Sno Division/PIU Project ID Project Name NH Total Stage Total Contract Appointed Scheduled Likely Date of Date of PCOD

ract Appointed Scheduled Likely Date of Date of PCOD Cumulative Cumulative Name of
Name No(New) Length(km) Project Value (Cr) Date Completion PCOD/ date of and COD if Length Physical Contractor/Concession
Cost Date full given Completed(k Progress in % aire, TL Name &
1 MSRDC Nashik I 65465 Kolde village to Khetia MP 752G 48.62 Under (Original
509.18 298.11 27-Jul-17 27-Jul-19 completion
31-Dec-20in m)42.46
till date 78.62 Contact
H. G. Infra No
Engineering
border section 2L + PS Const. Sanctione case PCOD Limited,,9772203939
d in Cr) already given

2 MSRDC Nashik I 146208 2 lane + PS Pimplner to Satana 752G 42.57 Under 277.82 193.14 15-Jan-20 8-Jul-21 0 2.11 ,Mahesh P
-[Design chainage km 21.427 Const. Asthana,8222020301
to 64.00 ] of NH-752G]

3 MSRDC Nashik I 50073 Pahur to Bodhvad section of 753L 44.76 Under 244.93 163.33 1-Jun-18 1-Jun-20 31-Dec-20 33.08 80.61 M/s SCIW & Gangamai
NH-753L - 2L + PS Const. Industries and
Construction
L,,9922818599
4 MSRDC Nashik I 65463 Bodhwad to Mah./MP State 753L 33.38 Under 178.26 128.27 27-Jul-17 27-Jul-19 31-Jul-20 33.38 100 M/s. Sarswati
Border section of Nh-753L - Const. Constructions- Mahesh
2L+PS Vaniya,,9925044948
5 MSRDC Nashik I 146209 2 lane + PS Chandwad - 752G 24.05 Under 168.45 103.55 15-Jan-20 14-Jul-21 0 4.57 ABC & VPSC & MAC
Manmad [Design chainage km Const. (JV),,
104.600 - 128.650] NH-752G]
Name of Project :
Diviosn
Project ID

Status and details of EOT


EOT 1 status -
Contractor request
EOT requested upto : 26.07.2020
EOT proposal submitted on 31.07.2018
AE Action
EOT recommeded upto 06.10.2020
EOT recommedation submitted to PWD on 10.01.2019
PWD Action
Sec(NH) recommeded EOT upto 31.05.2020
Sec(NH) recommedation submitted to RO on 27.09.2019
RO Action
RO approved/recommeded EOT upto 31.05.2020
RO approval/recommedation submitted to MoRTH HQ on -
13.03.2020
MoRTH HQ Action
HQ approved EOT upto ---------(date)
RO approval submitted to MoRTH HQ on ----------(date)
HQ returned EOT unapproved for clarification on ----- (date)

Status and details of COS


COS 1 status -
Contractor request
COS amount requested : Rs 0.59( amount Cr )
COS proposal submitted on 28.11.2017
AE Action
COS amount recommeded Rs 0.58 (Amount Cr)
COS recommedation submitted to PWD on 10.12.2017
PWD Action
Sec(NH) recommeded COS Rs 0.58 (Amount Cr )
Sec(NH) recommedation submitted to RO on 28.03.2018
RO Action
RO approved/recommeded COS Rs 0.58 (amount Cr)
RO approval/recommedation submitted to MoRTH HQ on -
25.11.2019
MoRTH HQ Action
HQ approved COS Rs ---------(amount Cr )
HQ approval issued on ----------(date)
HQ returned COS unapproved for clarification on ----- (date)

If COS returned by HQ : give its present status , likely date of


resubmission

HPC Reconstruction COS (Approved from RO)


Kolde village to Khetia MP border section 2L + PS
MSRDC Nashik I
65465

Status and details of EOT


EOT 2 status ( upto 9 months in EE Power as per Atmanirbhar
circular) if applicable
Contractor request
EOT requested upto : 31.03.2021
EOT proposal submitted on 24.04.2020
AE Action
EOT recommeded upto 31.12.2020
EOT recommedation submitted to PWD on 29.04.2020
PWD Action
Approved EOT upto 31.12.2020
Date of approval from PWD 14.05.2020
if not approved,likely date of EOT approval ----------(date)

Status and details of COS


COS 2 status -
Contractor request
COS amount requested : Rs 0.52 (amount Cr)
COS proposal submitted on 27.12.2017
AE Action
COS amount recommeded Rs 0.52 (amount Cr)
COS recommedation submitted to PWD on 09.03.2017
PWD Action
Sec(NH) recommeded COS Rs -----------(Amount Cr )
Sec(NH) recommedation submitted to RO on ----------(date)
RO Action
RO approved/recommeded COS Rs ---------(amount Cr)
RO approval/recommedation submitted to MoRTH HQ on
----------(date)
MoRTH HQ Action
HQ approved COS Rs ---------(amount Cr )
HQ approval issued on ----------(date)
HQ returned COS unapproved for clarification on ----- (date)

If COS returned by HQ : give its present status , likely date of


resubmission
EOT 3 status ( if required beyond EOT 2 )
Contractor request
EOT requested upto : 31.12.2021
EOT proposal submitted on 22.01.2021
AE Action
EOT recommeded upto 30.06.2021
EOT recommedation submitted to PWD on 01.02.2021
PWD Action
Sec(NH) recommeded EOT upto 30.06.2021
Sec(NH) recommedation submitted to RO on ----------(date)
RO Action
RO approved/recommeded EOT upto ---------(date)
RO approval/recommedation submitted to MoRTH HQ on
----------(date)
MoRTH HQ Action
HQ approved EOT upto ---------(date)
HQapproval issued on ----------(date)
HQ returned EOT unapproved for clarification on ----- (date)

If EOT returned by HQ : give its present status , likely date of


resubmission

COS 3 status -
Contractor request
COS amount requested : Rs 13.43 ( amount Cr )
COS proposal submitted on 22.02.2020
AE Action
COS amount recommeded Rs 14.97
COS recommedation submitted to PWD on 26.02.2020
PWD Action
Sec(NH) recommeded COS Rs 14.97 (Amount Cr )
Sec(NH) recommedation submitted to RO on 30.04.2020
RO Action
RO approved/recommeded COS Rs ---------(amount Cr)
RO approval/recommedation submitted to MoRTH HQ on
----------(date)
MoRTH HQ Action
HQ approved COS Rs ---------(amount Cr )
HQ approval issued on ----------(date)
HQ returned COS unapproved for clarification on ----- (date)

If COS returned by HQ : give its present status , likely date of


resubmission

4 lane COS (Pending at RO)