Professional Documents
Culture Documents
Total
Total Awarded Loa Date Civil
S.no Project Name state PIU Lanes NH (New) Mode Concessioner
Length Cost (Rs work
Cr)
Solar Highway Lighting at 18 locations
from Km 741.255 to Km 1022.494 on
Anakapalli – Annavaram – Diwancheruvu Morphing Inovations
1 3.975 Andhra Pradesh Rajamahendravaram Others 16,216A Item Rate 2.50 14/10/2023
section of NH-16 & Diwancheruvu - (OPC) Pvt. Ltd.
Siddhantham - Gundagolanu section of
NH-216A
Major Maintenance for the stretch from
KM. 1076.480 Chinna Avutupalli to KM. Raghava Project
2 1100.254 Kanaka Durgamma Vardhi on 23.774 Andhra Pradesh Vijayawada 4L 16 Item Rate Constructions 14.99 21/04/2023
Vijayawada - Gundugolanu section of NH- Privated Limited
16
Road Safety works with construction of 1
Nos ROB, 2 Nos VUPs, Service roads,
provision of lighting and construction of
other miscellaneous works at various
3 5.45 Andhra Pradesh Tirupati 4L PS 4 EPC SD Infra 149.77 13/04/2023
stretches including maintenance of
existing section of NH-4 from AP/Tamil
Nadu Border (Km.134.890) to
Nalagampalli village (Km.172.000)
Construction of LVUP for IISER Campus at
Km 504.850 in Penchalkona-Yerpedu
4 0.25 Andhra Pradesh Tirupati 2L PS 565 EPC JP Infrastructures 4.43 08/06/2023
section from Km 424.400 to Km 509.400
of NH-565
Rehabilitation and Strengthening of
SSA Techno
Distressed Major Bridge 649/1 on NH-67
5 0.16 Andhra Pradesh Nellore 2L 67 Item Rate Construction Pvt. 2.40 11/10/2023
near Kadirinayudupalli Village at Km
Ltd.
648.030 to Km 648.190
Operation and Maintenance of Nagaon to
Doboka section (Km 5.500 to Km. 35.862)
Basanta Kumar
6 of Package AS-17 of NH-36 and Km. 0.000 54.469 Assam Guwahati 4L NH-27 EPC 7.28 09/01/2024
Kakati
to Km. 22.000 including 2.107 Km.
Doboka Bypass of AS-16 of NH-54
Operation & Maintenance work from Km.
Basanta Kumar
7 162.620 to Km. 278.685 NH 37 (New NH 116.065 Assam Guwahati 4L NH-27 EPC 13.96 16/12/2023
Kakati
27) in the state of Assam.
Total
Total Awarded Loa Date Civil
S.no Project Name state PIU Lanes NH (New) Mode Concessioner
Length Cost (Rs work
Cr)
Strengthening under one time
improvement of 4L of Bakarpur Hat ( RKD Construction
8 38.81 Bihar Motihari 4L 139W HAM 1121.65 03/08/2023
NH19 Bypass) –Manikpur section of NH- Pvt. Ltd.
139W
4L Elevated Corridor and at-grade
improvements from Design Ch:0+000 to
Design Ch: 19+870 of Danapur – Bihta
Section, Design Ch:0+000 to Design
Ch:0+231 connecting the existing RoB
Ceigall India Limited-
near Danapur station ,1.35 Km ramps and
9 25.081 Bihar Patna 4L 922 EPC YFC Projects Private 1969.00 13/09/2023
at-grade improvements to 4-lane section
Limited JV
on Danapur side and Upgradation of
existing Two lane carriageway to Four
Lane carriageway from Design Ch:19+870
to Design Ch:23+500 of Bihta - Koilwar
section
4L Greenfield starting from NH-30 near H.S. Engineers &
Saristabad (Patna) to Nathupur (Project Associates-Velji
10 3.914 Bihar Gaya 4L PS 83 EPC 96.78 09/10/2023
end point of Patna-Gaya-Dobhi Section of Ratna Sorathia Infra
NH-83) Pvt. Ltd. JV
Rectification of Blackspots for 4nos. of
Black Spots Locations, Construction of Vishesh
11 Mandir Hasaud Flyover and Electrical 0.954 Chhattisgarh Raipur-I 4L 53 EPC Infrastructure Pvt. 33.51 24/08/2023
work of 04 nos at Raipur-Aurang section Ltd.
of NH-53 from Km. 239 to Km 282
Rectification/closure of unauthorized
Median Cuts and unauthorized access
from Main Carriage on Six laning of Satish Aggarwal &
47 9.05 Haryana, Punjab Ambala 6L 44 Item Rate 8.14 25/05/2023
Panipat-Jalandhar old NH-1 (New NH-44) Co
from Km 96.000 to Km 387.100 (length-
291.100 km)
Construction / Widening of Structures i.e.
Major Bridges, Minor Bridges, ROBs etc.
Ram Kumar
48 and other works on Panipat-Jalandhar 291.1 Haryana, Punjab Ambala 6L 44 EPC 485.00 11/07/2023
Contractor
section of NH 44 from Km. 96.000 to Km.
