QUESTION 1
Construct the Network diagram for this project.
Identify the critical path for this network diagram? Explain how do we know. [2 marks]
QUESTION 2
1
QUESTION 3
2
QUESTION 5
What do the Schedule Performance Index and the Cost Performance Index demonstrate? How
can a project manager use this information to estimate future project performance??
13.1
QUESTION 6
Suppose the SPI is calculated as less than 1.0. Is this good news for the project or bad news?
Why?
QUESTION 7
Identify the following terms: PV, EV, and AC. Why are these terms important? How do they
relate to one another?
QUESTION 8
You have collected EV, AC, and PV data from your project for a five-month period. Complete
the table. Calculate SPIC and CPIC. Compare the cost and schedule performance for the project
on a month-by-month basis and cumulatively. How would you assess the performance of the
project? (All values are in thousands $)