Professional Documents
Culture Documents
सु 4ागतम्
Presentatio
n on
Railway Electrification works
of N F Rly.
Review Meeting of GM/NFR
on 19.12.2022 (R0)
Geographical Map of Projects:
Status of EPC Contracts for Railway Electrification works under EPC-4, 5A & 6 of NFR:
RKM MOU Date & TDC
S. (Work
PKG Section / Amount Status of Tender
No. Completion
TKM Rs. (In Cr.) )
7 Droppering Shots 83
& Clipping
8 Bracket / Nos. 1348
ATD Adjustment
9 SED Checking Nos. 1348 815 533 29-12-2022 48
Major Drawing
Status Completed
Plinth Completed, CRB finishing Road Plinth CRB finishing Brick Work
Column in work in CRB Roof Slab Approach Completed, work in Completed,
CRB Works Completed
progress. progress. work in Column in progress finishing work
progress progress. in
progress.
Retaining Wall
Fencing under progress (30 To be
Works Completed In progress undertaken 6 /9 completed. Completed Completed
Meter out of 260
Meter)
Erection To be To be To be To be To be To be
Works To be undertaken undertaken undertaken undertaken undertaken undertaken undertaken
Target Date of
Completion Mar’23 Jan’23 Jan’23 Jan’23 Jan’23 Jan’23 Jan’23
WORK STATUS FOR PSI WORKS IN PRIORITY-3 SECTION as on 17.12.2022
Sl No. Golakganj (GKJ) TSS NCB SP 1 NCB SP 2 TFGN SSP BDYR SSP
Major
Drawing Completed Completed Completed Completed Completed
Status
Foundation To be
Works To be undertaken Completed Completed Work in progress undertaken
Plinth Completed,
Slab Casted, Brick work CRB finishing work CRB finishing work in Column in To be
CRB Works under progress in progress progress undertaken
progress.
Erection To be
Works To be undertaken To be undertaken To be undertaken To be undertaken undertaken
Target Date of
Completion Mar'22 Feb'22 Feb'22 Feb'22 Feb'22
Status of S&T Works as on 17.12.2022
Priority 1 Priority 2 Priority 3
Description Unit Cum. Target for Cum. Target for Cum. Target for
Qty Progress Balance completion Qty Progress Balance completion Qty Progress Balance completion
Location Box
Foundation & Nos. 45 45 0 - 120 22 98 10-01-2023 60 0 60 15-01-2022
Erection
Track Circuit
alteration Work -
including glued Stn. 5 100% 0 12 25% 75% 15-01-2023 6 0% 100% 15-02-2023
joint insertion
Cable
Termination & Stn. 5 100% 0 - 12 5% 95% 20-01-2023 6 0% 100% 15-02-2023
wiring
Signaling Indoor
Execution Stn. 5 100% 0 - 12 0% 100% 20-01-2023 6 0% 100% 15-02-2023
STATUS OF MATERIAL
1. Galvanised Steel Structures & SPS for OHE & PSI work : 2500 MT.
2. Material for Bracket Assembly : 4200 sets (Approx).
3. Regulating Equipment & Counter-weights - 340 sets.
4. Fittings & Fasteners – 200 TKM (Approx.)
5. Copper wires: Contact wire-130 KM, Catenary wire-151 KM, Dropper wire –
115 KM.
6. 132/27 kV Power Transformer- 1 No. for NMZ TSS., 1 No. for MHBA TSS.
7. ST/BT Insulators- 4200 Sets.
Status of 132 kV Transmission Line work : 4 Nos. in WB & 1 in Assam
SN Name of the GSS Name of the TSS Approx. Length of 132 Remarks
kV Tr. Line
West Bengal
Payment of Rs. 24.81 Cr. released to WBSEDCL on
1 Chalsa New Mal Jn 11.50 km 22.07.2022.
Tender yet to be floated by WBSETCL
Madarihat
2 Birpara (Previously at 12 km Estimate awaited from WBSEDCL.
Hasimara)
Payment of Rs. 12.66 Cr. released to WBSEDCL on
3 Dinhata Falimari 7.50 km 22.07.2022.
Tender yet to be floated by WBSETCL
Assam
Contract awarded to M/s RS Infra on 30.06.2022.
5 Golakganj Gauripur 14 km Preliminary survey completed & submitted to AEGCL for
approval.
ASSISTANCE REQUIRED: PKG-7
Falimari TSS
Staff Qtr. At
NMZ