Railway Electrification works
of N F Rly.
Review Meeting of GM/NFR
on 19.12.2022 (R0)
Geographical Map of Projects:
Status of EPC Contracts for Railway Electrification works under EPC-4, 5A & 6 of NFR:
RKM MOU Date & TDC
S. (Work
PKG Section / Amount Status of Tender
No. Completion
TKM Rs. (In Cr.) )

Siliguri - New Mal Jn. - Alipurduar-Samuktala


Rd and Alipurduar - New Coochbehar incl. EPC Contract awarded to M/s.
492 04.12.2020 SIPS-LUMINO-ZETWERK (JV
PKG 7 New Mal Jn. - Changrabandha, July’
01 / / Rs. 475.31 EPC-04), Agreement
(EPC-4) New Changrabandha-New Coochbehar incl.
New 587 Cr. signed on 28.10.2021 at a 2023
Mal Jn. Changrabandh, New Changrabandh- total cost of
New Coochbehar, New Coochbehar – Rs. 354.14 Cr.
Fakiragram - Dhubri
LOA for EPC Contract, issued
Badarpur (Excl.) - Jiribam, Katakhal - MoU signed
550 to M/s. L&T Ltd. on 19.01.2022
PKG 2 Bhairabi & Badapur - Karimganj - Sabroom on 03.08.2021 Dec’
02 / at a total cost of Rs. 511.94 Cr.
(EPC-6) Incl. Karimganj - Maishasan, Agartala - / Rs. 658.64
Akaura & Baraigram – Dullabachera 679 Agreement signed on
Cr. 2023
14.03.2022.
Validated Estimate Amounting
to Rs. 731.53 Cr. sanctioned
by NFR on 30.11.2021.
PKG 6 488 04.12.2020
Lumding – Dibrugarh Via Tinsukia LOA for EPC Contract, issued Dec’
03 / / Rs. 313.00
and Simaluguri – Dibrugarh to M/s. KEC on 05.03.2022 at a
(EPC- 650 Cr.
total cost of Rs. 455.18 Cr. 2023
5A)
Agreement signed on
04.04.2022
Total: 1525/1916 RKM/TKM
Detail of the Section under EPC - 4 (PKG-7):

Siliguri - New Mal Jn. – Alipurduar - Samuktala Rd


and Alipurduar - New Coochbehar incl. New Mal Jn. -
Changrabandha, New Changrabandha - New
Coochbehar incl. New Mal Jn. Changrabandh, New
Changrabandh - New Coochbehar, New Coochbehar
– Fakiragram – Dhubri.
SECTION / YEAR WISE COMMISSIONING TARGET - IRCON NFR EPC-04 (PKG-7)
FY WISE
TARGET FOR
SN PRIORITY NO SECTION DETAILS RKM TKM COMM. TARGET
(in RKM)
1 1st : SGUJ (Excl.) - SVQ – NMZ (Incl.) 48 61 Dec’2022
2022-
2 2nd : NMZ (Excl.) - APDJ – SMTA (Excl.) 124 160 Jan’2023 2023 250
3 3rd : NCB (Excl.) – GKJ – DBB (Incl.) 78 89 Feb’2023
YLSC (Excl.) – MYGD – MHBA - NCB (Excl.)
4 4th : 83 108 Aprl’2023
including CBD
5 5th : APDJ (Excl.) – BSW – NCB (Excl.) 21 22
2023-
6 6th : FKM (Excl.) – GKJ (Excl.) 45 45 May’2023 2024 242
7 7th : NMZ (Excl.) – MYGD (Excl.) 43 47

8 8th : NCB (Excl.) - BXT 50 55 June’2023

TOTAL : 492 587


STATUS OF OHE WORKS PRIORITY- 1
SECTION: SILIGURI-SIVOK-NEW MAL JN. (RKM/RKM: 48/61)
TDC: Dec’2022
Cumulative progress as on Balance as on Target for Present Asking Rate for
SN Item Unit Qty 17.12.2022 18.12.2022 completion balance Qty

1 LOP / CSD TKM 61


2 Foundation Nos. 1327
3 Mast Erection Nos. 1278
4 Boom Erection Nos. 137
5 Bracket Erection Nos. 1348 SECTION IS READY FOR ELECTRIC LOCO TRIAL.
6 Cat. & Cont. Stringing Shots 166

