PROGRESS STATUS FOR ESP DGWR PACKAGES

STATUS FOR 15 SEPTEMBER 2021


PROGRESS
No PACKAGES Contract
Plan Real FINDING
SUNGAI DAN PANTAI

`2 Preparation of Belawan-Deli 31 July 2019 100 62.75 `2 Preparation of Belawan-Deli Percut-Padang River Basin Flood Management Project
Percut-Padang River Basin September 2021. Progress : 62,75% and Deviation = -37.25
Flood Management Project - PPC was proposed extension (Addendum 3) as much as 4,5 months and still processing
Survey and Data Collection
- Lidar : completed
- Baseline Survey: completed
- Topography :75% and target completion date 9 November 2021
- the first stage of the survey before determining the subproject completed February
2021
- Pengendalian Banjir Sungai Belawan: 22 Sept 2021
- Pengendalian banjir ROB Kota Belawan: 30 Sept 2021
- Pengendalian banjir Sungai Babura: 30 Sept 2021
- Pengendalian banjir sungai Sikambing: 30 Sept 2021
- Pengendalian banjir sungai Selayang: 30 Sept 2021
- Pengendalian banjir sungai Putih/ Shortcut Sikambing: 30 Sept 2021
- Pengendalian banjir sungai Deli: 30 Sept 2021
- Sistem drainase Kawasan USU: 30 Sept 2021
- Sistem drainase kawasan KIM dan sekitarnya: 30 Sept 2021
- Perencaan floodway Bahilang-Sigiling: 16 Des 2021
- Peningkatan kapasitas Sungai Bahilang-Sungai Padang: 16 Des 2021
- Peningkatan kapasitas Sungai Sigiling: 1 Des 2021
- Peningkatan kapasitas Sungai Padang Hilir (Bendung Sei padang-Muara): 1 Des
2021
- Pengendalian Banjir Sungai Padang (kota Tebing: Pertemuan Sungai Sibarau sd
Sungai Bahilang): 9 Des 2021
- Reporting will conduct parallel with the survey activities

- Geotechnical : 46% and target completion date 30 November 2021


- the first stage of the survey before determining the subproject completed March
2021
- Pengendalian Banjir Sungai Belawan: 1 Oct 2021
- Pengendalian banjir ROB Kota Belawan: 1 Oct 2021
- Pengendalian banjir Sungai Babura: 1 Oct 2021
- Pengendalian banjir sungai Sikambing: 1 Oct 2021
- Pengendalian banjir sungai Selayang: 1 Oct 2021
- Pengendalian banjir sungai Putih/ Shortcut Sikambing: 1 Oct 2021
- Pengendalian banjir sungai Deli: 1 Oct 2021
- Perencaan floodway Bahilang-Sigiling: 1 Nov 2021
- Peningkatan kapasitas Sungai Bahilang-Sungai Padang: 1 Nov 2021
- Peningkatan kapasitas Sungai Sigiling: 9 Nov 2021
- Peningkatan kapasitas Sungai Padang Hilir (Bendung Sei padang-Muara): 9 Nov
2021
- Pengendalian Banjir Sungai Padang (kota Tebing: Pertemuan Sungai Sibarau sd
Sungai Bahilang): 16 Nov 2021
- Reporting will conduct parallel with the survey activities

- Calibrated runoff rainfall model and corresponding report (Hydrology) : 100% final on 3
Sept 2021
- 1st draft submitted by 15 Jan 2021
- 2nd draft submitted by 16 Jun 2021 based on TAN but the results have not
complied with what was requested by TAN
- Final version based on TAN will be submitted by 3 Sept 2021 – delayed 15 Sept
2021
- Calibrated 2-dimensional hydraulic model and report (Hydraulics) :100% final on 10 Sept
2021
- 1st draft submitted by 7 Feb 2021
- 2nd draft submitted by 22 Jun 2021
- Final version based on TAN will be submitted by 10 Sept 2021 - delayed 30 Sept
- Survey and Investigation
Water Quality (15 Subproject) have been completed
Terrestrial Ecology have been completed
Aquatic Ecology have been completed
The survey and documents have been completed

Master Plans
- Technical components (as per ToR) : 30% and target completion date on 30 Sept 2021
- ToC completed by 7 Jun 2021
- Chapter 1-3 submitted: 9 Sept 2021
- Chapter 4 - 7 : 15 Sept 2021
- Chapter 8 – 11 : 22 Sept 2021
- Chapter 12 – 14 : 28 Sept
- Final version will be submitted by 30 Sept 2021
- EFA report and survey : 0% and target completion on 24 Sept 2021
- EFA Calculation will be completed by 17 Sept 2021 (1 week after hydraulic model
completed)
- ToC will be submitted by 3 Sept 2021 - delayed
- Final Report will be submitted by 30 Sept 2021
DED
- DED reports for each selected subproject : 0% and the target completion on 7 Dec 2021
Plan for submission September 15, 2021
- Increasing of the capacity Badera River (field=100%, data processing=90%)
- Flood Control Rob Belawan City (field=100%, data processing=50%)

Plan for submission September 29, 2021


- Kambing River Renormalization (field=100%, data processing=30%)
- Belawan Hulu River Flood Control

Plan for submission October 13, 2021


- The control of Rob flood of Belawan in the downstream on the left

Plan for submission October 27, 2021


- Flood control and installation of valve doors at drain outlets along Babura River
- Increasing the capacity of Selayang River

Plan for submission November 10, 2021


- Increasing the capacity of Putih River
- Deli River Flood Control from the North Sumatra Provincial DPRD Office to Deli
Bendung.

