PROJECT NAME.

- Construction Program 03-Dec-22 11:18


Document No.- 01

Activity ID Activity Name Start Finish OD RD Schedule % Performance % Budgeted Total Total Float Jan 24 Jan 31
Complete Complete Cost 265 266
Sat Sun M Tue W Thr Fri Sat Sun Mon Tue WThr
P6TEST Construction Program 31-Jan-17 11-Mar-17 40d 40d 0% 0% $4,800.00 0d

P6TEST.1 Project Manangement 0d 0d 0% 0% $0.00 0d

P6TEST.2 Construction 31-Jan-17 11-Mar-17 40d 40d 0% 0% $4,800.00 0d

A400 Desing Compliance 31-Jan-17 01-Mar-17 30d 30d 0% 0% $2,400.00 10d


A500 Procurement 10-Feb-17 11-Mar-17 30d 30d 0% 0% $2,400.00 0d
P6TEST.3 Desing & Approval 0d 0d 0% 0% $0.00 0d

P6TEST.4 Test & Commission 0d 0d 0% 0% $0.00 0d

Remaining Level of Effort Project Baselin... 1 of 2 TASK filter: IMPORTANTE.


Actual Level of Effort Secondary Bas... © Oracle Corporation
PROJECT NAME.- Construction Program 03-Dec-22 11:18
Document No.- 01

Jan 31 Feb 07 Feb 14 Feb 21 Feb 28 Mar 07 Mar 14 Mar 21


266 267 268 269 270 271 272 273
Thr Fri Sat Sun Mon Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat Sun M Tue W Thr Fri Sat
Sun

Remaining Level of Effort Project Baselin... 2 of 2 TASK filter: IMPORTANTE.


Actual Level of Effort Secondary Bas... © Oracle Corporation