387.100
Providing and Fixing view cutter on RE
Wall, Structures in front of Police
49 Stations/Government Offices at various 2.758 Haryana, Punjab Ambala 6L 44 Item Rate EQRA International, 1.61 01/09/2023
locations on Panipat - Ludhiana Section of
NH-44 (old NH -01)
Strengthening with renewal work from
Gawar Kiratpur
Km 159+945 to km 167+080 (Jarol to
50 11.49 Himachal Pradesh Mandi 4L 1,54,154 Item Rate Nerchowk Highway 34.13 05/11/2023
Pung) & km 177+860 to km 182+215
Private Limited
(Dadour to nagchala)
Construction of Alternate Road from
Pandoh Dam to HPPWD Rest house,
51 3.7 Himachal Pradesh Mandi 4L 03,03 Item Rate State PWD 3.16 04/10/2023
Pandoh & Kenchi Mod to HPPWD Rest
House
Total
Total Awarded Loa Date Civil
S.no Project Name state PIU Lanes NH (New) Mode Concessioner
Length Cost (Rs work
Cr)
Reconstruction of damaged location
between Kullu to Manali section of NH-03 Gawar Construction
52 3.8 Himachal Pradesh Mandi 4L 03 Item Rate 19.81 03/11/2023
from km 272.000 to km 309.345 in the Ltd
state of Himachal Pradesh
S&P Infrastructure
Strenthening and major maintenance
Developers Pvt. Ltd.
work from Km 8.000 to Km 68.900 of NH-
154 60.9 Uttar Pradesh Lucknow 4L PS NH-27 EPC in Joint Venture with 161.26 26/10/2023
28 (new NH-27) of Lucknow-Ayodhya
Surya Construction
Section Pkg-1
Company
Kaluwala
Widening of Raebareli to Prayagraj
Construction Private
Section from Km. 82.650 to Km. 161.450
159 63.171 Uttar Pradesh Raebareli 4L 30 EPC Limited - Nirmal 638.35 10/11/2023
of NH-30 and Link road from Km. 161.450
Buildinfra Private
to Km. 641.350 (NH-2)
Limited (JV)
Total
Total Awarded Loa Date Civil
S.no Project Name state PIU Lanes NH (New) Mode Concessioner
Length Cost (Rs work
Cr)
Strengthening and improvement works of
Kaiser Constructions
2L Palia-Khutar Section of NH-
160 40 Uttar Pradesh Bareilly 2L 731 Item Rate Engineers & 23.14 12/02/2024
731(Package-1A) from Km 0.00 to Km
Contractors
40.00 in the State of Uttar Pradesh
4L Kasganj-Badaun Section from Km.
G R Infraprojects
161 123.100 to Km. 179.500 (Pkg-III) of 56.4 Uttar Pradesh Badaun 4L 530B HAM 1085.47 16/06/2023
Limited
NH530B
4L Prayagraj Greenfield By-pass from
Joint Stock company
design Km 50+860 (near Nibi Kala
Buer(JSC BUER) - oss
162 Uperhar) to design Km 64+763 on NH-19 14.98 Uttar Pradesh Prayagraj (WB) 4L PS RING ROAD EPC 349.48 19/10/2023
Construction Private
(near Khodaypur Kasgaon) including
Ltd.(JV)
Interchange loop at NH-19
4 Lane Inner Ring Road around Allahabad
GPT Infra Projects
163 City Pkg-2 (Prayagraj Southern Bypass 7.66 Uttar Pradesh Prayagraj (WB) 4L PS RING ROAD EPC 739.00 17/10/2023
Ltd.
43.200 - 50.860)
BRN Infrastructure
Development of Jhajra - Asharori Link Private Limited in JV
164 12.17 Uttarakhand VasantViharDehradun 4L 7 EPC 269.99 21/02/2024
Road (Design Ch 0.050 to Ch 12.220) with Ganesh
Builders
Four/Six laning of Bhaniyawala-Jollygrant- Brij Gopal
165 Rishikesh spur section of NH-07 from Km. 19.78 Uttarakhand VasantViharDehradun 4L/6L 7 HAM Construction Pvt. 549.00 18/10/2023
0.000 to Km 19.780 Ltd.
Short term improvement and Routine
maintenance of NH-31D from Km. Biswajyoti
166 41.654 West Bengal Alipurduar 4L 31D Item Rate 5.86 22/06/2023
113.200 to Km. 154.854(Pkg IIA), Falakata Bhattacharyya
to Salsalabari section
O&M of Dalkhola-Islampur-Sonapur-
Ghospukur from Km.447.000 to
167 96.28 West Bengal Jalpaiguri 4L 31 OMT 7.23 26/09/2023
Km.551.500 (excluding Km.498.780 to
Km.507.000)
Short term Improvement and Routine
Maintenance from Km.228.000 to
Biswajyoti
168 Km.254.500 of Salsalabari to Assam 26.5 West Bengal Alipurduar 4L 27 OMT 4.01 22/06/2023
Bhattacharyya
Bengal Border section of NH-31C (New
NH-27)
Repair & Maintenance of Barasat-
Midaas Construction
169 Barajaguli Section from KM. 31.000 to 17.553 West Bengal Krishnagar 2L 12 Item Rate 4.45 09/08/2023
Co Pvt. Ltd.
KM. 48.553 of NH-34