Kachukhana
Harichara Paglagaunj to Dhubri - Phulbari Bridge approach (Package- M/s Jandu Construction India
34 EPC EAP (JICA) 127B 26.504 909.02 453.9 04/08/2022 Not given - 0.00% 0.00% - -
II) of Srirampur - Dhubri Section of NH-127B from existing Km 28.050 Pvt. Ltd.
to Km 55.060 (Design Km 27.650 to Km 54.154), (Design
Length=26.504 Km) under JICA ODA Loan assistance (Phase-V)

Rehabilitation & upgradation to 4-Lane with Paved shoulder of


M/s Rajinder Infrastructure
35 EPC NH(O) Dergaon Town section from Km 426.800 to Km 437.800 (Total length- 2/ NH-37 11 287.63 122.5 19/03/2020 6/30/2020 75.55% 73.12% 73.10% 6/19/2022 -
Pvt.Ltd.
11.00 km) on NH 37 on EPC basis

Widening/improvement to 4-Lane with paved shoulder from km.


581+700 to km 606+300 of NH-37 on existing Dibrugarh-Lahoal-
36 EPC NH(O)-NE 37 24.6 215.27 115.82 31/03/2022 to be given 0.00% 0.00% 0.00% - - Ganpati Builders
Chabua Bypass i.e. from Lepetketa to Kandulibari Grant Gaon
section under NH(O) - NE
Widening/improvement to 4-Lane with paved shoulder from km.
37 EPC NH(O)-NE 606+300 to km 626+030 of NH-37 on existing Lahoal-Chabua Bypass 37 19.73 170.95 101.16 05/04/2022 to be given 0.00% 0.00% 0.00% - - JKM Infra works LLP
i.e. Kandulibari Grant Gaon to Nalanihulla section under NH(0) - NE

Total 726.56 20597.87 10358.18


Status as on 31.08.2022
Remarks/ Issues
Target date
NH Awarded Right of way (Land Aquisition
NHDP Sanctioned Date of Cumulative Cumulative of
SL. No. Length Cost Date of (ROW) Likely date of Issues/ Forest
Mode Phase/ Name of Project Cost/TPC Start/Appoin Physical Financial completion Name of the Contractor
No. (Old/ (Km) Rs. in Award Available completion Issues/ Utility
Scheme Rs. in crore ted Date progress % progress % as per
New) crore % Shifting/
contract
Contractor Issue)
UT of Jammu & Kashmir
Restoration of road by way of clearance of landslide, surface
boulders side drain, culverts including construction of R/wall
Item M/s Khandey Infra Pvt Ltd
1 NH(O) and B/walls and laying of WBM-I, WBM-II, WBM-III & Bituminous 244 23.20 16.49 12.47 16/02/2018 3/7/2018 100.00% 100% 100% 8/31/2019 Completed
Rate
Carpeting on Sinthanpass- Anantnag –Khanabal road (Km
184.00 to Km 265.000)
Restoration of Road by way of clearance of landslide, surface
boulders side drain, culverts including construction of
Item R/wall/Scuppers and laying of WBM-II, WBM-III, & Pre- Mixed M/s Khandey Infra Pvt Ltd
2 NH(O) 244 14.00 8.01 6.55 01/03/2018 3/7/2018 100.00% 95.00% 76.26% 11/10/2020 Completed
Rate Surfacing/Mixed seal Surfacing (PC) on Batote-Kishtwar-
Chatroo- Sinthan top road NH-244 Km from Km 170.000 to Km
184.000
Work of construction, operation and maintenance of Z-Morh
3 EPC NH(O) tunnel including approaches on NH-1 (Srinagar Sonamarg 1 6.5 2680.42 2378 19/12/2019 6/24/2020 99.58% 52% 56% 12/21/2023 12/21/2023 M/s APCO Infratech Pvt. Ltd
Gumri road) on DBFOT (Annuity basis)
Construction of
(I) Connecting road from Z-Morh Tunnel to Zojila Tunnel (Road
Megha Engineering &
4 EPC NH(O) Length= 18.475km) and 1A 32.62 6808.69 4509.5 25/08/2020 10/1/2020 100.00% 18.82% 14.76% 6/1/2024 9/29/2026
Infrastructures Ltd
(II) 14.150 Km long Bi- directional Tunnel accross Zojila Pass on
Sonamarg - Kargil section of NH-01
Construction of Bi-directional Tunnel at Km 83 of Length 495 m
including approach road of 664 m and a Major Bridge of 110 m M/s Beigh Construction Co. Pvt.
5 EPC NH(O) 244 1.269 91.29 76.49 07/02/2020 6/8/2020 100.00% 29.03% 27.58% 6/8/2022 3/17/2023
from Km 82.675 to Km 82.925 on NH-244 on EPC basis (Khellani- Ltd.
Kishtwar) in the UT of J&K
Up-gradation to 4-lane with Paved Shoulder of Jammu-Akhnoor M/s. S.P Singla Construction Pvt.
6 EPC NH(O) road section of NH-144A from Canal head (Km 0.800) to Ganesh 144-A 5.2 458.06 277.03 15/03/2018 8/7/2018 100.00% 96.04% 94.01% 2/4/2021 9/15/2022 Ltd. Land Acquisition
Vihar (Km 6.000) Pkg-II
Up-gradation to 4-lane with Paved Shoulder of Jammu-Akhnoor
7 EPC NH(O) road section of NH-144A from Ganesh Vihar (Km 6.000) to Khati 144-A 20.35 435.82 193.99 02/03/2019 7/12/2019 94.50% 58.67% 53.25% 7/12/2021 3/3/2023 M/s. Tarmat Ltd. Land Acquisition
Chowk (Km 26.350) Pkg=IIIA
Widening and up-gradation to 2 lane with paved shoulder
M/s. ECI Engineering in JV with
8 EPC NH(O) configuration and geometric improvement from km 0.000 to km 244 16.99 264.21 155.04 27/03/2018 11/22/2018 93.85% 73.61% 73.23% 11/22/2020 4/3/2023 Land Acquisition
M/s SRM Projects
16.990 (Phase-I) on Chenani – Sudhmahadev section of NH-244

Up-gradation to 2-lane with Paved Shoulder from Km 12.850 to


9 EPC NH(O) Km20.300 of 7.450Km length on Goha-Khellani section and a link 244 9.46 228.39 118.41 31/07/2020 10/1/2020 98.94% 43.92% 41.20% 4/1/2022 6/30/2023 OASIS - VIPL (JV) Land Acquisition
road to Goha village of 2.016 km on NH-244 (Package I)
Up-gradation to 2-lane with Paved Shoulder from Km 20.300 to
10 EPC NH(O) Km 29.030 of 8.730 Km length on Goha-Khellani section on NH- 244 8.73 210.79 99 31/07/2020 10/1/2020 96.84% 46.12% 43.62% 4/1/2022 5/31/2023 E5 Infrastructure Pvt. Ltd. Land Acquisition
244 (Package II)
Up-gradation to 2-lane with Paved Shoulder form Km 29+030 to
Km 31+449 of 2.419 Km length of Uni-Directional (1.574 Km)
11 EPC NH(O) 244 2.42 749.61 431.28 08/02/2021 3/25/2021 100.00% 30.25% 24.24% 3/25/2023 5/23/2023 APCO Infratech Pvt Ltd
Khellani Tunnel including its approach road on NH-244
(Package III)
Construction & Upgradation to 2 lane with paved shoulder from
Design Km. 31.449 (Khellani) (Ex. Km 44.946) to Km 51.700 R&C Infra Engineers Pvt. Ltd.-
12 EPC NH(O) 244 20.251 486.45 208.581 03/02/2021 3/29/2021 86.02% 47.40% 41.36% 9/28/2022 9/28/2022 Forest Issues
(Prem Nagar) (Ex. Km 68+617) of 20.251 Km length on Khellani - SKS Infra Projects Pvt. Ltd. (JV)
Kishtwar - Chattroo section (PKG- 1)
Construction & Upgradation to 2-lane with paved shoulder from
Design Ch. Km 51+700 (at Premnagar km 66+315) to Km 66+535
Mathiyan Construction Pvt. Ltd. -
13 EPC NH(O) New Thatri (at Start of Km 83rd, Tunnel Km 82+665) of 14.835 244 14.84 512.43 220.33 19/07/2021 8/26/2021 91.08% 17.63% 16.26% 2/25/2023 2/26/2023
Unique Construction (JV)
Km design length on Chenani-Sudhmahadev-Goha Khellani-
Kishtwar-Vailoo Donipawa-Ashajipora Section (Pkg - 2).

construction & Upgradation to 2-lane with paved shoulder from


Design Km 67.805 (end of Km 83rd tunnel) (Ex. Km 83+905) to
Km 80.675 (start of Kislhtwar Bypass) (Ex. Km 97+0751 of 12.870 Land Acquisition/Forest
14 EPC NH(O) 244 12.871 398.51 134.353 30/03/2021 7/1/2021 99.84% 25.63% 19.01% 12/30/2022 12/30/2022 R & B Infra Project Pvt. Ltd
Km length on chenani-Sudhmahadev-Goha Khellani-Kishtwar- Issues
vailoo-Donipawa-Ashajipora seition of NH-244 in the UT of J&K
on EPC Mode under NH(O)-Gen (Pkg-3)
Construction of Kishtwar bypass with 2 lane with paved
shoulder from Design Km. 80.675 (Dulhasti) to km 95.550
(Bandarkoot ) of 14.88 km & link road from 0+000 to 1.871 of APS Hydro Pvt. Ltd. - Unique Land Acquisition/Forest
15 EPC NH(O) 244 16.746 859.67 436.337 07/07/2021 8/24/2021 94.33% 5.99% 5.84% 8/23/2023 8/23/2023
length=1.871 Km on Khellani - Kishtwar - Chattroo section and Construction (APS - UC) (JV) Issues
including a link road to Kishtwar town.
(Pkg-4)
Construction/upgradation to 2-lane with paved shoulder from
Shree Girrajjee Infra Heights Pvt.
Design Km 95.55 (gandarkoot) to Km. 111.06 (Chattroo) of 15.52
16 EPC NH(O) 244 15.520 497.09 202.603 13/07/2021 8/24/2021 99.74% 15.84% 12.64% 2/19/2023 2/19/2023 Itd. - Narendra Builders (SGIHPL- Land Acquisition
Km length on Chenanisudhmahadev-Goha-Khettani-Kishtwar-
NB) (JV)
vailoo-Donipawa-Ashajipoora section on NH-244 (Pkg-5)

Construction & Upgradation to 2/ 4-lane with paved shoulder


New India Contractors &
from Design Km 148+589 (Existing km 235+070) (Vailoo )to
17 EPC NH(O) 244 27.943 285.28 158.15 03/02/2021 3/31/2021 100.00% 59.64% 44.44% 9/30/2022 9/30/2022 Developers Pvt. Ltd. - Khanday
Design Km 176+532 (Existing km 263+070) Donipawa of 27.943
Infrastructure Ltd. (JV)
km length on Khellani-Khanabal section (PKG- 6)
construction of New 2-Lane bypass from Design Km 176+532
(Existing km 263+070; (Donipawa) to Design Km 185+002 (Near
18 EPC NH(O) Khudwani on NH-44 at Existing km 238+500) Alstop via 244 8.470 260.40 57.264 30/03/2021 6/15/2021 100.00% 23.08% 14.43% 12/16/2022 12/16/2022 E5 Infrastructure Pvt. Ltd.
Ashajipora of 8.470 Km length i.e., to connecting NH-244 & NH-
44 (Pkg-7)
Strengthening & Upgradation of existing carriageway to
19 EPC NH(O) intermediate lane from km0.00 to km42.82 of Length 42.820kms 701A 42.820 146.31 84.62 31/08/2020 10/8/2020 0.00% 90.15% 84.10% 4/6/2022 1/0/1900 0
on Baramulla-Gulmarg section
4-L Jammu-Akhnoor Pkg-1
20 EPC NH(O) 144A 1.350 245.34 Under bidding - - 0.00% - - - - Under bidding
(4th Tawi bridge to Canal Head )

21 EPC NH(O) 4-L Jammu-Akhnoor Pkg-3B 144A 3.740 198.28 Under bidding - - 0.00% - - - - Under bidding

Construction of Uni-directional Sudhmahadev - Dranga Tunnel


and its approach roads on Chenani - Sudhmahadev - Goha road
22 EPC NH(O) (design length 12.850 km including Uni-directional Tunnel 1- 244 12.850 3703.16 Under bidding - - 0.00% - - - - Under bidding
5.449/ 5.417 km (Tube-1/ Tube-2) and Tunnel 2- 2.64/2.63 km
(Tube-1/ Tube-2) on NH-244 in UT of J&K on EPC Mode.
Constructon of Uni-Directional Singhpora-Vailoo Twin Tube
Tunnel (Under Sinthan pass) and its approach road (of 2-lane
with paved shoulder) on Sudhmahadev-Goha-Khellani-Kishtwar-
23 EPC NH(O) 244 38.610 4807.97 Under bidding - - 0.00% - - - - Under bidding
Vailoo-Khanabal stretch (Design Length 38.61 KM including Uni
directional twin tube Tunnel 10.36) on NH-244 in the UT of J&K
on EPC Mode.

