UNIT OF WORK: BALAI BESAR WILAYAH SUNGAI CIDANAU-CIUJUNG-CIDURIAN
COMMITMENT MAKER OFFICER: WATER RESOURCES MANAGEMENT WORK: PROCUREMENT AND INSTALLATION OF HYDROMETEOROLOGICAL NETWORKS AND THE STATIONS CONTRACT NO.: HK.02.02/01/Az.01.3/2022 CONTRACT DATE: 21 APRIL 2022 LOCATION: KOTA SERANG, KABUPATEN SERANG DAN KABUPATEN LEBAK SOURCE OF FUNDING: ADB LOAN 3440-INO FISCAL YEAR: 2022
AUG. 2022 SEPTEMBER 2022 OCTOBER 2022 NOV. 2022
NO WORK ITEM~DETAILS 21-25 26-31 1-5 6-10 11-15 16-20 21-25 26-30 1-5 6-10 11-15 16-20 21-25 26-31 1-5 6-10 11-15 16-20 1 Persiapan Fabrikasi Rumah Pos 2 Fabrikasi Rumah Pos (Workshop) 3 Joint Inspection Material Rumah Pos (Workshop) 8 4 Pondasi AWLR N, A, F, I & M (El. 0) 5 Pondasi AWLR L & U (El. 1) 6 Persiapan Instalasi Rumah Pos 7 Instalasi Rumah Pos AWLR N, A, F, I & M (El. 0) 8 Instalasi Rumah Pos AWLR L & U (El. 1) 9 Pengukuran, Pengikatan & Pembuatan BM ~ 21