Plan for submission November 24, 2021


- Floodway Bahilang – Sigiling and Normalization of Bahilang River
- Increasing the capacity of Sigiling River

Plan for submission Dec 7, 2021


- Increasing the capacity of Downstream Padang River
- Increasing the capacity of the Padang River (Meeting Sibarau River – Downstream
Meeting Bahilang River)
- TOR, Bill of Quantities, and Cost Estimates for each selected subproject : 0% and the target
completion date on 7 Dec 2021
Plan for submission September 15, 2021
- Increasing of the capacity Badera River (field=100%, data processing=90%)
- Flood Control Rob Belawan City (field=100%, data processing=50%)

Plan for submission September 29, 2021


- Kambing River Renormalization (field=100%, data processing=30%)
- Belawan Hulu River Flood Control

Plan for submission October 13, 2021


- The control of Rob flood of Belawan in the downstream on the left

Plan for submission October 27, 2021


- Flood control and installation of valve doors at drain outlets along Babura River
- Increasing the capacity of Selayang River

Plan for submission November 10, 2021


- Increasing the capacity of Putih River
- Deli River Flood Control from the North Sumatra Provincial DPRD Office to Deli
Bendung.

Plan for submission November 24, 2021


- Floodway Bahilang – Sigiling and Normalization of Bahilang River
- Increasing the capacity of Sigiling River

Plan for submission Dec 7, 2021


- Increasing the capacity of Downstream Padang River
- Increasing the capacity of the Padang River (Meeting Sibarau River – Downstream
Meeting Bahilang River)

- O&M plans and manual : 0% and the target competition date on 7 Dec 2021
Plan for submission September 15, 2021
- Increasing of the capacity Badera River (field=100%, data processing=90%)
- Flood Control Rob Belawan City (field=100%, data processing=50%)

Plan for submission September 29, 2021


- Kambing River Renormalization (field=100%, data processing=30%)
- Belawan Hulu River Flood Control

Plan for submission October 13, 2021


- The control of Rob flood of Belawan in the downstream on the left

Plan for submission October 27, 2021


- Flood control and installation of valve doors at drain outlets along Babura River
- Increasing the capacity of Selayang River

Plan for submission November 10, 2021


- Increasing the capacity of Putih River
- Deli River Flood Control from the North Sumatra Provincial DPRD Office to Deli
Bendung.

Plan for submission November 24, 2021


- Floodway Bahilang – Sigiling and Normalization of Bahilang River
- Increasing the capacity of Sigiling River

Plan for submission Dec 7, 2021


- Increasing the capacity of Downstream Padang River
- Increasing the capacity of the Padang River (Meeting Sibarau River – Downstream
Meeting Bahilang River)
Riparian Zone Study
- Riparian Zone Report : 23.33% and the target completion date 8 Oct 2021
- ToC submitted by 9 Sept 2021
- chapter 1-3: 10 September 2021 - delayed
- Chapter 4-6: 24 September 2021
- Chapter 7-9: 8 Oct 2021

Enviroment safeguard:
- Belawan River
- Screening and Categorization
Draft REA completed, ADB Category A based on Permen LHK No. 4 Tahun 2021.
Application letter for direction of environmental documents to KLHK is in process
at the initiator
- Environmental Document Directive
Already published
- Preparation of Terms of Reference Document
Ongoing (informasi belum diperoleh dari pihak management)
Plan of submission ……( information has not been obtained from the management)
- Document Preparation of ANDAL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
- Document Preparation of RKL-RPL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)

- Deli River
- Screening and Categorization
Draft REA completed, ADB Category A based on Permen LHK No. 4 Tahun 2021.
Application letter for direction of environmental documents to KLHK is in process
at the initiator
- Environmental Document Directive
Already published
- Preparation of Terms of Reference Document
Ongoing (information has not been obtained from the management)
Plan of submission ……( information has not been obtained from the management)
- Document Preparation of ANDAL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
- Document Preparation of RKL-RPL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)

- Percut River
- Screening and Categorization
Draft REA completed, ADB Category A based on Permen LHK No. 4 Tahun 2021.
Application letter for direction of environmental documents to KLHK is in process
at the initiator
- Environmental Document Directive
Already published
- Preparation of Terms of Reference Document
Ongoing (information has not been obtained from the management)
Plan of submission ……( information has not been obtained from the management)
- Document Preparation of ANDAL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
- Document Preparation of RKL-RPL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)

- Padang River
- Screening and Categorization
Draft REA completed, ADB Category A based on Permen LHK No. 4 Tahun 2021.
Application letter for direction of environmental documents to KLHK is in process
at the initiator
- Environmental Document Directive
Already published
- Preparation of Terms of Reference Document
Ongoing (information has not been obtained from the management)
Plan of submission ……( information has not been obtained from the management)
- Document Preparation of ANDAL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)
- Document Preparation of RKL-RPL
Not yet
Plan of submission…… (waiting for a reply letter from KLHK)

Social Safeguards:

Social Safeguards Report 40%, the target completion date of 30 November 2021.
Social Impact Assessment Report; 50% the target completion date of 30 November 2021.

Implementation of PCM 1: River of Babura, Deli and Badera are done.


Implementation of PCM 2: River of Badera is done.
Implementation of PCM 1 and 2 another locations are not yet.

LARP of topography Survey for:


River of Babura is done (100%)
River of Badera is done (100%)
River of Deli isn’t finished (15%)
Another locations are not yet.

IOL and SES Survey for


River of Babura is done (100%)
River of Badera is done (100%)
Another locations are not yet.

Screenings and categorisations are 50%.


DPPT Reports (15 units); 15%, the target completion date of 30 November 2021
LARP Reports (5 units); 30%, the target completion date of 30 November 2021

Issues / problems
-