Total 356.75 24352.67 9759.99


Status as on 31.08.2022
Remarks/ Issues
Right of way Cumulative Cumulative (Land Aquisition
NHDP NH No. Sanctioned Awarded Date of Target date of
SL. Length (ROW) Physical Financial Issues/ Forest
Mode Phase/ Name of Project (Old/ Cost/TPC Cost Date of Award Start/Appointed completion as per Name of the Contractor
No. (Km) Available progress progress Issues/ Utility
Scheme New) Rs. in crore Rs. in crore Date contract
% % % Shifting/ Contractor
Issue)
UT of Ladakh
Widening & Upgradation to 2 lane with paved shoulder of NH-301 Shiva Buildtech Pvt Ltd-
1 EPC NH(O) Kargil Zanskar Road from Design Km 0.000 (Ex. Km.0.000) to Km 301 30.040 384.24 192.30 3/31/2021 7/1/2021 17.31% 16.29% 11.58% 1/2/2023 Haidary Construction Pvt. Ltd Land Acquisition
30.040 (Ex. Km. 30.000) of 30.040 Km length (Pkg-I) (JV)
Widening & Up-gradation to 2 lane with paved shoulder of NH-301
2 EPC NH(O) Kargil- Zanskar Road from Design Km .30.940 (Ex. Km. 30.000) to 301 26.960 404.89 229.19 3/31/2021 7/1/2021 9.27% 3.42% 0.77% 1/2/2023 Topline Infra Projects Pvt. Ltd. Land Acquisition
Design Km 57.000 (Ex. Km. 57.905) of 26.960 Km length (Pkg-II)

Widening & Up-gradation to 2 lane with Paved shoutder of NH-301


3 EPC NH(O) Kargil- Zanskar Road from Design km 57.000 (Ex. Km. 57.905) to Km 301 30.000 381.01 217.09 3/31/2021 7/1/2021 41.67% 16.05% 12.61% 1/2/2023 Topline Infra Projects Pvt. Ltd. Land Acquisition
87.000 (Ex. Km. 88.2491) of 30.000 Km length (Pkg-lll)
Up-gradation to Intermediate lane with earthen shoulder of NH-301
80.92 United Jehlum Road and Roof
4 EPC NH(O) Kargil- Zanskar road from km 87+00 to KM 98+524 in the UT of 301 11.520 49.73 8/5/2020 3/2/2021 100.00% 16.02% 15.15% 3/1/2024
Ladakh(Formally State of J&K) on EPC Mode PKG-IV Builders
S&P lnfrastructure Developers
Up-gradation to intermediate lane of NH-301 Kargil- Zanskar road
Pvt. Ltd -
5 EPC NH(O) from Km 98+524 to Km. 117+180 in the UT of Ladakh (Formally State 301 18.650 169.79 151.74 8/11/2020 12/10/2020 100.00% 74.16% 71.09% 12/9/2023
of J&K) on EPC Mode PKG-V Skylark lnfra Engineering Pvt
Ltd.(JV)
S&P lnfrastructure Developers
Up-Gradation to Intermediate lane of NH-301 Kargil- Zanskar Road
Pvt. Ltd -
6 EPC NH(O) from Km 117+180 to Km. 148+320 in the UT Ladakh (Formerly State 301 31.140 239.81 185.37 1/27/2021 5/24/2021 100.00% 44.23% 43.51% 5/23/2022
of J&K) on EPC mode PKG-VI Skylark lnfra Engineering Pvt
Ltd.(JV)
S&P lnfrastructure Developers
Up-Gradation to Intermediate lane of NH-301 Kargil- Zanskar Road
Pvt. Ltd -
7 EPC NH(O) from Km 148+320 to Km. 196+250 in the UT of Ladakh (Formerly 301 47.930 308.86 239.00 1/27/2021 6/14/2021 100.00% 35.35% 34.37% 6/13/2024 Land Acquisition
State of J&K) on EPC mode PKG-VII Skylark lnfra Engineering Pvt
Ltd.(JV)
Widening & Up-gradation to 2 lane with paved shoulder of NH-301
8 EPC NH(O) Kargil Zanskar Road from Design Km 196.250 (Ex. Km. 194.1901 to 301 33.770 398.37 195.29 3/31/2021 7/1/2021 51.53% 21.93% 15.10% 1/2/2023 Satish Aggarwal & Co. Land Acquisition
Design Km 230.020 (Ex Km. 231.692) of 33.770 Km length (pkg-Vlll)

Total 230.01 2286.97 1459.71


Status as on 31.08.2022
Right of Remarks/ Issues
Awarded
NHDP NH No. Sanctioned Date of way Cumulative Cumulative Target date of (Land Aquisition
SL. Length Cost Date of Likely date of
Mode Phase/ Name of Project (Old/ Cost/TPC Start/Appoin (ROW) Physical Financial completion as Name of the Contractor Issues/ Forest Issues/
No. (Km) Rs. in Award completion
Scheme New) Rs. in crore ted Date Available progress % progress % per contract Utility Shifting/
crore
% Contractor Issue)
Manipur
EAP 2- Laning of Imphal – Moreh Section of NH 39 from
1 EPC 39/102 44.78 868.75 457.77 01/06/2018 10/16/2018 100.00% 100.00% 100.00% 10/15/2021 Completed M/s GR Infra Projects ltd
(ADB) Km 350.000 to Km 395.680 (Package II)

Construction of :(i) 154m span steel superstructure


Bridge at km 145.090 over river Barak & (ii) 122m
2 BW NH(O) span steel superstructure Bridge at km 189.800 over 53 2 141.14 109.00 02/12/2016 4/27/2017 100.00% 100.00% 83.18% 4/24/2020 Physically Completed M/s Bhartia Infra (BIPL)
river Makru and Approaches of both the Bridges to
be constructed is 1595m.
Construction of 4-Lane Bridge over Irang River on
3 EPC NH(O) 53/ 37 0.377 49.31 41.88 27/11/2020 1/4/2021 100.00% 44.26% 32.45% 10/16/2022 1/4/2023 Paratech Constructions Pvt. Ltd.
Imphal-Jiribam road section (95.50 Km)
Improvement/Strengtening to 2-lane with hard
4 EPC NH(O)-NE shoulder of Pallel-Chandel section of NH-102C (Km 102C 18.292 107.72 71.01 27/03/2020 7/1/2020 100.00% 100.00% 96.84% 6/30/2022 Physically Completed Krishna Construction Co.
0.000 to Km 18.292) on EPC basis
Widening to 2 -Lane with Paved shoulder of Imphal
to Jiribam section of NH-37 from Design Chainage
5 BW NH(O)-NE 53/ 37 12.665 139.38 78.99 30/03/2021 7/1/2021 96.35% 22.82% 18.55% 1/2/2023 1/2/2023 Avantika Contractor (I) Ltd.
3.275 km to 15.940 Km (Total length=12.665 Km)
(PKG-1)
Widening to 2 -Lane with Paved shoulder of Imphal
to Jiribam section of NH-37 from Design Chainage
6 EPC NH(O)-NE 15.940 km to 33.120 Km (Existing Chainage Km 53/ 37 17.18 195.14 120.74 26/03/2021 6/11/2021 58.49% 20.20% 18.38% 12/13/2022 12/13/2022 CMM Infraprojects Ltd.
15.946 to Km 33.395) (Total length=17.180 Km)
(PKG-2)

Widening to 2 -Lane with Paved shoulder of Imphal


to Jiribam section of NH-37 from Design Chainage Mehta Construction Company -
7 EPC NH(O)-NE 53/ 37 33.16 467.00 253.84 15/07/2021 9/15/2021 35.22% 19.20% 16.99% 3/19/2023 3/19/2023 Land Acquisition
33.000 km to 66.390 Km (Existing Chainage from km Ganpati Builders (JV)
33.395 to km 67.496) (PKG-3)

Widening to 2 -Lane with Paved shoulder of Imphal


to Jiribam section of NH-37 from Design Chainage BLA Projects Private Limited - G P
8 EPC NH(O)-TSP 53/ 37 35.17 579.63 268.34 23/08/2021 27.06.2022 100.00% 0.42% 0.00% 12/29/2023 12/29/2023 Land Acquisition & Forest Issues
66.110 km to 101.280 Km (Existing Chainage km Projects Ltd. (JV)
67.496 to km 103.557) (PKG-4)
Widening to 2 Lane with Paved shoulder of lmphal
to Jiribam section of NH-37 from Design Ch. from
9 EPC NH(O)-TSP 53/ 37 30 410.68 218.52 25/03/2022 to be given 0.00% 0.00% 0.00% - - Aarpee Infraprojects Pvt. Ltd. Land Acquisition & Forest Issues
Km 101+280 Near Khongsang Village to Km
131+280 near Puilon (Kambiron) Village ( PKG-5 )

Widening to 2 Lane with Paved shoulder of lmphal


10 EPC NH(O)-TSP to Jiribam section of NH-37 from Design Ch. from 53/ 37 38.29 504.76 243.99 31/03/2022 to be given 0.00% 0.00% 0.00% - - Sarjan Infracon Pvt. Ltd. Land Acquisition & Forest Issues
km 131.280 to km 169.570 (PKG-6)

Improvement/widening to 2 laning of stretch from M/s Shivalaya Construction Pvt.


11 EPC SARDP 137 37.97 424.62 296.25 08/03/2019 8/1/2019 100.00% 84.51% 79.18% 7/31/2022 2/18/2023 Land Acquisition & Forest Issues
Khongsang to Tamenglong of NH-137 Limited

Construction of 2 -Lane with paved shoulders road


from Tamenglong to Mahur in the state of Manipur M/s Roadridge Developers Pvt. Ltd.
12 EPC NH(O)-TSP 137 10 185.80 111.80 19/07/2021 9/15/2021 100.00% 15.48% 11.26% 3/16/2023 3/16/2023
from km 0.000 at Tamenglong to km 10.000 near - Sunshine Overseas Pvt. Ltd. (JV)
Dialong (Package-1)
Construction of of 2 -Lane with paved shoulders
road from Tamenglong-Tousem-Lisang-Mahur M/s Jandu Construction India Limited
13 EPC NH(O)-TSP Road (NH-137) starting near Dialong Village at km 137 21.43 483.87 292.45 20/07/2021 9/15/2021 100.00% 22.98% 16.02% 3/16/2023 3/16/2023 - Niraj Cement Structurals Limited
10.000 and ending near Barak River at km 31.430 (JV)
(Package-2)
Construction of 2 -Lane with paved shoulders road
from Tamenglong to Mahur in the state of Manipur
14 EPC NH(O)-TSP 137 12.05 234.08 150.06 26/03/2021 6/21/2021 100.00% 22.81% 18.41% 12/20/2022 4/23/2023 M/s Kalyan Toll Infrastructure Ltd.
from Km 20.500 at old Tamenglong to Km 30.800
near Phelong (Package-3)
Construction of 2 -Lane with paved shoulders road
from Tamenglong to Mahur in the state of Manipur M/s Roadridge Developers Pvt. Ltd.
15 EPC NH(O)-NE 137 10.7 198.77 119.74 19/07/2021 9/15/2021 100.00% 15.49% 11.69% 3/16/2023 3/16/2023
from km 34+000 at Phelong to km 44+700 near - Sunshine Overseas Pvt. Ltd. (JV)
Azuram (Package-4)
Construction of 2 -Lane with paved shoulders road
from Tamenglong to Mahur (NH-137) in Manipur M/s Shri Swami Samarth Engineers
16 EPC NH(O)-TSP 137 26.45 477.86 286.71 23/08/2021 11/18/2021 100.00% 7.20% 4.37% 5/19/2023 5/19/2023
starting from km 54.180 near Azuram to km 80.630 Ltd.
near Mandeu (Package 5)
Construction of 2 -Lane with paved shoulders road
from Tamenglong to Mahur (NH-137) starting from
17 EPC NH(O)-TSP 137 16.24 311.18 191.08 10/09/2021 11/19/2021 100.00% 10.75% 10.42% 5/20/2023 5/20/2023 M/s B R Goyal Infrastructure Ltd.
km 80.630 near Mandeu to km 96.870 near Jiri River
(Package-6)
Widening/Improvement to 2-lane with Paved
shoulder of Yaingangpokpi - Finch corner road
18 EPC NH(O)-NE 202 16.9 478.81 124.81 28/03/2020 7/1/2020 94.80% 37.81% 34.72% 6/30/2022 3/3/2023 M/s Varaha Infra Limited Land Acquisition & Forest Issues
section of NH-202 from Km 0.000 to Km 16.900 (part
of contract Package -I) on EPC
Widening/Improvement to 2-lane with Paved
shoulder of Yaingangpokpi - Finch corner road
19 EPC NH(O)-NE 202 14.07 0.00 135.63 28/03/2020 7/1/2020 100.00% 35.31% 21.76% 6/30/2022 6/5/2023 M/s Varaha Infra Limited Forest Issues
section of NH-202 from Km 16.900 to Km 30.970
(part of contract Package -II) on EPC basis