7 Droppering Shots 83
& Clipping
8 Bracket / Nos. 1348
ATD Adjustment
9 SED Checking Nos. 1348 815 533 29-12-2022 48

10 Tower TKM 61 56 5 31-12-2022 1


Wagon Checking
(Forwarded from
11 Application for EIG 16-11-2022 Division to HQ on
09.12.2022)
STATUS OF OHE WORKS PRIORITY- 2
SECTION: NEW MAL JN.-ALIPURDUAR JN.-SAMUKTALA RD. (RKM/TKM: 124/160)
T
SN Item Unit Qty
Cumulative progress as Balance as on Target for D
Present Asking Rate
on 17.12.2022 18.12.2022 completion for balance Qty
C
1 LOP / CSD TKM 172 172 0 - : -
2 Foundation Nos. 3789 3579 210 31-12-2022 16
J
3 Mast Erection Nos. 3658 2146 1514 06-01-2023 a 80
n
4 Boom Erection Nos. 271 37 234 08-01-2023 11

5 Bracket Erection Nos. 3950 791 3159 10-01-2023
2 137
0
6 Cat. & Cont. Stringing Shots 478 1 477 12-01-2023 2 19
3
7 Droppering & Clipping Shots 239 0 239 14-01-2023 10

8 Bracket / ATD Adjustment Nos. 3950 0 3950 16-01-2023 180

9 SED Checking Nos. 3950 0 3950 18-01-2023 165


10 Tower Wagon Checking TKM 172 0 172 20-01-2023 9
11 Application for EIG 20-01-2023 0
STATUS OF OHE WORKS PRIORITY- 3
SECTION: NEW COOCHBEHAR (Excl.) - GOLAKGANJ - DHUBRI (RKM/TKM: 78/89)
TDC: Feb’2023
Cumulative progress Balance as on Present Asking Rate for
SN Item Unit Qty Target for completion
as on 17.12.2022 18.12.2022 balance Qty

1 LOP / CSD TKM 93 93 - - -


2 Foundation Nos. 1900 1392 508 10-01-2023 22
3 Mast Erection Nos. 1690 0 1690 20-01-2023 65
4 Boom Erection Nos. 125 0 125 22-01-2023 6
5 Bracket Erection Nos. 1860 0 1860 25-01-2023 66
6 Cat. & Cont. Stringing Shots 148 0 148 31-01-2023 6
7 Droppering & Shots 74 0 74 03-02-2023 3
Clipping
8 Nos. 1860 0 1860 10-02-2023 56
Bracket /
ATD Nos. 1860 0 1860 13-02-2023 55
Adjustment
10
9 SED Checking TKM 93 0 93 15-02-2023 4
Tower Wagon 15-02-2023
Checking
11 Application
for EIG
WORK STATUS FOR PSI WORKS IN PRIORITY-1 SECTION as on 17.12.2022
Sl No. New Mal Junction (NMZ) TSS Sivok (SVQ) SSP Bagrakot (BRQ) SSP

Major Drawing
Status Completed

FDN Works Completed

READY FOR COMMISSIONING.

CRB Works Finishing works under progress. EIG SUBMITTED ON 22.11.2022.

Fencing Works Foundation & Retaining Wall Completed.

Traction Transformer main tank erected.


Erection Works Structure Erection completed by 80%.
Target Date of
Completion Jan'22 - -
WORK STATUS FOR PSI WORKS IN PRIORITY-2 SECTION as on 17.12.2022
Madarihat (MDT) APDJ SP cum
Sl No. TSS NKB SSP BNV SP MJE SSP HSA SSP RVK SSP SSP
Major
Drawing Completed Completed Completed Completed Completed Completed Completed
Status
Transformer FDN
Foundation Completed. To be To be 4/7
Works Completed undertaken undertaken completed. Completed Completed
(3 / 67 Nos)

Plinth Completed, CRB finishing Road Plinth CRB finishing Brick Work
Column in work in CRB Roof Slab Approach Completed, work in Completed,
CRB Works Completed
progress. progress. work in Column in progress finishing work
progress progress. in
progress.
Retaining Wall
Fencing under progress (30 To be
Works Completed In progress undertaken 6 /9 completed. Completed Completed
Meter out of 260
Meter)
Erection To be To be To be To be To be To be
Works To be undertaken undertaken undertaken undertaken undertaken undertaken undertaken
Target Date of
Completion Mar’23 Jan’23 Jan’23 Jan’23 Jan’23 Jan’23 Jan’23
WORK STATUS FOR PSI WORKS IN PRIORITY-3 SECTION as on 17.12.2022
Sl No. Golakganj (GKJ) TSS NCB SP 1 NCB SP 2 TFGN SSP BDYR SSP

Major
Drawing Completed Completed Completed Completed Completed
Status

Foundation To be
Works To be undertaken Completed Completed Work in progress undertaken

Plinth Completed,
Slab Casted, Brick work CRB finishing work CRB finishing work in Column in To be
CRB Works under progress in progress progress undertaken
progress.

