Progress Status For Each Esp Packages (Social Safeguards) 20211030
Progress Status For Each Esp Packages (Social Safeguards) 20211030
`2 Preparation of Belawan-Deli 31 July 2019 100 62.75 `2 Preparation of Belawan-Deli Percut-Padang River Basin Flood Management Project
Percut-Padang River Basin September 2021. Progress : 62,75% and Deviation = -37.25
Flood Management Project - PPC was proposed extension (Addendum 3) as much as 4,5 months and still processing
Survey and Data Collection
- Lidar : completed
- Baseline Survey: completed
- Topography :75% and target completion date 9 November 2021
- the first stage of the survey before determining the subproject completed February
2021
- Pengendalian Banjir Sungai Belawan: 22 Sept 2021
- Pengendalian banjir ROB Kota Belawan: 30 Sept 2021
- Pengendalian banjir Sungai Babura: 30 Sept 2021
- Pengendalian banjir sungai Sikambing: 30 Sept 2021
- Pengendalian banjir sungai Selayang: 30 Sept 2021
- Pengendalian banjir sungai Putih/ Shortcut Sikambing: 30 Sept 2021
- Pengendalian banjir sungai Deli: 30 Sept 2021
- Sistem drainase Kawasan USU: 30 Sept 2021
- Sistem drainase kawasan KIM dan sekitarnya: 30 Sept 2021
- Perencaan floodway Bahilang-Sigiling: 16 Des 2021
- Peningkatan kapasitas Sungai Bahilang-Sungai Padang: 16 Des 2021
- Peningkatan kapasitas Sungai Sigiling: 1 Des 2021
- Peningkatan kapasitas Sungai Padang Hilir (Bendung Sei padang-Muara): 1 Des
2021
- Pengendalian Banjir Sungai Padang (kota Tebing: Pertemuan Sungai Sibarau sd
Sungai Bahilang): 9 Des 2021
- Reporting will conduct parallel with the survey activities
- Calibrated runoff rainfall model and corresponding report (Hydrology) : 100% final on 3
Sept 2021
- 1st draft submitted by 15 Jan 2021
- 2nd draft submitted by 16 Jun 2021 based on TAN but the results have not
complied with what was requested by TAN
- Final version based on TAN will be submitted by 3 Sept 2021 – delayed 15 Sept
2021
- Calibrated 2-dimensional hydraulic model and report (Hydraulics) :100% final on 10 Sept
2021
- 1st draft submitted by 7 Feb 2021
- 2nd draft submitted by 22 Jun 2021
- Final version based on TAN will be submitted by 10 Sept 2021 - delayed 30 Sept
- Survey and Investigation
Water Quality (15 Subproject) have been completed
Terrestrial Ecology have been completed
Aquatic Ecology have been completed
The survey and documents have been completed
Master Plans
- Technical components (as per ToR) : 30% and target completion date on 30 Sept 2021
- ToC completed by 7 Jun 2021
- Chapter 1-3 submitted: 9 Sept 2021
- Chapter 4 - 7 : 15 Sept 2021
- Chapter 8 – 11 : 22 Sept 2021
- Chapter 12 – 14 : 28 Sept
- Final version will be submitted by 30 Sept 2021
- EFA report and survey : 0% and target completion on 24 Sept 2021
- EFA Calculation will be completed by 17 Sept 2021 (1 week after hydraulic model
completed)
- ToC will be submitted by 3 Sept 2021 - delayed
- Final Report will be submitted by 30 Sept 2021
DED
- DED reports for each selected subproject : 0% and the target completion on 7 Dec 2021
Plan for submission September 15, 2021
- Increasing of the capacity Badera River (field=100%, data processing=90%)
- Flood Control Rob Belawan City (field=100%, data processing=50%)
- O&M plans and manual : 0% and the target competition date on 7 Dec 2021
Plan for submission September 15, 2021
- Increasing of the capacity Badera River (field=100%, data processing=90%)
- Flood Control Rob Belawan City (field=100%, data processing=50%)
Enviroment safeguard:
- Belawan River
- Screening and Categorization
Draft REA completed, ADB Category A based on Permen LHK No. 4 Tahun 2021.
Application letter for direction of environmental documents to KLHK is in process
at the initiator
- Environmental Document Directive
Already published
- Preparation of Terms of Reference Document
Ongoing (informasi belum diperoleh dari pihak management)
Plan of submission ……( information has not been obtained from the management)
- Document Preparation of ANDAL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
- Document Preparation of RKL-RPL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
- Deli River
- Screening and Categorization
Draft REA completed, ADB Category A based on Permen LHK No. 4 Tahun 2021.
Application letter for direction of environmental documents to KLHK is in process
at the initiator
- Environmental Document Directive
Already published
- Preparation of Terms of Reference Document
Ongoing (information has not been obtained from the management)
Plan of submission ……( information has not been obtained from the management)
- Document Preparation of ANDAL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
- Document Preparation of RKL-RPL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
- Percut River
- Screening and Categorization
Draft REA completed, ADB Category A based on Permen LHK No. 4 Tahun 2021.
Application letter for direction of environmental documents to KLHK is in process
at the initiator
- Environmental Document Directive
Already published
- Preparation of Terms of Reference Document
Ongoing (information has not been obtained from the management)
Plan of submission ……( information has not been obtained from the management)
- Document Preparation of ANDAL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
- Document Preparation of RKL-RPL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
- Padang River
- Screening and Categorization
Draft REA completed, ADB Category A based on Permen LHK No. 4 Tahun 2021.
Application letter for direction of environmental documents to KLHK is in process
at the initiator
- Environmental Document Directive
Already published
- Preparation of Terms of Reference Document
Ongoing (information has not been obtained from the management)
Plan of submission ……( information has not been obtained from the management)
- Document Preparation of ANDAL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
- Document Preparation of RKL-RPL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
Social Safeguards:
Social Safeguards Report 40%, the target completion date of 30 November 2021.
Social Impact Assessment Report; 50% the target completion date of 30 November 2021.
Issues / problems
-