Construction of 2-laning with Hard shoulder road of


Ukhrul - Toloi - Tadubi section of NH-102A from
20 EPC NH(O)-TSP 102A 31.02 315.56 181.26 22/10/2021 to be given 0.00% 0.00% 0.00% - - A K Shivhare Infrastructure Pvt Ltd Land Acquisition
Design Chainage 50.850 km to 81.870 km (Package -
3)
Construction of 2-laning with Hard shoulder road of
Ukhrul - Toloi - Tadubi section of NH-102A from
21 EPC NH(O)-TSP 102A 23.96 310.76 150.14 27/08/2021 to be given 79.03% 0.00% 0.00% 1/22/2024 - A K Shivhare Infrastructure Pvt Ltd
Design Chainage 81.870 km to 105.825 km (Package
-4)
Widening to 2-lane with Hard shoulder of
22 EPC NH(O)-TSP Churachandpur to Tuivai Section from km0.00 to 102B 13.75 167.95 92.71 31/03/2020 7/1/2020 100.00% 84.71% 77.99% 6/30/2022 3/23/2023 Krishna Construction Co.
km13.747 (Pkg- I A)
Widening to 2-lane with Hard shoulder of
23 EPC NH(O)-TSP Churachandpur to Tuivai Section from km13.747 to 102B 19.09 241.52 139.80 31/03/2020 7/1/2020 100.00% 53.75% 46.50% 6/30/2022 11/22/2022 RSM Infra Projects
km32.835 (Pkg- I B)
Widening to 2-lane with Hard shoulder of
24 EPC NH(O)-TSP Churachandpur to Tuivai Section from km32.835 to 102B 15.76 232.99 139.19 31/03/2020 7/1/2020 100.00% 74.78% 70.04% 6/30/2022 6/5/2023 Bharat Vanijya Eastern Pvt. Ltd
km48.587 (Pkg- IIA)
Widening to 2-lane with Hard shoulder of
25 EPC NH(O)-TSP Churachandpur to Tuivai Section from Km 48.587 to 102B 21.88 365.53 206.41 30/06/2020 8/5/2020 100.00% 71.52% 56.11% 8/4/2022 6/2/2023 Bharat Vanijya Eastern Pvt. Ltd
Km 69.875 (Package-II B)
Widening to 2-lane with Hard shoulder of
26 EPC NH(O)-NE Churachandpur to Tuivai Section of NH-102B from 102B 51.89 673.27 404.48 14/07/2021 8/25/2021 100.00% 27.37% 22.33% 8/24/2023 8/24/2023 M/s M & S Co.
Design Chainage 69.875 Km to 121.769 Km (Pkg-3)

Widening to 2-lane with Hard shoulder of


27 EPC NH(O)-TSP Churachandpur to Tuivai Section from Km118.850 102B 11.15 204.12 114.68 31/03/2020 7/1/2020 100.00% 70.44% 64.94% 6/30/2022 6/2/2023 M/s GPT Infraprojects Ltd.
to km130.00 (Pkg- IVA)

Widening to 2-lane with Hard shoulder of


28 EPC NH(O)-TSP Churachandpur to Tuivai Section from Km130.00 to 102B 11.03 177.76 102.80 01/07/2020 8/5/2020 100.00% 72.70% 62.82% 8/4/2022 6/18/2023 M/s GPT Infraprojects Ltd.
km 141.029 (Pkg- IVB)

Improvement of existing road to 2 laning with Hard


Shoulders of Maram -Peren section (Package-1A, CSR Infratech India Pvt. Ltd.- Raam
29 EPC NH(O)-TSP 129A 22.34 226.32 151.15 05/02/2021 6/21/2021 82.23% 14.19% 7.87% 12/22/2022 6/30/2023 Land Acquisition
length- 22.340Km) from Design Chainage 0.000 km Infratech India Pvt. Ltd. (JV)
to 22.340 km on NH-129A

Improvement of existing road to 2 laning with Hard


Shoulders of Maram-Peren section (Package-1B, CSR Infratech India Pvt. Ltd.- Raam
30 EPC NH(O)-TSP 129A 17.66 188.36 128.55 05/02/2021 6/21/2021 100.00% 36.90% 33.64% 12/22/2022 12/22/2022 Land Acquisition
length- 17.660 km) from Design Chainage 22.340 km Infratech India Pvt. Ltd. (JV)
to 40.000 km
Improvement of existing road to 2 laning with Hard
Shoulders of Maram-Peren section (Package-2A, Heera Ram Godara - Dudi &
31 EPC NH(O)-TSP 129A 16.84 204.58 121.00 07/07/2021 9/15/2021 100.00% 52.04% 48.23% 3/18/2023 3/18/2023
length- 16.840 Km) from Design Chainage 40.000 Company (JV)
km to 56.840 km on NH-129A
Improvement of existing road to 2 laning with Hard
Shoulders of Maram-Peren section (Package-2B,
32 EPC NH(O)-TSP 129A 18.16 232.26 145.87 12/02/2021 6/21/2021 87.39% 22.75% 16.56% 12/22/2022 6/30/2023 Satya Builders Land Acquisition
length- 18.160 Km) from Design Chainage 56.840
km to km 75.000 on NH-129A
Improvement of existing road to 2 lanning with
New India Contractors & Developers
Hard Shoulders of Maram Peren section (Package-
33 EPC NH(O)-TSP 129A 34.494 467.41 269.42 27/08/2021 11/26/2021 95.68% 10.15% 7.32% 11/25/2023 11/25/2023 Pvt. Ltd. - Bharat Construction Co.
III, length - 34.494 km) from Design Chainage km
(JV)
75+000 to 109+494 km on NH-129A
Improvement/Upgradation of existing 2-lane to 4-
Lane Divided Highway from Taphou Kuki to Daili Lekcon Infrastructure Pvt. Ltd. -
34 EPC NH(O)-NE 39/ 02 12.44 379.39 212.54 31/08/2020 10/15/2020 45.86% 14.08% 10.39% 4/18/2022 2/20/2023 Land Acquisition
section of Imphal-Kohima Road (Design Ch.: km R.S.V. constructions Pvt. Ltd. (JV)
262.175 to 274.610) (Pkg-4A)
Improvement/Upgradation of existing 2-lane to 4-
Project has been Foreclosed due to
Lane Divided Highway from Daili to Kuraopokpi
35 EPC NH(O)-NE 39/ 02 12.39 268.98 - - - 0.00% - - - - Non-availability of land. Land Acquisition
section of Imphal-Kohima Road (Design Ch.: km
Project to be Re-awarded
274.610 to 287.00 ) (Pkg-4B)
Improvement/Upgradation of existing 2-lane to 4-
Project has been Foreclosed due to
Lane Divided Highway from Kuraopokpi to Sekmai
36 EPC NH(O)-NE 39/ 02 10.7 228.97 - - - 0.00% - - - - Non-availability of land. Land Acquisition
section of Imphal-Kohima Road (Design Ch.: km
Project to be Re-awarded
287.00 to 297.700) (Pkg-5A)
Improvement/ Up-gradation of existing 2-Lane road
to 4-Lane Divided Highway from Sekmai to
37 EPC NH(O)-NE Nilkhuthi section of Imphal-Kohima Road (Design 39/ 02 11.029 211.70 126.58 27/03/2021 7/20/2021 45.34% 1.40% 0.00% 1/21/2023 1/21/2023 NSC Projects Pvt. Ltd
Chainage from Km 297+700 to Km 308+729) of NH-
39 (Pkg-5B)

EAP 4- Laning of Imphal – Moreh Section of NH 39 from


38 EPC 39/ 02 20 761.54 397.00 05/09/2019 6/1/2020 98.16% 76.71% 67.73% 5/31/2023 3/31/2023 M/s GR Infra Projects ltd Land Acquisition
(ADB) Km 330.000 to Km 350.000 (Contract Package I)