Fencing Retaining Wall in progress Retaining Wall In To be


Works (20 / 150 Meter completed) Completed Completed progress undertaken

Erection To be
Works To be undertaken To be undertaken To be undertaken To be undertaken undertaken
Target Date of
Completion Mar'22 Feb'22 Feb'22 Feb'22 Feb'22
Status of S&T Works as on 17.12.2022
Priority 1 Priority 2 Priority 3
Description Unit Cum. Target for Cum. Target for Cum. Target for
Qty Progress Balance completion Qty Progress Balance completion Qty Progress Balance completion

Drawing Nos. 45 45 0 - 108 96 12 25.12.2022 63 12 51 15-01-2023

Trenching Km 23 23 0 - 48 22 26 05-01-2023 24 0 24 15-01-2023

Cable Laying Km 74 74 0 - 168 73 95 10-01-2023 84 0 84 15-01-2023

Location Box
Foundation & Nos. 45 45 0 - 120 22 98 10-01-2023 60 0 60 15-01-2022
Erection

Track Circuit
alteration Work -
including glued Stn. 5 100% 0 12 25% 75% 15-01-2023 6 0% 100% 15-02-2023
joint insertion

Cable
Termination & Stn. 5 100% 0 - 12 5% 95% 20-01-2023 6 0% 100% 15-02-2023
wiring
Signaling Indoor
Execution Stn. 5 100% 0 - 12 0% 100% 20-01-2023 6 0% 100% 15-02-2023
STATUS OF MATERIAL

Major Material of OHE/PSI: Status of Materials received as on 17.12.2022:

1. Galvanised Steel Structures & SPS for OHE & PSI work : 2500 MT.
2. Material for Bracket Assembly : 4200 sets (Approx).
3. Regulating Equipment & Counter-weights - 340 sets.
4. Fittings & Fasteners – 200 TKM (Approx.)
5. Copper wires: Contact wire-130 KM, Catenary wire-151 KM, Dropper wire –
115 KM.
6. 132/27 kV Power Transformer- 1 No. for NMZ TSS., 1 No. for MHBA TSS.
7. ST/BT Insulators- 4200 Sets.
Status of 132 kV Transmission Line work : 4 Nos. in WB & 1 in Assam
SN Name of the GSS Name of the TSS Approx. Length of 132 Remarks
kV Tr. Line
West Bengal
Payment of Rs. 24.81 Cr. released to WBSEDCL on
1 Chalsa New Mal Jn 11.50 km 22.07.2022.
Tender yet to be floated by WBSETCL

Madarihat
2 Birpara (Previously at 12 km Estimate awaited from WBSEDCL.
Hasimara)
Payment of Rs. 12.66 Cr. released to WBSEDCL on
3 Dinhata Falimari 7.50 km 22.07.2022.
Tender yet to be floated by WBSETCL

Payment for Rs. 9.52 Cr. released to WBSEDCL


4 Mathabhanga Mathabhanga 3.90 km on 22.07.2022.
Tender yet to be floated by WBSETCL

Assam
Contract awarded to M/s RS Infra on 30.06.2022.
5 Golakganj Gauripur 14 km Preliminary survey completed & submitted to AEGCL for
approval.
ASSISTANCE REQUIRED: PKG-7

• Early finalisation of Tunnel Drawing in Sivok -


Bagrakot section of Priority-1. Drawing submitted to
Division.
• Availability of 3rd Diesel Loco. Demand placed vide this
office letter dated 21.09.2022.
• Availability of one GS Coach with CBC coupling for formation
of Wiring Train.
Priority - 1 : New Mal Jn TSS
Priority – 1: Sivok SSP
Priority – 1: Bagrakot SSP
Mathabhanga TSS

Falimari TSS
Staff Qtr. At
NMZ