Professional Documents
Culture Documents
2023
1. Highlights:
i. An agreement 23.03.2023 entered on 23.03.2023 with NCRTC to share knowledge and
technological support in project implementation. The NCRTC will help the HRIDC with
implementation of its in-house developed IT tool “SPEED” for monitoring and
management of the project.
ii. Sub-Structure work of major bridge no 134 on Manesar-Patli priority section has been
completed. Erection of OWG is in progress by Super-structure Contractor.
iii. Technical bid of Contract package C-23 has been opened on 31-12-2022 & Financial bid
opened on 28.02. 2023.Notice of Intention of Award (NOIL) issued on 20.03.2023.
iv. Technical bid of Contract package C-4 has been opened on 17-02-2023 & Financial bid
opened on 17.03.2023.
20-E notifications for Land Acquisition for entire route length covering all the five districts
namely Palwal, Nuh, Gurugram, Jhajjar & Sonipat have been published. Land awards declared
for. The status of disbursement of compensation upto 31.03.2023 is as under: -
3. Contracts Awarded:
S. Physical Financial
PKG Description Contractor
No Progress (%) Progress (%)
Priority Section: Civil
Works from Km 49.7 to
KCC Buildcon
1 C-1 Km 55.6 and its 24.00% 8.61%
Pvt. Ltd.
connectivity from
Manesar to Patli.
OWG on NH-352 on
M.G Contractor
2 Br-1 priority section of Pkg- 60.00% 47.63%
Pvt. Ltd
C-1.
Track works from km Shivakriti
3 T-1 9.00% 4.15%
32 to km 61.5. International Ltd
Electrification of
4 EL
connectivity line
ii. Physical progress of PKG C-1: Civil Works from Km 49.7 to Km 55.6 and its connectivity
from Manesar to Patli.
% Completed % Completed % Completed
S.
Items Unit Scope up to from 01-01-2023 up to
No
31-12-2022 to 31-03-2023 31-03-2023
Major Bridge -
1 Nos 1 40% 57% 97%
134
2 Minor Bridge Nos 16 13% 25% 38%
3 Retaining Wall Rmt 3200 10% 15% 25%
4 Earthwork L.Cum 23.1 0.36% 0.17% 0.53%
5 Blanketing Cum 85,655 0% 0% 0%
6 IMD Building Nos 1 15% 5% 20%
iv. Physical progress of PKG T-1: Track work from Ch:32 to 61.5 km
% Completed
Progress. up % Completed
S. from 01-01-
Items Unit Scope to 31-12- up to 31-03-
No 2023 to 31-03-
2022 2023
2023
1 Ballast Depot supply Cum 1,30,000 0.2% 4.6% 4.8%
2 Cess Supply Cum 9,00,000 0% 0.0% 0.0%
Transportation of Spl
PSC Sleepers:
3 P&C 1:12 Sets 70 0% 100.0% 100%
4 P&C 1: 8.5 Sets 7 0% 100.0% 100%
5 P&C 1:8.5 DS Sets 3 0% 100.0% 100%
6 PSC For SEJ Sets 74 0% 100.0% 100%
PSC for Br itself T-
Nos 2,800 0% 77.5% 77.5%
7 8672
PSC for Br App
Sets 30 0% 100.0% 100%
8 (Sets):
9 Fittings Material
10 ERC Mark V (Nos): Nos 6,00,000 0% 20.5% 20.5%
11 Rail Screw T:4153 Nos 12,600 0% 100.0% 100%
12 Plate Screw T:3912 Nos 16,500 0% 100.0% 100%
13 Plate Screw T:3915 Nos 2,670 0% 100.0% 100%
14 Plate Screw T:3916 Nos 1,485 0% 100.0% 100%
15 Fish Bolt T: 1899 Nos 8,640 0% 100.0% 100%
Single Coil Spring
Nos 45,500 0% 100.0% 100%
16 Washer (T-10773)
Wide Base PSC line
Nos 13,000 0% 23.4% 23.4%
17 Sleepers
7. dStatus of General Arrangement Drawings (GAD) of Rail Flyover (RFOs) over IR routs:
Equity Total
Equity infusion Equity
Total Equity
S. infused upto during infused
Shareholders Amount (INR
No. 31.12.2022 01.01.2023 to upto
Cr.)
(INR Cr.) 31.03.2023 31.03.2023
(INR Cr.) (INR Cr.)
1 HRIDC 831 443.2 - 443.20
2 HSIIDC 285 152 - 152
3 GMDA 75 40 - 40
4 MSIL 195 104 - 104
5 ACL 114 60.80 - 60.80
Total 1500 Cr. 800 Cr. - 800 Cr.
2 HSIIDC 38 38
3 GMDA 10 10
4 MSIL 26 26
i. From GoH:
a) Early disbursement of compensation for land by respective CALAs.