Widening and Improvement to 2-Lane with paved


39 EPC NH(O)-NE shoulders of Imphal-Moreh section of NH-39 from 39/ 02 10.32 259.31 150.11 22/03/2021 6/21/2021 100.00% 66.05% 56.29% 12/20/2022 - Dwarakamai Constructions Pvt. Ltd.
Km 395.680 to Km 406.000 (Package-III)
Widening and Improvement to 2-Lane with paved
40 EPC NH(O)-NE shoulders of Imphal-Moreh section of NH-39 from 39/ 02 19.411 277.99 140.00 22/03/2021 7/20/2021 100% 34.65% 31.80% 12/31/2021 1/19/2023 M/s SKV & SPG Pvt. Ltd.
km 406.000 to Km 425.411 (Package-IV)
Construction of Moreh Bypass to 2-lane with Paved
shoulder from km421.950 to 425.411 of NH-39
41 EPC NH(O)-NE 39/ 02 2.52 68.14 21.51 27/03/2020 7/1/2020 100% 39.15% 30.81% 12/31/2021 10/10/2022 M/s L.K. & Sons
(Length= 2.52 km) near Indo-Myanmar border on
EPC
Construction of 2 laning with hard shoulder road of
Akash bridge - Jessami section of NH-202 in M/s HVS Construction Materials Pvt.
42 EPC NH(O)-NE 202 14.72 152.11 73.48 21/06/2022 to be given 0.00% 0.00% 0.00% 1/19/2023 -
Nagaland- Manipur from design Ch. 325.440 km to Ltd.
340.160 km (Pkg-II)
Total 820.28 12875.02 7041.28
Status as on 31.08.2022
Remarks/ Issues
Right of Target date
Awarded (Land Aquisition
NHDP NH No. Sanctioned Date of way Cumulative Cumulative of Likely date
SL. Length Cost Name of the Issues/ Forest
Mode Phase/ Name of Project (Old/ Cost/TPC Date of Award Start/Appointe (ROW) Physical Financial completion of
No. (Km) Rs. in Contractor Issues/ Utility
Scheme New) Rs. in crore d Date Available progress % progress % as per completion
crore Shifting/ Contractor
% contract
Issue)
Meghalaya
2- laning of Ranikor-Nonghyllam- Maheshkola- M/s Dhar Construction
1 EPC SARDP Baghmara (from design Ch. 0.000 to Ch. 129.385) SH 04 33.25 306.28 216.33 09/03/2019 9/30/2019 90.04% 53.21% 47.80% 3/30/2022 10/7/2022 Company & Chanchal Paul
Package-I: Existing Ch. 0.000 to Ch.31.700 (Pkg-1) (JV)
lmprovement/widening to 2-laning with earthen
shoulder of Nongjri (Design Ch. 30.00km) to
Maheshkola (Design Ch. 55.525km )[R-M-B M/s Dhar Construction
2 EPC NH(O)-NE SH 04 25.525 283.5 140.928 07/03/2022 to be given 76.49% 0.00% 0.00% - - Forest Issues
Package 2 on SH-4 section of Ranikor- Company
Maheshkhola- Baghmara Project in the state of
Meghalaya under NH (O)-NE (Pkg-2)
lmprovement/ widening to 2-laning with earthen
shoulder from Maheshkola to kanai existing
3 EPC SARDP chainage from Ch. 59.270 to Ch. 85.970 (Design Ch. SH 04 25 260.21 150.2 27/03/2021 6/28/2021 82.86% 28.45% 27.65% 12/28/2022 5/31/2023 M/s DMR Builders Pvt. Ltd. Land Acquisition
55.525 to Ch. 79.680) on SH-4 Ranikor-Baghmara
Project (Package-3)
Improvement/widening to 2-lane with Earthen
shoulder of Ranikor-Maheshkhola- Baghmara road
section from Kanai to Rongara, existing Ch. From
4 EPC NH(O)-NE SH 04 14.763 157.86 82.798 30/09/2020 10/24/2020 100.00% 55.84% 50.82% 4/24/2022 4/30/2023 M/s Narendra Sharma
Km 85.970 to Km 102.345 (Design Ch. From Km
81.100 to Km 96.000) Design length-14.763 km on
EPC (Pkg-4)
Improvement/widening to 2-lane with Earthen
shoulder of Ranikor-Maheshkhola- Baghmara road
section from Rongara to Panda, existing Ch. From
5 EPC NH(O)-NE SH 04 16.3 146.88 74.409 30/09/2020 10/24/2020 100.00% 60.90% 57.37% 4/24/2022 4/30/2023 M/s Narendra Sharma
Km 102.345 to Km 119.810 (design Ch. From Km
96.00 to Km 112.300) design length-16.30 km on
EPC (Pkg-5)
lmprovement/ widening to 2-laning with earthen
shoulder of Panda (Design Ch. 112.300 km) to
Baghmara (Design Ch. 129.385 km )[R-M-B Nidhi Creative
6 EPC NH(O)-NE SH 04 17.085 144.99 82.336 27/01/2022 to be given 100.00% 0.00% 0.00% - - Forest Issues
Package-Vl] on SH-4 section of Ranikor- Infrastructure Pvt. Ltd.
Maheshkhola- Baghmara Project in the state of
Meghalaya under NH(O)-NE (Pkg-6)
Rehabititation and up gradation of Nongstoin-
Rambrai-Kyrshai road up to Meghalaya-Assam
M/s SPICA Projects &
7 EPC NH(O)-NE border from Km 0.335 to km 34.039 to 2-Lane - 33.7 359.86 155.543288 27/01/2022 27.05.2022 94.07% 5.00% 0.00% 5/28/2024 -
Infrastructures Pvt. Ltd.
under NH(o) - NE in the State of Meghalaya
(Package-l)
Widening to 2- lane with Geometric improvement
M/s Manaranjan Brahma
of Tura-Dalu Road from Km 85.000 to Km 95.000 &
8 EPC EAP (JICA) 51 51.536 553.41 358.65 28/03/2018 9/15/2018 92.59% 46.28% 45.29% 9/14/2021 23.04.2023 (MB Constructions) Land Acquisition
Km 101.000 to km 145.000 to 2-lanes with paved
shoulder of Tura- Dalu section

Improvement/Widening to 2-L with Paved Shoulder


from (design Km 0.00 to Km 10.670) / 4-Laning from
9 EPC EAP (JICA) 40 11.6 351.12 91.26 02/11/2020 12/14/2020 28.62% 6.66% 4.94% 12/14/2022 - 0
(design Km 0.00 to Km 0.930) between Shillong-
Dawki (Pkg-1)

Improvement/Widening to 2-Lane with Paved


M/s ARSS Infrastructure
10 EPC EAP (JICA) Shoulder from (design Km 10.670 to Km 37.550) 40 26.55 525.68 210 24/11/2020 12/26/2020 85.66% 30.46% 25.51% 12/26/2022 7/15/2023 Land Acquisition
Pvt Ltd
between Shillong-Dawki (Pkg-2)

Improvement/Widening to 2-Lane with Paved


11 EPC EAP (JICA) Shoulder from (design Km 45.760 to Km 63.530) 40 17.77 445.51 88.2 02/11/2020 12/14/2020 19.20% 13.22% 12/14/2022 - M/s SS Infrazone Pvt. Ltd. Land Acquisition
84.29%
between Shillong-Dawki (Pkg-4)

Improvement/Widening to 2-Lane with Paved


M/s Niraj Cement
12 EPC EAP (JICA) Shoulder / 4-Laning from (design Km 63.530 to Km 40 7.99 284.21 141.14 23/11/2020 12/28/2020 63.27% 14.00% 5.18% 12/28/2022 - Land Acquisition
Structurals Limited.
71.520) between Shillong-Dawki (Pkg-5)

Total 281.07 3819.51 1791.79


Status as on 31.08.2022

NH Awarded Right of way Cumulative Cumulative Remarks/ Issues


NHDP Sanctioned Date of Target date of Likely date
SL. No. Length Cost Date of (ROW) Physical Financial (Land Aquisition Issues/
Mode Phase/ Name of Project Cost/TPC Start/Appoi completion as of Name of the Contractor
No. (Old/ (Km) Rs. in Award Available progress progress Forest Issues/ Utility
Scheme Rs. in crore nted Date per contract completion
New) crore % % % Shifting/ Contractor Issue)

Mizoram
Rehabilitation and Up-gradation to 2 lane with
paved shoulders of Economic Corridor of NH-
1 EC NH(O)-NE 6 13.51 206.9 134.91 3/31/2020 7/1/2020 94.00% 55.26% 54.89% 6/30/2022 2/7/2023 M/s GVV Construction Pvt. Ltd. Forest Issues
6 from Design Chainage Km 00+000 to Km
13+510 (Selling-Dulte - I)
Rehabilitation and Up-gradation to 2-lane with
paved shoulders of Economic Corridor of NH-
2 EC NH(O)-NE 6 13.89 216.49 138.75 3/31/2020 7/1/2020 100.00% 90.00% 88.56% 6/30/2022 11/20/2022 M/s NG Projects Ltd.
06 from Design Chainage Km 13+510 to km
27+400 (Selling-Dulte - II)
Rehabilitation and Up-gradation to 2- lane with
paved shoulders of Economic Corridor of NH-
3 EC NH(O)-NE 6 17.64 292.23 197.38 3/31/2020 7/1/2020 64.51% 48.47% 46.19% 6/30/2022 4/15/2023 M/s NG Projects Ltd.
6 from Design Chainage km 27+400 to km
45+040 (Selling-Dulte - III)
Rehabilitation and Up-gradation to 2-lane with
pave shoulders of Economic Corridor of NH-6
4 EC NH(O)-NE 6 17.16 281.77 185.49 3/31/2020 7/1/2020 95.00% 83.05% 81.24% 6/30/2022 2/3/2023 M/s Anusha Projects Pvt. Ltd.
from Design Chainage Km 45+040 to Km
62+200 (Selling-Dulte - IV)
Up-gradation to 2 lane with paved shoulders
of Dulte-Kwalkulh road
5 IC NH(O)-NE 6 17.95 374.39 212.365 3/31/2021 6/25/2021 81.31% 60.00% 58.95% 12/25/2022 12/25/2022 Dhariwal Buildtech Ltd.
(International Corridor) of NH-6 from Design
Chainage Km 54.400 to Km 72.350 (Package-I)
Rehabilitation and Up-gradation to 2 lane with
paved shoulders of
6 IC NH(O)-NE Kwalkuth-Khawzawl road (lnternational 6 12.45 233.25 121.031 3/31/2021 6/25/2021 100.00% 42.00% 40.73% 12/25/2022 12/25/2022 Dwarakamai Constructions Pvt. Ltd.
Corridor) of NH-6 from Design Chainage Km
72.350 to Km 84.800 (Package-ll)
Up-gradation to 2 lane with paved shoulders
RKC Infrabuilt Pvt. Ltd. - Shri Balaji
of Khawzawl-Champhai road (lnternational
7 IC NH(O)-NE 6 26.78 674.71 370.432 3/31/2021 6/25/2021 100.00% 44.00% 42.30% 6/25/2023 6/25/2023 Construction Company [RKCIPL-
Corridor) of NH-6 from Design Chainage Km
SBCC] (JV)
84.800 to Km 111.580 (Package-lll)

4-Laning of Vairengte - Chhimluang section


(Package-3) of NH-306
from Existing Chainage km 43+000 to Km
Dhatarwal Construction Company
8 EC NH(O)-NE 59+700 (Design Chainage km 46+000 to km 306/ 6 14.85 491.39 244.6895 1/27/2022 to be given 0.00% 0.00% 0.00% - - Land Aquisition
Pvt. Ltd.
60+850) on Silchar - Vairengte- Sairang road
in the State of Mizoram under Bharatmala
Pariyojna under NH(O)-NE

4-Laning of chhimluang-Kolasib from section


(pkg-4) of NH-306 & NH-6 existing chainage
km 59+700 to km 86+000 (design chainage km
9 EC NH(O)-NE 61+000 to km 77+500) on Silchar-vairengte- 306/ 6 16.5 561.91 276.728 1/28/2022 to be given 0.00% 0.00% 0.00% - - Shiwalay Infra Projects Pvt. Ltd. Land Aquisition
sairang road in the state of Mizoram under
Bharatmala Pariyojna on EPC mode
Vairengte - Sairang Pkg-4

4-Laning of Kolasib - Sethawn section


(Package-5) of NH-6 from Existing Chainage
km 86+000 to km 107+850 (Design Chainage Rajendra Singh Kiledar
10 EC NH(O)-NE km 77+500 to km 95+500) on silchar - 306/ 6 18 720.4 323.6545 3/25/2022 to be given 0.00% 0.00% 0.00% - - Construction Company (RSK) - Land Aquisition
vairengte - sairang road under Bharatmala MLN (JV)
Pariyojna on EPC mode under NH(O)-NE
Vairengte - Sairang Pkg-5
4-Laning of Sethawn - N. Kawnpui section
(Package-6) of NH-6 from Existing Chainage
km 107+850 to km 126+315 (Design Chainage
km 95+500 to km 111+850) on Silchar-
11 EC NH(O)-NE 306/ 6 16.35 595.65 268.152 3/28/2022 to be given 0.00% 0.00% 0.00% - - Anusha Projects Pvt. Ltd. Land Aquisition
Vairengte-Sairang road in the State of
Mizoram under Bharatmala Pariyojna on EPC
mode
Vairengte - Sairang Pkg-6
Construction of 2-laning with hard shoulder
configuration of Lunglei to Chhumkhum from SRK Constructions and Projects
12 IC NH(O)-NE 302 37.42 698.45 404.592 3/30/2021 6/30/2021 70.92% 9.70% 9.27% 12/30/2022 12/30/2022
Design Chainage Km 0.000 to Km 37.420 of Pvt. Ltd.
NH-302 [Pkg-A]
Construction of 2-laning with hard shoulder
configuration of Chhumkhum to Tlabung from SRK Constructions and Projects
13 IC NH(O)-NE 302 37.53 740.58 435.392 3/31/2021 7/10/2021 74.82% 9.00% 7.82% 1/9/2023 1/9/2023
Design Chainage Km 37.420 to Km 74.950 of Pvt. Ltd.
NH-302 [Pkg-B]
Widening and up-gradation to 2-lane with
paved shoulder configuration and geometric
14 ICR EAP (JICA) 54 56.96 1099.947 699.3 11/25/2019 1/24/2020 99.14% 39.93% 35.60% 7/25/2023 7/25/2023 M/s Gawar-SCCPL (JV) Land Aquisition & Forest Issues
improvements from km 8.00 to km 65.00
(Package-1) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with


