STATE GENCOS OF
SOUTHERN REGION
1
APGENCO & APPDCL : Rake Supply Plan for H2 (2022-23)
(Rakes/day)
PLF % in 2022-23
70.52 63.23 57.82 54.65 52.75 57.28
(Actual)
PLF% in 2023-24
74.75 67.03 61.29 66.16* 57.69* 60.72
(Projected)
*For July & August Month 10% growth has been taken on Actual PLF of respective 2021-22 month.
** % Growth of actual PLF (2022-23) and projected PLF (2023-24) has been used for calculation of projected coal demand for 2023-24.
Outstanding Dues Andhra Pradesh
(Fig in Rs Cr.)
PLF% in 2023-24
56.09 60.43 59.24 28.13* 56.89* 46.22*
(Projected)
*For July ,August & Sept month 10% growth has been taken on Actual PLF of respective 2021-22 month.
** % Growth of actual PLF (2022-23) and projected PLF (2023-24) has been used for calculation of projected coal demand for 2023-24.
Outstanding Dues Karnataka
(Fig in Rs Cr.)
Timely Freight payments to be ensured. E-payment Agreement should be secured for avoiding any delays particularly on holidays.
Tamil Nadu (Capacity 4320 MW) – Demand Projection 2023-24
Particulars Apr May Jun Jul Aug Sept
PLF% in 2023-24
70.85 58.53 59.57 55.49 71.56* 51.82*
(Projected)
*For Aug & Sept month 10% growth has been taken on Actual PLF of respective 2021-22 month.
** % Growth of actual PLF (2022-23) and projected PLF (2023-24) has been used for calculation of projected coal demand for 2023-24.
Outstanding Dues Tamil Nadu
(Fig in Rs Cr.)
Genco-Name
SCCL Import Grand Total
State Gencos
PLF% in 2023-24
89.15 82.58 76.14 75.37* 80.22* 81.91*
(Projected)