M/s Gammon Engineers and
paved shoulder configuration and geometric
15 ICR EAP (JICA) 54 53.263 1027.833 512 3/8/2019 12/23/2019 100.00% 44.00% 42.11% 6/23/2023 6/23/2023 Contractors Private Limited Land Aquisition & Forest Issues
improvements from km 65.00 to km 125.00
(Package-2) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with M/s Bhartia Infra Projects Ltd
paved shoulder configuration and geometric (BIPL) -ABCI Infrastructures Private
16 ICR EAP (JICA) 54 41 867.09 450.45 2/13/2019 10/25/2019 100.00% 49.29% 47.37% 4/25/2023 2/9/2024 Land Aquisition & Forest Issues
improvements from km 125.00 to km 166.00 Limited (JV)
(Package-3) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with


M/s ABCI Infrastructures Private
paved shoulder configuration and geometric
17 ICR EAP (JICA) 54 42.53 899.45 440.5 2/13/2019 10/25/2019 100.00% 53.06% 50.03% 4/25/2023 4/25/2023 Limited Land Aquisition & Forest Issues
improvements from km 166.00 to km 208.00
(Package-4) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with


M/s ABCI Infrastructures Private
paved shoulder configuration and geometric
18 ICR EAP (JICA) 54 34.58 752.89 395.37 2/13/2019 10/25/2019 100.00% 53.08% 47.94% 4/25/2023 4/25/2023 Limited Land Aquisition & Forest Issues
improvements from km 208.00 to km 250.00
(Package-5) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with M/s ABCI Infrastructures Private


paved shoulder configuration and geometric Limited-Bhartia Infra Projects Ltd
19 ICR EAP (JICA) 54 45.46 811.536 546.05 3/8/2019 12/16/2019 94.97% 41.07% 39.97% 6/16/2023 6/16/2023 Land Aquisition & Forest Issues
improvements from km 250.00 to km 298.00 (BIPL) (JV)
(Package-6) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with


paved shoulder configuration and geometric Power Mech Projects Ltd.- SRC
20 EAP EAP (JICA) 54 40.344 719.574 446.4 9/21/2020 10/1/2020 96.67% 33.34% 29.81% 4/1/2024 4/1/2024 Land Aquisition & Forest Issues
improvements from km 298.00 to km 339.00 Infra Developers Pvt. Ltd. (JV)
(Package-7) on Aizawl-Tuipang section

Widening and up-gradation to 2-lane with M/s Bhartia Infra Projects Ltd
paved shoulder configuration and geometric (BIPL) - ABCI Infrastructures
21 EAP EAP (JICA) 54 39.94 713.439 443.94 2/13/2019 3/16/2020 94.60% 39.50% 37.63% 9/15/2023 9/15/2023 Land Aquisition & Forest Issues
improvements from km 339.00 to km 380.00 Private Limited (JV)
(Package-8) on Aizawl-Tuipang section
Construction of 2-L Chhiathlang -Serchhip
Kram Infracon Pvt. Ltd.(KIPL) -
22 ICR EAP (JICA) Bypass (Pkg-1) on Aizawl-Tuipang section of 54 14.4 275.02 153.1 9/30/2020 10/15/2020 98.90% 35.00% 32.92% 10/15/2022 10/15/2022
VKMCPL (JV)
NH-54
Construction of 2-L Hnathial Bypass (Pkg-2)
23 ICR EAP (JICA) 54 7 113.58 60.3 7/31/2020 10/1/2020 100.00% 22.37% 18.57% 4/3/2022 6/29/2023 Mathiyan Construction Pvt. Ltd.
on Aizawl-Tuipang section of NH-54

Construction of 2-L Lawngtlai Bypass (Pkg-3)


24 ICR EAP (JICA) 54 2.273 58.85 31.14 10/29/2020 11/20/2020 93.00% 31.77% 30.28% 5/23/2022 11/19/2022 David Zohmachhuana
on Aizawl-Tuipang section of NH-54
Up-gradation to 2-lane with paved shoulders of
Khawkawn (from Bridge across River Tuivai) - Ngopa
section of NH-102B of Aizawl - Imphal Economic
25 EC NH(O)-NE Corridor from Existing Chainage km 0.000 to km
102B 31.28 492.94 265.6 9/2/2021 11/26/2021 27.17% 7.50% 7.21% 5/19/2023 5/19/2023 B R Goyal Infrastructure Ltd. Land Aquisition
32.796 [Design Chainage km 0.000 to km 31.280]
(Package-1)
Up-gradation to 2-lane with paved shoulders of Ngopa
- Pawlrang section of NH 102B of Aizawl - Imphal
26 EC NH(O)-NE Economic Corridor from Existing Chainage km 32.796 102B 36.89 523.78 271.74 1/27/2022 to be given 0.00% 0.00% 0.00% - - Shri Swami Samarth Engineers Ltd. Land Aquisition
to km 72.030 [Design Chainage km 31.280 to km
68.170] (Package-2) Keifang- Tuivai Pkg-2

Up-gradation to 2 lane with paved shoutders of


Pawlrang - Rulchawm section- of NH-102B of Aizawl -
Imphal Economic Corridor from Existing Chainage km
72.030 to km 104.129 including 2.459 km re-alignment
27 EC NH(O)-NE section from Tuivai River to Rulchawm connecting km
102B 30.41 500.88 276 3/25/2022 to be given 0.00% 0.00% 0.00% - - Dhariwal Buildtech Ltd Land Aquisition
48.150 of NH-6 [Design Chainage km 68.170 to km
98.579] (Package-lll)
under Bharatmata Pariyojna (Keifang- Tuivai Pkg-3)

Total 736.36 14944.93 8305.46


Status as on 31.08.2022
Remarks/ Issues
Awarded Right of way (Land Aquisition
NHDP NH No. Sanctioned Date of Cumulative Cumulative Target date of
SL. Length Cost Date of (ROW) Likely date of Name of the Issues/ Forest
Mode Phase/ Name of Project (Old/ Cost/TPC Start/Appointe Physical Financial completion as
No. (Km) Rs. in Award Available completion Contractor Issues/ Utility
Scheme New) Rs. in crore d Date progress % progress % per contract Shifting/ Contractor
crore %
Issue)
Nagaland
Construction of 2-Lane with hard shoulders Kantilal Khimjibhi Bhalala (KKB)
1 EPC SARDP - 20 237.72 136.73 3/22/2018 11/8/2018 100.00% 100.00% 100.00% 11/8/2021 Completed
of Pfutsero- Phek (PP) road from Km 0-20 Project Pvt. Ltd.

Construction of 2-Lane with hard shoulders M/s Madhucon Projects Limited


2 EPC SARDP - 20 251.97 160.1 3/22/2018 11/15/2018 100.00% 100.00% 100.00% 11/14/2021 Completed
of Pfutsero- Phek (PP) road Km 20-40 Ph.

Construction of 2-Lane with hard shoulders M/s Madhucon Projects Limited


3 EPC SARDP - 22.56 282.98 192.6 3/22/2018 11/15/2018 100.00% 100.00% 100.00% 11/14/2021 Completed
of Pfutsero- Phek (PP) road Km 40-62.558 Ph.

Construction of 2-Lane with Hard shoulders


M/s Shivalaya Construction Co
4 EPC SARDP of Chakabama-Zunheboto (C-Z) road Km 0- - 25 339.57 233.35 3/23/2018 7/3/2019 99.52% 99.79% 91.01% 7/2/2022 Physically Completed
Pvt
25 PKG-I
Construction of 2-Lane with hard shoulders
5 EPC SARDP of Merangkong-Tamlu-Mon (MTM) Km 0-20 - - 20 215.12 143.6544 3/23/2018 11/18/2018 100.00% 100.00% 98.76% 11/17/2021 Completed M/s Keystone Infra Pvt. Ltd.
PKG-I
4 Laning of Dimapur Kohima Road from
Design Km 123.840 to Km 138.775 in the
6 EPC SARDP 39/29 14.935 489.01 387.00 5/12/2016 9/16/2016 100.00% 96.71% 94.14% 9/15/2019 10/30/2022 M/s Ramky-ECI (JV) Phone
state of Nagaland under SARDP-NE on EPC
basis (Package - I).
4 Laning of Dimapur Kohima Road from
Design Km 138.775 to Km 152.490 in the
7 EPC SARDP 39/29 13.715 519.72 339.55 5/12/2016 8/3/2016 100.00% 97.17% 94.80% 8/2/2019 10/30/2022 M/s Ramky-ECI (JV) Phone
state of Nagaland under SARDP-NE on EPC
basis (Package - II).
4 Laning of Balance work of Dimapur
Kohima Road from Design Km 152.490 to
8 EPC SARDP Km 166.700 (Existing Km 156.000 to Km 39/29 14.21 562.98 111.197 7/16/2021 9/1/2021 100.00% 28.06% 26.45% 8/31/2022 1/31/2023 OASIS Technocons Ltd.
172.900), in the state of Nagaland under
SARDP-NE (Package - III).
Construction of 4/6 Laning from Km
132.375 to Km 153.058 (Total New
Connecting
Alignment length of 20.683 Km ) of Daboka
9 EPC SARDP NH-39 & NH- 20.68 819.38 387.00 4/12/2017 9/5/2017 100.00% 96.67% 94.56% 9/4/2020 12/15/2022 M/s Simplex Infrastructure Limited
Dimapur Section (Dimapur Bypass) of NH-
36
36 & 39 in the State of Nagaland on EPC
basis.
Construction of Dimapur Bypass (Assam
Portion) of 4/6 Lane pavement on EPC
Connecting
basis from existing Km 159.400 of NH-36 to M/s Gawar - Singh (JV)
10 EPC SARDP NH-39 & NH- 14.33 583.31 336.49 3/19/2018 11/26/2019 100.00% 60.07% 59.33% 11/25/2022 6/6/2023
existing Km 102.500 of NH-39 and upto end consultants Pvt Ltd
36
point of Assam portion [Design Km 118.050
to design Km 132.375] (length 14.325 Km)
Construction of 2-Lane with Hard shoulders
M/s Shivalaya Construction Co
11 EPC SARDP of Chakabama-Zunheboto (C-Z) road Km25- 702A 25 239.3 174.7 3/23/2018 5/20/2019 98.24% 94.67% 78.85% 5/19/2022 31.12.2022 Land Acquisition
Pvt
50 PKG-II
Construction of 2-Lane with Hard shoulders
12 EPC SARDP of Chakabama-Zunheboto (C-Z) road on 702A 25 285.68 194.1 3/23/2018 9/5/2019 97.28% 64.68% 61.42% 9/3/2022 3/31/2023 M/s Madhucon Projects Limited Land Acquisition
EPC [Design Km 50 -75] PKG-III
Construction of 2-Lane with hard shoulders
M/s Madhucon Projects Limited
13 EPC SARDP of Chakabama-Zunheboto (C-Z) road Km 75- 702A 20 315.03 213.3 3/28/2018 12/13/2018 98.11% 67.75% 66.16% 12/12/2021 31.12.2022 Land Acquisition
Ph. No. 01242359234
95 PKG-IV
Construction of 2-Lane with Hard shoulders
14 EPC SARDP of Chakabama-Zunheboto (C-Z) road Km 702A 20.53 255.58 188.1 3/28/2018 12/20/2018 100.00% 76.51% 72.26% 12/19/2021 12/31/2022 M/s Madhucon Projects Limited Land Acquisition
95-115.534 PKG-V
Construction of 2-Lane with hard shoulders
15 EPC SARDP of Merangkong-Tamlu-Mon (MTM) Road Km - 20 215.79 161.99 3/28/2018 12/3/2018 100.00% 54.81% 53.32% 12/1/2021 12/31/2023 M/s Manaranjan Brahma
20-40 PKG-II
Construction of 2-Lane with hard shoulders
M/s SSR Crest Engineers and
16 EPC SARDP of Merangkong-Tamlu-Mon (MTM) Road Km - 19 272.89 187 3/28/2018 10/24/2019 100.00% 59.94% 55.42% 10/22/2022 6/8/2023 Land Acquisition
Constructions Limited
40-59 PKG-III

Construction of 2-Lane with hard shoulders


17 EPC SARDP of Merangkong-Tamlu-Mon (MTM) Road Km - 23.035 323.98 103.8 9/9/2021 12/9/2021 100.00% 4.37% 4.08% 6/10/2023 6/10/2023 M D Enterprise Land Acquisition
63.800- 86.835 PKG-IV (Balance work)
Construction of 2-lane with hard shoulders
of Merangkong-Tamlu-Mon road (Wakching
Twon portion) on EPC basis from existing
18 EPC NH(O)-TSP Chainage Km 59+000 to Km 73+640 - 13.45 161.73 79 7/16/2021 9/1/2021 100.00% 14.93% 14.40% 3/3/2023 3/3/2023 C Gopal Reddy & Company Land Acquisition
[Design Km. 59+000 to Km, 72+450]
(Design length - 13.450 Km) (package-V)

Construction of 2-lane with hard shoulder


of Changtongya - Longleng Road on EPC
19 EPC NH(O)-NE basis from existing Km0.00 to Km16.592 702 18.779 278.95 177.1 3/2/2020 7/1/2020 93.45% 75.48% 72.40% 6/30/2022 10/30/2022 M/s RKIPL-NSC(JV) Land Acquisition
[Design Km 0.00 to Km.18.779 ] (Design
Length-18.779km) (Pkg-1)

Construction of 2-lane with hard shoulder


of Changtongya - Longleng Road on EPC
Ksheeraabd Construction Pvt.
20 EPC NH(O)-NE basis from existing Km16.592 to Km29.530 702 14.649 206.53 128 3/11/2020 7/1/2020 93.51% 75.99% 74.96% 6/30/2022 12/31/2022 Land Acquisition
Ltd. (KCPL)
[Design Km.18.779 to Km 33.428] (Design
Length-14.649 km) (Pkg-2) 2019-20

Construction of 2-Lane with paved


shoulder of Kohima-Bypass Road
connecting NH-39(New NH-02), NH-150(New
21 EPC NH(O)-NE NH 29/ NH-02 10.5 232.29 - - - - - - - - To be Re-awarded Land Acquisition
NH-02), NH-61(New NH-29) and NH-39(New
NH-02) from design Km 0.00 to Km 10.500
[Design Length- 10.500 km] (Pkg.- 1)

Construction of 2-Lane with paved


shoulder of Kohima-Bypass Road
connecting NH-39(New NH-02), NH-150(New
22 EPC NH(O)-NE NH-02), NH-61(New NH-29) and NH-39(New NH 29/ NH-02 10.5 277.44 177 9/25/2020 10/15/2020 97.80% 29.40% 28.39% 10/15/2022 12/31/2023 Ms Bharat Construction Pvt. Ltd Land Acquisition
NH-02) from design Km10.500 to 21.00Km
[Design Length- 10.500 km] (Pkg.- 2) incl.
(TUNNEL of 0.500 Km)

Construction of 2-lane with Paved shoulder


39/02,
of Kohima-Bypass Road connecting NH-2,
23 EPC NH(O)-NE 150/02, 11 159.85 - - - - 0.00% 0.00% - - To be Re-awarded Land Acquisition
29 from Design km21.0 to km32.0 [Design
61/29, 39/02
length=11.0 km] (Pkg.- 3)

Construction of 2-lane with Paved shoulder


39/02,
of Kohima-Bypass Road connecting NH-2,
24 EPC NH(O)-NE 150/02, 11.45 202.36 118.56 8/14/2020 10/15/2020 72.54% 13.29% 13.00% 4/17/2022 6/30/2023 M/s Pele Khezhie Land Acquisition
29 from Dsign km32.0 to km43.454 [Design
61/29, 39/02
length=11.454] (Pkg.- 4)

Construction of 2- lane with hard shoulder


of Kohima-Jessami Road on NH-29 (Old NH-
150) from existing Km 7.880 (near chedama
25 EPC NH(O)-TSP Junction) to existing km 30.474 (Near 150 / 29 21.72 320.97 193.79 3/17/2020 7/1/2020 92.13% 55.14% 48.53% 6/30/2022 3/31/2023 M/s RKIPL-NSC(JV) Land Acquisition
Chakahabama) (Design km 7.88 to km
29.60) (Design length - 21.72 km) on EPC
Mode (Package -I)

Construction of 2-lane with hard shoulder


of Kohima - Jessami road on NH-29 (Old NH-
150) from existing Km 30.474 (Near
Kidwema road Chakahabama) to existing Ksheeraabd Construction Pvt.
26 EPC NH(O)-TSP 150 / 29 21.9 355.79 202 3/18/2020 7/1/2020 95.57% 50.75% 47.72% 6/30/2022 3/31/2023 Land Acquisition
Km 53.220 (Near Kikruma Village) (Design Ltd. (KCPL)
Km 29.60 to Km 51.50) (Design length-21.90
Km) on EPC mode (Package II) under NH(O)
2019-20

Construction of 2-lane with hard shoulder


of Kohima - Jessami road on NH-29 (Old NH-
150) from existing Km53.220 (Near Kikruma
27 EPC NH(O)-TSP Village) to existing Km 76.320 (Near 150 / 29 22.7 361.53 206.26 3/23/2020 7/1/2020 93.39% 34.30% 31.49% 6/30/2022 6/30/2023 M/s SIPL - RMN (JV) Land Acquisition
Mesulumi Village) (Design Km51.50 to
Km74.20) (Design length-22.70 Km) on EPC
mode (Package III) under NH(O) 2019-20
Construction of 2-lane with hard shoulder
of Kohima - Jessami road on NH 29 (old NH
150) from existing km 76.320 (near
28 EPC NH(O)-TSP 150 / 29 21.5 330.78 205.26 3/30/2020 7/1/2020 100.00% 53.00% 48.03% 12/31/2021 3/31/2023 M/s Keystone Infra Pvt. Ltd. Land Acquisition
Mesulumi Vill.) to existing Km98.380 (near
Chizami Vill.) [Design Length= 21.50 km] on
EPC (Package IV)
Construction of 2-lane with hard shoulder
of Kohima - Jessami road on NH 29 (old NH
150) from existing km 98.380 (near Chizami
29 EPC NH(O)-TSP vill.) to km120.367 (Nagaland/Manipur 150 / 29 21.5 330.8 214.37 4/24/2020 7/1/2020 100.00% 35.14% 29.51% 12/31/2021 6/30/2023 M/s Stroyproekt LLC - OIA (JV) Land Acquisition
Border) [Design km 95.700 to design km
117.200] [Design Length= 21.500 km] on
EPC (Package V)
Upgradation of existing road to 2-lane with
paved shoulder from Kohima to Mao from
30 EPC NH(O)-TSP 39/ 02 26.249 315.63 167.23 9/30/2020 10/20/2020 - 13.25% 11.29% 4/22/2022 3/2/2023 Fortune Group
km 185.540 to km 211.709 under
Bharatmala- NH(O)-TSP
Construction of 2-lane with hard shoulder
of Peren-Dimapur section on NH129A from M/s Mayasheel Construction -
31 EPC NH(O)-TSP 129A 17.281 257.15 139.88 9/10/2020 10/20/2020 85.07% 64.45% 60.45% 4/22/2022 3/31/2023 Land Acquisition
design Km109.494 to Km126.775 JPS Projects Pvt. Ltd. (JV)
(Length=17.281) (Pkg-1)
Construction of 2-lane with hard shoulder
of Peren-Dimapur section on NH129A from
32 EPC NH(O)-TSP 129A 19.433 258.52 117.5 7/19/2021 8/25/2021 98.45% 45.95% 45.06% 2/25/2023 2/25/2023 C Gopal Reddy & Company Land Acquisition
design Km 126.775 to Km 146.208 under
NH(O)-TSP (Pkg-2)
Construction of 2 lane with Hard shoulder
from Design Chainage Km 283.000 to Km Kantilal Khimjibhi Bhalala (KKB)
33 EPC NH(O)-NE 325.440 (5- legged junction at Old 202 42.44 605.36 275 3/30/2022 to be given 100.00% 4.67% 2.88% 12/20/2024 12/20/2024 Projects Pvt. Ltd. - Y. N. Dhanani
Akhegwo) to (Akash Bridge) of Akegwo- (JV)
Jessami section of NH-202 (Package-I)

Construction of 2 laning with Hard shoulder


of Peren-Dimapur section on NH 129A from
34 EPC NH(O)-TSP 129A 17.384 177.77 89.54 2/5/2021 to be given - 0.00% 0.00% - - Fortune Group Land Acquisition
Design Km 146.208 to Km 163.592 (Length-
17.384 km) under NH(O)-TSP (Pkg - 3)

Construction of 2 Laning with Hard


Shoulder of Peren - Dimapur section on NH
35 EPC NH(O)-TSP - 129A from Design Km 163.592 to Km 129A 10.258 116.54 55.93 3/16/2021 to be given - 0.00% 0.00% - - Multi Builders Land Acquisition
173.850 (Length - 10.258 km) (Pkg - 4)
under NH (0) - TSP
Construction of 2 laning with Hard shoulder
of Peren-Dimapur section on NH 129A from
36 EPC NH(O)-TSP Design Km 173.850 to Km 190.850 (Length - 129A 17 207.33 97.01 2/4/2021 to be given - 0.00% 0.00% - - Multi Builders Land Acquisition
17.000 Km) in the state of Nagaland on EPC
Mode (Package-5) under NH(O)-TSP

Total 687.69 11367.33 6294.07


Status as on 31.08.2022
Remarks/ Issues
Right of way Cumulative Cumulative
NHDP NH No. Sanctioned Awarded Date of Target date of (Land Aquisition Issues/
SL. Length (ROW) Physical Financial Likely date of
Mode Phase/ Name of Project (Old/ Cost/TPC Cost Date of Award Start/Appointe completion as Name of the Contractor Forest Issues/ Utility
No. (Km) Available progress progress completion
Scheme New) Rs. in crore Rs. in crore d Date per contract Shifting/ Contractor
% % %
Issue)
Sikkim
Special Repair of NH-10 as Improvement & Rehabilitation
Item
1 NH(O) of existing Indira Bye Pass road form Km 0.000 to km NH-10 10.12 33.24 17.57 3/28/2018 5/4/2018 100.00% 100.00% 100.00% 8/15/2019 Completed M/s Pasang Lama & Sons
Rate
10.117 on NH-10 in the State of Sikkim on Item Rate Basis
Project 100%
2-lane Chisopani Traffic Tunnel of length 250 m including
2 EPC NH(O) NH-10 0.42 35.69 29 05/03/2019 9/10/2019 100.00% 100.00% 99.72% 9/8/2021 completed on 22-05- M/s Nagyan Constrcution Pvt. Ltd
approaches from Km 67+080 to Km 67+500
2022

Construction of Rangpo-Viaduct at Rangpo town Km Dinesh Chandra R Agrawal


3 EPC SARDP 10 1.12 133.49 55.79 16/12/2016 2/20/2017 100.00% 100.00% 96.88% 2/20/2020 Completed
51.100 to 53.800 NH-10 Infracon Pvt Ltd.(DRAIPL)

Construction of Alternate Highway from Rhenock- M/s Dinesh ChandraAgarwal


4 EPC SARDP 717A 26.70 447.37 318.42 31/03/2017 11/1/2017 99.98% 99.60% 99.55% 10/31/2020 Completed Land Acquisition
Pakyong NH-717A. Infracon Pvt.Ltd.Jagdish Agarwal

Construction of 48m Bridge over Chuba Khola at Km


5 EPC NH(O) NH-10 0.48 8.93 7.45 21/05/2019 9/16/2019 100.00% 93.55% 80.19% 9/15/2021 9/15/2022 M/s Mohan Bajaj Land Acquisition
75+300 to Km 75+800 on NH-10

Construction / Upgrade existing road to 2 lane with paved


6 EPC SARDP 510 16.00 375.8 163 26/02/2019 10/5/2019 95.19% 61.85% 59.32% 4/5/2022 3/21/2023 M/s. VKJ-NSPR (JV) .
shoulder from Km 0.000 to 16.000 Singtam - Tarku NH-510

Construction / Upgrade existing road to 2 lane with paved


M/s S&P Infrastructures
7 EPC SARDP shoulder from Km 16.000 to 32.500 Tarku - Ravangla NH- 510 16.50 290.05 171.53 31/03/2017 11/1/2017 100.00% 85.64% 83.92% 10/31/2020 9/30/2022 Land Acquisition
Developers Pvt.ltd
510 .

Construction/Upgradation of Existing road to 2 lane with


paved shoulder including Geometric Improvement from
8 EPC SARDP 717A 14.17 275.26 - - - 74.50% 0.00% 0.00% 1/0/1900 - To be Re-awarded
Ranipool to Pakyong from km 2.000 to km 16.167 (Balance
Work) under SARDP-NE 'A'”

Realignment of NH717A from Design CH: 0.00 (Km 77.800


9 EPC SARDP of NH-10) to Design CH:2.00 (Km 3.100 of NH-717A) with 2- 717A 2.00 0 50 04/02/2021 4/10/2021 54.00% 16.22% 11.33% 4/10/2023 4/10/2023 Suryodaya Infra Project (I) Pvt. Ltd Land Acquisition
lane paved shoulder including Major Bridge of 680 m

Construction and upgradation of existing road to 2-lane


with Paved shoulder from km. 20.340 (Rongli Bazzar) to
km. 26.588 (Rongli Bypass End) and upgradation of L. G. Chaudhary (LGC)- Yogi
10 EPC NH(O)-NE 717 B 7.31 332.28 162.741 15/01/2021 3/10/2021 90.99% 12.63% 12.10% 9/8/2023 9/9/2023 Land Acquisition/Forest Issues
existing road at km 20.600 & km 26.400 for length of 0.520 Construction (YCC) (JV)
km & 0.554 km of Rhenok - Menla spur (NH-717B)
Package-IIA under SARDP-NE {Under NH(O)-NE}

Construction & Upgradation of existing road to 2-lane with


J.K. Associates - A.K. Builders
11 EPC NH(O)-NE paved shoulder from km27.200 (End of Rongli bypass) to 717 B 10.40 230.45 100.953 31/08/2020 10/15/2020 77.12% 34.13% 32.27% 4/15/2023 4/15/2023 Forest Issues
(JV)
km37.600(New Rolep Bridge) of Rhenok-Menla spur ( II B)

Construction & Upgradation of existing road to 2-lane with


paved shoulder from New Rolep Bridge at km 37.600 to Nalanda Engicon Pvt. Ltd.- Ujjain
12 EPC NH(O)-NE 717 B 14.40 493.42 236.121 16/03/2021 5/25/2021 95.52% 6.93% 5.19% 5/24/2024 5/24/2024 Forest Issues
Chochenpheri at km 52.00 in the section of Rongli to Engicon Pvt. Ltd. (JV)
Chochenpheri of NH 717B (Pkg-II C)
Construction of 2-lane with paved shoulder of new green
field alignment from Chochenpheri at km 52.000 to
13 EPC NH(O)-NE 717 B 30.00 816.79 532.52 28/10/2020 12/10/2020 100.00% 3.85% 2.97% 12/9/2023 10.11.2024 U.P. State Bridge Corporation Ltd. Forest Issues
Helipad near Menla at km82.00 of Rhenok-Menla spur of
NH-717B (Pkg-III A)
Construction of 2-lane with paved shoulder of new green
14 EPC NH(O)-NE field alignment from Helipad at Menla at km 82.00 to Menla 717 B 12.03 410.6 260.52 28/12/2020 2/25/2021 100.00% 9.49% 8.42% 2/25/2024 2/25/2024 A. G. Construction Forest Issues
at Km 94.030 of Rhenok-Menla spur of NH-717B (Pkg-III B)

Construction of 2-lane specification road with paved


shoulder including Tunnel (300m) at Rabangla (Singtam-
15 EPC NH(O)-NE 510 1.10 79.21 50.6 22/09/2020 10/15/2020 100.00% 9.30% 6.04% 10/15/2022 1/13/2023 Nagyan Construction Pvt. Ltd. Forest Issues
Tarku-Rabangla-Legship-Gyalshing) Pkg-III (Design Ch.:
32.500 km to 33.600 km) under SARDP-NE (Pkg- III)

Rehabilitation & Upgradation of existing road to 2-lane


with paved shoulder including geometric improvement of
16 EPC NH(O)-NE 510 25.24 292.8 144.9 31/08/2020 10/31/2020 86.57% 17.59% 17.15% 5/1/2022 3/6/2023 Shivam Condev Pvt. Ltd. Land Acquisition
section from start of Rabangla km33.600 to km58.840 (Pkg-
IV)
Construction of 2-lane specification road with paved
shoulder as realignment (Greenfield alignment) of existing
17 EPC NH(O)-NE 510 16.16 262.84 132.295 14/09/2020 11/10/2020 85.21% 12.07% 11.18% 5/9/2023 1/29/2024 JRA Infrastructure Ltd. (JRAIPL)
stretch between Legship - Gyalshing from km58.840 to
km75.00 (Pkg- V)

Construction of 2-lane road with paved shoulder


18 EPC NH(O)-NE (Greenfield alignment) of existing stretch between 510 15.21 183.31 89.566 14/09/2020 11/10/2020 52.60% 8.23% 5.45% 5/10/2022 12/7/2022 JRA Infrastructure Ltd. (JRAIPL)
Legship - Gyalshing from km75.00 to km 90.210 (Pkg- VI)
Special protection work on rehabilitation and restoration
of sliding/sinking zone from Km 70+900to Km 71+100 and
Km 71+550 to Km 71+850 with JICA Technical Assistance
19 EPC NH(O) NH-10 1.25 165.67 33.84 28/02/2020 6/11/2020 100.00% 64.00% 63.41% NA 04.06.2023 KCC Buildcon Pvt. Ltd.
including widening of narrow zone from Km 53+775 to Km
54+100 and fom Km 63+045 to Km 63+470 on NH-10
(Rangpo to Ranipool section)

Total 220.61 4867.20 2556.82


Status as on 31.08.2022
Sanctione Cumulativ Remarks/ Issues
NH Awarded Right of way Cumulativ
NHDP d Date of e Target date of (Land Aquisition
SL. No. Length Cost Date of (ROW) e Physical Likely date of Name of the
Mode Phase/ Name of Project Cost/TPC Start/Appoint Financial completion as Issues/ Forest Issues/
No. (Old/ (Km) Rs. in Award Available progress completion Contractor
Scheme Rs. in ed Date progress per contract Utility Shifting/
New) crore % %
crore % Contractor Issue)
West Bengal
EAP Construction of Mechi bridge across Indo- Dinesh Chandra R Agrawal
1 EPC 327B 1.50 158.65 103.78 3/23/2017 2/1/2018 100.00% 100.00% 94.93% 1/30/2021 Completed
(ADB) Nepal border on Asian Highway (AH -02). Infracon Pvt Ltd.(DRAIPL)
Constuction/Upgradation of existing
highway to 2 lane with paved shoulder
2 EPC SARDP from Km 0.00 to Km 13.00 NH-717A 717A 13.00 402.94 261 3/1/2019 10/4/2019 100.00% 40.55% 38.30% 4/3/2022 7/15/2023 M/s NSPR - VKJ (JV)
Bagrakot-Kafer
IV A.
Constuction/Upgradation of existing
Rani Constructions Pvt. Ltd. - Sri
highway to 2 lane with paved shoulder
3 EPC SARDP 717A 12.60 295.97 184.45 8/19/2020 10/5/2020 100.00% 38.85% 35.74% 4/5/2023 8/23/2023 Satya Sai Infrastructure Pvt. Ltd.
from Km 13.00 to Km 25.600 NH-717A
(JV)
Bagrakot-Kafer IV B.
Construction of alternative highway to
Gangtok in Sikkim via Bagrakot-Chuikhim-
Nimbong-Kafer-Bakhim-Algarah-Rhenok in
4 EPC SARDP W.B. and from Rhenok-Rorathang-Pkyong 717A 0.50 77.44 - - - - 0.00% 0.00% - - -
along with spur from Aritar-Rolep-Menla in
Sikkim from Km 25.60 to Km 26.10 of
Bagrakot-Kafer IV C.
Constuction/Upgradation of existing
Ketan Construction Ltd.(KCL)-
highway to 2 lane with paved shoulder
5 EPC SARDP 717A 13.90 242.97 177.99 3/20/2020 6/11/2020 100.00% 39.64% 37.37% 6/10/2022 1/15/2023 Bhutan Builders Pvt. Ltd.(BBPL)
from Km 26.10 to Km 40.00 NH-717A
(JV)
Bagrakot-Kafer IV D.
Construction & upgradation of existing
road to 2-lane with paved shoulder
Rani Constructions Pvt. Ltd. - Sri
including geometric improvement of Kafer-
6 EPC NH(O)-NE 717 A 21.10 311.02 189.26 8/21/2020 10/5/2020 100.00% 23.55% 19.67% 4/5/2023 7/22/2023 Satya Sai Infrastructrue Pvt. Ltd.
Lava More section from km 40.00 to km
(JV)
61.100 of NH717-A on EPC under SARDP-
NE A (Pkg-VA)

Construction & upgradation of existing


road to 2-lane with paved shoulder
including geometric improvement of sect.
M/s TTC Infra India - M/s
from Pedong bypass to Reshi Border km
7 EPC NH(O)-NE 717 A 16.55 345.38 240.3 7/24/2020 10/20/2020 100.00% 33.26% 26.87% 4/17/2022 12/28/2022 Suryodaya Infra Projects (I) Pvt.
79.700 to km96.254 of NH-717A under
Ltd. (JV)
SARDP-NE-A on EPC (Lava More-Rishi
Border )Pkg-VB as part of Alternate
connectivity to Gangtok.

Total 79.15 1834.37 1156.78


Status as on 31.08.2022
Right of Remarks/ Issues
NHDP NH No. Sanctioned Awarded Date of way Cumulative Cumulative Target date of Likely date (Land Aquisition Issues/
SL. Length Date of Name of the
Mode Phase/ Name of Project (Old/ Cost/TPC Cost Start/Appoin (ROW) Physical Financial completion as of Forest Issues/ Utility
No. (Km) Award Contractor
Scheme New) Rs. in crore Rs. in crore ted Date Available progress % progress % per contract completion Shifting/ Contractor
% Issue)

Tripura
2-laning with Paved shoulder of Udaipur-
44 (New M/s Oriental Structural
1 ICR SARDP Sabroom Section of NH-44 from Km 55.00 73.712 915 497.89 02/05/2014 31/10/2015 100.00% 100.00% 100.00% 4/30/2018 Completed
NH-08) Engineers Pvt. Ltd
to 128.712
Construction of Extra-dosed RCC Bridge
including viaduct and approaches over 44 (New
2 BW NH(O) 1.888 128.69 82.57 3/22/2017 10/27/2017 100.00% 99.50% 99.13% 4/26/2020 Completed M/S DRA Infracon Pvt. Ltd.
river Feni at Sabroom on Indo-Bangladesh NH-08)
Border on NH-8 (old NH-44)
2-laning with Paved shoulder of Agartala-
44 (New
3 ICR SARDP Udaipur Section of NH-44 from Km 6.800 to 48.2 649 369 10/31/2014 9/15/2015 100.00% 99.21% 97.23% 3/14/2018 Completed M/s KMC Construction
NH-08)
km 55.00
Strengthening of Churaibari - Agartala
4 EPC NH(O)-NE 8 74.9 257.96 202 6/3/2020 7/24/2020 100.00% 100.00% 99.65% 1/15/2022 Completed M/s Shiv Build India Pvt. Ltd.
section of NH-08 (74.876 Km) on EPC basis
Improvement/strengthening to 2-lane with
hard shoulder of Khayerpur-Amtali
Physically
5 EPC NH(O)-NE (Agartala) section from Ch. 0.00 Km to 8 12.9 147.06 97.07 3/20/2020 7/1/2020 100.00% 95.00% 89.31% 7/1/2022 M/s CIVTECT (INDIA) Pvt.
Completed
12.900 Km of NH-8 on EPC basis [Tripura
Bypass]
Rehabilitation & Upgradation of Road from
Km 0.00 to Km 18.600 (Total length-18.600
6 EPC NH(O)-NE km) of Kumarghat-Kailashahar section on 208 18.6 277.5 127.68 6/3/2020 7/15/2020 96.51% 31.65% 29.11% 1/13/2022 June'23 M/s Satish Prasad
NH-208 to 2-lane with Paved shoulder on
EPC bais
Improvement and Widening to 2 lanes with
7 EPC NH(O)-NE paved shoulders of Jolaibari - Belonia (from 108A 21.412 272.11 141.44 6/3/2020 7/15/2020 93.60% 32.85% 27.15% 1/6/2022 Mar'23 M/s Satish Prasad
km 0.000 to km 21.412) section of NH-108A

Rehabilitation & Upgradation of Road from


design Km 0.00 to Km 11.800 (Total length-
8 EPC NH(O)-NE 11.800 km) of Kailashahar-Kurti Bridge 208A 11.8 154.51 84.9 3/20/2020 7/15/2020 99.66% 33.15% 30.98% 7/14/2022 Mar'23 M/s ASC Infra Pvt. Ltd.
section on NH-208A to 2-lane with Paved
shoulder on EPC bais(PKG- I )

Rehabilitation and up-gradation of road


from design km 11.800 to km 25.250 (Total
9 EPC NH(O)-NE length: 13.450km) of Kailashahar-Kurti 208A 13.45 178.43 88.9 3/30/2020 7/15/2020 99.62% 29.24% 24.26% 7/14/2022 Mar'23 M/s ASC Infra Pvt. Ltd. Forest Issues
Bridge section on NH-208A to 2- lane with
paved shoulder on EPC basis (Package-II)
Rehabilitation and up-gradation of road
from design km 25.250 to km 36.460 (Total
10 EPC NH(O)-NE lengh: 11.210 km) of Kailashahar-Kurti 208A 11.21 140.55 73.21 6/3/2020 8/3/2020 97.99% 12.20% 10.39% 1/25/2022 Dec'23 A K Construction Co. Land Acquisition
Bridge section on NH-208A to 2-lane with
paved shoulder (Package-III)
Rehabilitation and up-gradation of road
from design km 6.500 to km 19.300 (Total
208A/ NH-
11 BR NH(O)-NE lengh: 12.800 Km) of Agartala - Khowai 12.8 165.55 86.47 3/30/2020 7/15/2020 100.00% 40.05% 35.38% 7/15/2022 June'23 M/s Shiva Buildtech Pvt. Ltd.
108B
section on NH-108B to 2- lane with paved
shoulder (Package-I)
Rehabilitation and up-gradation of road
from km 19.300 to km 31.300 (Total length:
208A/ NH- KLD Creation Infrastructure
12 BR NH(O)-NE 12.000km) of Agartala-Khowai section on 12 141.48 67.01 2/8/2021 6/8/2021 100.00% 5.30% 1.80% 12/17/2022 Mar'24
108B Pvt. Ltd.
NH-108B to 2- lane with paved shoulder on
EPC basis (Package-II)

Rehabilitation and up-gradation of raod


from design km 31.300 to km 45.300 (Total
208A/ NH-
13 BR NH(O)-NE length: 14.000km) of Agartala-Khowai 14 173.17 96 9/21/2020 10/22/2020 100.00% 26.20% 17.93% 4/15/2022 June'23 A K Construction Co.
108B
section on NH-108B to 2- lane with paved
shoulder on EPC basis (Package-III)

Rehabilitation and up-gradation of road


from km 0.000 to km 16.29 (Total Length:
Engineering Projects (INDIA)
14 EC NH(O)-NE 16.29 km) of Manu-Lalchara Section on Nh- 108 / 44A 16.077 247.76 166.94 3/30/2020 7/15/2020 96.41% 42.80% 39.35% 1/14/2022 June'23 Land Acquisition
Ltd. (EPIL)
44A to 2- lane with paved shoulder-on EPC
Mode (Manu-Simlung -I)

Rehabilitation and up-gradation of road


from km 16.077 to km 43.935 (total length Jugal Kishore Mahanta Infra
15 EC NH(O)-NE 27.858 km) of Lalchara-Kanchanpur section 108 / 44A 27.858 456.88 257.512 3/23/2022 to be given - 0.00% 0.00% - - works (JKM) - Keti Land Acquisition
on NH-44A to 2 lane with paved shoulder Construction (JV)
(Manu-Simlung -II)
Rehabilitation & Upgradation of Road from
Km 46.597 to Km 66.845 (Total length=
Rajendra Singh Bamboo Infra
16 EC NH(O)-NE 20.248 km) of Kanchanpur-Vaghmun 108 / 44A 20.25 347.36 225.09 6/3/2020 7/20/2020 87.51% 66.79% 61.06% 1/19/2022 June'23 Land Acquisition
Pvt. Ltd.
section(PKG- III) on NH-44A to 2 -lane with
Paved shoulder (Manu-Simlung-III)
Rehabilitation and up-gradation of road
from Km 66.845 to 85.125
JSR Constructions Pvt Ltd -
(Total length: 18.280 Km) of Vaghmun-
17 EC NH(O)-NE 108 / 44A 18.28 354.79 220.87 3/27/2021 6/25/2021 92.78% 10.52% 10.07% 12/24/2022 Mar'23 PRN Infratech, Engineers & Land Acquisition
simlung section on NH-44A (Package-lV) to
Contractors (JV)
2-lane with paved shoulder (Manu-Simlung-
IV)
Improvement & widening to 2-lane with
paved shoulder of road Kailashahar - Fultali
18 EAP EAP (JICA) 208 8.1 99.48 62.25 11/24/2020 12/29/2020 99.63% 35.19% 30.41% 6/30/2022 Apr'23 Sahu Construction Land Acquisition
section from Km 21.100 to Km 29.200 (Pkg-
1)
Improvement & widening to 2-lane with
paved shoulder of road Fultali - Jurichhara Narendra Builders - Jeet
19 EAP EAP (JICA) 208 20 206.78 121 11/24/2020 12/31/2020 93.60% 66.32% 61.57% 7/1/2022 Feb'23 Land Acquisition
section from Km 29.200 to Km 49.200 (Pkg- Construction Co. (JV)
2)
Improvement & widening to 2-lane with
paved shoulder of road Jurichhara - Jandu Construction India
20 EAP EAP (JICA) 208 14.5 280.91 199.49 11/24/2020 1/1/2021 96.24% 75.25% 72.96% 7/2/2022 Dec'22 Land Acquisition
Bamanchara section from Km 49.200 to Km Pvt. Ltd.- Maan Builders (JV)
63.700 (Pkg-3)
Improvement & widening to 2-lane with
paved shoulder of road Bamanchara -
21 EAP EAP (JICA) 208 12 159.13 84.48 11/24/2020 12/29/2020 87.50% 36.00% 27.64% 6/30/2022 Apr'23 Sahu Construction Land Acquisition
Srirampur section from Km 63.700 to Km
75.700 (Pkg-4)
Improvement & widening to 2-lane with
paved shoulder of road Srirampur - Khowai
22 EAP EAP (JICA) 208 25.6 332.14 149.92 11/24/2020 12/30/2020 100.00% 35.20% 29.04% 7/1/2022 Mar'23 CIVTECT (INDIA) Pvt. Ltd.
section from Km 75.700 to Km 101.300 (Pkg-
5)

Construction of 2 bridge on river Gomti and


23 NH(O)-NE 8 1.877 86.53 49.80 8/13/2020 7/16/2020 100.00% 30.90% 15.18% 3/25/2022 June'23 M/s Brijesh Agarwal
Mahuri

Total 491.39 6172.77 3551.48


Status as on 31.08.2022

Right of
Awarded Cumulative Cumulative Remarks/ Issues
NHDP NH No. Sanctioned Date of way Target date of Likely date
SL. Length Cost Date of Physical Financial Name of the (Land Aquisition Issues/
Mode Phase/ Name of Project (Old/ Cost/TPC Start/Appoint (ROW) completion as of
No. (Km) Rs. in Award progress progress Contractor Forest Issues/ Utility
Scheme New) Rs. in crore ed Date Available per contract completion
crore % % Shifting/ Contractor Issue)
%

Uttarakhand
Proposed Protection work at Nalupani Landslide (Km.
M/s KCC Buildcon Pvt.
1 EPC NH(O) 123+080 to Km. 123+480,123.665to 123.740& km. 123+770 NH-34 0.735 47.13 38.06 6/16/2017 9/11/2017 100.00% 100% 100% 3/15/2019 Completed
Ltd.
to Km. 123+970)
Rehabilitation/ Treatment of Landslide location with slope
protection and Drainage improvement at Helang (Km
31-01-2020 M/S R.G. Buildwell
2 EPC NH(O) 468.200), Govindghat-II (Km 497.000) and Govindghat-III NH-58 0.575 45.09 34.52 4/6/2016 11/4/2016 100.00% 100% 100% Completed
/ 31-01-2020 Engineers LTD.
(km 500.000) on NH-58 (New NH 07) with proposed length
of 275m, 150m & 150m respectively in Chamoli District
Proposed Protection work at Bareti landslide zone km.
3 EPC NH(O) NH-34 0.76 40.89 30.62 9/18/2017 1/4/2018 100.00% 100.00% 98.90% 1/3/2020 Completed M/s Bharat Construction
100.300 to km. 101.060
Construction of Road and Slope Protection works at
4 EPC NH(O) Gholteer Landslide from km. 379.100 to km. 380.275 of NH- NH-7 1.175 89.27 65.00 12/10/2018 5/3/2019 100.00% 100.00% 99.17% 5/2/2020 Completed M/s Bharat Construction
07 under “Chardham Pariyojna”
Construction of valley side slope stabilization treatment
M/s Chaudhary
including drainage, cross drainage work and pavement in
5 EPC NH(O) NH-34 0.89 23.51 18.00 11/22/2019 1/8/2020 100.00% 100% 100% 7/5/2020 Completed Construction Company
Dharasu- Gangotri road from km. 123.080 to km 123.970 of
Pvt Ltd.
NH-34 and stabilization of dumping zone
Construction of Road and Slope Protection works at
6 EPC NH(O) Patalganga Landslide from km. 458.900 to km. 459.475 of NH-7 0.6 45.37 37.00 12/10/2018 5/3/2019 100.00% 100.00% 99.95% 5/2/2020 Completed M/s Bharat Construction
NH-07 under “Chardham Pariyojna”
Rehabilitation/ treatment of landslide location with slope
protection work and drainage improvement at
Nandprayag (Km 420.400), Maithana (km 423.500), Birahi M/S R.G. Buildwell
7 EPC NH(O) NH-58 0.775 57.66 44.92 4/6/2016 11/4/2016 100.00% 100.00% 99.84% 5/6/2018 Completed
(km 437.400) & Gulabkothi (Km 464.400) on NH-58 with Engineers LTD.
proposed length of 200m, 350m, 100m & 125m
respectively in Chamoli district
Construction, Operation & Maintenance of 2-L Bi-
directional Silkyara Bend- Barkot Tunnel with escape 23-06-2021
M/s Navayuga
8 EPC NH(O) passage including approaches on Dharasu-Yamunotri NH-134 4.859 1383.78 853.79 31/05/2018 7/9/2018 100.00% 43.93% 42.43% 5th Milestone 08-07- 3/31/2024
Engineering Co. Limited
section b/w Chainage 25.400km and 51.00km falling along 2022
NH-134(Old NH-94)on EPC mode
Construction and upgradation of existing road to 2-lane
with paved shoulder from Km 368.000 to Km 399.000 of
9 EPC NH(O) Lameri to Karanprayag (Excluding km 379.000 to km NH-7 29.125 274.31 181.90 3/26/2018 5/23/2018 99.49% 90.19% 89.39% 11/20/2020 12/31/2022 M/s RCC Developers ltd
380.275).
Rudraprayag to Josimath Package-I
Construction and upgradation of existing road to 2-lane
with paved shoulder from km 399.000 to km 430.000 of
10 EPC NH(O) karanprayag to chamoli (excluding km 420.250 to km NH-7 28.8 403.36 258.26 3/26/2018 5/24/2018 95.42% 91.62% 89.29% 11/21/2020 12/31/2022 M/s SCCPL-HCCPL(JV) Forest Issues
420.500 and km 423.300 to 423.650) .
Rudraprayag to Josimath Package-II
Construction and Upgradation of existing road to 2-lane
with paved shoulder from Km 430.000 to Km 468.000 of
M/s NKG Infra. Struc
11 EPC NH(O) Chamoli to Paini (excluding Km 437.625 to Km 437.775, NH-7 36.675 417.24 307.28 3/26/2018 5/23/2018 98.34% 94.99% 94.56% 11/20/2020 12/31/2022 Forest Issues
Pvt. Ltd.
Km 458.900 to Km 459.475 and Km 464.425 to Km 464.525)
Rudraprayag to Josimath Package-III

Total 104.97 2827.61 1869.35